You are on page 1of 112

BTQS3063 PROJECT AND DISSERTATION II

THE EFFECTS OF COVID-19 ACT ON THE APPLICATION OF


LIQUIDATED DAMAGES IN MALAYSIAN CONSTRUCTION
INDUSTRY

BY
LEONG KHAR YEE

DEPARTMENT OF QUANTITY SURVEYING


FACULTY OF BUILT ENVIRONMENT
TUNKU ABDUL RAHMAN UNIVERSITY COLLEGE
KUALA LUMPUR

2022/2023

i
THE EFFECTS OF COVID-19 ACT ON THE APPLICATION OF LIQUIDATED
DAMAGES IN MALAYSIAN CONSTRUCTION INDUSTRY

by

LEONG KHAR YEE

Supervisor: Mr. Pang Khai Shuen

Project dissertation submitted in partial fulfilment of the requirements for the award

of the Bachelor of Quantity Surveying (Honours)

Department of Quantity Surveying

Faculty of Built Environment

Tunku Abdul Rahman University

College, Kuala Lumpur

2022/2023

Copyright © 2023 by Tunku Abdul Rahman University College.

All rights reserved. No part of this dissertation may be reproduced, stored in a

retrieval system, or transmitted in any form or by any means without the prior

permission of Tunku Abdul Rahman University College.

ii
DECLARATION OF ORIGINALITY

“The project submitted herewith is a result of my own investigations. All information that

has been obtained from other sources has been fully acknowledged. I understand that

plagiarism constitutes a breach of University College rules and regulations and would be

subjected to disciplinary actions.”

Signature

Leong Khar Yee

Date: 25th September 2022

ii
ACKNOWLEDGEMENT

First and foremost, I would like to express my gratitude to Mr. Pang Khai Shuen, my subject

supervisor, for providing me proper guidance and supervision throughout the academic

semester. He used to lead me on the right track by using his professional opinions and

suggestions. I would also like to take this opportunity thanks to the Faculty of Built

Environment at Tunku Abdul Rahman University College (TARUC) for giving students an

opportunity to be involved in this project dissertation I as a part of my degree programme.

Besides, I would also like to thanks to my classmate, Lau Juen Sien in giving me valuable

information during the research progress in order to complete my research successfully.

Last but not least, I am grateful to have my family accompany me in giving me motivation and

support. I am very appreciative for their kind cooperation and encouragement by giving me a

good environment to study and complete my dissertation successfully within the limited time

frame.

iii
TABLE OF CONTENT

DECLARATION OF ORIGINALITY .............................................................ii

ACKNOWLEDGEMENT ................................................................................ iii

TABLE OF CONTENT .....................................................................................iv

LIST OF FIGURES ............................................................................................ x

LIST OF TABLES .............................................................................................xi

LIST OF SYMBOL / ABBREVIATION ...................................................... xiii

ABSTRACT ......................................................................................................xiv

Chapter 1 Introduction....................................................................................... 1

1.1 Research Background .................................................................................................. 1

1.2 Problem Statement ...................................................................................................... 3

1.3 Previous Similar Studies ............................................................................................. 5

1.4 Research Aim .............................................................................................................. 6

1.5 Research Question ....................................................................................................... 6

1.6 Research Objective ...................................................................................................... 6

1.7 Scope and Limitations ................................................................................................. 6

1.7.1 Scope .................................................................................................................... 6

1.7.2 Limitation............................................................................................................. 7

1.8 Importance of Research ............................................................................................... 7

1.9 Research Design .......................................................................................................... 8

iv
1.10 Structure of the Report ................................................................................................ 9

Chapter 2 Literature Review ........................................................................... 11

2.1 Introduction ............................................................................................................... 11

2.1.1 Section 75 Contract Act 1950 ............................................................................ 11

2.2 Enforceability of Liquidated Damages ..................................................................... 12

2.2.1 Case Study ......................................................................................................... 12

2.2.1.1 Malaysia Law ............................................................................................. 12

2.2.1.2 Foreign law ................................................................................................. 13

2.3 Types of liquidated damages ..................................................................................... 15

2.3.1 Liquidated damages ........................................................................................... 15

2.3.2 Unliquidated damages ........................................................................................ 16

2.4 Benefits and drawbacks of having a Liquidated Damages clause in a contract ........ 17

2.4.1 Developer ........................................................................................................... 17

2.4.1.1 Benefits ....................................................................................................... 17

2.4.1.2 Disadvantages ............................................................................................. 18

2.4.2 Contractor .......................................................................................................... 20

2.4.2.1 Benefits ....................................................................................................... 20

2.4.2.2 Disadvantages ............................................................................................. 21

2.4.3 Summary ............................................................................................................ 21

2.5 The application in enforcing Liquidated Damages during pre-stage and final account

negotiation and the factors affecting liquidated damages enforce due to delay................... 22

v
2.5.1 Negotiation......................................................................................................... 22

2.5.2 Calculation of Liquidated Damages................................................................... 24

2.5.2.1 Developer to Purchaser ............................................................................... 24

2.5.2.2 Main Contractor to Sub-Contractor ............................................................ 24

2.5.2.3 Developer to Main Contractor .................................................................... 25

2.5.3 Type of damages caused by delay ..................................................................... 28

2.6 Enforcement of Liquidated Damages due to Covid-19 Pandemic ........................... 30

2.6.1 Relationship Between the Developer and Main Contractor .............................. 30

2.6.2 Relationship between Developer and Purchaser ................................................ 33

2.7 Conclusion................................................................................................................. 35

Chapter 3 Research Methodology ................................................................... 36

3.1 Introduction ............................................................................................................... 36

3.2 Research process ....................................................................................................... 37

3.3 Techniques for Data Collection................................................................................. 38

3.3.1 Secondary Data Collection ............................................................................... 38

3.3.2 Primary Data Collection ................................................................................... 38

3.4 Development of Research Instrument ....................................................................... 39

3.4.1 Questionnaire Design ......................................................................................... 39

3.4.1.1 Section A .................................................................................................... 40

3.4.1.2 Section B..................................................................................................... 40

3.4.1.3 Section C..................................................................................................... 41

vi
3.4.1.4 Section D .................................................................................................... 41

3.4.2 Type of Questions .............................................................................................. 42

3.4.2.1 Closed and Open - Ended Question ............................................................ 42

3.4.2.2 Checklist Question...................................................................................... 43

3.4.2.3 Likert Scale ................................................................................................. 44

3.5 Pre-testing Research Instrument................................................................................ 44

3.6 Sampling Method ...................................................................................................... 45

3.6.1 Population .......................................................................................................... 46

3.6.2 Sample................................................................................................................ 46

3.7 Technique for Data Analysis ..................................................................................... 48

3.7.1 Univariate Analysis ............................................................................................ 49

3.7.2 Relative Importance Index (RII) ........................................................................ 49

3.8 Research Model / Conceptual Framework ................................................................ 50

3.9 Summary ................................................................................................................... 54

CHAPTER 4 Data Analysis ............................................................................. 55

4.1 Introduction ............................................................................................................... 55

4.2 Data Collection.......................................................................................................... 55

4.3 Response Rate ........................................................................................................... 55

4.3.1 Response Rate for Pre-Test Survey ................................................................... 55

4.3.2 Response Rate for Questionnaire Survey .......................................................... 56

4.4 Result Analysis of Pre-Test Survey .......................................................................... 56

vii
4.5 Result Analysis of Questionnaire Survey.................................................................. 56

4.5.1 Demographic Information.................................................................................. 57

4.5.2 Findings in Relation to Objective One: Types, Advantages and Disadvantages

of Having Liquidated Damages Clause in Contract to Developer and Contractor .......... 62

4.5.3 Findings in Relation to Objective Two: Application in Enforcing Liquidated

Damages during Pre-Stage and Final Account Negotiation and the Factors Affecting

Liquidated Damages Enforce Due to Delay ..................................................................... 73

4.5.4 Findings in Relation to Objective Three: How the Covid-19 Act Affects the

Enforcement of Liquidated Damages ............................................................................... 75

4.6 Summary of Quantitative Data Analysis ................................................................... 82

CHAPTER 5 CONCLUSION .......................................................................... 83

5.1 Introduction ............................................................................................................... 83

5.2 Research Findings ..................................................................................................... 83

5.2.1 Findings in Relation to Objective One: Types, Advantages and Disadvantages

of Having Liquidated Damages Clause in Contract to Developer and Contractor .......... 83

5.2.2 Findings in Relation to Objective Two: Application in Enforcing Liquidated

Damages during Pre-Stage and Final Account Negotiation and the Factors Affecting

Liquidated Damages Enforce Due to Delay ..................................................................... 84

5.2.3 Findings in Relation to Objective Three: How the Covid-19 Act Affects the

Enforcement of Liquidated Damages ............................................................................... 85

5.2.4 Summary of Research Findings ......................................................................... 86

5.3 Limitation of Study ................................................................................................... 86

5.4 Recommendations of Future Studies......................................................................... 87

viii
5.5 Conclusion................................................................................................................. 87

REFERENCES .................................................................................................. 88

APPENDICES ................................................................................................... 92

Appendix A: Questionnaire.................................................................................................. 92

ix
LIST OF FIGURES

Figure 1.1 Comparison of Time Deviation of Public and Private Project ................................. 1

Figure 1.2 Comparison of Public Sector and Private Sector ..................................................... 2

Figure 3. 1 Research Journey (Kumar, 2010, p.37) ................................................................. 36

Figure 3. 2 Eight Steps Model in Research Process (Kumar, 2010, p.39)............................... 37

Figure 3. 3 Section A Question ................................................................................................ 40

Figure 3. 4 Closed-Ended Question ......................................................................................... 42

Figure 3. 5 Open-Ended Question ........................................................................................... 43

Figure 3. 6 Checklist Question................................................................................................. 43

Figure 3. 7 Research Framework Diagram .............................................................................. 51

Figure 3. 8 Programme Chart for PD I .................................................................................... 52

Figure 3. 9 Programme Chart for PD II ................................................................................... 53

Figure 4. 1 Respondents’ Gender............................................................................................. 57

Figure 4. 2 Respondents’ Highest Education Level................................................................. 58

Figure 4. 3 Respondents’ Type of Firm ................................................................................... 59

Figure 4. 4 Respondent’s Years of Working Experience ........................................................ 61

Figure 4. 5 Preference of Construction Parties on Having liquidated damages Clause in the

Contract .................................................................................................................................... 64

Figure 4. 6 Rate of Liquidated Damages Per Day ................................................................... 69

Figure 4. 7 Reason Choosing Rate of Liquidated Damages Base on Above Question ........... 70

Figure 4. 8 Agreement of Respondents Towards Type of Damages Caused by Delay ........... 73

Figure 4. 9 Entitlement of Developer to Impose Liquidated Damages Due to Lockdown ..... 75

Figure 4. 10 Number of Agreement on Reason Unable to Impose Liquidated Damages ....... 80

x
LIST OF TABLES

Table 1. 1 Research Design of this thesis .................................................................................. 8

Table 2. 1 Direct Cost Incurred under the Contract ................................................................. 25

Table 2. 2 Additional Project Administration Costs ................................................................ 26

Table 2. 3 Interest and Financing Costs ................................................................................... 26

Table 2. 4 Assumption of Liquidated Damages....................................................................... 26

Table 3. 1 Research Design of this thesis ................................................................................ 41

Table 3. 2 Z - table ................................................................................................................... 47

Table 4. 1 Respondents’ Gender .............................................................................................. 57

Table 4. 2 Respondents’ Highest Education Level .................................................................. 58

Table 4. 3 Respondents’ Type of Firm .................................................................................... 59

Table 4. 4 Respondent’s Years of Working Experience .......................................................... 61

Table 4. 5 Frequency and Percentage of whether Paying Liquidated Damages to the Innocent

Parties in Common Scenario.................................................................................................... 62

Table 4. 6 Relationship between Thoughts of Construction Parties on whether Paying

Liquidated Damages is a Common Scenario and the Years of Working Experience ............. 63

Table 4. 7 Preference of Construction Parties on Having Liquidated Damages Clause in the

Contract .................................................................................................................................... 64

Table 4. 8 Preference of Construction Parties on Having Liquidated Damages Clause in

Contract Throughout the Years of Experience ........................................................................ 65

Table 4. 9 Benefits of Having Liquidated Damages in the Contract to the Developer ........... 66

Table 4. 10 Benefits of Having Liquidated Damages in the Contract to the Contractor ......... 67

Table 4. 11 Drawbacks of Having Liquidated Damages in the Contract to the Developer and

Contractor ................................................................................................................................ 68

Table 4. 12 Rate of Liquidated Damages Per Day................................................................... 69

xi
Table 4. 13 Reason Choosing the Rate of Liquidated Damages Base on the Above Question

.................................................................................................................................................. 70

Table 4. 14 Agreement of Respondents Towards Type of Damages Caused by Delay .......... 73

Table 4. 15 Entitlement of Developer to Impose Liquidated Damages Due to Lockdown ..... 75

Table 4. 16 Opinion of Construction Parties on whether Developer Entitled to Impose

Liquidated Damages to Main Contractor ................................................................................. 76

Table 4. 17 Table Respondents’ Responses ............................................................................. 77

Table 4. 18 Agreement on Reason Unable to Impose Liquidated Damages ........................... 80

xii
LIST OF SYMBOL / ABBREVIATION

ADR Alternative Dispute Resolution

CMCO Conditional Movement Control Order

CIDB Construction Industry Development Board

CIPAA Construction Industry Payment and Adjudication Act

CAR Contractor's All Risk Insurance

EOT Extension of Time

LAD Liquidated And Ascertained Damages

LD Liquidated Damages

MCO Movement Control Order

PAM Pertubuhan Arkitek Malaysia

PCIDA Prevention and Control of Infectious Disease Act 1988

PWD Public Works Department

RMCO Recovery Movement Control

SPA Sale And Purchase Agreement

Covid-19 Act Temporary Measures for Reducing the Impact of Coronavirus Disease

COVID-19 Act 2020

RII Relative Important Index

xiii
ABSTRACT

This dissertation was carried out in order to determine the application of Liquidated Damages

clause in a different situation and focus on the types of liquidated damages, advantages and

disadvantages of the construction parties to enforce the Liquidated damages clause in the

Malaysian construction industry.

Paying liquidated damages to innocent parties due to a breach of certain provisions or criteria

in the contract such as the delay of the project is a very common phenomenon in the Malaysian

construction industry. Liquidated damages can be detrimental to a company as the amounts are

very high. Normally if a construction company fails to complete their work on time, they will

need to pay a certain amount of liquidated damages according to the contract but there may be

some liquidated damages that are not enforced or partially enforced which need to depend on

the situation. Basically, the Malaysian scene for liquidated damages is different from foreign

countries as every country has its contract provision. Although the contract has stated the

provision in the Appendix regarding the amount of liquidated damages to be paid due to the

delay of the project yet there may have been a commercial settlement between both companies’

top management. This research provides information on the study of liquidated damages and

focuses on the application and effect of the liquidated damages in the Malaysian Construction

Industry including the benefits and drawbacks of having the Liquidated Damages clause in the

contract, the calculation of preparing the amount of liquidated damages and others. This

research even allows construction parties to have a further understanding of their rights which

they are entitled to recover for compensation, especially during the lockdown which was

imposed by the Malaysian government due to the Covid-19 pandemic. This is owing to the fact

that many of the construction parties especially those senior managements that were early

involved in the construction industry might be unaware of this statement. Furthermore, a

questionnaire has been formed in order to collect the data from the respondents to analyse it.

xiv
All the respondents are from the construction parties which work in Malaysia as the targeted

group. Lastly, it is anticipated that this research will be able to provide the details related to the

liquidated damages and also increase the awareness of construction parties on reading through

all the details in the contract before signing an agreement in order to protect our own priority.

xv
Chapter 1 Introduction

1.1 Research Background

Nowadays, construction is considered one of the most difficult sectors in Malaysia. All

the construction companies are currently competing against each other for a single project

which causes the competition to become even harder as the winner always only has one.

