Professional Documents
Culture Documents
FACULTY OF ENGINEERING
UNIVERSITY OF RUHUNA
This report contains the knowledge and experience that I obtained from my second training
period from 28th January 2019 to 21st April 2019. I completed my training period in the
construction I roads in Monaragala district which was mainly handled by MAGA
Engineering (Pvt.) Ltd
The first chapter is an introduction to the training establishment which contains its main
functions, organizational structure, hierarchical levels.
Second chapter is about the project and the experience and knowledge gained from the
training.
Third chapter is about the training experience on the side of management which gives details
of administrative and office practices, financial and safety procedures and etc.
The fourth which is the final chapter is about the conclusion of the report and suggestions
according to my point of view.
i
Acknowledgement
Undergoing as an Engineering trainee into an industrial site is the most efficient way to
improve practical knowledge of BSc undergraduate student. For the success of this 12 weeks
training program, I got lot of help and guidance. Their influence and support guided me to
equipped with a good technical knowledge. Therefore, I would like to extend my sincere
gratitude to all respected persons
First, I would like to express my sincere gratitude to Dr. W.K.C.N Dayanthi, Head of the
Department of Civil Engineering department, training coordinator Dr. Ruwan Appuhamy ,
and the staff of Training Division of faculty of engineering, and the officials of National
Apprentice and Industrial Training Authority for providing me an opportunity of industrial
training at Maga Engineering Pvt Ltd. and their assistance during the training period.
I would also like to offer my sincere thanks to Mr. Indika Dhahanayaka, the Project
Manager and Mr. Sanjeewa Perera, Deputy Project Manager of project MO-03 at
Monaragala for giving responsibilities to trainees.
I express my deepest gratitude and special thanks to Mr .Madhushn (Site Engineer) and the
working staff for their careful and precious guidance which were extremely valuable for my
training.
I would also like to thank all the staff members such as engineering assistants, technical
officers, surveyors, quantity surveyors, accountants, safety managers, admin officers,
foremen, supervisors, machine operators and also the labours of Maga Engineering (Pvt).
Ltd who helped me to learn various technical and management matters.
Dodangoda D C K
EG/2015/2622
University of Ruhuna
ii
Table of Contents
Chapter 1................................................................................................................................ 1
VISION .......................................................................................................................... 2
MISION ......................................................................................................................... 2
Chapter 02.............................................................................................................................. 4
iii
2.3.4 Subbase preparation ....................................................................................... 14
2.3.6 Establishment of level pegs for laying subbase and ABC ............................. 19
Chapter 03............................................................................................................................ 42
3.4.2 Points should be considered when using tools and equipment ...................... 46
iv
3.4.6 Traffic control signboards ............................................................................. 49
Chapter 04............................................................................................................................ 51
References ........................................................................................................................... 54
v
List of Figures
Figure 1.1:Logo of the company ........................................................................................... 1
Figure 1.2:Site organization structure ................................................................................... 3
Figure 2.1:Project MO-03 in Monaragala district ................................................................. 5
Figure 2.2:Excavator used in site .......................................................................................... 6
Figure 2.3:Rammer ................................................................................................................ 6
Figure 2.4:4Ton roller used in site......................................................................................... 7
Figure 2.5:Using a 1Ton roller .............................................................................................. 7
Figure 2.6:Pnematic tired roller ............................................................................................. 8
Figure 2.7:Operating a bobcat loader .................................................................................... 9
Figure 2.8:Grading an ABC layer by Motor grader ............................................................ 10
Figure 2.9:prime bowser used at site ................................................................................... 10
Figure 2.10:Asphalt paver used in site ................................................................................ 11
Figure 2.11:Site clearing...................................................................................................... 12
Figure 2.12:Embankment preparation ................................................................................. 13
Figure 2.13:Subgrade compaction ....................................................................................... 14
Figure 2.14:Sub base laying ................................................................................................ 15
Figure 2.15:Grading of laid sub base................................................................................... 15
Figure 2.16:Finished sub base surface ................................................................................. 16
Figure 2.17;Laying of ABC ................................................................................................. 17
