Professional Documents
Culture Documents
Erich Kreidler
Risk Management – Point of View
Risk is inherent to projects and no amount of
planning can overcome risk and its potential
consequences. Risk Management recognizes and
manages potential trouble spots that may occur
when the project is implemented.
Complexity
Complexityofof
Requirements? Stability
Requirements? Stability
of
ofRequirements?
Requirements?TeamTeam
Skill Requirements?
Skill Requirements?
Policy
PolicyImplications
Implications How
Howlong
longwill
willthe
the
Smug
Smugprogram
program
take?
take?
33Days
Days
PROJECT RISK MANAGEMENT (PMBOK)
Definitio
ns
RISK and CONTINGENCY (PMBOK)
Future
Probabilistic
Impact or loss
Time-dependent
May provide opportunities
TYPES OF RISK
Technical performance
Schedule
Cost
Field support
Security
Other
Risk
Identification
How do you identify risks?
Brainstorming
Prior projects (history)
Parametric models
Delphi/Nominal Group Technique
Experts
Standards
The Risk Breakdown Structure
SOME ELEMENTS OF PROJECT RISK (ROSENAU)
SOME ELEMENTS OF PROJECT RISK (ROSENAU)
LIFE CYCLE RISK ANALYSIS (KERZNER)
Amount at
Stake Amount
risk at Stake
Typical Risk Events pre Phase
• Unavailable • No risk • Un-skilled labor • Poor Quality
subject matter management plan
experts • Material • Un-acceptable to
• Hasty planning availability customer
• Poor definition of
problem • Poor spec • Strikes • As-built changes
• No control
systems in place
Risk Analysis
TOOLS AND TECHNIQUES FOR RISK ANALYSIS
Severe 1
High 2
Moderate
Low
Trivial 4 3
0 100
Probability of Occurrence
RISK ANALYSIS (KERZNER)
SAMPLE RISK CHART (Pete Badzey)
Beginning Risk
5
Assessment (3.5-4)
4
• Risk chart shows
Mitigation Task 1
Analysis initial ranking
Severity
3 • Shows steps in
Mitigation Task 2 management
Test
2
plan to reduce to
acceptable level
Mitigation Task 3
Design Mod • Can be changed
1 dynamically as
the risk is
managed
1 2 3 4 5
Desired Probabilit Ref. Systems Engineering and
End State (1-1)
y Analysis, 3rd Ed, Blanchard and
Fabrycky, Prentice Hall, 1998, pgs 657-
661
PROBABILITY (KERZNER)
Almost Likely
Highly Likely
Very Good Chance
Likely
Probable
We Believe
Better than Even What uncertainty
We Doubt statement means to
Improvable different people
Unlikely
Probably Not
Little Chance
Almost no Chance
Highly Unlikely
0 10 20 30 40 50 60 70 80 90 100
Assigned Probability Percentage
QUANTIFY RISK
QUALITATIVE RATING IMPACTS FOR A RISK
DECISION TREE ANALYSIS (PMBOK)
COST RISK SIMULATION (PMBOK)
RISK ASSESSMENT (THOMSETT)
Risk Management
and Response
Planning
HOW DO YOU MANAGE RISK?
Control
• Identify the Risk
significant
risks • Risk
• Analyze the management
risks planning
• Prioritize • Risk resolution
Assess • Risk
monitoring
the Risks
CONCEPT OF OPTIMIZING (ROSENAU)
RISK MANAGEMENT PLAN
Documents procedures for managing risk
Covers
Who is responsible for managing risk
How initial identification and quantification will be maintained
Contingency plan implementation
Reserve allocation
RMP may be
Formal or informal
Detailed or broad-based/general
Based on needs of project
RISK MITIGATION/RESPONSE
After risk identified and assessed, four types of
actions
Reduce risk, e.g., parallel innovation processes
Transfer risk to another party (costs $), e.g., insurance
Retain risk
Some very large risks, e.g., earthquakes, cannot be reduced,
probability is low, so accept
Add budget reserve
Ignore
Share/allocate portions to other parties, e.g., Airbus R&D
among countries
RISK RESPONSE MATRIX
RISK RESPONSE MATRIX
Thanks!