However, bidding a project successfully does not mean that company will earn a profit.

In fact, around 70% of the project failed due to failure of project management, budget

overrun, lack of communication and others (TeamStage, 2022). The management of a

construction business must be meticulously planned and closely monitored because the

success or failure of the business will depend on every single small step.

In the construction sector, there are various kinds of projects, including government and

private projects. To give an example, the Malaysian government had established that

when a project is delayed beyond the agreed-upon completion date by more than one

month or by 10 percent from the planned completion date, the project will be considered

to be a delay by the Malaysian government (Nor Aida, Syuhaida & Faizal, 2019). At this

moment, the Liquidated damages clause is valid and enforceable.

Figure 1.1 Comparison of Time Deviation of Public and Private Project

1
Figure 1.2 Comparison of Public Sector and Private Sector

Figure 1.1 and figure 1.2 show that 20.5% of public sector projects and 33.3% of the

private sector projects were completed within the expected time without delaying the

project. On the other hand, it shows that 79.5% and 66.7% of public sector and private

sector projects respectively were not completed within the expected time (Rohani,

Akintoye & Kelly, 2005). As the saying goes, “Time is gold”. Nevertheless, delaying

projects is a global scenario including Malaysia because there are a lot of unpredictable

things due to the weather, site conditions and others (FU, 2013).

Eventually, constructing a project requires well planning and a good construction

schedule. The importance of a construction schedule is the good planning of the sequence

of work for plant and machinery, acting as a guideline and references for construction

parties to show the milestones of the project. Besides, Architect will use the work

schedule as a guideline to determine when is the contractors need to complete their work

and allow the Employer to recover the amount of liquidated damages when the contractor

fails to comply with the contract unless the delayed activities lie on the critical path of the

project (Lorman, 2018).

2
There are lots of types of the standard form of contract in this construction industry such

as PAM 2018, PWD Form 203A, IEM, CIDB 2000, AIAC and FIDIC forms of contracts.

A standard form of contract is a set of documents, an agreement, provision without

negotiation and in printed form (Faircontracts.org, 2022). It is used to govern the

contractual relations of the contracting parties (Ting, 2013). It is very common to see

liquidated damages as the standard form provision in the construction contract especially

in the Pertubuhan Arkitek Malaysia (PAM) Condition of Contract 2018 (With/Without

Quantities). As a result, commonly a standard form of construction contract is written to

allow both parties to agree on the amount of damages to be paid in the event of late

completion. Using it to prevent contractors breach the contract and compensate when

breaching the contract occurs.

1.2 Problem Statement

Paying liquidated damages to innocent parties due to a breach of certain provisions or

criteria in the contract such as the delay of the project is a very common phenomenon in

the Malaysian construction industry. Liquidated damages can be detrimental to a

company as the amounts are very high. Hence, the contractor should be aware of this and

avoid liquidated damages.

It is undeniable that delaying construction projects is a very common phenomenon in the

construction industry. When the contractor delays in completing the construction project

without granting any extension of time, the Architect shall issue a Certificate of Non-

Completion under PAM Contract 2018 Clause 22.0. The contractor may need to

compensate the innocent parties for their loss. There will be a financial impact on the

construction company. However, many parties still fail to comply with the clause due to

the failure of planning and sequence the work. There will be some criteria needed to be

fulfilled for a liquidated damages clause to be enforceable. Normally if a construction

3
company fails to complete their work on time, they will need to pay a certain amount of

liquidated damages according to the contract but there may be some liquidated damages

that are not enforced or partially enforced which need to depend on the situation. The

cases to be refer such as Selva Kumar Murugiah v Thiagarajah Retnasamy [1995] 1 MLJ

817, Cubic Electronics Sdn Bhd (in liquidation) v Mars Telecommunications Sdn Bhd

[2019] 6 MLJ 15 and Black J in Roberts v Bury Commissioners (HHQ, 2019).

Furthermore, there is a different between LD and LAD and different standard form of

contract using different terms. When there is a liquidated damages clause in the contract

during tender, there may be risks faced by the developer and contractor. In the view of

the contractor, no one knows if there is any delay happening once the project starts yet if

the contractor can foresee that they are not able to complete the project on time, then they

might mark up a higher percentage in the preliminaries in order to cover their loss and

damages in the future as the higher the risk, the higher contractor bid price (Laryea &

Hughes, 2008). Consequently, the client may need to pay more too. On the other hand, if

a contractor is unable to complete the project on time, then they will need to pay a large

number of liquidated damages as compensation to the client.

Apart from that, there are two types of liquidated damages which are liquidated and

unliquidated damages. Both are the amount needed to be paid to the innocent parties due

to the breach of contract but also have some differences too. In fact, the liquidated

damages could bring advantages and disadvantages to the construction parties. Not only

that, sometimes there might be a problem if one of the parties does not agree with the

amount of liquidated damages and both are not in a mutual agreement. Hence, they might

bring the case to the court or CIPAA for dispute resolution.

4
On top of that, the Covid-19 pandemic is a triggering event that meets the Force Majeure

criteria. The contractor able to use this contract provision to exclude its contractual

liability due to the delay is not his default but he needs to prove its causation and ensure

effects. However, there might be some restrictions to the contractor to claim an extension

of time which leads to being required to pay liquidated damages.

1.3 Previous Similar Studies

In 2007, an article titled “Liquidated Damages: A Comparative Study of Law in England,

Australia, New Zealand, and Singapore” by John Twyford was published in the Journal

of Professional Issues in Engineering Education and Practice 133(3). This research aim

was to examine the difference in Liquidated Damages provision in different countries. It

had shown that it was only a little different due to the courts in each jurisdiction having

relied on similar precedents.

In the year 2017, Nurul Iman BT Mustaffar Kamar published “Time at Large: Implication

for Liquidated Damages”. This research aim was to determine whether the circumstances

of “Time at Large” can be accepted to avoid paying liquidated damages when the delay

event occurs. In the result, it shows that the Contractor might utilise “Time at Large” to

avoid the imposition of liquidated damages from the Employer.

Another recent study by Tan Mei Lee in the year 2021, titled “Burden on developers

continues: payment of liquidated damages under Covid-19 Act”, aimed to discuss on

whether developers are able to exempt the right to pay liquidated damages to the

purchaser due to unable to hand over possession during the Covid-19 pandemic. In result,

it shows that the developer shall pay liquidated damages to the purchaser.

5
1.4 Research Aim

This research aim is to study the application of Liquidated Damages clause in a different

situation and focus on the types of liquidated damages, advantages and disadvantages of

the construction parties to enforce the liquidated damages clause in the Malaysian

construction industry.

1.5 Research Question

1) What are the types, benefits and drawbacks of having a Liquidated Damages clause in

a contract to the construction parties?

2) What is the application in enforcing Liquidated Damages during pre-stage and final

account negotiation and the factors affecting liquidated damages enforce due to delay?

3) How does Covid-19 Act affect the enforcement of Liquidated Damages?

1.6 Research Objective

1) To identify the types, advantages and disadvantages of having a Liquidated Damages

clause in a contract to the developer and contractor.

2) To investigate the application in enforcing Liquidated Damages during pre-stage and

final account negotiation and the factors affecting liquidated damages enforce due to

delay.

3) To find out how the Covid-19 Act affects the enforcement of Liquidated Damages.

1.7 Scope and Limitations

1.7.1 Scope

The scope of this research mainly focused on the study of Liquidated Damages in the

Malaysian construction industry. Since the amount of occurrence of contractor pay

liquidated damages are more and more due to failure to comply and breach the contract.

6
However, these issues can be improved once all the related parties are able to manage

well. This research also covered the application of enforcing the Liquidated Damages

clause in different situations. Likewise, the types, benefits and drawbacks of having a

Liquidated Damages clause in a contract to the developer and contractor. Therefore,

everyone should not brush this issue aside. The standard forms of contract and act that

will be referred to in this research are:

1. Pertubuhan Arkitek Malaysia (PAM) Condition of Contract 2018 (With/Without

Quantities)

2. Temporary Measures for Reducing the Impact of Coronavirus Disease (COVID-

19) Act 2020 (COVID-19 Act)

3. Housing Development (Control and Licensing) Regulations 1989

1.7.2 Limitation

1) The target group of respondents will be all the parties that are involved in the

construction industry such as Developers, Consultants, and Contractors that are registered

with the Construction Industry Development Board (CIDB).

2) The questionnaire will be only issued to all the parties involved in the construction

industry to investigate the study of Liquidated Damages.

1.8 Importance of Research

Doing this research is to highlight the preference of construction parties in

enforcing the Liquidated Damages clause and find out the reason that may affect their

preference. The advantages, and disadvantages of the liquidated damages clause in order

to prevent all the parties from leaving this issue aside. It also shows the enforcement of

the liquidated damages clause when meeting the situation of Covid-19 pandemic.

7
1.9 Research Design

Table 1. 1 Research Design of this thesis


Objectives Types of Data Sources of Data Methods of
Required Data
Collection
To identify the types, - Industry preference Primary Data
advantages and Questionnaire
disadvantages of having a - Comparison on among the
Liquidated Damages benefits and Malaysian
clause in a contract to the drawbacks of construction parties
developer and contractor. liquidated damages to
Developers and
Contractor

To investigate the - Agreement on type Quantitative:


application in enforcing of damages caused by Survey
Secondary Data Questionnaire
Liquidated Damages delay Comprehensive
during pre-stage and final literature review on
account negotiation and articles, journals,
the factors affecting reports, internet,
liquidated damages publications from
enforce due to delay. professionals and
others
To find out how the - Established the
Covid-19 Act affects the opinion enforcement
enforcement of of liquidated damages
Liquidated Damages. from the construction
parties

8
1.10 Structure of the Report

This thesis will be structured as follows

Chapter 1 – Introduction

This opening chapter presents the readers with the research background, problem

statement, previous similar studies, research aim, research objective and question, scope

and limitation, significant study and structure of research. The previous similar studies

are intended to assist the researcher in selecting the most appropriate methodology, data

sources, and data analysis methods for own research. However, the purpose of the scope

and limitation is to define the boundaries of the study problem that is to be examined in

more detail

Chapter 2 – Literature Review

The literature review chapter provides sufficient research information relevant to the

study. All the information was obtained from textbooks, articles, research journals and

other online resources. In the literature review, it will further explain comprehensively on

the objective review of the study of Liquidated Damages in Malaysian construction

industry such as the type, advantages and disadvantages of the liquidated damages to the

developer and contractor, the application in enforcing Liquidated Damages during pre-

stage and final account negotiation and the factors affecting liquidated damages enforce

due to delay, some calculation, types of damages due to delay of the project and

enforcement of liquidated damages due to Covid-19 pandemic.

Chapter 3 – Research Methodology

Research methodology is to highlight the research process to be used in this research on

collecting, analysing and interpreting the data information to answer and solve the

research problem for the whole research study.


9
Chapter 4 – Data Analysis

All the data collected from the respondents will be discussed, examined and presented in

this chapter. Besides, carrying out the data analysis will be able to confirm and support

the point that described in the Chapter 2 literature review.

Chapter 5 – Conclusion

This is the final stage of this research. In this stage, it will recap the information described

in this research and also the contribution of findings to the Malaysian construction

industry.

10
Chapter 2 Literature Review

2.1 Introduction

2.1.1 Section 75 Contract Act 1950

One of the most important provisions in the construction contract is the liquidated

damages (LD) clause. All contracts must comply with Contract Act 1950 including

liquidated damages clause. This is because all the contracts including liquidated damages

in Malaysia are governed by Contract Act 1950. Section 75 of the Contract Act of 1950

provides compensation to the injured parties in the breach of contract which the contract

has clearly stated that the damages clause is a penalty. Besides, the courts play an

important role in exercising their supervisory jurisdiction to provide relief from the

oppressive and unconscionable liquidated damages clause.

Section 75 Contract Act 1950 - Compensation for breach of contract where penalty

stipulated for:

75. When a contract has been broken, if a sum is named in the contract as the amount to

be paid in case of such breach, or if the contract contains any other stipulation by way of

penalty, the party complaining of the breach is entitled, whether or not actual damage or

loss is proving to have been caused thereby, to receive from the party who has broken the

contract reasonable compensation not exceeding the amount so named or, as the case

may be, the penalty stipulated for.

11
2.2 Enforceability of Liquidated Damages

There are some cases that show liquidated damages that are not enforced or partially

enforced which need to depend on the situation.

2.2.1 Case Study

2.2.1.1 Malaysia Law

Selva Kumar Murugiah v Thiagarajah Retnasamy [1995] 1 MLJ 817

According to this case, in section 75 of the Contract Act 1950, the plaintiff should prove

to the court his or her actual damages had suffered although the appellant had breached

the contract. The damages suffered must be the actual loss suffered or a reasonable

compensation amount (Haken Arabi & Associates, 2020). According to this situation, it

might infringe contract parties’ autonomy and cause the liquidated damages clause to

become meaningless as the aim of this clause was to protect the innocent parties when

the other parties breach the contract. Hence, there were some construction parties

questioning the effectiveness of the liquidated damages clause in the contract as the Court

was refusing to tolerate and interpret such clauses by the parties to the contract (HHQ,

2019).

Cubic Electronics Sdn Bhd (in liquidation) v Mars Telecommunications Sdn Bhd

[2019] 6 MLJ 15

However, for this case, the court decision stated that the Selva Kumar Murugiah v

Thiagarajah Retnasamy decision was no longer applicable and changed the obligation of

parties in the contract as the plaintiff was no longer needed to prove his or actual loss

instead of letting the appellant proved that the liquidated damages were not enforceable.

This is because in Malaysia there was no difference between liquidated damages and

penalties under English law. (HHQ, 2019). Currently, the plaintiff was entitled to receive

12
reasonable compensation but not exceeding the amount stated in the contract only if meets

two requirements:

1. Able to show the evidence that the appellant has breached the contract

2. State the sum to be paid due to the breach of contract

2.2.1.2 Foreign law

If the amount of anticipated damages has a huge difference from the actual loss suffered,

the court may refuse to enforce the provision because it is a penalty instead of estimated

actual damages (Mathias, 2022). In the common law systems, if the liquidated damages

have been included as a ‘penalty’ for late completion, rather than a genuine pre-estimate

of loss, then the courts will not enforce it. Hence, some cases successfully strike down

the liquidated damages clauses in settlement agreements due to the unreasonable amount

paid for a settlement agreement (Tuckman, 2021). There may have been a commercial

settlement between both companies’ top management.

In order to further illustrate this point, Party A decided to sue Party B for $100,000. After

that, Party B agreed to have a commercial settlement by paying $60,000 in monthly

instalments to avoid a lawsuit. If Party B did not make the full payment, he will need to

pay the full amount of the original claim with the additional lump sum of $20,000

including the interest, attorney’s fees and vice versa (Tuckman, 2021).