Figure 2.18:ABC levelled surface ....................................................................................... 18
Figure 2.19:Compaction of ABC surface ............................................................................ 18
Figure 2.20:Marked peg of a subbase level ......................................................................... 19
Figure 2.21:Adjusting the height of peg .............................................................................. 20
Figure 2.22:Transverse measurement at a chainage point ................................................... 20
Figure 2.23:Taking longitudinal measurement .................................................................... 21
Figure 2.24:Cleaning by using boomer ............................................................................... 22
Figure 2.25:Priming of the ABC surface ............................................................................. 23
Figure 2.26:Applying sand layer on primed surface ........................................................... 23
Figure 2.27:Laid cable in road ............................................................................................. 24
Figure 2.28:Transfering levels to pegs ................................................................................ 24
Figure 2.29:Cheking dip value ............................................................................................ 25
vi
Figure 2.30:Laying of asphalt .............................................................................................. 25
Figure 2.31:Checking temperature in asphalt ...................................................................... 26
Figure 2.32:Manual adjustment of asphalt in road .............................................................. 26
Figure 2.33:Compaction by steel drum roller ...................................................................... 27
Figure 2.34:Compaction by PTR roller ............................................................................... 28
Figure 2.35:Cross section of road with shoulders ............................................................... 28
Figure 2.36:Removal of excess ABC .................................................................................. 29
Figure 2.37:Finished shoulder ............................................................................................. 30
Figure 2.38:Cross section of a culvert ................................................................................. 31
Figure 2.39:Head wall details .............................................................................................. 31
Figure 2.40:Details of a box reinforcement ......................................................................... 32
Figure 2.41:Bar schedule of a culvert .................................................................................. 33
Figure 2.42:Constructing of a Pipe culvert .......................................................................... 34
Figure 2.43:Cross section of a headwall .............................................................................. 34
Figure 2.44:Weep hole arrangement ................................................................................... 35
Figure 2.45:Sand cone test................................................................................................... 36
Figure 2.46:Sand used in sand cone test .............................................................................. 37
Figure 2.47:Sand cone ......................................................................................................... 37
Figure 2.48:Tray used in tray test ........................................................................................ 38
Figure 2.49:During tray test................................................................................................. 39
Figure 2.50:Slump cone test equipment .............................................................................. 39
Figure 2.51:Measuring the slump ........................................................................................ 40
Figure 2.52:Cube testing...................................................................................................... 41
Figure 3.1:Workshop on machine handling ........................................................................ 45
Figure 3.2:Sfety helmets ...................................................................................................... 47
Figure 3.3:Safety jackets wore by labours........................................................................... 47
Figure 3.4:Safety boots ........................................................................................................ 48
Figure 3.5:Fire point ............................................................................................................ 48
Figure 3.6:Slow-moving or stationary works in a traffic lane ............................................. 49
Figure 3.7:GO/STOP sign boards ........................................................................................ 49
Figure 3.8:Indication of that there is a hump....................................................................... 49
Figure 3.9:Road narrowing signs......................................................................................... 50
vii
List of Tables
Table 2.1: Asphalt temperature ........................................................................................... 27
viii
Chapter 1
In this history, Maga has made considerable effect into the local construction industry by
bringing together a professional team and developing construction materials, machineries
and construction techniques. These unique qualities have helped Maga to acquire ICTAD
Grade 1 status in the category of Buildings, Highways, Bridges, Water Supply and Drainage,
which no other construction company can be proud of. Today Maga has established its name
as a market leader and also as a model construction company in Sri Lanka.
In the history of Maga Engineering company it had so many achievements. From those
achievements annual green building awards that was taken in 2018 was highlighted. Maga
possesses over 70 senior project managers over 300 graduate engineers from the fields of
civil, electrical, mechanical and earth resource engineering together with designers planners
and over 8000 craftsmen.
