Professional Documents
Culture Documents
APPENDIX – F
PERCENTAGE
OF BID
Sl.
PARTICULARS OF THE COMPONENT AMOUNT
No.
WITHOUT
THE O&M
1 2 3
1. Barrage including scouring sluices, fish ladder, abutments and guide
walls, piers, pier cap etc. complete in all respect as per the Technical
specification and approved drawing.
3. Gates, stop logs & hoists including hoist bridge, gantry crane and
lifting beam, embedded parts, Power connectivity including all
structural works, cables for operation of hoist and lighting of the
barrage area and bridge etc. complete in all respect as per the relevant
Technical Specification and approved drawing.
Total 100
APPENDIX – F 1
Barrage including scouring sluices, fish ladder, abutments and guide walls, Piers, Pier cap etc.
complete in all respect as per the Technical specification and approved drawing.
Percentage of
Sl.
PARTICULARS OF THE COMPONENT Component
No.
Amount
1 2 3
1. After detail survey, investigation, foundation exploration for fixing
alignment of Weir, etc, as per relevant IS codes, IRC codes, MoRTH
specification and circulars, issued by department from time to time,
planning and design of all components, Preparation of detail estimate
as per Schedule of Rates of Odisha on the basis of approved design- 2
drawing, clubbing of items for record of measurement and basis of
payment, getting approval from competent authorities. Processing of
land acquisition, forest clearance and Right of Way, if required &
getting approval from competent authorities.
TOTAL 100
Note: “A”=0.93(Bid value for the work executed ÷ the sanctioned estimate amount for the
work executed)
APPENDIX – F 2
Bridge deck including parapet, expansion joint, wearing coat and bearing etc. complete in all
respect as per Technical Specification and approved drawing.
Percentage of
Sl.
PARTICULARS OF THE COMPONENT Component
No.
Amount
1 2 3
1. After Detail survey, investigation, foundation exploration for fixing
alignment of barrage and bridge, etc, as per relevant IS codes, IRC
codes, MoRTH specification and circulars, issued by department
from time to time, planning and design of all components,
Preparation of detail estimate as per Schedule of Rates of Odisha on
2
the basis of approved design-drawing, clubbing of items for record of
measurement and basis of payment, getting approval from competent
authorities. Processing of land acquisition, forest clearance and
Right of Way, if required & getting approval from competent
authorities.
TOTAL 100
Note: “A”=0.93(Bid value for the work executed ÷ the sanctioned estimate amount for the
work executed)
APPENDIX – F 3
Gates, stop logs & hoists including hoist bridge, gantry crane and lifting beam, embedded parts,
Power connectivity including all structural works, cables for operation of hoist and lighting of the
barrage area and bridge etc. complete in all respect as per the relevant Technical Specification and
approved drawing.
Percentage of
Sl.
PARTICULARS OF THE COMPONENT Component
No.
Amount
1 2 3
1. After Detail survey, investigation, foundation exploration for fixing
alignment of barrage, bridge, Power connectivity etc, as per relevant
IS codes ,IRC codes, MoRTH specification, OERC norms and
circulars, issued by department from time to time, planning and
2
design of all components, preparation of detail estimate as per
Schedule of Rates of Odisha on the basis of approved design-
drawing, clubbing of items for record of measurement and basis of
payment, getting approval from competent authorities.
TOTAL 100
Note: “A”=0.93(Bid value for the work executed ÷ the sanctioned estimate amount for the
work executed)
APPENDIX – F 4
PAYMENT SCHEDULE FOR
Guide banks/Afflux Bund including all ancillary works, Approach roads including all cross
drainage works & watchman and operator quarter includes electrification, water supply and
sewerage system as per Technical Specification and approved drawing.
Percentage of
Sl.
PARTICULARS OF THE COMPONENT Component
No.
Amount
1 2 3
1. After Detail survey, investigation, foundation exploration for fixing
alignment of Guide banks/Afflux Bund to avoid any type of
submergence , Approach roads & staff quarters , etc, as per relevant
IS codes ,IRC codes, MoRTH specification and circulars, issued by
department from time to time, planning and design of all
components, Preparation of detail estimate as per Schedule of Rates 1
of Odisha on the basis of approved design-drawing, clubbing of
items for record of measurement and basis of payment, getting
approval from competent authorities, processing of land acquisition,
forest clearance and Right of Way ,if required & getting approval
from competent authorities.
2. After construction of the Guide banks/Afflux Bund, up to the Pond
level of the barrage, Approach roads up to the sub-base level and
staff quarters up to roof level as per approved design-drawing,
specifications , IS codes, IRC codes, MOST Manual etc Running
70
Bills will be paid as detailed below :- Amount of running Bill = Bill
amount as per actual quantity of work executed based on Sanctioned
estimates and by clubbing of items as approved by the competent
authorities x “A” Where “A” is defined in the note below.
3. After completion of construction of Guide banks/Afflux Bund
complete up to the design level, Approach roads and staff quarters
complete in all respect including all finishing work as per approved
design-drawing, specifications,. IS codes, IRC codes, MOST Manual
etc. Running Bills will be paid as detailed below :- Amount of 24
running Bill = Bill amount as per actual quantity of work executed
based on Sanctioned estimates and by clubbing of items as approved
by the competent authorities x “A” Where “A” is defined in the note
below.
4. After commissioning of weir, approach road, quarters etc. & after
defect liability period is over. 5
TOTAL 100
Note: “A”=0.93(Bid value for the work executed ÷ the sanctioned estimate amount for the
work executed)
APPENDIX F-5
Total
APPENDIX – MS
MILESTONES
Time in month
Milestone to
for achieving
be achieved as
milestone from
MS Particular physical % of
No. the
respective
commencement
item
of work
Total -----