Black J in Roberts v Bury Commissioners had stated a principle that “no person can take

advantage of the non-fulfilment of a condition the performance of which had been

hindered by himself”. It is a principle of prevention that states a party cannot take

advantage of their own wrong. Somehow, some of the contractors may use “time at large”

to avoid paying liquidated damages (Kamar, 2017). When the time is at large meaning to

say that there is no workable contract and the contractor will require to complete their

13
work within a reasonable period of time. There will no longer be a fixed date from which

LD can run and therefore the employer will lose his right to claim LD (Beg, 2019).

In PAM Contract 2018 Clause 22 Damages for Non-Completion is stated “Liquidated

Damages” (LD) instead of Liquidated and Ascertained Damages” (LAD) as the damages

is no longer required to be proved and ascertained before being levied (Mimi Yuslinda

Yusof, 2021). This is because the LAD means sum need to be ascertained and agree upon

by the contracting parties (Yeoh, 2021). Below shows different standard form of contract

using different terms of liquidated damages:

Liquidated Damages:

• PAM Contract 2018

• IEM 2017

• CIDB 2000

• AIAC 2019

Liquidated and Ascertained Damages:

• PWD 203A

14
2.3 Types of liquidated damages

2.3.1 Liquidated damages

Liquidated damage is not a financial penalty or punishment, it is a genuine pre-estimate

of loss and damages. It is a fixed sum agreed by both parties in the contract which is stated

in the appendix and is fixed in advance before a breach occurs and used to replace the

right to claim damages measured by the amount of loss suffered. Liquidated damages are

imposed for delays in project completion. By their nature, the delayed activities involved

must rely on the critical path of the project as it is completed (Michael, 2018). It can be

many problems that cause the delay of the project such as some crucial items being

unavailable due to a sourcing issue. Mostly the liquidated damages will be calculated on

a daily or weekly basis.

When the Contractor Administrator (Architect or Client Representative) certifies the

Certificate of Non-Completion, the Employer is entitled to the liquidated damages to

which the total amount will be calculated and anticipated reasonably. The amount will be

paid when one of the parties breaches the contract due to non-performance, late

performance or inadequate performance such as the delay in completing the project on

time under PAM Contract 2018 Clause 22.0, and without the need of the employer to

prove the loss and damages to the contractor.

The employer is entitled to claim liquidated damages as debt, monies due or going to due

to the contractor or performance bond which stated under PAM Contract 2018 Clause

22.1. The place to be deducted by the employer for liquidated damages when it is

insufficient to recovered shall according to the following sequences:

15
1. Interim Payment (Contractor’s payment)

2. Retention Sum

3. Performance Bond

4. Payment from contractor

According to the RICS (2015), it stated that it is not mandatory for developer to deduct

the liquidated damages in interim payment. Developer can deduct from final payment

certificate and clearly stated in the final account statement. Besides, liquidated damages

also can be deducted from agreed final account. This is because the extension of time may

be given after the Certificate of Non-Completion is issued to the contractor as the new

completion date will be issued. Thus, deduction during the final stage helps to prevent

complications. In reality, if contractor notices that the liquidated damages will be

deducted from the final account, then it will surely influence their decision in the final

account negotiations and bargaining posture. Even though PAM Contract 2018 clause

30.11(e) say cannot state in final account, but employer can still deduct separately from

final payment.

2.3.2 Unliquidated damages

Unliquidated damages are damages that will be assessed and proved after the breach

occurs. The amount of damages is determined by a court because the parties to a contract

had not agreed in advance on the amount of damages that would be imposed in the event

of a breach of the contract's terms (Legal Choices, 2022). Besides, it is unforeseeable as

the amount to be paid will be exactly the total amount of loss suffered by the parties. In

this situation, the sum is ‘at large’ and it may need to be determined by the court after the

breach occurred. It allows the parties to recover their losses which are unable to be

anticipated during the tender stage but all the contemporary records and documents are

16
compulsory to be kept as proof in case there is a dispute resolution. In fact, the loss must

not be judged too remote (DesigningBuildings, 2022).

A claim for unliquidated damages under common law is available when the liquidated

damages clause was strike off in the contract or the employer fill ‘NIL’ or ‘n/a’ for the

rate for liquidated damages in the Appendix to the contract to wish not to claim liquidated

damages and have excluded the right to recover the general damages. Therefore, the

parties shall state clearly in the contract about applying the unliquidated damages clause

or delete the liquidated damages clause if they wish to exclude liability for liquidated

damage (DesigningBuildings, 2022).

2.4 Benefits and drawbacks of having a Liquidated Damages clause in a

contract

2.4.1 Developer

2.4.1.1 Benefits

● The benefit of having liquidated damages clause in contract is without the need to

prove actual damages to the contracting parties. According to the case Cubic

Electronics Sdn Bhd (in liquidation) v Mars Telecommunications Sdn Bhd [2019]

6 MLJ 15, the developer can straightforward use the sum agreed by both parties

in the contract without proving his loss to the contractor due to the actual damages

are difficult to calculate and prove. The employer is also not required to go

through the process of bringing a claim under the common law for damages. Not

only that, the amount set by the client can be in any amount that he or she likes

but should be agreed upon by both parties on penalizing the breaching parties

instead of compensating the innocent party (Carney & Felsen, 2022).

17
● Liquidated damages clause helps to save the time and cost of arbitration and

litigation. It also reduces the resources and procedure in dispute resolution as

liquidated damages are beneficial for long-term supply contracts. All the

arguments over the intensive negotiation in any specific breach can be avoided

(Hallellis, 2021).

● Developer can get back his possession on time as the contractor will try his best

to complete the work on time to prevent the project delay and pay the amount of

liquidated damages as compensation. Aside from that, paying liquidated damages

may reduce the profit earned by the contractor. It also benefits the client as it

removes the obligation to prove the loss and damages to other contract parties

(DesigningBuilding, 2021).

● It acts as a type of insurance against the cost of breach by the contractor which

gives protection to the employer from risk.

● Liquidated damages also helps to reduce any unnecessary ambiguity over the

project which saves a lot of time and money to argue on certain matters as the

innocent parties no longer need to prove to other parties their loss and damages.

They will straight away use the amount of liquidated damages as remedies

(Bhumesh, 2017).

2.4.1.2 Disadvantages

● The liquidated damages might not be sufficient to pay for the specific breach as

liquidated damages is estimated and fixed during the tender stage. Damages are

unforeseeable which could be far higher than the recoverable loss experienced by

the party in a damages assessment. Therefore, clients might set a greater amount

of liquidated damages during forming the contract to cover the risk that might face

in the future once the project starts (Hallellis, 2021).

18
● Cost of the project can be affected depending on the rate of liquidated damages

set by the developer. Cost of the project turns out to be very high if the developer

sets the rate of liquidated damages too high. Tower & Baccarini (2008) had stated

some contractors may choose not to tender and lesser tenderers are involved in

the bidding and the developer may only have a few choices in choosing which

contractor to be chosen with the best price. Some of the contractors will choose

not to bid on the project because the risks faced by the contractor are way too

high. On the other hand, if the developer sets the liquidated damages too low, the

contractor may not work according to the schedule effectively and accelerate their

work to complete the work on time. Therefore, although some developers may

still price high the liquidated damages but the market forces can ensure liquidated

damages is set appropriately (Sorbara Law, 2015).

19
2.4.2 Contractor

2.4.2.1 Benefits

● Liquidated damages helps in weighing the cost performance against the cost of a

breach. (Mathias, 2022). The contractor is fully aware of the monetary rights and

liabilities and the amount that the contractor could price for the risk.

● Contractors get to know early from the beginning as much as possible about risks

they bear on the amount to be paid if they fail to complete on time. They will

estimate the amount and find a way to price a certain item at a higher price to

cover that amount. At least they will have a clear mind and confidence in their

financial capability if they breach the date stated in the contract (PropertyGuru,

2021) and limit their liability to a specific amount in the event of delay

(DesigningBuildings, 2021).

● It also provides contractors useful information for analysing their risks and

deciding what steps to take during the construction process. For example, if the

subcontractor knows the information of the contract that the amount of liquidated

damages is RM5000 per day, then they will try their best to accelerate and

complete the project on time without delaying the project to prevent paying the

liquidated damages (Carney & Felsen, 2022).

● Liquidated damages act as a motivator to the contractor so that they will complete

the project on time or within the specified time stated in the contract (SorbaraLaw,

2015). The contractor will try their best endeavour to prevent breaching contract

because it may be robbing company’s profit in the job and sometimes make things

become even worst such as facing financial problems and bankruptcy (Michael,

Ian, Crystal, Sean & Gilda, 2015)

20
2.4.2.2 Disadvantages

● It may bring unfairness to the contractor as some of the clients may set the amount

of liquidated damages way too high and not calculate proportionately. Sometimes

the client will abuse the clause to extract an unreasonable amount that is greater

than the actual loss (Hallellis, 2021).

● It is very time consuming and difficult for the contractor to prove that liquidated

damages is not genuine pre-estimate if the contractor wants to challenge the

calculation of liquidated damages due to the amount of liquidated damages is too

high and unreasonable but employers do not need to prove to the contractor. It is

a tough task that causes contractor work not effectively and efficiently (Mathias,

2022).

2.4.3 Summary

Liquidated damages provide certainty to the parties. It acts as a motivation and reminder

to the contractor in order to complete their work on time. A clear deadline for completing

a construction project with the rate of liquidated damages is important and beneficial to

both developer and contractor. This is due to the fact that developer always wishes to use

the final product as soon as possible so that he can have full enjoyment of the benefits

from his investment. While on the other hand, the contractor may also want to complete

the job as soon as possible but still ensure to make good use of all the resources properly

so that contractor can move on to another project (SorbaraLaw, 2015). Therefore, in order

to solve this problem properly, deciding on damages at the outset allows both parties to

settle on an amount that they think is fair instead of leaving this decision to the courts.

Besides the uncertainty of litigation, it is also time-consuming and costly.

21
2.5 The application in enforcing Liquidated Damages during pre-stage

and final account negotiation and the factors affecting liquidated

damages enforce due to delay

2.5.1 Negotiation

Although there is a provision in the contract stating the breached parties shall pay

liquidated damages and all the rate is being set and agreed upon by both parties at the

early stage in the contract anyhow negotiation of the final account is still required to

protect financial status of both parties. Instructing negotiation is to prevent lengthy

alternative dispute resolution procedures (ADR) such as arbitration, mediation, litigation

and vice versa. The settlement should be carried out professionally, calmly and fairly so

that the discussion can be carried out successfully but quantity surveyors are not entitled

to be involved in the negotiation unless instructed by the employer. Both parties will

clarify their own goals to allow each other to understand and conclude a reasonable

outcome which in this situation we call it as “win - win situation.” All the final decisions

made during the settlement by both parties shall be bound in the contract and written form.

A successful negotiation needs to be in a mutual agreement and depends on the employer's

willingness and kindness (RICS, 2015). However, it is not always amount of liquidated

damages can be agreed by both parties. There might be a few reasons cause both parties

are not in a mutual agreement. One of the reasons that negotiation is unsuccessful is due

to the time for completion and Extension of Time (EOT). There are some disputes

between both parties about the number of days the contractor is entitled to claim EOT.

As we know, liquidated damages will be charged once EOT are not granted and EOT can

be claimed when the contractor fails to delay the project due to others’ default or mother

nature. There are several relevant events stated in the standard form of contract such as

PAM Contract 2018, PWD 203A CIDB and others form. In fact, some unforeseeable

22
relevant events can be claimed but not stated in the standard form of contract. Therefore,

negotiation is required in this situation (Tan, 2020). For example, the weather conditions

are unpredictable and unforeseeable. For this reason, no construction project is free from

problems and when problems are not immediately solved as they arise, they can become

major issues that eventually end up in court or before an arbitrator for resolution.

A breaching parties may attempt to avoid payment for non-completion by attributing the

overrun on the contract programme to the following number of failings by the employer

and consultants such as:

● Employer fail to give possession of site to the contractor within the specified time

● Architect late issue Architect Instruction (AI) to the contractor

● Architect untimely issue variation works to the contractor

● Disruption and disturbance contractor’s work by the employer

● Inequitable extension of time awarded by the Architect to the contractor

However, if the architect fails to grant EOT when delay occurs caused by the employer,

then the contractor can claim for time is at large and there is no longer a completion date.

The contractor can complete his work in a reasonable time. If both parties are unable to

come to a final decision, then both parties will go for dispute resolution to resolve

conflicts. When a project is involved in protracted dispute, it may result in no longer

meeting the original goal and expectation. The employer may suffer from the payment of

high legal fees and delayed completion, which lead to late occupation and affect sales and

result in incur loss of revenue.

23
2.5.2 Calculation of Liquidated Damages

2.5.2.1 Developer to Purchaser

Source: Joseph (2018)

2.5.2.2 Main Contractor to Sub-Contractor

Sub Contract
Sum Rate of Client Charge
= X Main Contractor
Total Contract
Liquidated Damages
Sum

Normally if the total amount is below RM 500, then they will charge RM 500 as the

minimum rate of liquidated damages per day to be charged to the sub-contractor.

However, if it is above RM500, then the rate of liquidated damages per day will follow

that specified calculated amount.

24
** If the calculated amount is less than RM 500, paid amount shall be equal or exceed

RM 500, whichever is higher.

2.5.2.3 Developer to Main Contractor

Preparation an estimate of liquidated damages

Liquidated damages clause is required to be in the contract. Most developers may use the

amount of liquidated damages received from the main contractor to recover his loss of

damages. When the employer is estimating and calculating the liquidated damages, some

costs that need to be considered by the employer.