VISION
“To be the most competitive construction firm in Sri Lanka.
MISION
Maga is driven by excellence and is committed to ensure the satisfaction of customer need
with utmost care by constantly providing quality product and service at affordable price.
This creates a fire and growing return to our organization an inspiring workplace and a
continued sense of security to our employees thereby enabling us to contribute to society by
elevating the quality of life.
2
Project Manager
(Section 1A)
Senior Material Environment & QA Engineer
1.5 Site organization chart
Laboratory Laboratory
3
This is a figure of site organization in the project.
Technician Technician
Technical
Store Keeper Accounts
Officer
Clerk
QA Document
Quality Control Inspector
1. Kiri-ibbanara
2. Hathporuwa
3. Koulara
4. Hambegamuwa
4
2.1.1 Site location
Following figure 2.1 shows the Monaragala district and location of the MO-03 site.
5
2.2 Machinery used
2.2.1 Excavator
Excavators are mainly used for site clearing, trench excavation and for shoulder preparation.
This also can be used for loading of materials like soil, subbase, ABC and etc. to trucks and
for concrete crushing. In this site used excavator type was wheel mounted type. Following
Figure2.2 shows an excavator used in site.
2.2.2 Rammer
Rammer is used for the compaction of materials like soil, subbase and ABC where vibratory
roller cannot be used. These are mainly used in places like culvert backfilling, subgrade
subbase and ABC compaction in narrow areas and for trenches that used for pipe laying.
This can be operated by one person and a meter is indicated to represent the working hours.
Safety should be considered when operating this as this exerts a repetitive force on the
ground. Figure 2.3 is an image of a rammer.
Figure 2.3:Rammer
6
2.2.3 Vibratory roller
Vibratory rollers provide compact force by combination of weight and vibration of their steel
roller, commonly referred as drums. These rollers achieve compaction by its self-weight,
impact forces and vibration response. Roller drum available in different weights.
Above are different size of rollers used in the site and some rollers are categorized as single
drum and double drum roller. Following figure is a 4 Ton roller used in site.
7
2.2.4 Pneumatic tired roller
This machine has two sets of wheels which are arrange in such a manner that the rear wheels
will run in the spaces between the front wheels provided. These are used for compacting
asphalt surface as even. The Pneumatic Tired Roller (PTR) is recommend to be used on
asphalt surface treatment. The resilient tires on these rollers force the aggregate firmly into
the asphalt binder without crushing the particles. It is also widely used on asphalt mix paving
in combination with tandem steel rollers. The most popular type of pneumatic-tired roller
for road maintenance is the self-propelled smooth-thread tired roller with 3 or 4 wheels at
front and, 4 or 5 wheels at rear. This picture shows compacting of asphalt using pneumatic
tired roller.
8
2.2.5 Bobcat loader
This is a most economical loading type vehicle. This can be used for loading of materials to
trucks, moving of materials to small distance and laying of soil, ABC on road. Main use of
this is to fix the boomer for the cleaning purpose of the ABC surface before laying asphalt.
This figure 2.7 shows a bobcat used to remove excess soil.
9
Figure 2.8:Grading an ABC layer by Motor grader
10
2.2.8 Asphalt paver
The asphalt paver is used to pave as per levels. It consists two main units, the tractor unit
and the floating screed unit. The tractor unit provides the motive power through the
pneumatic tires travelling on the surface to be paved. The screed unit consists of the screed
plate, vibrators and thickness control sensors. The paver is equipped with distributing screws
of the reversing type to place the mixture evenly in front of adjustable steering devices and
have reverse as well as forward travelling speeds. Paver shall also equip with vibrating
screeds furnished with suitable burners or heaters to prevent the mix from sticking to the
screed plate. It is used to heat the screed plate at the start of paving Operation. Following
figure shows a VOLVO asphalt paver.
