You are on page 1of 2

Kathmandu Valley Water Supply lmprovement Project

ep4sa
=.,,"n,"n,=:l;"-:::::::: fl,",l:?:i::ii;i;,lii,li G,,-,.*-'#
Ref N o: EPT/KU KL-D SC07 12023-201 8 Date 6th February 2023
Mr. Pawan Mahato
Contractor's Represe ntative
Sharma-Raman JV

Project: Distribution Network lmprovement for Efficient NRW Management (Package - 5)


Contract No.: KU KUDNI -7 B

Subject: - Reminder (ll) Low Resource Mobilization and Slow Rate of Progress

Letters Ref:

Dear Mr. Mahato,

This is to bring in to your attention that the contract completion date is 24th April2023, and there is little time left.

It is noted that there is still a huge work pending to be completed from your side: physical progress is 30.51% at the end of
January 2023, pipeline trenches executed 370/o and HDD pipelines 22o/0.

It is also been noted that you are not working with the adequate resources since a few months back, and this is the dry
season, when the progress should be the highest compared to the monsoon season. Regarding our letter ref. no. EPT/KUKL-
D5C0712023-1869 dated 10th January 2023 and our several verbal instructions about the above captioned subject, we have
instructed you to increase the adequate resources on site but we could not find any noticeable increment in resources on
field due to which there is very little progress on the pgect. The project will not be completed within anticipated date of
completion with the current rate of progress. lt is, therefore, completely needed that you must increase your workforce or
resources to complete the pending work in time. Your efforts in these months pending up to the completion date and the
daily work progress will be taken in account for the extension of time approval conditions.

Please note that your resource mobilization for month of January 2023, enclosed herewith, depict the average of only 58
workers per day working on site. You had only achieved 200/o of your targeted work for the month. The tabulated summary
shows you are lagging your scheduled activity by 80%. The monthly work schedule for the month of February 2022 should
reflects the recovery plan for the work that you have lagged in the previous month. You are again instructed to increase the
adequate resources on site in order to accomplish the remaining work as soon as possible.

Yours sincerely,

M;;,;i
Team

CC:
Project Director, PID/KUKL, Kathmandu

Project Office Address Tanka Prasad Ghumti Sadak, Anamnagar, Kathmandu, Phone: +977 1 5705678 Email. eptisadsc0T@gmail.com
Kathmandu Valley Water Supply lmprovement Project
Design, Supervision and Contract Management Consultant (DSC-07) t^-
epqsa ..,*n,"nf :l;"-::::U: fl,",I:?:i:;i j;l,,:ijJi G , .,0*- #
Contractor Resource Mobilization Record for the month January 2023

Schedule / Tarqet Vs Actual Proqress


Date Manpower (nos.) Pipeline (m) Reinstatement (m) Pump House / CIhers
Schedule Actual Schedule Taroet Schedule Tarqet Schedule Tarqet
01 Jan2023 222 82 755 00 293.00 562.00 141.00 0.36
02 Jan 2023 226 74 774.50 265 00 590.00 75.00 0.32
03 Jan 2023 214 81 730 00 343.00 534 00 155.00 0.34
04 Jan 2023 218 80 737.00 226.00 576.00 85.00 0.34
05 Jan 2023 235 71 BOB OO 212.00 548 00 85.00 0.36
06 Jan 2023 aEn
63 858.50 248.00 492.00 15 00 0.40
07 Jan2023 241 44 836 00 164.00 506.00 25.00 0.44
08 Jan 2023 237 62 808.00 154 00 534 00 63.00 0.40
09 Jan 2023 t40 63 827.50 122.00 477.00 63 00 0.42
10 Jan 2023 236 7B 803.00 284.00 463.00 91.00 0.40
'7,1
11 Jan2023 231 797.00 51.00 505.00 169.00 040
12 Jan 2023 227 B4 805.00 214.00 435.00 90.00 0.44
aAa 70
13 Jan 2023 L+J 786.00 149.00 505 00 70 00 0.40
14 Jan 2023 231 60 794.00 269.00 491.00 40.00 0.42
15 Jan 2023 ltJ 0 833.50 393.00 054
16 Jan 2023 tlo 34 768 00 113 00 393.00 16.00 0.48
17 Jan 2023 225 44 759 50 435 00 1 13.00 0.56
18 Jan 2023 221 65 814.00 13300 421.00 133 00 040
19 Jan 2023 222 65 791.00 16.00 421.00 140.00 0.30
20 Jan 2023 231 85 786 00 13800 435.00 378.00 0.32
21 lan2023 212 49 794.00 24.00 407 00 205.00 0.28
22 Jan2023 208 53 833.00 96 00 421.00 146 00 030
23 Jan 2023 209 61 747 00 140.00 435 00 344.00 0.32
24 Jan 2023 211 4J 791.00 66 00 407.00 93 00 0.30
25 Jan 2023 lvc 53 750.50 159.00 421.00 0.32
26 Jan 2023 240 65 852.50 269.00 421.00 0.40
27 Jan 2023 245 37 872.00 192.00 407 00 125 00 0.32
28 Jan 2023 tto IJ 781.50 168.00 407.00 18.00 0.40
29 Jan2023 219 13 789.50 407 00 0.40
30 Jan 2023 215 67 754.00 240.00 407.00 117.00 0.40 0.40
31 Jan2023 213 52 753 50 246.00 435 00 0.44 0.M
Total 6998 1 801 24590.00 4994.00 14291.00 2995,00 11.92 0.84
Target 0/o
25.73 20.30% 20.95Yo 7.040/o
Achieved %
Average per
58 161 .09 96.61
dav

Pro1ectOfflceAddress:TankaPrasadGhumtiSadak,Anamnagar,Kathmandu'Phone:+97715705678@

You might also like