Cost Estimate
The cost estimating approach was used to anticipate all of the expenses
associated with executing this project within its scope and timeline.
PERT/CPM
Installation of Steel
Mobilization Reinforcing Steel, Grade 40 Railings Demobilization
1 1 CD 2 CD
3 CD 4 CD 5
Structural Concrete,
Class A
CD
Painting Works
CD
Figure ___ illustrated the project's PERT/CPM, which organized the tasks.
The nodes represented the succession of activities, while the lines denoted the
connections between each event. Along with the item of work, the assigned days
for each task were also given. During the project, the PERT/CPM specified all key
The PERT/CPM diagram depicted the flow of minor activities as well as the
project's critical path. The critical path includes the following activities such as