• Back filling
11
• Shoulder construction
• Culvert construction
• Labour handling
• Industrial safety
There was no any item can be sold. So, we were in the invitation to disposal in the safe
manner. Special attention was given to social and environmental aspects. Especially, we did
not used incineration techniques to dispose the cleared items. Attention about the telecom
posts and electricity posts which disturb to project works (in 4.6m distance from centre line)
should also be concerned. For removing these documents on posts details and should submit
to CEB & SLT. Following figure shows site clearance using an excavator.
12
2.3.2 Embankment preparation
Embankments were constructed to reach the elevation of the rail track from the existing
ground profile accordance with standard drawings. In areas where embankment is to be
constructed, top soil will be removed to a depth of l 50mm to remove natural vegetation
cover. After the site has been cleared, the limits of embankment will be set out as required.
The pegs will be fixed at 1m distance outside the actual limits of the fill to keep the pegs un
disturbed. Figure 2.12 is embankment preparation of a road.
13
After preparation of subgrade sand cone test should be done. If the test value is 95% or more
than 95% surface is satisfactory. Figure 2.13 shows compacting of subgrade using a 4 Ton
roller.
Subbase material could be change according to site and according to laboratory tests. In our
site subbase was prepared by mixing soil and ABC in the ratio of 4 to 1.
Procedure
• In cases where sub-base material has to be spread on a sub-grade, the surface of sub-
grade should be cleared from any extraneous materials, compacted and called for
sand cone test. It should be greater than 95%.
• Then excavated levels should be taken, this is used when preparing bills.
14
• After checking the underlying layer for damages or deficiencies, Sub-base material
layer will be spread in layer of material not less than 150 mm thick & the length of
spreading will be 250m or less at a time. If necessary, a thicker layer of material will
be spread by mean of above mention machineries such as backhoe loader, Motor
grader and compaction will be done using suitable heavier roller.
Above figure 2.14 shows laying of sub base and Figure 2.15 shows about the grading of sub
base layer y motor grader.
15
• Before starting the compaction, if necessary, the required water content should be
added and mix with soil by water Bowser maintaining a suitable moisture content for
compaction. After that inspect the compacted surface.
• The compacted layer will be tested for degree of compaction & moisture content.
• Then sub base second layer can be applied if the subbase thickness is more than
160mm, and above procedure can be followed.
• Once the sub base filling is finished the final surveying will be carried out to check
the finished levels. The finished levels should be in the range from +10mm and -
20mm.
After that sub base layer will be protected by over laying of ABC layer.
In the case of sub base preparation on the existing paved road, the bituminous crust shall be
removed by scarifying and the exposed surface shall be suitably compacted. And sub base
material will be spread by motor grader or any other above machines. Following Figure 2.16
shows the finished sub base surface.
16
2.3.5 Aggregate base course layer (ABC) preparation
Aggregate base course layer known also as ABC should be lay after laying of subbase layer.
Thickness can be varied according to design. This is a mixture of granite particles less than
of size 37.5mm and quarry dust. This acts as an impermeable and stiff layer below the asphalt
layer.
Procedure
• First ABC finished levels for each chainage should be provided with sufficient
compaction. In our site compaction for ABC was 20mm. Usually we should provide
levels for each chainage. Those levels are given bellow.
01. Center levels. In our site center levels were not established as road width
was only 3m.
02. Required and useful levels of offsets measured from center point. In our
site established level pegs 1.6m from the center line as the road width was
3m.
• Next, we can lay approximately amount of ABC on sub base final layer. Following
figure shows laying of ABC on the subbase layer.
• Then we should mix water with ABC properly by using Motor Grader and water
bowser. water content of the ABC should be maintained properly. Because
segregation can be occurred.
17
• By using required and useful levels of offsets measured from center line, we can
prepare the levelled ABC layer by Motor grader. Figure 2.18 shows a levelled surface
of ABC.