For example, we are assuming there is a mixed development with the concept that the

total contract sum (RM 800,000,000) has been divided proportionally to the Block A

(hotel), Block B (service apartment), Block C (commercial shop lot) and 3-storey podium

car park with the percentage ratio of 51%, 33%, 9% and 7% respectively. The assumption

or conception for liquidated damages per day is calculated on a 30 days' basis. The criteria

and calculation of Liquidated Damages that can claim by all types of buildings are listed

below (Malconlaw, 2012):

Table 2. 1 Direct Cost Incurred under the Contract

Description Cost per month Cost per day


Extra Wages of Workers (Internal Employee such RM 180,000.00 RM 6,000.00
as Manager, Clerk and Site staff and others)

Transportation Fee RM 12,000.00 RM 400.00

Rental of Developer Office RM 60,000.00 RM 2,000.00


TOTAL (RM) RM 252,000.00 RM 8,400.00

25
Table 2. 2 Additional Project Administration Costs
Description Professional Fee per month Professional Fee per
day
Project Manager RM 18,000.00 RM 600.00
Architects RM 20,000.00 RM 667.00
Engineers RM 18,000.00 RM 600.00
Clerk of Work RM 10,000.00 RM 334.00
TOTAL (RM) RM 66,000.00 RM 2,201.00

Table 2. 3 Interest and Financing Costs


Description Interest per month Interest per day
Interest of Construction Loan RM 1,300,000,00.00 x interest rate 8% RM 28,888.00

= RM 10,400,000.00 per annum

RM 10,400,000.00/12 months

= RM 866,667.00 per month

TOTAL (RM) RM 866,667.00 RM 28,888.00

Table 2. 4 Assumption of Liquidated Damages


Liquidated Hotel Service Apartment Commercial Shop
Damage Lot
1. Direct costs RM 8,400.00 x RM 8,400 x 33% RM 8,400 x 9%
incurred under the 51% =RM2,772.00 =RM756.00
contract =RM4,284.00
2. Lost revenue and Assume 10 No assumption of cost. No assumption of
profit rooms / floor, cost.
RM250/room/ni
ght, 70% hotel
occupancy rate,
30% net profit
margin, Hence,
(10 rooms x 28
stories) x
RM250 x 70% x
30% =
RM14,700.00
3. Additional project RM 2,201.00 x RM 2,201.00 x 33% RM 2,201.00 x 9%
administration costs 51% =RM726.33 =RM198.09
=RM1,122.51

26
4. Damages and No assumption No assumption of cost. No assumption of
penalties to which of cost. cost.
they may be liable
5. Interest and RM 28,888 x RM 28,888 x 33% RM 28,888 x 9%
financing costs 51% =RM9,533.04 =RM2599.92
=RM14,732.88

6. Cost implications No third party Assume there are 20 Assume there are 16
to third-party involved. units in each floor, units in each floor,
contract RM750,000.00/unit, RM 900,000.00 per
85% sold, 10% of unit, 75% sold, 10%
purchase price for late of purchase price for
delivery of property, 2% late delivery of
of purchase price for property
late delivery of common
property Expected
Compensation to the
Expected purchaser of Shop
Compensation to the Lot:
purchaser:
(16 units x 5 stories) x
(a) Building RM 900,000 x 75% x
10% / 365days
(20 units x 18 stories) x
RM 750,000 x 85% x = RM14,794.52
10% / 365days
= RM 62,876.71
(b) Common
Property
(20 units x 18 stories) x
RM 750,000 x 85% x
2% / 365days
= RM 12,575.34
Total Cost per day =
RM62,876.71
+ RM12,575.34 =
RM75,452.05
7. Losses for tax or Assume: Daily No tax and incentives. No tax and incentives.
investment income=RM
incentives 50,000
Incentives= 10%

27
Hence, RM
50,000 x 10%
=RM5,000
Total: RM 39,839.39 RM 88,483.42 RM 18,348.53

2.5.3 Type of damages caused by delay

The delaying of the project may bring lots of loss and damages to the developer and

contractor. According to Malconlaw (2012) and ACPG (2019), there are several types of

damages caused by delay:

a) Indirect cost

It is a cost which are required to be used to support the work in the site such as:

- Rental expenses

● The land may belong to the developer and the developer is just rent the land from

the landowner. When the contract ends, the developer may need to negotiate with

the landowner on renting the land for the further few months. However, the

expenses may be more expensive than previous.

● Site vehicles, site office rental

-Insurance

● Insurance needs to be extended such as Contractor’s All Risk (CAR), Erection All

Risk (EAR), Workmen Compensation, Employees’ Social Security Scheme,

Public Liability Policy and others.

- Salaries and Wages

● Site office staff, Sub-contractor and general workers

28
- Utilities

● Site office utilities and telephones

● Utilities such as electricity, water supply and sewer usage

b) Direct costs incurred under the Contract

c) Lost revenue and profits

● Daily operating profit

d)Additional project administration costs

● Quantity surveyor need to do extra work and a longer period of time to close the

account.

e) Damages and penalties to which they may be liable from the Local Authority

f) Interest and financing costs

● Bridging loan from bank

g) Cost implications to third-party contracts

● The developer fails to hand the commercial building to the third party due to the

contractor default on delaying the project and it causes the developer to breach

the third-party contract and liquidated damages is required to pay.

● For example, based on the sell then built form, numerous purchasers have been

purchasing the residential property and the date for handed over property has been

set, if the contractor delays in progress, the developer would likely delay handing

over the property as well.

● This scenario may bring a big effect to the third party as they are unable to operate

their business on time and lose the chance to earn profit.

29
h) Losses for tax or investment incentives

i) Others

● Inspection fees for the project

● Cost for ongoing design services

● Cost for maintaining current facilities

● Cost for additional storage

● Additional relocation cost

● Inflation cost

● Idling of labour and equipment

● Additional material storage

2.6 Enforcement of Liquidated Damages due to Covid-19 Pandemic

During the lockdown, everyone was unable to go out to work and unable to perform their

obligation. The Temporary Measures for Reducing the Impact of Coronavirus Disease

(COVID-19) Act 2020 can be used to reduce the unforeseeable and unprecedented impact

caused by the Covid-19 pandemic such as lack of manpower and supply chain disruptions.

This act is used to protect parties or businesses which are unable to perform their

obligations due to the Covid-19 pandemic. It will give some time to both parties to

negotiate and proceed with their work. This act will be enforced for two years starting

from 23rd October 2020 or until the Prime Minister gives another order for extension

(Tan, 2020).

2.6.1 Relationship Between the Developer and Main Contractor

Construction operations frequently comprise actions that are sequential, corresponding

and interrelated to determine which activity falls within or outside of the relief in Section

7 of the Covid-19 Act because it may not always be approved in a construction contract.

30
There is only limited protection due to the requirement of inability to comply is

attributable to the measures prescribed by the authority under PCID Act to control the

spread of Covid-19. The provision under the PCID Act may apply during the MCO,

CMCO and RMCO.

For example, a project is unable to construct completely the basement level due to the

government imposing the MCO which caused delaying the further work of the project.

Level 1 is unable to commence and construct as the basement level is not completed yet.

In this situation Extension of Time is granted to the contractor due to consideration of the

“inability to perform” under Section 7 of Covid-19 Act. However, Section 7 of Covid-19

Act does not protect the relevant event in the work programme which is not affected by

the critical path. Starting from 29th March 2020 onwards, the exemption will be given to

the critical path events only such as cleaning and removing stagnant water and insecticide

spraying at building sites to prevent the spawning of Aedes mosquitoes and other pests,

and other tasks that may put people in danger (Tan, 2020).

According to the standard form of contract like PAM Contract 2018, there is also force

majeure clause but inside only states limited relevant events that can be claimed by the

contractor. Section 7 Covid-19 Act does not contain any force majeure events but it would

not invalidate the relevant event in the standard form of contract. Furthermore, it even

covers others those events which are not stated under the force majeure clause (Tan, 2020).

Moreover, the Covid-19 Act covers any contract cancellation, loss of performance bond,

or damages obtained before the Covid-19 Act's enforcement on 23rd October 2020. This

has been criticised since it jeopardises the contracting parties' interests, which are really

harmed by the PCID Act's provisions before the Covid-19 Act takes effect. Section 10 of

the Covid-19 Act would have worked as a catalyst for non-defaulting parties to file legal

31
actions before the Covid-19 Act's enactment. Furthermore, it encourages parties to pursue

their contractual rights before the enforcement date because such measures will be

recognized as valid (Tan, 2020).

However, the provisions under Covid-19 Act do not help much to the contractor and

subcontractor. For instance, the contractor is unable to suspend or terminate the contract

between the employer. They may face financial problems due to the employer fail to make

payment and the contractor forced to complete the work without being paid. Moreover,

the provision of Covid-19 Act does not protect contractors from enforcing liquidated

damages by the employer as a result of the delay caused by the PCID Act's provisions

(Tan, 2020).

Thus, when the contractor is entitled to claim extension of time due to the Covid-19

pandemic causes the contractor delay in completing the project and without Certificate of

Non-Completion required to be issued by the Architect. This shows that contractor will

no longer need to compensate the amount of liquidated damages to the employer due to

there being extra time given and a new completion date will be fixed by the Architect

under PAM Contract 2018 Clause 22.3.

Nevertheless, the contractor needs to notify the Architect of events causing delayed.

When it becomes reasonably apparent that the progress of works is likely to be delay

beyond the Completion Date, the Contractor shall submit a notice to the Architect on his

intention to claim for extension of time not later than 28 days and state the event to claim

with all the details and documents under PAM Contract 2018 Clause 23.1(a). All the

detail and contemporary records shall be kept properly and given one set to the Architect.

All the records are very important and useful for when disputes happen (Yasmin,2022).

The notice also needs to state the estimate of extension of time required. According to

32
PAM Contract 2018 Clause 23.1(b), if the contractor fails to submit notice within 28 days,

the contractor waived his right to claim extension of time where the contractor still needs

to comply with Architect’s Instruction (AI) to cure any default of the contractor himself.

As a result, this may turn out to be that the contractor shall pay liquidated damages to the

employer.

2.6.2 Relationship between Developer and Purchaser

According to the relationship between the developer and purchaser, liquidated damages

is essential due to the Covid-19 pandemic as the developers were unable to deliver the

key to the purchaser. The different schedules signed by the purchaser will have different

duration times in delivering the key. The Sales and Purchase Agreement (SPA) under

Schedule G and H is a contract for the purchase of new uncompleted properties while

Schedule I and J is a contract to purchase completed properties. It is an important

instrument that will protect the buyer by ensuring the housing developer cannot change

the terms and conditions to their benefit whichever they like.

However, the modification of Housing Development Act 1966 will be effective on 18th

March 2020. Hence, those agreements that sign before 18th March 2020 will be covered

while for the other type of sales and purchase agreement such as commercial properties

are not entitled for modification (Tan, 2020).

Schedule G is for the sale and purchase of landed property which is delivered in a ‘sell

then build’ concept. In Clause 23(1) of the SPA, the time for delivery of vacant possession

is 24 months for landed buildings. The property units under the category are sold under

individual titles which will be issued to the homebuyers.

In Clause 25 of the SPA, Schedule H is for strata properties and in the ‘sell then build’

concept. It is even more complicated than the Schedule G as it includes ownership of

33
common properties and owners’ rights. It is a high-rise building in which its parcel is

subdivided from a piece of land such as service apartment, condominium, flats and others.

Once the buyer owns the strata title, he or she will have the right of ownership to the

specific unit and a parking space but the land is still belonging to the developer. The time

for delivery of vacant possession is 36 months for high rise buildings. The developer also

can apply for an application for extending the delivery time period from 36 to 48 months.

If the developer fails to deliver vacant possession on time, liquidated damages will be

charged and paid to the buyer. According to the Clause 22(2) of the SPA, liquidated

damages is a late payment charge which calculated from day to day at the rate of ten per

centum (10%) per annum of purchase price from the expiry of the period until the date

the purchaser takes vacant possession of the said property.

For example:

[(Purchase Price x 10%) x 365 days] x number of date has delay

To quote an example, a developer shall deliver the vacant possession of property to the

buyer on 18th February 2020 but he passes the key on 26th November. However, the

Malaysian Government has announced a partial lockdown from 18 March to 31st March

2020. After that, the government further extended 4 times from 14th April to 9th June 2020

(the exemption period), enforced under Prevention and Control of Infectious Disease Act

1988 (“PCIDA”). Although the buyer and developer have the agreement on the liquidated

damages, the judge disallowed liquidated damages during the exemption period from 18th

March to 31th August 2020 (Md Saad, & Yaacob, 2022) by examining the Section 32 and

35 of Covid-19 Act (Tan, 2021).

There are also some exceptions under Section 37 of Covid-19 Act. Any legal proceedings

commenced, or any judgement or award obtained to recover late payment charges payable

34
by the purchaser, liquidated damages payable by the developer, or any other sum between

18th March 2020 and the date of publication of this Act shall be unaffected by the

modifications in sections 34, 35, and 36. The Section 37(1) is a saving clause for the

buyers who did not realise the Section 35. Hence, the developer is unable to use Covid-

19 Act to relieve their obligation of paying liquidated damages due to the exemption date

to the buyer for the late delivery of vacant possession. It is only limited to the Part II of

Covid-19 Act which is “Inability to perform contractual obligations” (Tan, 2021).

However, the developer can submit an application to the minister of urban wellbeing,

housing and local authority to extend the time for delivery of vacant possession. The

decision is based on the case Bludream City Development Sdn Bhd v Kong Thye & Ors

and other appeals [2022] MLJU 74 (Tan, 2021). According to this case, the judgement of

the court grants a second extension of time of 17 months for the developer to complete

the service apartment as the developer does not try to take advantage to delay vacant

possession. The delay is caused by the Stop Work Order (SWO) which was imposed by

the minister instead of developer default (Annabel, 2022).

2.7 Conclusion

In conclusion, construction parties are allowing to be exempt in paying liquidated

damages due to the Covid-19 pandemic, but it is only entitled for those parties who meet

the provisions stated by the government.

35
Chapter 3 Research Methodology

3.1 Introduction

This chapter will cover research methods. The research methodology should achieve the

research aims. It also collects, analyses, and interprets data to answer questions. This

chapter will also cover the research process, data collection method, research sample, and

data analysis methodologies for this study. In short, research methodology describes how

we take an idea and turn it into a study that produces an accurate and reliable finding that

meet your research's objectives. To get the desired response, we must also ask

ourselves why, how, and what. Additionally, research samples are chosen depending on

data from the construction parties.

Figure 3. 1 Research Journey (Kumar, 2010, p.37)

36
3.2 Research process

Figure 3. 2 Eight Steps Model in Research Process (Kumar, 2010, p.39)


The research process outlines the entire research process.

The Kumar (2010, p.36) stated that there are eight steps in carrying out research. The

steps include:

a) Formulating a research problem

b) Conceptualising a research design

c) Constructing an instrument for data collection

d) Selecting a sample

e) Writing a research proposal

f) Collecting data

g) Processing data

h) Writing a research report

37
3.3 Techniques for Data Collection

In order to get the correctness and validity of the data, two stages of data collecting,

namely primary and secondary data. Secondary research has been obtained since the

researcher introduced secondary data analysis 50 years ago, in which previously obtained

qualitative and quantitative data are extracted to gain useful information about the study's

scope (Andrews, et.al. 2012). Data collection techniques allow us to collect data

systematically. There are two types of major approaches to information gathering which

are primary and secondary data.

3.3.1 Secondary Data Collection

On the other hand, secondary data is the information that is already being collected and

analysed by others. It is also taken and used by other researchers and we can directly

extract the data that is needed for our own research only. This data can be obtained from

articles, journals, reports, publications from professionals and others. It saves cost, time

and effort than conducting the primary data. Similarly, the data is taken from the writings

of the top scholars in the globe (Roy Rabindra, Saha & Roy, 2013). The secondary data

that was gathered has been reviewed before by others.

3.3.2 Primary Data Collection

Primary data collection method is used when you are planning to collect data by your

own specifically for that particular study. Meanwhile, primary research is essential in

conducting this study since the uniqueness of the data acquired is high, but it must be

relevant to the study's scope. Through this method, the researcher is able to confirm all

the data collected are in the standards of quality, availability and statistical power (The

World Bank, 2022). Large amounts of data are obtained by quantitative research methods

in the aforementioned primary research approach which is using questionnaire surveys.

However, collecting this data may be time consuming, expensive and complicated

38
compared with the secondary data such as case study, observation and questionnaire

survey (Kumar, 2011).

3.4 Development of Research Instrument

The research instrument to be used in this research is referring to questionnaire form.

Most of the content will be focused on the literature review as a basis. The questionnaire

is created through Google Forms and will be distributed to the targeted respondents

through electronic communication like email. The survey will be divided into four

sections which include Section A, B, C, and D. The three objectives are addressed in part

B, C, and D. The questionnaire survey form will be included in the appendices.

3.4.1 Questionnaire Design

Questionnaire survey is a data collection technique that is commonly used by most of the

researchers. Questionnaire is not suitable for collecting information related sensitive topic

such as sexual or illegal activities. It is a commonly used descriptive and analytical survey

to find out answers on asking the 5W and 1H questions including which, what, who,

where, when and how. Mostly the questionnaire will ask ‘closed-ended’ questions such

as ‘yes’ or ‘no’ or giving the ranking from 1 to 5. There will be a list of questions to be

asked from a huge number of respondents. Using this technique is to save cost and time

but the question cannot be too difficult to answer. Normally people would not talk too

much about their privacy and put them at risk.

