You are on page 1of 1

Mr.

Saqib Sb, Revised Quotation Date: 10/14/2021


Installation Testing and commissioning of 12 Ton Self Contained
Package Units at Mangla Site
Sr No. Description Qty Rate Amount
1. Installation Testing and
Commissioning of 12 Ton self- 03 55,000/Each Unit 165,000.00
contained Package Unit
2. Electrical Cable Connections
from Main Panel to Unit. 03 8,000/Each Unit 24,000.00

3. Fabrication and Installation of


Duct Connections with 22 SWG 01 / RM 10,000/RM 80,000.00
GI Sheet Metal.(Estimated 4 RM)
4. Installation of Fiber Glass Duct
Insulation 50mm 16 Kg/m3 with 01 / RM 3600/RM 28,800.00
6 OZ Canvas Cloth Rapping.
(Estimated 4 RM)
5. Fabrication and Installation of GI 01/RM 7500/RM 60,000.00
Sheet Metal Cladding 26 SWG .
(Estimated 4 RM)
6. Installation of Flexible
Connection (Imported) Between 03 10,000/Each 30,000.00
Unit and Duct.
TOTAL 387,800.00

Terms and Conditions:


 Rates are Valid for 2 weeks only.
 Rates are Exclusive of all Taxes.
 For Lifting and Placing of Units Crane or Lifter
will be provided from the User.

 Living and Meal will be Provided By the User.


 Self-Contained Units Must be Pre Refrigerant Charged.
 Mode of Payment 75% advance and 25 % after Completion of Work.
 Transportation Loading & Unloading will be provided be the User.
 Electrical cables and Will be provided by the User.