• Next, we can compact above ABC layer by using a suitable vibrating roller. After
that we can call for sand cone test to know existing relative compaction. It should be
greater than 98%. Following Figure 2.19 shows ABC compaction with adequate
amount of water.
Figure 2.19:Compaction of
ABC surface
• Finally, the finished design ABC levels should be checked. The finished levels
should be in the range from +10mm and -20mm.
18
2.3.6 Establishment of level pegs for laying subbase and ABC
Before laying of subbase and ABC level pegs should be established. For these offcuts were
used and levels were established by adding 20mm for compaction.
So,
Following figure 2.20 shows the marked subbase level of a chainage point that was checked
by level machine and marked by a tape. This level is marked with 20mm for the compaction.
Remaining part of the peg should be removed.
Following Figure 2.21 shows removing the additional length of the peg that was previously
marked.
19
Figure 2.21:Adjusting the height of peg
Procedure
20
Undulation bar that used for Rd -03 was 3m in length and the road width was also 3m.
• Two measurements should be taken from transverse locations and one measurement
should be taken from each longitudinal location. Figure 2.23 shows taking a
longitudinal measurement when checking undulation.
Allowable range for transverse measurement is +8mm- -8mm and for longitudinal location
it is +10mm- -10mm. If the values are different from these rectifications should be done.
• As a waterproof membrane
21
• Strengthens the surface
Procedure of priming
• First of all, we should clean the existing ABC surface entirely using boomer
connected to Bobcat. This is to remove the quarry dust in top of ABC layer. This
should be done before the undulation check. Cleaning by using boomer is shown in
Figure 2.24.
Figure 2.24:Cleaning by
using boomer
• After that the surface should be cleaned by high pressured air compressor.
CSS1 should be mix well before apply on the ABC surface. (Suitable for wet ABC surface)
MC30 should be heated well before apply on the ABC surface. (Suitable for dry ABC
surface)
22
Figure 2.25:Priming of the ABC surface
At least we should keep priming surface one day entirely. Sometime after priming sand layer
should be laid to avoid sticking of prime in vehicles like in Figure 2.26.
23
layer which is not thicker that previous one. This is to increase the bondage between asphalt
layer to road. The flow is approximately 0.5lm-2. After this, asphalt paving can be started.
Following Figure 2.27 shows the guiding cable used in the road.
After laying guiding cable level pegs should be levelled. Figure 2.28 shows the levelling of
pegs.
24
After levelling the pegs required asphalt depth may not be gained. So that dip should be
checked and adjusted like in Figure 2.29.
Asphalt is paved by asphalt paver. First the paver width should be adjusted to the road width
and paver sensors to the guiding cable. This will provide an accurate road width. Following
Figure 2.30 shows laying of asphalt.
25
Paver and the asphalt truck should move together to get a uniform surface and the
temperature of every asphalt truck should be checked.
Manual adjustment should be done to road edges and to other required areas. Following
figure 2.32 shows that.
26
Temperatures of the asphalt mixture should be as follows in following steps.
Compaction of asphalt
Compaction is intended to achieve a uniform high density of the asphalt layer. Best result is
obtained only when the rolling is performed in the definite pattern and as soon after placing
as mix as possible. Rollers should move transversely across the run and travel at such a
speed. Asphalt layer is compacted by steel drum roller and after that by pneumatic tired roller
(PTR).
Steel drum roller is used to gain the required density quickly of the asphalt layer. This will
compact the layer fast. Figure 2.33 shows compaction by steel drum roller.
27
PTR is used after that. This makes the asphalt layer an impermeable layer and it fills the
voids in the asphalt. By this asphalt will be a laminated surface. Following Figure 2.34 shows
compacting by PTR roller.
28
There are two main methods of road and shoulder construction, one being construction of
the shoulder after the base-course and the other is construction of the shoulder before
the base-course.
