Mr. Humayun Haroon,
Sapphire Textile Mills,
Phool Nagar, Pakistan.
Respected Sir,
Thank you for giving SME Energy (pvt) Ltd a chance to present you our financial proposal for the
solar system that will be installed at your premises. We hope this will be the start of a long-term,
prosperous relationship. We thrive to deliver savings in our clients’ electricity costs and help to
manage energy resources for optimum availability and efficiency. We take pride in helping our
clients to reduce their dependency on noisy generators, enjoy the benefits of clean energy and help
make the world a better place.
Our team consists of experts from the Renewable Power segment, and especially from the Solar PV
sector, capable of executing large scale Solar PV projects in compliance with industry best practices
and regulatory & statutory norms.
After the Installation of Solar System at your premises, it is remotely monitored by our technical
personnel to ensure smooth operations. In case of any issue, our personnel will immediately
respond to diagnose the issue and to troubleshoot remotely or at site.
As per the part of the quotation, Net Metering application will be submitted on your behalf to the
concerned Grid operator and we will ensure that our customers get full benefit of this facility, The
Net Metering package allows solar system owners to sell excess energy back to the grid, translating
to a direct economic benefit for system owners. In addition, Net Metering also contributes towards
increasing overall energy efficiency in the country by increasing energy availability on the Grid near
the point of consumption.
We look forward to helping you achieve more energy independence, providing a good investment
for years to come, and helping you make a more positive environmental impact.
Name of Salesperson:
Contact Number:
Quotation
Net Metering
Not Applicable
Bank Details
Account Title: SME Energy (pvt) LTD
Account Number: 0289-0105319889, Meezan Bank Raja Market Branch Lahore.
On-Grid Solar Solution - Payback Calculation
Grid Cost Per Unit (bill analysis) 17.16 Rs / kWh Installed Modules 1,000.08 kWp
Total System Cost 75,694,700 Rs Invested
Tariff Inflation 5.0% per year Annual Maintenance 1.0% % of System cost
IRR 35.5%
Client: Mr. Humayun Haroon
Address: Sapphire Textile Mills, Phoolnagar, Kasur.
PVsyst V7.2.2
VC0, Simulation date:
16/09/21 21:01
with v7.2.2
Project summary
Geographical Site Situation Project settings
Basti Sher Nagar Latitude 31.15 °N Albedo 0.20
Pakistan Longitude 73.91 °E
Altitude 194 m
Time zone UTC+5
Meteo data
Basti Sher Nagar
Meteonorm 8.0, Sat=24% - Synthetic
System summary
Grid-Connected System No 3D scene defined, no shadings
System information
PV Array Inverters
Nb. of modules 1852 units Nb. of units 7 units
Pnom total 1000 kWp Pnom total 770 kWac
Pnom ratio 1.299
Results summary
Produced Energy 1443 MWh/year Specific production 1443 kWh/kWp/year Perf. Ratio PR 82.80 %
Table of contents
Project and results summary 2
General parameters, PV Array Characteristics, System losses 3
Main results 6
Loss diagram 7
Special graphs 8
P50 - P90 evaluation 9
PVsyst V7.2.2
VC0, Simulation date:
16/09/21 21:01
with v7.2.2
General parameters
Grid-Connected System No 3D scene defined, no shadings
PV Field Orientation
Orientation Sheds configuration Models used
Fixed plane No 3D scene defined Transposition Perez
Tilt/Azimuth 10 / 0 ° Diffuse Perez, Meteonorm
Circumsolar separate
PV Array Characteristics
PV module Inverter
Manufacturer Longi Solar Manufacturer Ginlong Technologies
Model LR5-72 HIH 540 M Model GCI-110K--5G
(Original PVsyst database) (Original PVsyst database)
Unit Nom. Power 540 Wp Unit Nom. Power 110 kWac
Number of PV modules 1852 units Number of inverters 7 units
Nominal (STC) 1000 kWp Total power 770 kWac
Array #1 - PV Array
Number of PV modules 1548 units Number of inverters 58 * MPPT 10% 5.9 units
Nominal (STC) 836 kWp Total power 644 kWac
Modules 86 Strings x 18 In series
At operating cond. (50°C) Operating voltage 180-1000 V
Pmpp 764 kWp Max. power (=>40°C) 121 kWac
U mpp 672 V Pnom ratio (DC:AC) 1.30
I mpp 1137 A
Array #2 - Sub-array #2
Number of PV modules 304 units Number of inverters 12 * MPPT 10% 1.1 units
Nominal (STC) 164 kWp Total power 126 kWac
Modules 16 Strings x 19 In series
At operating cond. (50°C) Operating voltage 180-1000 V
Pmpp 150 kWp Max. power (=>40°C) 121 kWac
U mpp 709 V Pnom ratio (DC:AC) 1.30
I mpp 212 A
Array losses
Array Soiling Losses Thermal Loss factor LID - Light Induced Degradation
Loss Fraction 1.0 % Module temperature according to irradiance Loss Fraction 2.0 %
Uc (const) 29.0 W/m²K
Uv (wind) 0.0 W/m²K/m/s
PVsyst V7.2.2
VC0, Simulation date:
16/09/21 21:01
with v7.2.2
Array losses
IAM loss factor
Incidence effect (IAM): User defined profile
PVsyst V7.2.2
VC0, Simulation date:
16/09/21 21:01
with v7.2.2
DC wiring losses
Global wiring resistance 8.3 mΩ
Loss Fraction 1.5 % at STC
System losses
Unavailability of the system
Time fraction 0.3 %
1.0 days,
3 periods
PVsyst V7.2.2
VC0, Simulation date:
16/09/21 21:01
with v7.2.2
Main results
System Production
Produced Energy 1443 MWh/year Specific production 1443 kWh/kWp/year
Performance Ratio PR 82.80 %
Legends
GlobHor Global horizontal irradiation EArray Effective energy at the output of the array
DiffHor Horizontal diffuse irradiation E_Grid Energy injected into grid
T_Amb Ambient Temperature PR Performance Ratio
GlobInc Global incident in coll. plane
GlobEff Effective Global, corr. for IAM and shadings
PVsyst V7.2.2
VC0, Simulation date:
16/09/21 21:01
with v7.2.2
Loss diagram
1649 kWh/m² Global horizontal irradiation
+5.7% Global incident in coll. plane
PVsyst V7.2.2
VC0, Simulation date:
16/09/21 21:01
with v7.2.2
Special graphs
Daily Input/Output diagram
PVsyst V7.2.2
VC0, Simulation date:
16/09/21 21:01
with v7.2.2
Probability distribution