You are on page 1of 20

Introduction to Delay Analysis

Forensic Planning

Ahmed Fouad Sedky


April 10, 2019
Delay Analysis & Forensic Planning

Preparing Successful
Critical Path vs. Delay Analysis
1 Presenter Bio 2 Introduction 3 4 5 Extension of Time
Longest Path Techniques
Requests

2
Bio
Civil Engineering background
16 years’ experience

Oil & gas Railway Mixed-Use


Seaports Healthcare Resi/High-rise

Ahmed Fouad Sedky


LL.M., B.Sc.(Eng.) Civil, MCIArb, MCIOB, MQSi, PMP, SP, RMP

Senior Claims Consultant


Cost & Project Management, Altus Group Limited
Toronto, ON, Canada $ Managed $13 Billion (USD)
in scope of work

3
Preparing Successful
Critical Path vs. Delay Analysis
1 Presenter Bio 2 Introduction 3 4 5 Extension of Time
Longest Path Techniques
Requests

4
What is a Delay?

Definition Reasons Disputes


Time overrun beyond Unanticipated Common Disputes:
planned dates, such as: Circumstances:
Assigning or Assuming
• Scope change
1. Contract completion date • Late change Variance Responsibility
• Access to work site
2. Delivery date (agreed by • Contractor / subcontractor
performance
all parties)

5
How do Disputes Arise?
Source Attribution
• Disagreement • Employer,
• Misunderstanding • Contractor(s),
• Poor relationships • Subcontractor(s), or
• Escalation of conflicts between the • Consultant(s)
parties
• Wide variety of interactions between
diverse people
• Failure of one party to the contract to
keep their promise

6
Contractual Root Causes

Pre-Construction Construction
• Ambiguous contracts & contract documents
(specifications, drawings, errors, discrepancies)
• Changes
(extra works, additional scope, late info)
• Poor Risk allocation • Extension of Time requests caused by events
• Poor Procurement Process (extra work, late access, disruption, late
changes)
• Defective work
• Latent conditions (Hidden or Underlying)
• Failure to adequately document the works
and daily events

7
Types of Delays
Delay

Inexcusable Excusable Pacing Delay

Non-
Compensable
compensable

Non-Concurrent
Concurrent Delay
Delay

8
Preparing Successful
Critical Path vs. Delay Analysis
1 Presenter Bio 2 Introduction 3 4 5 Extension of Time
Longest Path Techniques
Requests

9
Critical Path

Definition Conditions However


The path of This is true in the following If any of the conditions
conditions: change…
ZERO Total Float
through the project 1. No project deadline It well could be the path or
paths with the least Total
2. No constraints Float
3. No actuals

10
Longest Path
Definition

The Path Through a


Project Network Reasoning
Project Network: a series
of activities logically linked
to identify the required
Understanding
sequence of work. Impacts All Paths Aren’t Equal
Focus on a project’s
Longest Path works Longest Path!
through the Project ≠
Network from start to finish This is the path where Longest Path is a Critical
What to Watch
where the Total Duration is deviations from the plan Path
longer than any other path. will affect the project’s
finish date. HOWEVER, not all Critical Longest Path
Paths are Longest Paths
This is the main path to
monitor. Timely completion of
longest path activities leads to
projects finishing on time.

11
Preparing Successful
Critical Path vs. Delay Analysis
1 Presenter Bio 2 Introduction 3 4 5 Extension of Time
Longest Path Techniques
Requests

12
Delay & Time Impact Analysis Techniques
Retrospective Analyses Prospective Analyses
LOOKING BACK LOOKING FORWARD

• As-planned vs. As-built • Time-Impact Analysis


• As-built But For • Impacted As-planned
• Windows Analysis

13
Delay & Time Impact Analysis Techniques
Method of Analysis Analysis Type Critical Path Delay Impact Requirements
Determined Determined
Logic linked baseline schedule
Impact As-Planned Analysis Cause & Effect Prospectively Prospectively
Selection of delay events to be modelled

Logic linked baseline schedule


Update schedules/progress information with
Time Impact Analysis Cause & Effect Contemporaneously Prospectively
which to update the baseline schedule
Selection of delay events to be modelled
Logic linked baseline schedule
Time Slice Windows Analysis Effect & Cause Contemporaneously Retrospectively Update schedules/progress info with which to
update the baseline schedule

Baseline schedule
As-Planned vs. As-Built Windows Analysis Effect & Cause Contemporaneously Retrospectively
As-built data

Baseline schedule
Longest Path Analysis Effect & Cause Retrospectively Retrospectively
As-built schedule

Logic linked as-built schedule


Collapsed As-Built Analysis Cause & Effect Retrospectively Retrospectively
Selection of delay events to be modelled

Source: Society of Construction Law, Delay Disruption Protocol, 2nd Edition


February 2017, p.34 14
Preparing Successful
Critical Path vs. Delay Analysis
1 Presenter Bio 2 Introduction 3 4 5 Extension of Time
Longest Path Techniques
Requests

15
Preparing Successful Extension of Time Requests

Event Delay Critical Path Facts & Evidence Delay Analysis Verification

Only after an event delay For an event to affect the Must consider all relevant Delay Analysis should be Are there facts and / or
becomes a fact, the Other completion date, it must facts and evidence based on a calculated evidence available and
Party / the Courts are fall on the Critical Path of regardless of a positive or approachCannot be accessible to verify the
interested in what actually the project a the time the negative impact in relation subjective delay cause?
happened rather than in event occurred to the issues in question
what could have
happened

16
Claims Management Advice & Rules to Follow
Evaluate & quantify time and/or cost
01 Record keeping 07
entitlement

02 Knowledge of contract & your obligations 08 Assemble heads of claim

03 Give notice as per contract requirements 09 Define objectives & realistic expectations

04 Collect evidence pertaining to events 10 Develop strategy & timing

05 Establish contractual entitlement & validity 11 Submit, support, negotiate & resolve

06
Analyze data: schedules, correspondence, 12
If unsuccessful, refer to Dispute Resolution
submissions, documents, etc. under contract mechanism

17
EOT Request | Assessment, Presentation & Submission
Claims should be genuine and
01 Keep good records 05
demonstrable

Good presentation
02 06 Update claims and notices as necessary
(know your audience & keep it simple)

Fully understand the contract Monitor and accurately record the full
03 07
and scope of works impact of disruption events

04
Appropriately discharge contractual 08
Select an appropriate delay analysis
obligations in every respect methodology in compliance with the contract

18
Contact Details
D: 416.234.4283

T: 416.641.9500 X 2087

M: 416.807.5316

E: ahmed.fouadsedky@altusgroup.com

Ahmed Fouad Sedky linkedin.com/in/ahmedfouadsedky


LL.M., B.Sc.(Eng.) Civil, MCIArb, MCIOB, MQSi, PMP, SP, RMP

Senior Claims Consultant


Cost & Project Management, Altus Group Limited altusgroup.com
Toronto, ON, Canada

33 Yonge Street, Suite 500, Toronto, ON M5E 1G4

19
Thank You! Thank you
Any questions? Just ask!

20

You might also like