This is the preferred method in modern constructions. The principle advantages are that
water is able to drain from the road surface, large capacity compaction equipment can be
used to roll the shoulder and it is easy to use graders.
Before the base-course is spread the shoulder, material should be brought in and placed in a
windrow at the edge of the formation. Small drainage slots can be cut in the windrow to let
any rain water escape. After the base-course has been spread and compacted the shoulder
is spread to the edge of the base, trimmed and then compacted along with the base-
course. The grader will set the moldboard to the required cross fall and use the general tilt
position for spreading. Following Figure 2.36 shows removal of excess ABC in both sides
of road.
29
Following is a figure of finished shoulder.
This method is not suggested If a grader is being used. Water can collect in the
base-course area (box) and as the shoulders are generally small in its width only small rollers
can be used. The edge of the shoulder on the base side has to be trimmed to the correct line
and this can be very time consuming. A grader will have to work with on side wheels
on the shoulder and the other in the box. This can make it hard to get a good fine
surface. But we can prevent waste of ABC and damage to base course.
30
Figure 2.38:Cross section of a culvert
31
Following Figure 2.40 shows the box reinforcement details and Figure 2.41 shows a bar
schedule used to culvert construction.
32
Figure 2.41:Bar schedule of a culvert
33
• Reinforcement and formwork were done for wall, upper hunch and deck
were concreted by using grade 30 concrete.
• Curing was done for required time period.
• Formwork was removed after required setting time.
• The wing wall was constructed by Grade 15 concrete.
• Then backfilling should be done.
• Parapet wall and guard stones were constructed.
Backfilling of culverts
After completion of concreting backfilling should be done. When backfilling near the head
walls weep holes also should be consider. Weep hole arrangement should be as follows.
34
Figure 2.44:Weep hole arrangement
When doing backfilling each layer should be around 200mm and should be test for the degree
of compaction.
Apparatus used
Electronic Balance
Brush
Buckets
Standardized sand
35
Procedure
• First measure the weight of empty sand cone and weight of the sand cone after filled
with sand.
• A hole was drilled using bit and hammer slightly larger than to its hole size. The
drilling depth normally should be 150mm. Collect the soil collected from the hole
and measure the weight. Figure 2.45 shows drilling a hole for sand cone test.
• The sand cone is placed on the hole with help of the base plate and is allowed
to fill the hole by opening the control valve.
• When the sand stops running, the valve is closed and the cone is weighed with the
remaining sand.
• Then the dry density of soil can be calculated and the percent of compaction of soil
is determined by using the maximum dry density. It should be above the specific
value of compaction.
36
w is the moisture content.
Embankment -95%
Base -98%
Apparatus used
Standard trays
Electronic balance
Figure 2.48:Tray
used in tray test
Procedure
• Remove the tray carefully and measure the weight after the bowser left.
w1−w0
Prime flow per 1m2 = 0.3x0.3 gm-2
38
So that applied prime volume per 1m2
𝑤1−𝑤0
=0.3𝑥0.3𝜌𝑥1000 lm-2
This rate should be in the range of 1 lm-2-1.5lm-2. If the rate is more than 1.5 lm-2 bleeding
of the road can be occurred and if the value is less the bond between the ABC and asphalt
could be less. Figure 2.49 shows colleting the tray for measuring the weight of tray and
collected prime.
This is a test used to measure the workability of concrete. Before concreting a culvert Slump
of concrete should be checked. According to the site acceptance, there should be a 180mm
(+ 25mm or -25mm) Slump height as the design factor of the concrete. Figure 2.50 shows
the equipment needed for the slump cone test.
Equipment needed
1. Slump cone
2. Tamping rod
3. Base plate
4. Meter ruler
5. Small scoop
6. Wire brush
Figure 2.50:Slump cone test equipment
39
Procedure
• The concrete should be placed in the slump cone in to three equal layers.