Besides, the questions shall be formed carefully and clearly without any mistakes. A

questionnaire survey is only useful if the respondents are able to understand the

information and are capable of answering the questions. Respondents must have the

information and ability to answer questions that are relevant to them. Children are

typically excluded from surveys because they lack the information needed to respond to

39
the questions, the issues under research are often irrelevant to them, and young children

may lack the cognitive ability to respond to complex questions (Preston, 2019).

3.4.1.1 Section A

Section A is made up of six questions. Closed-ended questions are commonly used in

Section A that are based on the respondent profile, such as the participant's gender,

educational level, years of experience, and working firm. Only a few of the questions in

this section. The demographics of the respondents will be obtained through the questions

in this section. This section contains five questions, some of which have only two options,

while the others have multiple choices. Respondents were simply asked to check a box

next to the answer that they preferred. Here's an example of a question that was asked:

Figure 3. 3 Section A Question


3.4.1.2 Section B

Section B is regarding to objective 1, which is the type, advantages and disadvantages of

having a Liquidated Damages clause in a contract to the developer and contractor. In this

section of survey, respondents are asked to choose which statement that they agree on the

advantages and disadvantages of the liquidated damages to the specific construction

parties. Besides, the survey will ask about the preference of companies having liquidated

damages in the contract while signing during the tender stage because as we know that

there is some difference between liquidated, unliquidated damages and so forth.

40
3.4.1.3 Section C

Apart from that, Section C is relating to the objective 2 which is the application in

enforcing Liquidated Damages during pre-stage and final account negotiation and the

factors affecting liquidated damages enforce due to delay. In this section will find out the

detailed information which related to the enforcing liquidated damages during the pre-

stage and final account negotiation. There are certain things that need to be considered by

the employer while estimating the rate of liquidated damages in order to be able to recover

back the loss once damages happen in the future. Therefore, from this survey it discussed

the type of damages occur which caused by delay to the developer and contractor.

3.4.1.4 Section D

In section D, it will be related to the enforcement of liquidated damages due to the Covid-

19 pandemic. As we know, the government had regulated a new act called as Temporary

Measures for Reducing the Impact of Coronavirus Disease (COVID-19) Act 2020 in

order to reduce the impact caused by the Covid-19 pandemic.

Table 3. 1 Research Design of this thesis


Questionnaire Objective Description
Section B Objective 1 To identify the types, advantages, and disadvantages of
having a Liquidated Damages clause in a contract to the
developer and contractor.

Section C Objective 2 To investigate the application in enforcing Liquidated


Damages during pre-stage and final account negotiation and
the factors affecting liquidated damages enforce due to
delay.
Section D Objective 3 To investigate the enforcement of liquidated damages under
Covid-19 pandemic.

41
3.4.2 Type of Questions

3.4.2.1 Closed and Open - Ended Question

In an open-ended question, there is no answer given to the respondents. The respondents

are required to write down answers by their own words. Hence, all the answers given by

respondents most slightly would not be the same.

On the other hand, answers will be provided in the questionnaire for the closed-ended

question. Respondents just have to choose the best answer according to the questionnaire.

However, if the both answers given are not respondents choice, then respondents are

allowed to write down their choices in the ‘Other/please explain’ category.

For this research, there will be part of the question and demographic information used in

closed-ended questions. The targeted group of respondents will be construction parties,

so closed-ended questions suit them because most of the construction parties are busy and

have insufficient time to entertain us in doing research. Therefore, respondents just need

to tick their answer between the specific answer given by the researcher. Below are

closed-ended question and open-ended question as shown in Figure 3.3 and Figure 3.4.

Figure 3. 4 Closed-Ended Question

42
Figure 3. 5 Open-Ended Question

3.4.2.2 Checklist Question

A checklist question is essentially a list of items designed specifically for a group of

respondents who have accurate information and can answer it with a high degree of

certainty (Naoum ed. 2007). To achieve the first goal of this research study, checklist

questions will be used. A checklist question is formed by designing various defects for

various components. The checklist question requires respondents to tick. The following

is an example of a checklist question from Figure 3.5.

Figure 3. 6 Checklist Question

43
3.4.2.3 Likert Scale

The Likert scale is also known as summated rating scale. It is given the respondent some

statement and required the respondents to give a rating in ranking order to show their

preference, priorities and importance (Naoum ed. 2007). The likert scale can be in

different forms such as five-point categorical scale or seven-point numerical scale. From

this research study, 5-point likert scale will be used in section B to achieve Objective 2

which is to investigate the advantages and disadvantages of liquidated damages clause in

the contract to the construction parties. Respondents can express their preference by

giving a tick to that specific statement on strongly disagree to strongly agree. There are

several choices to be choose such as:

• 1 = Strongly Disagree

● 2 = Disagree

● 3 = Neutral

● 4 = Agree

● 5 = Strongly Agree

3.5 Pre-testing Research Instrument

After a research instrument is constructed, a testing research instrument is a must before

using it to carry out an interview or questionnaire in order to obtain the actual data

collection (Kumar, 2010). It is an essential step as it helps in increasing validity and

reliability of the testimonial survey evidence. Pre-testing ensures that respondents

perceive and respond to questions according to the research plan. Pre-testing will allow

us to see if responders comprehend the questions, as well as if they are capable of

performing the tasks or possessing the information needed to answer them. For most items,

pre-tests also provide the most direct proof of the validity of the questionnaire data (GAO,

44
2009). Not only that, pre-testing is able to reduce the sample errors while at the same time

increasing the rate of response. However, the purpose of doing pre-test is to identify

problems instead of just collecting data. In order to identify whether the question can be

understood by the respondent, the appropriateness of its communication. If there are

problems met during the pre-test, rephrasing the wording to make it clearer and easy to

understand (Kumar,2010).

3.6 Sampling Method

Sampling is a process of selecting a few samples from a big group so that information is

able to be obtained to answer research questions. This method is able to help in reducing

the time consumed, cost and manpower in the research process. There are several types

of sampling such as:

• Random sampling

- It is also called as probability sampling. It increases the study's validity

because each element in the sample was chosen at random, without any bias or

personal preferences.

• Non-random sampling

- It also calls as non-probability sampling design as it is not taken according to the

probability instead of asking for the permission and if they willing to do so then

only take observations or interviews such as quota sampling, judgemental

sampling, snowball sampling and others (ReadingCraze, 2014).

For this research, simple random is used. This is to ensure that each of the population

has the equal chance to be picked.

45
3.6.1 Population

A population is a group of people or things that are the focus to carry out research. A

population is also defined as a well-defined group of individuals or objects with similar

characteristics. In this research the population are construction parties. Main focus will

be the developer and contractor. Developer is a client and also known as paymaster which

involves payment directly. Contractor is act as a ‘worker’ who is required to comply with

his obligation by providing services to complete the project which is employed by the

developer. The questionnaire will mainly focus on them. The contractors which involve

shall be registered with the Construction Industry Development Board (CIDB). The

population for this study concentrates on people in Malaysia.

3.6.2 Sample

Furthermore, the questionnaire survey form will be sampled using a simple random

sampling method as every member in the population will have a fairly equal chance to be

selected (McCombes, 2020). This is because the respondents for this research paper may

come from a variety of firms or companies. As a result, the random sampling method will

be the most efficient way to distribute the questionnaire survey form. In addition, the

majority of the questionnaire survey form will be e-mail to the respondents because

respondents may not have enough time for a face-to-face interview, it will be more

efficient. All the respondents shall be the parties which are involved in the construction

industry. The Cochran’s formula is mostly used for large populations. Below is the

Cochran’s formula for sample size (Stephanie Gan, 2022):

46
Where:

• e = desired level of precision

• p = (estimated) proportion of the population which has the attribute in question

• q=1–p

• Z = Z-score to determine the confidence level

Table 3. 2 Z - table

The formula assumes to find 95% confidence level with ±5% precision. The proportion

of 50% gives maximum level of variability in population. Hence, p=0.5.

Calculation:

Form calculation we know that sample size is found to be 384 respondents from the

population of 1875 respondents. However, if the sampling fraction exceed 5%, finite

population correction (FPC) has to be made (Cochran, 1977).

47
The sampling fraction is 20.5%. Therefore, the modification for the sample size is

required by using equation below:

Where

• n₀ = Corrected sample size

• N = sample size

• N = population size

Calculation:

In conclusion, the sample size required in this research is 319 respondents. The sample

size used can be used for any size of target population (as long as the sampling fraction

does not exceed 5%) and the yield is accurate.

3.7 Technique for Data Analysis

Data analysis can be defined as a systematic procedure for defining, evaluating, analysing,

and transforming data using statistical and intellectual skills. After the respondents' data

48
has been collected, the data will be analysing through the Excel. The data analysis will

be provided in the form of a graphs, and pie chart, all of it will make the data analysis

clearer and understandable.

3.7.1 Univariate Analysis

The descriptive statistical approach will be used on Section A of the questionnaire to

analyse demographic background of respondents. Some of the questions in Section B and

D also applies it too. According to Naoum (2012), descriptive statistics is the simplest

technique of data analysis. It offers a broad overview of the results by summarising the

data collection, which can be a reflection of the full population or a sample of it. It will

be evaluated using central tendency and interpreted in the form of a pie chart, bar chart,

or table. The central measure is made up of three key estimates which include mean and

standard deviation.

3.7.2 Relative Importance Index (RII)

In Section B, there is 3 questions will be requiring to use this formula to obtain the relative

satisfaction rating on the criteria shown in Section B. The rating scale is in five-point

categorical scale. The method of calculating RII is shown below:

Where

W = weights given to each factor by respondents

N = total number of respondents

A = highest weight (5)

49
3.8 Research Model / Conceptual Framework

This research is to establish the relationship between the Covid-19 Act and the application

of Liquidated Damages. This is done by first establishing the current state of liquidated

damages to the construction parties, rate of liquidated damages and reason chosen.

Comparison between opinion and years of working experience of respondents is done for

several question. The agreement on advantage and disadvantage of having liquidated

damages to the developer and contractor are rated. Then, the type of damages caused by

delay are selected. The entitlement of liquidated damages impose to main contractor and

reason are chosen according to their experience, thus lead to the result of this study. Refer

to Figure 3.7 for the research framework diagram.

50
Establish the relationship between COVID-19

and the application of Liquidated Damages

between Developer and Contractor

Usage of Frequency Usage of Preference Usage of RII

Comparison between Identify and justify Rate relative importance

the opinion and years the rate of LD per day of selection benefits of

of working experience and reason chosen having LD in contract to

the Developer

Identify the current


Rate relative importance
Justify type of damages
status of LD in the
of benefits of having LD
caused by delay to the
construction industry
in the contract to the
Developer and Contractor
Contractor

Entitlement Developer Justify the reason Rate relative importance


impose LD due to unable impose LD of drawbacks of having
lockdown
LD in the contract to the

Developer and Contractor

Figure 3. 7 Research Framework Diagram

51
Figure 3. 8 Programme Chart for PD I

52
Figure 3. 9 Programme Chart for PD II
53
3.9 Summary

In this chapter is to describe the way of research to be conducted. It concluded that

research methodology is very important as it helps us in resolving problems with a better

solution. Methodology clarifies the research inquiry and why it is necessary. It clarifies

the research's beginning stage, the research's bearings, and the potential ramifications of

the research when it is completed. Therefore, methodology is one of the crucial steps

which is required to be carried out in the research progress.

54
CHAPTER 4 Data Analysis

4.1 Introduction

This chapter is to explains data collection and analysed data collected in this research

according to the format presented in the questionnaire, which referring to the content

arrangement in Chapter 2.

4.2 Data Collection

All the data in questionnaire survey which received from the respondent will be analyse

in this chapter. There are 5 sections require to be analyses and there are some questions

are set as ‘required question’. It is a function in the Google Form to ensure respondents

answer specific question before proceed to others. This is to prevalent 100% valid cases

and 0% missing data happen. Section 4.2 will be elaborate on the result of respondent rate

of the questionnaire survey, followed by Section 4.3 shows the outcome result analysis

and findings of the questionnaire survey. The last section will be Section 4.4. It will

summarize the overall conclusion on the analysis of the actual respondents’ data analysis.

4.3 Response Rate

4.3.1 Response Rate for Pre-Test Survey

On 1st June 2022, 30 sets of pre-test questionnaires were distributed to relatives, friends,

and the general public via invitations sent through LinkedIn, WhatsApp, and email prior

to the distribution of the questionnaire to respondents. Fortunately, the response rate for

the pre-test survey was a perfect 100%, as all respondents did their best to participate. All

respondents for the pre-test survey must be at least 24 years old to ensure they can notice

any questionnaire inaccuracies. The survey spanned nearly one month, beginning on

1st June 2022 and ending on 29th June 2022.

55
4.3.2 Response Rate for Questionnaire Survey

A total of 319 sets of questionnaires were sent through email to the construction parties,

with a total of 114 responses received. The response rate was calculated at 35.7%. The

questionnaire survey was started at 30th June 2022 and cut-off on 03rd August 2022.

4.4 Result Analysis of Pre-Test Survey

Respondents’ Feedback for Pre-Test Survey

Feedback 1:

Feedback 2:

After pre-test by the respondents, it was found out that there were a few inappropriate

wordings in the instructions of Section D, which confuse the responders to answer the

question. However, after amendment of the Section D’s instruction, there shall be good

enough.

4.5 Result Analysis of Questionnaire Survey

Data collected from the questionnaire survey is detailed and analysed in section according

to the format presented in questionnaire. The below data are analysed through frequency,

Relative importance index (RII) and mean. The higher the RII value, the higher the mean

56
value. Some of the question will use RII to analyses the level of significant and rank of

the factors and with the support.

4.5.1 Demographic Information

The backgrounds of respondents are sorted and presented in the form of frequency tables.

The analysed information includes the respondents’ gender, highest education level, type

of firm and years of working experience in the construction industry.

Table 4. 1 Respondents’ Gender

Gender Male Female Total

Frequency 74 40 114
Percent 64.9 35.1 100.0
Cumulative Percent 64.9 100.0

Figure 4. 1 Respondents’ Gender


Table 4.1 reveals that 64.9 percent of the respondents are male, whereas only 35.1 percent

of the respondents are female.

57
Table 4. 2 Respondents’ Highest Education Level

Bachelor
Highest Education Level SPM Diploma Master Total
Degree

Frequency 2 11 93 8 114

Percent 1.8 9.6 81.6 7.0 100.0

Cumulative Percent 1.8 11.4 93.0 100.0

Figure 4. 2 Respondents’ Highest Education Level


Table 4.2 shows that 81.6% of the respondents are Bachelor Degree holders, followed by

9.6% of Diploma holders and 7.0% of Master holders, while just 1.8 percent of

respondents are SPM holders. According to the finding shows that there is no any

respondent are from the STPM and Doctor of Philosophy (PhD) holder.

58
Table 4. 3 Respondents’ Type of Firm

Type of Firm Frequency Percentage ( % )

Developer 15 13.16
Contractor 44 38.60
Engineer 3 2.63
Quantity Surveyor 46 40.35
Supplier 1 0.88
Architect Engineer 1 0.88
Telecommunications 1 0.88
Interior Designer 1 0.88
Student 1 0.88
Government 1 0.88
Total 114 100.00

Frequency

Developer
13.2%
Contractor
0.9%
0.9%
0.9%
0.9%
0.9%
0.9% Engineer
Quantity Surveyor
Supplier

40.4% Architect Engineer


Telecommunications
38.6%
Interior Designer

2.6% Student
Government

Figure 4. 3 Respondents’ Type of Firm

59
According to the data presented in table 4.3, the vast majority of respondents are

employed in the capacity of quantity surveyor, with 46 out of 114 respondents

representing a percentage of 40.4%. This is followed by those who are employed in the

capacities of contractor, developer, and engineer, with 44 out of 114 respondents

representing 38.6%, 15 out of 114 respondents representing 13.2%, and 3 out of 114

respondents representing 2.6% respectively.

