Professional Documents
Culture Documents
Forensic Planning
Preparing Successful
Critical Path vs. Delay Analysis
1 Presenter Bio 2 Introduction 3 4 5 Extension of Time
Longest Path Techniques
Requests
2
Bio
Civil Engineering background
16 years’ experience
3
Preparing Successful
Critical Path vs. Delay Analysis
1 Presenter Bio 2 Introduction 3 4 5 Extension of Time
Longest Path Techniques
Requests
4
What is a Delay?
5
How do Disputes Arise?
Source Attribution
• Disagreement • Employer,
• Misunderstanding • Contractor(s),
• Poor relationships • Subcontractor(s), or
• Escalation of conflicts between the • Consultant(s)
parties
• Wide variety of interactions between
diverse people
• Failure of one party to the contract to
keep their promise
6
Contractual Root Causes
Pre-Construction Construction
• Ambiguous contracts & contract documents
(specifications, drawings, errors, discrepancies)
• Changes
(extra works, additional scope, late info)
• Poor Risk allocation • Extension of Time requests caused by events
• Poor Procurement Process (extra work, late access, disruption, late
changes)
• Defective work
• Latent conditions (Hidden or Underlying)
• Failure to adequately document the works
and daily events
7
Types of Delays
Delay
Non-
Compensable
compensable
Non-Concurrent
Concurrent Delay
Delay
8
Preparing Successful
Critical Path vs. Delay Analysis
1 Presenter Bio 2 Introduction 3 4 5 Extension of Time
Longest Path Techniques
Requests
9
Critical Path
10
Longest Path
Definition
11
Preparing Successful
Critical Path vs. Delay Analysis
1 Presenter Bio 2 Introduction 3 4 5 Extension of Time
Longest Path Techniques
Requests
12
Delay & Time Impact Analysis Techniques
Retrospective Analyses Prospective Analyses
LOOKING BACK LOOKING FORWARD
13
Delay & Time Impact Analysis Techniques
Method of Analysis Analysis Type Critical Path Delay Impact Requirements
Determined Determined
Logic linked baseline schedule
Impact As-Planned Analysis Cause & Effect Prospectively Prospectively
Selection of delay events to be modelled
Baseline schedule
As-Planned vs. As-Built Windows Analysis Effect & Cause Contemporaneously Retrospectively
As-built data
Baseline schedule
Longest Path Analysis Effect & Cause Retrospectively Retrospectively
As-built schedule
15
Preparing Successful Extension of Time Requests
Event Delay Critical Path Facts & Evidence Delay Analysis Verification
Only after an event delay For an event to affect the Must consider all relevant Delay Analysis should be Are there facts and / or
becomes a fact, the Other completion date, it must facts and evidence based on a calculated evidence available and
Party / the Courts are fall on the Critical Path of regardless of a positive or approachCannot be accessible to verify the
interested in what actually the project a the time the negative impact in relation subjective delay cause?
happened rather than in event occurred to the issues in question
what could have
happened
16
Claims Management Advice & Rules to Follow
Evaluate & quantify time and/or cost
01 Record keeping 07
entitlement
03 Give notice as per contract requirements 09 Define objectives & realistic expectations
05 Establish contractual entitlement & validity 11 Submit, support, negotiate & resolve
06
Analyze data: schedules, correspondence, 12
If unsuccessful, refer to Dispute Resolution
submissions, documents, etc. under contract mechanism
17
EOT Request | Assessment, Presentation & Submission
Claims should be genuine and
01 Keep good records 05
demonstrable
Good presentation
02 06 Update claims and notices as necessary
(know your audience & keep it simple)
Fully understand the contract Monitor and accurately record the full
03 07
and scope of works impact of disruption events
04
Appropriately discharge contractual 08
Select an appropriate delay analysis
obligations in every respect methodology in compliance with the contract
18
Contact Details
D: 416.234.4283
T: 416.641.9500 X 2087
M: 416.807.5316
E: ahmed.fouadsedky@altusgroup.com
19
Thank You! Thank you
Any questions? Just ask!
20