• Fill the slump cone to approximately 1/3 capacity (100mm height) and then
tamp the concrete with exact 25 blows.
• Repeat the above procedure two times until the slump cone is filled in its
volume
• Level the top surface of the concrete using the tamping rod
• Lift the slump cone carefully straight upwards, aiming to complete the
movements in 5-10 seconds, as the cone becomes clear, the concrete will
slump
• Using the steel ruler measure as shown in the Figure2.51 from the underside
of the bar to the top of the slump.
Compressive strength test for concrete is done at the site laboratory for 7 days and 28 days.
Generally, 150mm*150mm*150mm cubes are casting for both grades G20 & G25.
Procedure
40
• After curing of cubes, they were tested in the site lab.
75% of the strength should be in a cube for 7-day testing
When doing compressive strength test uneven surface of the cube shouldn’t be place
touching the machine plate as it causes high probability in failing.
41
Chapter 03
3. TRAINING EXPERIENCE-MANAGEMENT
3.1 Introduction
In this chapter site management and site safety is described.
5. Kiri-ibbanara
6. Hathporuwa
7. Koulara
8. Hambegamuwa
There are 3 site engineers who are appointed to these areas. Considering about site
management there is one project manager, deputy project manager, three site engineers,
technical officers and supervisors. Duties and responsibilities of these persons are as follows.
Project Manager
The project manager is the main person who handles the project and his role is as follows,
Site Engineer
Site engineer should answer to the project manager and consultants. He or she should,
42
• Implementation of safety measures.
Surveyor
He is the person who is bearing all the responsibilities about the details related to the
surveying of the site. There was one surveyor and four assistant surveyors in our project.
Accountant
He should,
Store keeper
Every activity within the stores comes under the storekeeper. He should,
Main stores issue the items through Good Received Note (GRN). They use these forms to
inform it. It includes with quantity, rate and date.
43
From other sites
When materials are requested from other sites, store keeper uses a transfer note. This form
should be filled and handover a copy to received officer.
When material needed, they were ordered from private suppliers also. When material ordered
from them original bill was sent to the head office and site stores and supplier keeps carbon
copy of bill.
44
• Material transfer note
Store keeper use these forms to transfer goods or material to another site. We fill
this form and hand over the one copy to received officer.
45
3.4.2 Points should be considered when using tools and equipment
• When handling the machine or truck mixture covered area properly by placing traffic
cones and required sign boards.
• Do not throw any heavy things from the high-level grounds that may cause injuries.
• When handling machine like back-hoe loader ensures that there is no danger from
live electrical cables or equipment closer to working place.
46
Safety helmets
Every working person should wear a helmet during his working period.
Safety gloves
These used to protect hands from chemicals used in site and to prevent from hand
injuries.
Safety jackets
These used as a luminous cloth during night time and that will prevent accidents. This
also used to identify the workers in the site from normal people.
47
Safety boots
These used to protect legs from injuries and mainly used during concreting.
Fire is a main way of happening accidents. Fire point is established in site to overcome that
problem. There were some skilled people to operate the fire extinguishers. Following Figure
3.5 shows the fire point of site.
In places of constructing culverts and during ABC, subbase levelling and during laying of
asphalt temporary roads should be introduced for the vehicle movement. Temporary roads
could be a part of the existing road or an alternate road.
48
3.4.5 Traffic safety and control
Safety officer is responsible for the traffic control and safety. He should visit all construction
areas and check about the safety. All necessary measures for the safety to traffic during
construction shall be taken by providing and maintaining barricades by using traffic cones,
barricade boards, direction boards, road signs, markings, flags, lights, etc.
At the point where traffic deviates from its normal path traffic boards with clear directions
should be placed. At night also they should be visible to traffic and people.
Following Figure 3.6 sign board is used to warn drivers that men are working ahead and they
need to turn.
