FRM-ENG-020

PERKIRAAN PRODUKSI HARIAN BERDASARKAN PERHITUNGAN TRUCK COUNT


PT. RIUNG MITRA LESTARI PROJECT HAULING ROAD SITE EBH
Jobsite EBH
Date : 04-May-2022

4-May-22 MTD
NO. KEY PERFORMANCE INDICATOR UNIT
PLAN ACTUAL ACH PLAN ACTUAL ACH
1 OB Removal (by Monthly Plan) BCM 12,701 7,601 59.8% 31,108 21,087 67.8%
2 Coal Getting (by Monthly Plan) Ton 0 0.0 0.0% 0.0 0 0.0%
3 SR (by Monthly Plan) 0.00 0.00 0.0% 0.00 0.00 0.0%
4 Distance OB Mtr 600.0 181.8 30.3% 600.0 253.2 42.2%
5 Distance Coal Getting Mtr 0.0 0.0 0.0% 0.0 0.0 0.0%
6 Physical Availability (PA) % 90.8% 97.3% 107.2% 90.8% 97.1% 106.9%
7 Utilization of Availability (UA) % 70.9% 59.1% 83.4% 70.9% 50.9% 71.8%
8 Utilization of MoHH (UoMOHH) % 64.4% 57.6% 89.4% 64.4% 49.5% 76.8%
9 Rain Hrs 1.20 2.3 187.5% 4.80 5.0 105.1%
10 Slippery Hrs 1.00 1.1 108.0% 4.00 3.4 85.3%
11 Rain Intensity mm 8.00 1.00 12.5% 4.00
12 Fuel Ratio OB Ltr/BCM 0.593 0.789 133.2% 0.593 0.830 140.0%
13 Fuel Ratio Coal Ltr/Ton 0.000 0.000 0.0% 0.000 0.000 0.0%
14 Fuel Inventory Ltr 0 0 0.0%
15 Effective Working Hours Hrs 15.46 15.79 102.2% 15.46 12.83 83.0%
16 Coal Inventory Ton 0.0 0 0.0%
17 Blast Inventory / Broken Material BCM 0.0 0 0.0% 0.0 0 0.0%
18 Blast Material Loaded (By truck count) BCM 0.0 0 0.0% 0 0 0.0%
11200

NO. REMAINING TARGET UNIT


DAILY MTD
a Overburden Bcm 12,976 337,382
b Coal Mine Ton 0 0

Prepared by, Acknowledge by,

( Lula Teqwil Arrizal ) ( Andy Dwi )


FGDP Moco Officer Act. Sect. Head