Nevertheless, there is only one respondent for the government, the student, the architect

engineer, the telecommunications, the interior designer, and the supplier as well. On the

other hand, it was discovered that this finding does not contain any architects who

responded to the survey.

60
Table 4. 4 Respondent’s Years of Working Experience

Years Frequency Percentage (%)


Less than 5 years 94 82.46
5 to 10 years 15 13.16
11 to 20 years 3 2.63
More than 20 years 2 1.75
Total 114 100.00

Figure 4. 4 Respondent’s Years of Working Experience

The respondent’s years of working experience in the construction industry were

categorised in four ranges. As per table 4.4 reveals that there is a vast majority of

respondent having less than 5 years working experience with the result of 94 out of 114

respondents in total (82.5%). Followed by that, there are 15 out of 114 respondents

(13.2%) are having 5 to 10 years working experience, followed by 3 respondents out of

114 respondents (2.6%) and 2 respondents out of 114 respondents (1.8%) with 11 to 20

years working experience and more than 20 years working experience respectively.

61
4.5.2 Findings in Relation to Objective One: Types, Advantages and

Disadvantages of Having Liquidated Damages Clause in Contract to Developer and

Contractor

This section seeks to determine the current perspective of construction industry players

on the liquidated damages. All the information provided by the respondents is their

thoughts are based on their working experience in the construction industry. In this

section, data collected were analysed using frequency, Relative Importance Index (RII)

and mean. Those criteria that were arranged in the ranking were in ascending order.

Table 4. 5 Frequency and Percentage of whether Paying Liquidated Damages to


the Innocent Parties in Common Scenario

Opinion Yes No Total

Frequency 94 20 114

Percent 82.5 17.5 100.0

Cumulative Percent 82.5 100.0

As per table 4.5, clarifying that there are large proportion of the respondents agree that

paying liquidated damages to the innocent party is a common scenario in the construction

industry which is 94 out 114 respondents and with 82.5%. Only 17.5% of the remaining

respondents disagreed with this assertion with only. As the table shows that the numbers

of contracting parties who choose no as not a common scenario are varied and no linear

relationship with different range of years of working experience.

62
Table 4. 6 Relationship between Thoughts of Construction Parties on whether
Paying Liquidated Damages is a Common Scenario and the Years of Working
Experience
Years of Percentage
Opinion Total
Experience (%)
Yes No
< 5 years 77 17 94 82.46
5 to 10 years 14 1 15 13.16
11 to 20 years 1 2 3 2.63
>20 years 2 0 2 1.75

Total 94 20 114 100

As the table above shows that the rating results from majority of the respondent thinking

that paying liquidated damages is a common scenario in the present construction industry.

Majority of the respondent in the category years of experience of less than 5, 5 to 10 years

and more than 20 years choose ‘yes’ with the total rating of 94 vote. While in the category

of 11 to 20 years’ experience of respondent, choosing ‘no’ has the higher vote than ‘yes’.

From the table above, we do able to see that all the respondents with more than 20 years

experiences chose ‘yes’. This is to say that most of the construction parties used to face

the issue of project delay and lead to pay liquidated damages during their working life.

63
Table 4. 7 Preference of Construction Parties on Having Liquidated Damages
Clause in the Contract

Preference Yes No Total

Frequency 107 7 114

Percent 93.9 6.1 100.0

Cumulative Percent 93.9 100.0

Figure 4. 5 Preference of Construction Parties on Having liquidated damages


Clause in the Contract
The question asked for the respondents’ preference on having liquidated damages in a

contract, either yes or no. According to the table 4.6 shows that 107 out of 114

respondents prefer to have liquidated damages clause in the contract and with the

percentage of 93.9%. Meanwhile, there is only 6.1% of the respondents disagree and wish

to contract out from the main contract. Many of them think that liquidated damages

clause is necessary to the contract.

64
Table 4. 8 Preference of Construction Parties on Having Liquidated Damages
Clause in Contract Throughout the Years of Experience

Years of Preference of having liquidated damages in


Total Percentage
Experience contract
Yes Percentage No Percentage

< 5 years 89 78% 5 4% 94 82%


5 to 10 years 14 12% 1 1% 15 13%
11 to 20
years 2 2% 1 1% 3 3%
>20 years 2 2% 0 0% 2 2%
Total 107 94% 7 6% 114 100%

According to the data presented in the table above, majority of the respondents (107

responses) were agreeing on the adoption of a liquidated damages clause in a contract. It

was found that there are 89 out of 114 respondents (78%) of less than 5 years’ experience

agree on having liquidated damages clause in contract. This was followed by respondents

who prefer having liquidated damages in contract with working experience of 5 to 10

years by 14 out of 114 respondents (12%). At the same time, there are total of 4

respondents (4%) with working experience within 11 to 20 years and more than 20 years

agree on having liquidated damages clause in contract. In contrast, according to the result

indicated that there are up to 7 out of 114 respondents (6%) which are acquire less than 5

years, 5 to 10 years, and 11 to 20 years working experience were disagreeing adoption of

liquidated damages clause in the contract.

65
Table 4. 9 Benefits of Having Liquidated Damages in the Contract to the
Developer

Benefits of having liquidated damages in the


N RII Mean Rank
contract to the developer
Act as a type of insurance to give protection to
114 0.828 4.14 1
the employer from risk
Helps to reduce any unnecessary ambiguity
114 0.775 3.88 2
over the project

Save time and cost of arbitration and litigation 114 0.749 3.75 3

Able to get back his possession on time 114 0.740 3.70 4

Not required to prove actual damages to the


114 0.637 3.18 5
contracting parties

This question has been set through Likert scale with several choices from strongly

disagree to strongly agree. Therefore, the variable of this question will be analysing by

using the mean, RII and standard deviation to determine the overall result from the

questionnaire survey. Mean gives the average (centre) of a data set in order to find the

tendency. While standard deviation reveals which of the data sets has a wider range of

values.

According to Table 4.9 shows the respondents’ perspective on advantages of having

liquidated damages in the contract to the Developer. This table reveals that of 5 selections,

liquidated damages act as a type of insurance to provide protection has the highest rating,

the greatest mean value (µ:4.14) and the highest RII value is 0.828. In contrary, without

proof of actual damages to the contracting parties has the lowest mean value of 3.18 (µ),

lowest RII value of 0.637 and is located at ranked fifth.

Many respondents believe that liquidated damages act as a protection due to the fact it is

a compensation to cover the losses faced by the developer. One of the respondents stated

that when the contractor fails to comply his obligation on hand over the site possession

66
to the developer on time, developer might face some losses such as late vacant possession

to the homebuyer, require to extend the rental for storage material if developer does not

own land.

Table 4. 10 Benefits of Having Liquidated Damages in the Contract to the


Contractor

Benefits N RII Mean Rank

Allow analysing their risks 114 0.811 4.05 1

Get to know early the amount to be pay if delay


114 0.781 3.90 2
project
Help in weighing the cost performance against
114 0.760 3.80 3
the cost of a breach

Act as a motivator 114 0.698 3.49 4

According to the table 4.10, it shown that allow analysing their risks has the highest mean

value of 4.05 and highest RII value of 0.811. While the statement of liquidated damages

act as motivator has the lowest ranked with the lowest mean value and lowest RII value

which are 3.49 and 0.698 respectively.

67
Table 4. 11 Drawbacks of Having Liquidated Damages in the Contract to the
Developer and Contractor

Drawbacks N RII Mean Rank

Tender price of the project can be affected based


114 0.772 3.86 1
on the rate of liquidated damages

The liquidated damages might not be sufficient


to pay for the specific breach as the amount is 114 0.739 3.69 2
fixed
Difficult for the contractor to prove that
liquidated damages is not genuine pre-estimate
114 0.714 3.57 3
if the contractor wants to challenge the
calculation of liquidated damages

Unfair to the contractor as amount of liquidated


114 0.704 3.52 4
damages way too high

The majority of respondents agree with the statement that one of the drawbacks of having

liquidated damages in contract is that it causes the tender price to be affected by the

liquidated damages, with the highest mean and RII value of 3.86 and 0.772 respectively,

placing at first ranked. These findings are based on the data that is presented in table 4.9.

Ranked third is difficulties of contractor prove liquidated damages is genuine pre-

estimate with the RII value of 0.714 and mean value of 3.57 which is higher than ranked

forth, unfair to the contractor as liquidated damages is too high. It has the lowest RII and

mean value which are 0.704 and 3.52 respectively.

Based on all the table above, we can see that first ranked will have the highest RII value

and mean value. The higher the RII value means it is the most influential and significance

factor. A factor with more vote, the higher RII value, the higher the ranking.

68
Table 4. 12 Rate of Liquidated Damages Per Day
RM RM RM More
Rate of liquidated damages per 10,000 to 30,001 50,001 than
Total
day RM to RM to RM RM
30,000 50,000 100,000 100,000
Frequency 54 27 20 13 114

Percent 47.4 23.7 17.5 11.4 100.0

Cumulative Percent 47.4 71.1 88.6 100.0

Rate of Liquidated Damages

11%

18% 47%

24%

RM 10,000 to RM 30,000 RM 30,001 to RM 50,000


RM 50,001 to RM 100,000 More than RM 100,000

Figure 4. 6 Rate of Liquidated Damages Per Day


According to table 4.10, which demonstrates that the RM10,000 to 30,000 has the highest

ranked rating among respondents which is more than half (54 people chose this rate).

While RM30,001 to RM50,000, RM50,001 to RM100,000 and more than RM100,000

has a lower rate compared to the range of RM10,000 to 30,000 and it is decreasing which

are 27, 20 and 13 respectively. However, it does not mean that liquidated damages must

be in this range. It is depending on the project involve by the respondents. Liquidated

damages can be affected by the types of projects. The larger the project, higher the risk,

the higher the liquidated damages. There is a lot reason that affect the amount of

liquidated damages. This complication is later addressed in 4.3.2.7.

69
Table 4. 13 Reason Choosing the Rate of Liquidated Damages Base on the Above
Question

Number of Percentage
Reasons Rank
Agreement (%)
Project cost and contract sum 12 35.29 1
Size of project 7 20.59 2
Experience 4 11.76 3
Type of project 4 11.76 3
Reasonable rate 3 8.82 5
Common in construction industry 2 5.88 6
Market rate 2 5.88 6
Based on contract 1 2.94 8
Based on Gross Development Value of the project 1 2.94 8
Client liability 1 2.94 8
Duration of project 1 2.94 8
Inflation 1 2.94 8
No fixed rate 1 2.94 8
scale of project 1 2.94 8
Potential losses generated 1 2.94 8

Reasons
40
35
30
25
20
15
10
5
0

Number of Agreement Percentage ( % )

Figure 4. 7 Reason Choosing Rate of Liquidated Damages Base on Above Question

70
This question is not set as required question in Google Form. Therefore, it only

contains 34 respondents answer it. According to the data presented in the table that is

located above, the vast majority of respondents indicated the cost of the project and the

total value of the contract is the reason that led them to select the rate of liquidated

damages. It has the highest percentage of 35.29%, which is remarkable. Meanwhile, there

are 8 reasons with the same ranking and with 2.94%, placing rank eighth such as based

on contract, Gross Development Value of the project, client liability, duration of project,

inflation, no fixed rate and scale of project. This is because all these reasons only contain

one respondent.

One of the respondents mentioned that the standard rate for a mixed development project

(commercial and residential), which could be somewhere between RM50,001 and

RM100,000. Other than that, a respondent had stated that some of the projects’ Liquidated

Damages can be reach to RM1,000 only. Furthermore, respondent 5 noted that there are

various factors that could influence the amount of liquidated damages. Client liability is

one of the reasons. For example, a contractor fails to complete and hand over site

possession to the client. It means that the client is require to continue rent the factory to

manufacture and in store material. Therefore, the client requires to pay the extra rental

and all the losses faced by the client will be claim through imposing Liquidated Damages

to the contractor. Some of the respondents had shown their calculations on different

approaches to compute the rate of Liquidated Damages which are stated below.

71
Calculation

Respondent 2:

= 0.35% x [Contract sum / 365 days]

Respondent 4:

= (Total construction cost / Construction period) x 0.1

Respondent 19:

= Contract sum x certain %

Respondent 22:

= (10% x Estimated construction cost) / 365 days

Therefore, the amount of liquidated damages can be affected different types of reason and

it is very wide range and without a fixed rate. However, the most significant reason is

cost of the project and contract sum. This is because the larger the project, higher the risk

and higher the amount of liquidated damages required to impose to recover developer’s

losses in construction project.

72
4.5.3 Findings in Relation to Objective Two: Application in Enforcing Liquidated

Damages during Pre-Stage and Final Account Negotiation and the Factors Affecting

Liquidated Damages Enforce Due to Delay

In this section, respondents were asked to rate their agreement on 8 different types of

damages where these 8 criteria were analysed using frequency and arranged in ascending

order.

Table 4. 14 Agreement of Respondents Towards Type of Damages Caused by


Delay

Number of Percentage
Type of Damages Rank
Agreement (%)
Lost revenue and profits 97 85.09 1
Additional project administration cost 88 77.19 2
Direct cost incurred under the contract 84 73.68 3
Indirect cost (E.g: rental expenses, insurances,
salaries & utilities) 83 72.81 4
Interest and financing costs 78 68.42 5
Damages and penalties charges by local
authority 76 66.67 6
Cost implications to third-party contract 70 61.40 7
Losses for tax or investment incentives 46 40.35 8

Type of Damages caused by the delay of the Developer


and Contractor
Percentage ( % ) Number of Agreement

Losses for tax or investment incentives 40.35


46
Cost implications to third-party contract 61.40
70
Damages and penalties charges by local authority 66.67
76
Interest and financing costs 68.42
78
Indirect cost (Eg: rental expenses, insurances,… 72.81
83
Direct cost incurred under the contract 73.68
84
Additional project administration cost 77.19
88
Lost revenue and profits 85.09
97
0 20 40 60 80 100 120

Figure 4. 8 Agreement of Respondents Towards Type of Damages Caused by Delay

73
This is a multiple selection question. Therefore, all the respondents are allowed to

select more than one answer. According to the table 4.14, the majority of respondents

believe that lost revenue and profit is the most significant sort of damage caused by the

Developer and Contractor's delay, with 97 agreeing and with the percentage of 85.09%,

placing it top. Meanwhile, losses for tax or investment incentives have the lowest rating

with 46 agreeing and with the percentage of 40.35%, which is under ranked eighth.

Additional project administration cost is rated second highest, with 88 agreeing and

77.19%. While the direct cost of the contract is the third highest with 84 agreeing, the

percentage is 73.68%. As we can see, the higher the percentage, the higher the ranking,

the more respondents choose that factor.

In short, the major damages caused by the developer's and contractor's delays are lost

revenue and profit.

74
4.5.4 Findings in Relation to Objective Three: How the Covid-19 Act Affects the

Enforcement of Liquidated Damages

This section is to determine the thoughts of the respondents regrading whether employer

is entitled to impose liquidated damages due to lockdown which the lockdown impose is

due to the Covid-19 pandemic.

