REPORT KESESUAIAN DESAIN

SEGMENT 1 - Hauling Road

STA Description STA Description

ONDESAIN - wait progress drop cut badan jalan


0+150 0+500 ONDESAIN - need construct paritan
by SPK 12 & 13

ONDESAIN - wait progress drop cut badan jalan ONDESAIN - need perapian spoil badan jalan dan
0+200 0+550
by SPK 12 & 13 pelebaran geometri jalan

Data topografi belum update area FILL STA


0+250 0+600 ONDESAIN - need perapian spoil badan jalan
tersebut

Data topografi belum update area FILL STA


0+300 0+650 ONDESAIN - need perapian spoil badan jalan
tersebut

Data topografi belum update area FILL STA Penimbunan (on desain) wait instalasi Gorong-
0+350 0+700
tersebut gorong Aramco by EBH

Penimbunan (on desain) wait instalasi Gorong- Penimbunan (on desain) wait instalasi Gorong-
0+400 0+750
gorong Aramco by EBH gorong Aramco by EBH

0+450 ONDESAIN - need construct paritan


REPORT KESESUAIAN DESAIN
SEGMENT 1 - Hauling Road

STA Description STA Description

NEED - Penimbunan (on desain) wait source


0+800 CLOSED - need perapian spoil badan jalan 1+150
material CUT (issue overdistance)

Data topografi belum update area FILL STA


0+850 ONDESAIN - need construct bundwall 1+200
tersebut

Penimbunan (on desain) wait instalasi Gorong- Data topografi belum update area FILL STA
0+900 1+250
gorong Aramco by EBH tersebut

Penimbunan (on desain) wait instalasi Gorong- Data topografi belum update area FILL STA
0+950 1+300
gorong Aramco by EBH tersebut

UNDERCUT slope material freedig pasiran


Data topografi belum update area FILL STA
1+000 (tabungan source material utk alocate 1+350
tersebut
penimbunan gorong" STA 0+900)

UNDERCUT slope material freedig pasiran


Data topografi belum update area FILL STA
1+050 (tabungan source material utk alocate 1+400
tersebut
penimbunan gorong" STA 0+900)

NEED - Penimbunan (on desain) wait source Data topografi belum update area FILL STA
1+100 1+450
material CUT (issue overdistance) tersebut
REPORT KESESUAIAN DESAIN
SEGMENT 1 - Hauling Road

STA Description STA Description

UNDER Level elevasi - tabungan material keras


Data topografi belum update area FILL STA
1+500 1+850 untuk finising badan jalan dan rencana
tersebut
penimbunan Aramco

Data topografi belum update area FILL STA


1+550 1+900 ONDESAIN - remaining construct tanggul
tersebut

Data topografi belum update area FILL STA


1+600 1+950 ONDESAIN - remaining construct tanggul
tersebut

Data topografi belum update area FILL STA NEED pelebaran jalan dan update topografi area
1+650 2+000
tersebut FILL

NEED pelebaran jalan dan update topografi area


1+700 ONDESAIN - remaining construct tanggul 2+050
FILL

UNDER Level elevasi - tabungan material keras


1+750 untuk finising badan jalan dan rencana 2+100 ONDESAIN - remaining construct parit
penimbunan Aramco

UNDER Level elevasi - tabungan material keras


1+800 untuk finising badan jalan dan rencana 2+150 ONDESAIN - remaining construct parit
penimbunan Aramco
REPORT KESESUAIAN DESAIN
SEGMENT 1 - Hauling Road

STA Description STA Description

NEED - pelebaran badan jalan (resloping Data topografi belum update area FILL STA
2+250 2+600
penegakan slope tersebut & NEED monitoring level base jalan

2+300 ONDESAIN - remaining construct parit

2+350 ONDESAIN - remaining construct tanggul

2+400 ONDESAIN - remaining construct parit

NEED - Penimbunan (on desain) wait source


2+450
material keras

2+500 ONDESAIN - remaining construct tanggul

2+550 ONDESAIN
REPORT KESESUAIAN DESAIN
SEGMENT 1 - Hauling Road

STA Description STA Description

Data topografi belum update area FILL STA


2+650 tersebut & NEED pengukuran sampai toe
dumpingan

UNDER Level elevasi - NEED smoothing dan


2+700
monitoring level base jalan

2+750 ONDESAIN - Need finishing bundwall

NEED - Penimbunan level elevasi & lebar badan


2+800
jalan (follow up monitoring Survey)

NEED - Pelebaran badan jalan (follow up survey


2+850
based on BORROW area sisi selatan- barat

ONDESAIN - NEED update topo area FILL


2+900
sampai dengan toe dumpingan

ONDESAIN - NEED update topo area FILL


2+950
sampai dengan toe dumpingan
REPORT KESESUAIAN DESAIN
SEGMENT 1 - Hauling Road

STA Description STA Description

ONDESAIN - NEED update topo area FILL


3+000 3+300 UNDER - level elevasi badan jalan
sampai dengan toe dumpingan

UNDER slope sisi timur & Progress construct


ONDESAIN - Case kaki dumpingan sliding di area
3+050 3+350 slope landai sisi barat (Dominan material pasiran
cekungan
lepas) *concern : lebar badan jalan

NEED - penimbunan sesuai level desain (case UNDER - level elevasi badan jalan & slope sisi
3+100 3+450
subsidence dumpingan sliding di area cekungan) timur

ONDESAIN - NEED update topo area FILL UNDER - level elevasi badan jalan (follow up
3+150 3+500
sampai dengan toe dumpingan kontinu monitoring by Survey)

ONDESAIN - NEED update topo area FILL NEED - perapian level & lebar badan jalan (follow
3+200 3+550
sampai dengan toe dumpingan up kontinu monitoring by Survey)

ONDESAIN - NEED update topo area FILL NEED - perapian level & lebar badan jalan (follow
3+250 3+600
sampai dengan toe dumpingan up kontinu monitoring by Survey)