GXY PCM1 - Schedule Draft Update DD210830 (CP)
GXY PCM1 - Schedule Draft Update DD210830 (CP)
Galaxy Sal de Vida Package 1 EPC Act Aug21 476 23-Jul-21 A 19-Dec-22
Actual Level of Effort Remaining Work Critical Remaining Work Page 1 of 3 TASK filter: Critical.
Actual Work Sub Critial Milestone © Oracle Corporation
Sal de Vida Lithium Brine Project
Package 1 Procurement & Constrution Schedule
(Critical Path)
Activity ID Activity Name Remaining Start Finish Indicators2021 2022 2023
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
A2050 SVWP20_06, Diesel Generator & Storage Mounting 3 11-Dec-21 13-Dec-21
A2060 SVWP20_06, Electrical Equipment Mounting & Wiring 5 11-Dec-21 15-Dec-21
A5970 SVWP20_06 Valve Installation on Well Head 1 12-Dec-21 13-Dec-21
A6080 SVWP20_06, Early SU 0 16-Dec-21
Main Brine Duct & Interconnections 33 13-Nov-21 16-Dec-21
Construction 33 13-Nov-21 16-Dec-21
A2930 HDPE Pipe Laydown from Booster Station to Halite Ponds (5.000 Mts.) 24 15-Nov-21 08-Dec-21
A2940 Hydraulic Tests (HDPE) 30 13-Nov-21 13-Dec-21
A5890 SVWP20_08 to HDPE Main Pipeline PEX Pipe Laydown and Installation 2 08-Dec-21 09-Dec-21
A5900 SVWP20_07 to HDPE Main Pipeline PEX Pipe Laydown and Installation 1 10-Dec-21 11-Dec-21
A5910 SVWP20_06 to HDPE Main Pipeline PEX Pipe Laydown and Installation 1 11-Dec-21 12-Dec-21
A5920 SVWP20_08 to HDPE Pipe Tie In Installation 1 13-Dec-21 14-Dec-21
A5930 SVWP20_07 to HDPE Pipe Tie In Installation 1 14-Dec-21 15-Dec-21
A5940 SVWP20_06 to HDPE Pipe Tie In Installation 1 15-Dec-21 16-Dec-21
A6620 SVWP20_05 to HDPE Main Pipeline PEX Pipe Laydown and Installation 1 12-Dec-21 13-Dec-21
Actual Level of Effort Remaining Work Critical Remaining Work Page 2 of 3 TASK filter: Critical.
Actual Work Sub Critial Milestone © Oracle Corporation
Sal de Vida Lithium Brine Project
Package 1 Procurement & Constrution Schedule
(Critical Path)
Activity ID Activity Name Remaining Start Finish Indicators2021 2022 2023
Duration
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
A4540 PCK2.M001-8 - Slaking Lime Package, Quotations Reception 21 11-Sep-21 01-Oct-21
A4550 PCK2.M001-8 - Slaking Lime Package, Bid Analysis & Po Placement 52 02-Oct-21 22-Nov-21
A4560 PCK2.M001-8 - Slaking Lime Package, Fabrication & Delivery 154 23-Nov-21 25-Apr-22
Subcontracts 185 04-Aug-21 A 02-Mar-22
A4042 PCK2.W001 - EPC Contractor, Quotations Reception 25 04-Aug-21 A 23-Sep-21
A4044 PCK2.W001 - EPC Contractor, Bid Analysis & Po Placement 70 24-Sep-21 02-Dec-21
A4047 PCK2.W001 - EPC Contractor, Mobillisation 30 01-Feb-22 02-Mar-22
Liming 80 26-Apr-22 14-Jul-22
Construction 80 26-Apr-22 14-Jul-22
A5080 Early Liming, Equipment Mounting 45 26-Apr-22 09-Jun-22
A5240 Early Liming, Pumps Installation 15 31-May-22 14-Jun-22
A6680 Early Liming, Pipe Installation (Lime Plant to Muriate Buffer Pond) 15 15-Jun-22 29-Jun-22
A6681 Early Liming, Precomm / Com / Start Up 15 30-Jun-22 14-Jul-22
Process Plant 288 06-Mar-22 19-Dec-22
Construction 288 06-Mar-22 19-Dec-22
A5095 Event Pond, Earthworks & Liner Installation 10 06-Mar-22 15-Mar-22
A5100 Process Plant, Earthworks 15 16-Mar-22 30-Mar-22
A5110 Process Plant, Precast Elements Mounting 120 31-Mar-22 28-Jul-22
A5120 Process Plant, Equipment Mounting 180 13-May-22 08-Nov-22
A5125 Process Plant, Steel Structures & Buildings Assembly 180 12-Jun-22 08-Dec-22
A5130 Process Plant, Racks Mounting 150 30-Apr-22 26-Sep-22
A5140 Process Plant, Piping Mounting & Interconnections 180 02-Jun-22 28-Nov-22
A5160 Process Plant, Instrumentation Trays Mounting 150 30-May-22 26-Oct-22
A5180 Process Plant, Instrumenation Mounting & Wiring 120 29-Jul-22 25-Nov-22
A5190 Process Plant, Hydraulic Tests 90 10-Sep-22 08-Dec-22
A5200 Process Plant, Instrumentation Calibration & Tests 90 07-Sep-22 05-Dec-22
A5210 Process Plant, Precommissioning 30 09-Nov-22 08-Dec-22
A5220 Process Plant, Commissioning 30 19-Nov-22 19-Dec-22
Actual Level of Effort Remaining Work Critical Remaining Work Page 3 of 3 TASK filter: Critical.