Table 4. 15 Entitlement of Developer to Impose Liquidated Damages Due to


Lockdown

Yes, but there


Yes, developer No, unable
is certain
entitled to impose to impose
Opinion condition Total
for all liquidated liquidated
should be
damages damages
complied
Frequency 11 51 52 114
Percent 9.6 44.7 45.6 100.0
Cumulative
9.6 54.4 100.0
Percent

Entitlement of Developer To Impose Liquidated Damages


Due To Lockdown

9.6%

45.6%

44.7%

Yes Yes but with certain condition No

Figure 4. 9 Entitlement of Developer to Impose Liquidated Damages Due to


Lockdown
The opinions of the respondents are displayed in the table above on whether the developer

can impose liquidated damages on the contractor because of the lockdown. We can see

from the table that 52 persons voted against being able to impose liquidated damages,

which places them in the top position among the rankings. Although the answer of yes,

75
there are some conditions that must be met in order to comply with them has received 51

votes, which is one vote less than the statement that says no.

Table 4. 16 Opinion of Construction Parties on whether Developer Entitled to


Impose Liquidated Damages to Main Contractor

Years of Percentage
Experience Opinion Total (%)
Yes, but with
Yes condition No
< 5 years 11 46 37 94 82.46
5 to 10 years 0 4 11 15 13.16
11 to 20 years 0 1 2 3 2.63
>20 years 0 0 2 2 1.75
Total 94 51 52 114 100.00

According to the table above shows that there is linear relationship with different range

of years of working experience. As there are only 11 respondents stated yes on able to

impose for all liquidated damages and all the 11 respondents are having less than 5 years’

experience.

In this survey questionnaire,15 respondents have 5 to 10 years of working experience, 3

have 10 to 20 years of experience, and 2 have more than 20 years of experience. Meaning

to say that there are 20 respondents required 5 years and above experiences. According

to the survey questionnaire, the majority of construction industry experience respondents

(15 respondents) agree that liquidated damages cannot be imposed, while 5 respondents

voted yes but with certain conditions that must be met.

As a result, the majority of respondents with less than 5 years of experience chose yes but

with certain requirements that must be met.

Below table states the responses of respondents on whether developer entitled to impose

liquidated damages to main contractor.

76
Table 4. 17 Table Respondents’ Responses
Rate of Liquidated Damages
Respondent Comments
Chosen
Some are only 1k per day, it
1 RM10,000 to RM30,000
depends on project cost.
Depends on contract sum, the
2 RM10,000 to RM30,000 calculations are 0.35% * contract
sum / 365 days.
3 RM10,000 to RM30,000 Based on experience.
Based on total construction cost
percentage for normal factory (total
4 RM10,000 to RM30,000
construction cost/construction
period*0.1.
This depending on the project type,
project size which to reason will
affecting the amount of the LAD.
moreover, the client liability may
have affected the LAD Amount
also. For example, the client
required to rent the Land for storing
good and material is the project is
5 RM50,001 to RM100,000 for factory or another case which
retail shop, developer unable hand
over key to the purchaser due to
contractor delay and cause those
purchasers unable to operate their
business on time. Amount will be
determined through estimated
number of customers may come to
consume.
6 RM30,001 to RM50,000 Common
LD calculation is solely based on
7 More than RM100,000 the GDV of the project in relative
to scale of project as well.
8 RM50,001 to RM100,000 There is not fixed rate.
It's based on the calculation of total
9 RM30,001 to RM50,000
contract award amount.
The rate I normally encounter in a
10 RM10,000 to RM30,000
project.
11 RM10,000 to RM30,000 NIL
The rate was chosen based on the
practice in the construction industry
12 RM30,001 to RM50,000
on the amount of LD to be charged
per daily on contractor.

77
Rate of Liquidated Damages
Respondent Comments
Chosen
The rate of LD shall be different for
13 More than RM100,000 every project based on the project
size, type, and contract sum amount.
The rate of LD is calculated based
on the percentage of property price.
14 RM10,000 to RM30,000
The rate chosen is a common rate
for common residential property.
15 RM10,000 to RM30,000 Reasonable rate
I think that is the reasonable for
16 RM50,001 to RM100,000 both parties and amount over that
would be too high for developer.
17 RM50,001 to RM100,000 Based on my experience.
Various factor to be considered
including potential losses generated
18 RM50,001 to RM100,000
by delay of vacant possession and
price hike of raw material.
19 RM30,001 to RM50,000 Based on contract sum x certain %.
20 RM50,001 to RM100,000 Based on project sum price.
Depend on the estimated
21 RM10,000 to RM30,000
construction cost.
LD very much depend on the
size/cost of project and subject to
22 RM50,001 to RM100,000 developer. Normally we propose
10% of estimate construction cost /
365 days.
Help to cover over the construction
23 RM30,001 to RM50,000
period.
Based on a mixed development
24 RM50,001 to RM100,000
project (commercial + residential).
Actually, the LD amount will be
25 RM10,000 to RM30,000 depending on the contract sum or
the scale of project.
The question above is hard to justify
as the rate provided above are too
26 RM10,000 to RM30,000
generalized considering all types of
projects, contacts, duration, etc.
27 RM10,000 to RM30,000 Fair rate
Based on the project of the contract
28 RM50,001 to RM100,000
sum.
The rate of LAD is still depending
29 RM30,001 to RM50,000
on the size of the project.
Reasonable
30 RM10,000 to RM30,000

78
Rate of Liquidated Damages
Respondent Comments
Chosen
Eventually rate of liquidated
damages are varies for every
31 RM50,001 to RM100,000 construction project due to the size
of the project. But not to determine
by range.
Average market rate, can be higher
32 RM50,001 to RM100,000
for big development.
33 RM50,001 to RM100,000 Based on the size of project.
34 RM30,001 to RM50,000 Size of project.

79
Table 4. 18 Agreement on Reason Unable to Impose Liquidated Damages

Number of Percentage
Reasons Rank
Agreement (%)
Do not comply the requirement under
Prevention and Control of Infectious Diseases 67 58.77 1
Act 1988 Act (PCID)
Relevant event in the work programme which
36 31.58 2
is not critical path
Contractor fails to submit notice to the
35 30.70 3
Architect during lockdown
Government decision 14 12.28 4
EOT shall be granted 5 4.39 5
It depends on the context of the contract 2 1.75 6

Number of Agreement

It depends on the context of the contract 2

EOT shall be granted 5

Government decision 14

Contractor fail to submit notice to the Architect 35


during lockdown
Relevant event in the work programme which is not 36
critical path
Do not comply the requirement under Prevention and 67
Control of Infectious Diseases Act 1988 Act (PCID)

0 10 20 30 40 50 60 70

Figure 4. 10 Number of Agreement on Reason Unable to Impose Liquidated


Damages

80
This is also a multiple-choice question but include “other” answer option which allow

respondents state their own opinion. This can avoid from bias due to the limit of answer

to the question.

According to the table 4.18 shows the agreement on the reason that unable to impose

Liquidated Damages. Do not comply with the requirement under the Prevention and

Control of Infectious Diseases Act 1988 Act (PCID) has received the highest ranking

from respondents, with 67 agreeing and with 58.77%. While second highest is relevant

event in the work programme which is not critical path with 36 votes, following by

contractor fail to submit notice to the Architect during lockdown which is ranking third.

The percentages of those in ranks two and three are 31.58% and 30.70% respectively.

Meanwhile, 21 respondents voted for the 'other' option, followed by their own opinions,

which are listed below.

As we can see, 14 respondents think that government decision is the reason that lead to

developer unable to impose Liquidated Damages. Below is the overall opinion stated by

the respondents.

Respondents’ Response:

Government Decision:

Responses 1: The developer was unable to implement because the Malaysian

government had officially ordered the contractor to stop work in order to

reduce the spread of COVID -19 disease.

Responses 2: Everyone involved in the project will face the same challenging

circumstances throughout the lockdown period, in terms of time, money,

and quality. Overall, it is not the contractor's fault because this might be

deemed an unforeseen event, which the developer should take into account.

81
There should be no Liquidated Damages charged to the contractor. When

a contractor is granted an Extension of time, liquidated damages are not

charged as well.

Responses 3: Ministry of Housing had granted an extension for the vacant possession to

the purchaser which also allowed developer to grant Extension of Time to

contractor as well. While for others lockdown which does not

getting the consent from Ministry of Housing, EOT shall not be eligible

and Liquidated Damages will still have incurred to the contractor if they

delay upon the extended completion date. This statement can be related to

the Chapter 2.6 that some activities which falls outside the relief in Section

7 of the COVID-19 Act may not always be approved in a construction

contract. There is only limited protection due to the requirement of

inability to comply condition.

Contract:

Responses 1: It depends on the context of contract to see whether entitled Extension of


Time.
Responses 2: Refer to the contract which use in the project. Extension of Time shall be
entitled due to lockdown.

4.6 Summary of Quantitative Data Analysis

As shown in demographic information, majority of the respondents are involving in

quantity surveyor and contractor firm with the percentage of 40.4% and 38.6%

respectively. Most of them are having less than 5 years working experience. However,

we can clearly compare the responses of experience and non-experience workers as these

two groups of population have a very clear difference on their responses. Some of the

respondents even give their own opinion base on their experience and project involved.
82
CHAPTER 5 CONCLUSION

5.1 Introduction

This chapter brings this research to a close. The research findings recap discussion on the

three objectives and findings from the questionnaire survey which has been answered by

the relevant construction parties to the study.

5.2 Research Findings

5.2.1 Findings in Relation to Objective One: Types, Advantages and

Disadvantages of Having Liquidated Damages Clause in Contract to Developer

and Contractor

This objective is regarding to the perspective of respondents on preference of liquidated

damages to the contract. While it was apparent that the industry prefers contracts with

liquidated damages clause. The literature review has also reflected that liquidated

damages clause is the most significant provision in the construction contract since it

compensates the affected parties in the event of a breach of contract. From the developers’

standpoint in this survey, liquidated damages act as a type of insurance to give protection

to the developer in order to cover their loss that incurred. This is due to the fact that when

a contractor unable to complete project on time, it may lead to loss of profits and cost

overruns. In addition, the developer was unable to make good use of the site to make

profit too. From the questionnaire survey data shows that the amount of liquidated

damages should not be set at whatever number the developer desires, but rather at a

reasonable amount, even though the developer has the right not to prove actual harm to

the contractor. This statement can be related to the Cubic case as stated in the Chapter 2

Literature Review. The judgement in Cubic case overturns the decision in Selva case and

affects the liquidated damages clause in the main contract. As we know, a condition of

83
contract must be fair to both parties. Besides, the factor of tender price of project can alter

the rate of liquidated damages has highest vote. This is due to the risk that is taken on by

the contractor increases proportionally with the amount of liquidated damages paid by the

developer. When every contractor raises their tender price in an effort to offset their losses,

this is not a good indicator for the developer because it means that they will need to spend

more money on that particular project. Moreover, from the data collected from

questionnaire survey, it was found that the rate of liquidated damages per day can be can

be vary widely and without fixed rate because it affected by many factors as it is

depending on the type of the project deal by the construction parties. According to the

respondents’ responses, they stated that the amount cannot be determine through range

because it can be any amount but as long as it is reasonable. For example, a renovation

company used to deal with a smaller amount of liquidated damages then design and build

construction company. This is because the larger the project, the more difficulties faced,

the higher the risk, the higher rate of liquidated damages may impose by the developer.

There is a lot of way to calculate the amount of liquidated damages. Every company has

their own method but there is no right or wrong as long as contract has been agreed and

signed by both parties.

5.2.2 Findings in Relation to Objective Two: Application in Enforcing Liquidated

Damages during Pre-Stage and Final Account Negotiation and the Factors

Affecting Liquidated Damages Enforce Due to Delay

According to the data collected from questionnaire survey, it was found that majority of

the respondents voted for lost revenue and profits as the type of damages that caused by

delay to the developer and contractor. In the Chapter 2 Literature Review has stated that

it is regarding to the daily operating profit. While this factor has supported by one of the

responses in the questionnaire survey objective 3, which is purchasers unable to operate

84
their business on time due to developer fail to hand over key to them. Their losses will be

determined through the estimated number of customers that may come to purchase. This

is because the longer the time contractor delay, the buyers unable to start their business

and loss their chance in making profit.

5.2.3 Findings in Relation to Objective Three: How the Covid-19 Act Affects the

Enforcement of Liquidated Damages

There is a very close vote between ‘yes, the ability to impose liquidated damages under

specific conditions’, and ‘no, the inability to impose liquidated damages’. While the

statement of developer unable to impose liquidated damages has the highest ranking and

it is one vote higher than the statement of ‘yes but with condition’. However, according

to the objective 3 Literature Review stated that contractor is entitle to request Extension

of Time and developer unable impose liquidated damages, though certain conditions

required to be complied. It is not compulsory that all contractor is able to avoid from

paying liquidated damages due to delay project during lockdown as it is not all the

lockdown are approved. The exemption was given and valid to those event that happen

from 29th March 2020 until 23rd October 2020. Although contractor has right to claim

Extension of Time, but he is required to give written notice to the Architect his intention

to claim for such extension of time together with supporting documents with all

particulars of the cause of delay. Giving a notice to Architect shall be a condition

precedent to an entitlement of extension of time and lead to avoid from paying liquidated

damages.

85
5.2.4 Summary of Research Findings

From the information collected in questionnaire survey, a conclusion can be reached on

the importance of liquidated damages clause existing in the contract, as it able to protect

both parties including the purchaser. Besides, there are certain circumstances in which

developers are unable to impose liquidated damages due to the government’s order to

execute lockdown which is a restriction movement order and stop work order to everyone

in Malaysia. This is because the decision was made by government, not by contractors.

Therefore, contractors are permitted to request Extension of Time but with the condition

precedent of giving notice to the Architect.

5.3 Limitation of Study

The results of this study is subject to a few limitations. Firstly, the questionnaire results

were only targeted towards parties that involved in the construction industry. While

contractors must be registered with the Construction Industry Development Board

(CIDB). Quantity surveyor, contractor and developer form the major sector of the

construction industry, this may reflect the actual view on the entire industry. The usage

of questionnaire may also pose problem of misrepresentations and dishonestly, both of

which will affect the accuracy of data collected.

86
5.4 Recommendations of Future Studies

The government are no longer implement lockdown anymore. However, Covid-19 is still

continuously spread all around the world and people are still struggling on it. Therefore,

all the construction parties shall go through all the contract properly before sign as it may

bring a big effect towards parties when emergency activities happen such as Covid-19

pandemic and the lockdown impose by government.

The researcher recommends future researchers to undertake the study to investigate any

other emergency issues that have the possibility to develop in future which regarding to

the Covid-19 in the construction industry and the ways to be solve when disputes occur.

5.5 Conclusion

Liquidated damages is not a penalty to contractor. It is a compensation to the innocent

parties when breach of contract occurs. Liquidated damages is very important in a

contract to both parties as it able to give protection to both parties. There is no bias as the

amount of liquidated damages shall be reasonable and fair to both parties. Therefore,

everyone should be careful on forming and signing a contract including contract out the

liquidated damages from the contract. This is due to the contract is the main document to

be refer once anything happen.

