The quotation provides a breakdown of costs for installing, testing, and commissioning 12-ton self-contained package units at the Mangla site. The total cost is 387,800 rupees which includes installation of 3 package units at 55,000 rupees each, electrical connections, fabrication and installation of duct connections with sheet metal and insulation, sheet metal cladding, and flexible duct connections. Payment will be made in two installments with 75% advance and 25% after completion of work.
Original Description:
Original Title
Revised Quotation for Installation of Units at Mangla
The quotation provides a breakdown of costs for installing, testing, and commissioning 12-ton self-contained package units at the Mangla site. The total cost is 387,800 rupees which includes installation of 3 package units at 55,000 rupees each, electrical connections, fabrication and installation of duct connections with sheet metal and insulation, sheet metal cladding, and flexible duct connections. Payment will be made in two installments with 75% advance and 25% after completion of work.
The quotation provides a breakdown of costs for installing, testing, and commissioning 12-ton self-contained package units at the Mangla site. The total cost is 387,800 rupees which includes installation of 3 package units at 55,000 rupees each, electrical connections, fabrication and installation of duct connections with sheet metal and insulation, sheet metal cladding, and flexible duct connections. Payment will be made in two installments with 75% advance and 25% after completion of work.
Installation Testing and commissioning of 12 Ton Self Contained Package Units at Mangla Site Sr No. Description Qty Rate Amount 1. Installation Testing and Commissioning of 12 Ton self- 03 55,000/Each Unit 165,000.00 contained Package Unit 2. Electrical Cable Connections from Main Panel to Unit. 03 8,000/Each Unit 24,000.00
3. Fabrication and Installation of
Duct Connections with 22 SWG 01 / RM 10,000/RM 80,000.00 GI Sheet Metal.(Estimated 4 RM) 4. Installation of Fiber Glass Duct Insulation 50mm 16 Kg/m3 with 01 / RM 3600/RM 28,800.00 6 OZ Canvas Cloth Rapping. (Estimated 4 RM) 5. Fabrication and Installation of GI 01/RM 7500/RM 60,000.00 Sheet Metal Cladding 26 SWG . (Estimated 4 RM) 6. Installation of Flexible Connection (Imported) Between 03 10,000/Each 30,000.00 Unit and Duct. TOTAL 387,800.00
Terms and Conditions:
Rates are Valid for 2 weeks only. Rates are Exclusive of all Taxes. For Lifting and Placing of Units Crane or Lifter will be provided from the User.
Living and Meal will be Provided By the User.
Self-Contained Units Must be Pre Refrigerant Charged. Mode of Payment 75% advance and 25 % after Completion of Work. Transportation Loading & Unloading will be provided be the User. Electrical cables and Will be provided by the User.