When there is an ongoing work in the road sometimes it is need to stop the vehicles. This
method is used for that. If we want to stop the vehicles, lift the red flag or stop board. After
the work, lift the green flag or go board. This shown by Figure 3.7.
These sign boards shown in Figure 3.8 are used to show there is a hump and used before
30m and after 30m from a hump.
49
These signs shown in Figure 3.9 are used to give warning that the existing carriageway would
become narrow. The sign board should be chosen according to the narrowing side of the
road.
Barricades are used to separate the working area from trafficked areas. There prevent
vehicles and pedestrians entering the working area. Barrels or other types of containers also
can be used as barriers.
50
Chapter 04
I understood that only by having a theoretical knowledge we cannot involve in any site
works. To involve in a work, we should experience the work. A good civil engineer should
have the ability to solve each problem at the spot. During the training period I contact with
many people who have knowledge in different section. By this training I learned how to deal
with the labours and also about the villagers. As this is an I road project handling villagers
is very important and I learned that from this training. Site management is very important in
I road projects as sites are located in some distance from each other and they have to be
supervised by same people. That means they have to move from place to place to inspect the
relevant activities and that is somewhat difficult. So, I think this training period will be
helpful in my future to build up my carrier.
4.2 Conclusion
This was my second industrial training experience starting from 28th January 2019 to 21st
April 2019. I was successfully completed my training period with the help of theoretical
knowledge gained from university. In this period, I gained lot of knowledge from engineers
and supervisors about the road construction techniques and how to interact with people
during working.
I experienced lot and was able to get some basic knowledge regarding the field of civil
engineering. In this training I was able to gain the knowledge not only about the engineering
51
field but also who is an engineer? What are his duties and about his participation to the job
to perform well?
In my training period I had many difficulties as well as strengths. Following are some of
them.
Challenges
I was new to the road construction project. So, I had to learn about the working procedure of
the site and role of each person. Labour and villagers handling also very challenging.
Villagers always complain about the road problems and issues from site vehicles to houses.
So, the engineer should have to maintain those also.
This was done for the first time in my training. For this I got help from the site
engineer and the consultants also.
For this there were many methods used by different people and that was learned by
me from the supervisor of the area.
Strengths
On the side of strength, my in-charge did a lot of help. They always tried to teach something
to me as I was asking about things. Not only them labours also taught me new things. I
learned lot of new things like labour handling, quality checking, material testing. Very
important thing that I learned from this site was taking of responsibility like working on time,
finishing job on time with limited resources taking the right decision and so on. As our site
had limited resources, I learnt how to manage those efficiently.
Suggestions
In developing this project, I have some suggestions. Work schedule was not good in this site.
Most of the time labours waste their time due to lack of tools and machinery. That has to be
well maintained and developed by the officers. Most of labours were not skilled and they
were villagers. So, they have to learn and do the work. That also be a waste of time.
52
On this training according to my point of view, I think that circulating the trainees in works
would be helpful to the trainee in developing their skills.
53
References
1. Maga Engineering (Pvt) Ltd. Sri Lanka |. 2019. Maga Engineering (Pvt) Ltd. Sri Lanka
|. [ONLINE] Available at: https://www.maga.lk/. [Accessed 01 June 2019].
2. Company History & Timeline | Maga Engineering (Pvt) Ltd. Sri Lanka. 2019. Company
History & Timeline | Maga Engineering (Pvt) Ltd. Sri Lanka. [ONLINE] Available at:
https://www.maga.lk/about-us/company-history-timeline/. [Accessed 02 May 2019].
3. home.iitk.ac.in. 2019. No page title. [ONLINE] Available at:
http://home.iitk.ac.in/~pkbd/Lab-DensitySandCone.html. [Accessed 13 June 2019].
4. home.iitk.ac.in. 2019. No page title. [ONLINE] Available at:
http://home.iitk.ac.in/~pkbd/Lab-DensitySandCone.html. [Accessed 13 June 2019].
54