(1) The left port of the raw water pump is connected to the raw water tank,
and a manual valve needs to be added to the raw water tank (to prevent
1
(3)RO Pure water outlet
2
Step 2: After the above four ports are connected
The pretreatment tank and the membrane host are connected in sequence
Step 3: Next, connect the flush signal connector and the automatic valve
connector:
Dosing system point
3
Step 4: Connect the power cord of the automatic valve of the pretreatment
Step 5: Preprocess the jars. Before filling, turn on the machine to test the
1. Packing: (twist the automatic valve head, start packing, fill up to 60%,
and re-twist the valve head after the filter material is filled) (unscrew the
4
2. The pretreatment tank is backwashed and washed in sequence. After
the tank is washed, it can reach the running state. The first rinse is
Note: To replenish water in the raw water tank, half-open the water inlet
valve of the raw water pump to allow water to enter the raw water pump,
and unscrew the pump exhaust screw to fill the cavity with water. (Note:
if the valve opens too fast, the filter material will be lost)
precision filter, clean the filter and install the three-core filter membrane.
5
Step 7: Install RO membrane
6
Step 9: Adjust the right side of the pressure switch to 1-2, and the left side
7
Step ten: Panel flow valve adjustment
Dosing system:
1. Add 2kg flocculant and 38L pure water to the flocculant dosing box,
and adjust the output flow rate of the metering pump to 32%;
2. Add 2kg reducing agent and 38L pure water to the reducing agent
dosing box, and adjust the output flow rate of the metering pump to 32%;
3. Add 2kg of scale inhibitor and 38L of pure water to the antiscaling
agent dosing box, and adjust the output flow rate of the metering pump to
32%;