87
REFERENCES

ACPG 2019, Construction and engineering insurance Malaysia, viewed 27 February


2022,
<http://www.acpgconsultant.com/main/3143/index.asp?pageid=122529&t=malaysia-
construction-insurance,insurance,-malaysia-contractor-all-risk,-malaysia-workmen-
compensation-insurance,-malaysia-erection-all-risk-insurance,-malaysia-bond-
insurance,-insurance-guarantee>.
Andrews, L, Higgins, A, Andrews, Michael, AW & Joan, G 2012, Classic grounded
theory to analyse secondary data: Reality and reflections, viewed 28 February 2022,
<http://groundedtheoryreview.com/2012/06/01/classic-grounded-theory-to-analyse-
secondary-data-reality-and-
reflections/#:~:text=In%20other%20words%2C%20secondary%20data,process%20of%
20secondary%20data%20analysis>.
Annabel, T 2022, Case update: Court of appeal decides minister can grant extension of
time for vacant possession, viewed 22 February 2022,
<https://themalaysianlawyer.com/2022/02/03/minister-extension-time-vacant-
possession/>.
Beg, MA 2019, ‘Time at large: Concept and how it applies’, E-Journal of Law, vol. 5.
Bhumesh Verma 2017, India: Importance of liquidated damages clause in a contract,
viewed 01 February 2022, <https://www.mondaq.com/india/contracts-and-commercial-
law/615382/importance-of-liquidated-damages-clause-in-a-contract>.
BRM 2022, Simple random sampling, viewed 03 March 2022, <https://research-
methodology.net/sampling-in-primary-data-collection/random-sampling/>.
Carney, JP & Felsen, DK 2022, Understanding the purpose, limitations, and benefits of
a liquidated damages clause, viewed 30 January 2022,
<https://www.carltonfields.com/insights/publications/2020/understanding-a-liquidated-
damages-clause>.
Cochran, W. G 1977, Sampling Techniques, 3rd ed, Canada: John Wiley & Sons
Inc.
Cormac, M, Per JP & Matilda, L 2019, ‘Twelve tips for conducting qualitative research
interviews’, Medical teacher, vol. 41, no. 9, pp. 1002–1006.
DesigningBuildings 2021, Liquidated damages in construction contracts, viewed 01
January 2022,
<https://www.designingbuildings.co.uk/wiki/Liquidated_damages_in_construction_cont
racts>.
DesigningBuildings 2022, Liquidated V unliquidated damages, viewed 09 February
2022,
<https://www.designingbuildings.co.uk/wiki/Liquidated_v_unliquidated_damages>.
Faircontracts.org 2022, What are standard form contracts, viewed 25 January 2022,
<https://faircontracts.org/what-are-standard-form-contracts>.
Formplus 2009, Structured interviews: Definition, types+ [question examples], viewed
01 March 2022, <https://www.formpl.us/blog/structured-interview>.
88
FU, YQ 2013, ‘A Study on the causes and methods to prevent construction delay in
Selangor state and Kuala Lumpur’, Doctoral dissertation, Universiti Malaysia Pahang.
GAO 2009, Questionnaire pretest procedure, viewed 02 March 2022,
<https://www.ignet.gov/sites/default/files/files/14_Questionnaire_Pretest_Procedures.pd
f>.
Hakem Arabi & Associates 2020, Revisiting Selva Kumar Murugiah V Thiagarajah
Ratnasamy: The coming-of-age of the law on proving liquidated ascertained damages
in housing development contracts, viewed 05 April 2022,
<https://www.hakemarabi.com.my/articles-the-coming-of-age-of-the-law-on-proving-
liquidated-ascertained-damages.html>.
Hallellis 2021, Liquidated damages clauses (and unenforceable penalty clauses),
viewed 03 February 2022, <https://hallellis.co.uk/liquidated-damages
penalties/#:~:text=Disadvantages,in%20an%20assessment%20of%20damages>.
HHQ 2019, Liquidated damages clauses in contracts: An inviting shift in the law
through the federal court’s decision In Cubic Electronics Sdn Bhd (In Liquidation) V
Mars Telecommunications Sdn Bhd, viewed 28 January 2022 ,
<https://hhq.com.my/publications/liquidated-damages-clauses-in-contracts-an-inviting-
shift-in-the-law-through-the-federal-courts-decision-in-cubic-electronics-sdn-bhd-in-
liquidation-v-mars-telecommunications-sdn-bhd/>.

Joseph, W 2018, How are liquidated damages calculated?, viewed 27 February 2022,
<http://www.gmssolutions.com.my/blog/how-are-liquidated-damages-calculated/>.

Kamar, NIBM 2017, ‘Time at large: Implication for liquidated damages’.


Kumar 2010, ‘Research Methodology: A step-by-step guide for beginners’, 3rd edition,
Sage, London.
Laryea, S & Hughes, W 2008, ‘How contractors price risk in bids: Theory and
practice’, Construction management and economics, Vol. 26, No. 9, pp.911-924.
Legal Choices 2022, Definition of unliquidated damages, viewed 02 April 2022,
<https://www.legalchoices.org.uk/dictionary/unliquidated-damages>.
Lorman Education 2018, Resolving problems and disputes on construction projects:
Tackling contract performance delays, viewed 27 January 2022,
<https://www.lorman.com/resources/resolving-problems-and-disputes-on-construction-
projects-tackling-contract-performance-delays-15142>.
Malconlaw 2012, Malaysian construction and contract law, viewed 27 February 2022,
<https://simplymalaysia.wordpress.com/articles/liquidated-damages/liquidated-
damages-explained-how-to-calculate-them/>.
Mathias, C 2022, What is a liquidated damages provision?, viewed 24 January 2022,
<https://www.nolo.com/legal-encyclopedia/when-are-liquidated-damage-provisions-
enforceable.html>.
McCombes, S 2019, An introduction to sampling methods, viewed 03 March 2022,
from <https://www.scribbr.com/methodology/sampling-methods/>.
Md Saad, N.H. and Yaacob, Z 2022. Malaysian Government Digital Transformation
Stimulus Accelerate the Growth of SMEs in E-commerce Ecosystems: The Recovery
89
Phase of the Post Covid-19 Pandemic in 2020. In Marketing and Smart Technologies (pp.
673-683). Springer, Singapore.
Meagen, R 2016, ‘Qualitative research methods: Why, when, and how to conduct
interviews and focus groups in pharmacy research’, Currents in pharmacy teaching and
learning, Elsevier, vol. 8, no. 4, pp. 509–516.
Michael, H.P 2018, Liquidated damages, viewed 23 February 2022,
<https://www.cohenseglias.com/contracting-database/liquidated-damages/>.
Michael C, Ian H, Crystal R, Sean D & Gilda C 2015, Liquidated damages can destroy
your profit… and your business, viewed 23 February 2022,
<https://www.lexology.com/library/detail.aspx?g=04e01a3f-e2bc-4422-ab78-
56fe49b278f3>.
Miller Jr, RG 1997, ‘Beyond ANOVA: Basics of applied statistics’, CRC Press.
Mimi Yuslinda Yusof 2021, PAM Practice Burea, viewed 06 April 2022,
<http://pam.org.my/images/resources/bureau/CAT_G_JAN_JUN_2021_10_Items.pdf>.
Naoum, SG (ed.) 2007, ‘Dissertation research and writing for construction students’, 2nd
edn, Elsevir Ltd, UK.
Naoum, SG 2012, ‘Dissertation research and writing for construction students’,
Routledge.
Nor Aida I, Syuhaida, I & Faizal, AS 2019, ‘Delays in Malaysian government projects:
Learning from project management failure’, The institution of engineers, Malaysia.
Preston V 2019, Questionnaire survey, viewed 28 February 2022,
<https://www.sciencedirect.com/topics/earth-and-planetary-sciences/questionnaire-
survey>.
Properly 2020, What is schedule G, H, I, and J and certificate of fitness, viewed 23
February 2022, <https://properly.com.my/blog/schedule-g-h-i-and-j-and-certificate-of-
fitness/>.
PropertyGuru 2021, LAD in a construction contract and 3 causes for extension of time,
viewed 01 February 2022, < https://www.propertyguru.com.my/property-guides/what-
is-lad-in-a-construction-contract-30956 >.
ReadingCraze 2014, The research proposal sample, viewed 28 February 2022,
<http://readingcraze.com/index.php/types-sampling-research/>.
RICS 2015, ‘Final account procedures’, 1st edition, Royal Institution of Chartered
Surveyors, Coventry, UK.
Endut, IR, Akintoye, A & Kelly, J 2009, ‘Cost and time overruns of projects in
Malaysia’, retrieved on August, 21, pp.243-252.
Roy Rabindra, N, Saha, I, & Roy, R 2013, Chapter-24 Research Methodology, viewed
3 March 2022, In Mahajan and Gupta Textbook of Preventive and Social Medicine, pp.
450–459, Jaypee Brothers Medical Publishers (P) Ltd,
<https://doi.org/10.5005/jp/books/12262_24>.

90
SorbaraLaw 2015, Liquidated damages in construction contracts, viewed 21 February
2022,<https://www.sorbaralaw.com/resources/knowledge-centre/publication/liquidated-
damages-construction-contracts>.
Stephanie Glen 2022, Sample size in statistics (How to find it): Excel, Cochran’s
formula, general tips from StatisticsHowTo.com: Elementary statistics for the rest of
us!, viewed 02 March 2022, <https://www.statisticshowto.com/probability-and-
statistics/find-sample-size/>.
Tan, M.L 2020, COVID-19 Act: The impact on construction contracts and construction
disputes, viewed 22 February 2022, < https://www.ganlaw.my/covid-19-act-the-impact-
on-construction-contracts-and-construction-disputes/ >.
Tan, M.L 2021, Burden on developers continues: Payment of liquidated damages under
Covid Act, viewed 20 February 2022,
<https://www.lexology.com/commentary/litigation/malaysia/gan-partnership/burden-
on-developers-continues-payment-of-liquidated-damages-under-covid-act>.
TeamStage 2022, Project management statistics: Trends and common mistakes in 2022,
viewed 28 January 2022, <https://teamstage.io/project-management-statistics/>.
The World Bank 2022, Primary data collection, viewed 02 March 2022,
<https://dimewiki.worldbank.org/Primary_Data_Collection#:~:text=Primary%20data%
20collection%20is%20the,primary%20data%20is%20household%20surveys>.
Ting, SN 2013, ‘Construction procurement framework incorporating form enhancement
modules for the selection of standard form of contract in Malaysia’, Doctoral
dissertation, Curtin University.
Tower, M & Baccarini, D 2008, ‘Risk pricing in construction tenders-how, who,
what’, Construction Economics and Building, vol. 8, No.1, pp.49-60.
Tuckman, AM 2021, Three recent cases strike down liquidated damages clauses in
settlement agreements… A trend or an aberration?, viewed 24 January 2022,
<https://www.consensusdocs.org/three-recent-cases-strike-down-liquidated-damages-
clauses-in-settlement-agreementsa-trend-or-an-aberration/>.
Yasmin, B 2022, Penalty clause vs liquidated damages, viewed 23 February 2022,
<https://www.gannons.co.uk/insights/penalty-clause-vs-liquidated-damages/>.
Yeoh, EC 2021, Liquidated ascertained damages, viewed 07 April 2022,
<https://www.thomasphilip.com.my/articles/article-on-liquidated-ascertained-
damages/#:~:text=A%20Liquidated%20Ascertained%20Damages%20(LAD,of%20a%2
0breach%20of%20contract>.

91
APPENDICES
Appendix A: Questionnaire

The Effects of COVID-19 Act on the Application of Liquidated Damages in


Malaysian Construction Industry

The survey has been developed to identify the level of understanding of Liquidated
Damages Clause (LD) among the Malaysian construction parties and focus on the types
of liquidated damages, advantages and disadvantages of the construction parties to
enforce the liquidated damages clause in the Malaysian construction industry and to find
out how the Covid-19 Act affects the enforcement of Liquidated Damages

Section A: Demographic Profile

1. Gender * Kindly select one only

( ) Male
( ) Female

2. What is your highest education level? * Kindly select one only

( ) SPM
( ) STPM
( ) Diploma
( ) Bachelor Degree
( ) Master
( ) PHD

3. What is the type of firm you are working at? * Kindly select one only

( ) Developer
( ) Contractor
( ) Architect
( ) Engineer
( ) Quantity Surveyor
( ) Supplier
( ) Any others, please state: ___________________________

92
4. How many years of working experiences in the construction industry? * Kindly
select one only

( ) Less than 5 years


( ) 5 to 10 years
( ) 11 to 20 years
( ) More than 20 years

Section B: The Relationship of Liquidated Damages Between Developer and Contractor


5. Is delay of the project and paying Liquidated Damages to the innocent party
is a common scenario in the construction industry? * Kindly select one only

( ) Yes
( ) No

6. Do you prefer to have Liquidated Damages clause in the contract? * Kindly


select one only

( ) Yes
( ) No

7. Please indicate your extent of agreement on the following benefits of having


Liquidated Damages in the contract to the Developer. * Kindly select one for
each criterion

Benefits Strongly Disagree Neutral Agree Strongly


Disagree Agree
1 2 3 4 5
Not required to prove
actual damages to the
contracting parties
Save time and cost of
arbitration and
litigation
Act as a type of
insurance to give
protection to the
employer from risk
helps to reduce any
unnecessary ambiguity
over the project
Able to get back his
possession on time

93
8. Please indicate your extent of agreement on the following benefits of having
Liquidated Damages in the contract to the Contractor. * Kindly select one for
each criterion

Benefits Strongly Disagree Neutral Agree Strongly


Disagree Agree
1 2 3 4 5
Help in weighing the
cost performance
against the cost of a
breach
Get to know early the
amount to be pay if
delay project
Allow analysing their
risks
Act as a motivator

9. Please indicate your extent of agreement on the following drawbacks of


having liquidated damages in the contract to the Developer and Contractor.
* Kindly select one for each criterion

Benefits Strongly Disagree Neutral Agree Strongly


Disagree Agree
1 2 3 4 5
LD might not be
sufficient to pay for
the specific breach as
the amount is fixed
Tender price of the
project can be affected
based on the rate of
LD
Unfair to the
contractor as amount
of liquidated damages
way too high
Difficult for the
contractor to prove
that LD is not genuine
pre-estimate if the
contractor wants to
challenge the
calculation of LD

94
10. How much is the rate of liquidated damages mostly set in the construction?
* Kindly select one for each criterion

( ) RM 10,000 to RM 30,000
( ) RM30,001 to RM 50,000
( ) RM 50,001 to RM 100,000
( ) More than RM 100,000

11. Reason choosing the rate of liquidated damages base on above question?
___________________________

Section C: Type of Damages

12. Please indicate your agreement on the type of damages caused by delay to
the developer and contractor.

Type of Damages Please Tick


(✓)
Indirect Cost (eg. rental expenses, insurances, salaries &
utilities)
Direct costs incurred under the Contract
Lost revenue and profits
Additional project administration costs
Damages and penalties charges by Local Authority
Interest and financing costs
Cost implications to third-party contracts
Losses for tax or investment incentives

Section D: Enforcement of Liquidated Damages towards to COVID-19 Act

13. Is developer entitled to impose liquidated damages to main contractor due


to the delay of the project during lockdown which impose by the
government and why? * Kindly select one for each criterion

( ) Yes, developer entitled to impose for all liquidated damages


( ) Yes, but there is certain condition should be comply
( ) No, unable to impose liquidated damages

95
14. Please indicate your agreement on the reason that unable to impose liquidated
damages. * Kindly select one for each criterion

( ) Do not comply the requirement under Prevention and Control of


Infectious Diseases Act 1988 Act (PCID)
( ) Relevant event in the work programme which is not critical path
( ) Contractor fails to submit notice to the Architect during lockdown
( ) Other: ___________________________

96

You might also like