Professional Documents
Culture Documents
EXTERNAL SERVICES
EXTERNAL SERVICES
AND
FIELD SUPPORT SERVICES
FIELD SUPPORT ERECTION AND RLA AND
SERVICES COMMISSIONING R&M
SERVICE SECTORS
PRODUCT RANGE
• FERTIZERS
• INDUSTRIAL STEAM TURBINES
• PETROCHEMICALS
• GENERATORS • REFINERIES
• COMPRESSORS • STEEL
• CEMENT
• HEAT EXCHANGERS
• SUGAR
• PUMPS • PAPER
1
CASE STUDY
PROJECT ACTION TAKEN
1. SAIL ROURKELA (C P P) - 60 MW TG
2. DESU RAJGHAT - 67.5 MW TG • The problem was discussed with NTPC and
DESU engineers
PROBLEM
• Root cause was identified as lifting of casing at the
Bearing high vibrations causing load limitation exhaust hood
OBSERVATIONS • Bottom casing was dismantled, cutting the
• Machines developed high vibrations in due course condenser connecting piece
of operations • Turbine vertical flange was de-fastened and
• Rear bearing vibrations shoot up on loading the exhaust hood separated
machine beyond 40 mw
• Turbine casing exhaust hood getting lifted. • Exhaust hood bottom and sole plates were ground
and matched
• Casing deformed
• Normal overhauls could not resolve the problem
2
• Exhaust hood anchoring key was modified
STATUS
3
Bharat Heavy Electricals Limited
Ramachandrapuram
Hyderabad
INDIA
TEST REQUISITION
• FAILURE HISTORY
• STRESS ANALYSIS DATA ON CRITICAL COMPONENTS
• OPERATIONAL HOURS
• MATERIAL CERTIFICATES
• STARTUPS & SHUTDOWNS
4
SMALL COMPONENTS WHICH ARE RETIRED
OR RE-USED, BASED ON
H.P. ROTORS
DIMENSIONAL INSPECTION
Oper. Temp. >480 ° C )
! Turbine rotors ( Oper.
• SEALING FINS • Cyclic thermal stresses
• LABRYNTHS • Centrifugal stresses
• Creep
• FASTENERS
! Low cycle fatigue cracking.
• COUPLING BOLTS ! Bend / Bow - Deciding factor for repair-
repair-run
• OIL GUARDS or replacement.
• BEARINGS ! Remanent life of rotor by Manson&Halfords
10% rule.
• GEARS
L.P. ROTORS
MOVING BLADES
! Creep influence on LP rotors is negligible.
! Common defects on shrunk fits :
" Deformation ! Life of the moving blades is unpredictable.
" Cracking through keyways
! Condition assessment is by DP, MPI and
" Permanant elongation & relaxation shrunk
Frequency tests.
fit
" Corrosion cracking
! Bend / Bow
! Recommendations - Repair-
Repair-run / Replace. ! Recommendations - Repair / Replace
5
AUXILIARIES AUXILIARIES
! CONDENSER !EJECTOR
# Nozzle erosion
# Tube leakage # Tube leakage / puncture
# Scaling
!HEATERS
# Erosion / Corrosion on baffles tube # Too many flange joints in feed water
plate and other internals. system.
# Frequent tube failures from coil type tubes.
# Poor performance of level control system
Eddy Current Tests for tubes Eddy current test for tubes.
6
CASE STUDY - II CASE STUDY - II
THERMAL FATIGUE CRACKS ON A 110 MW HP THERMAL FATIGUE CRACKS ON A 110 MW HP
ROTOR. ROTOR.
12
the crack near Curtis wheel had a depth range of
12
R5 R 2.5
55 18 to 20mm.
CORRECTIVE ACTION
$ The rotor was machined and cracks were R26 25
12
12
removed. R5 R 2.5
55
7
CASE STUDY - III CASE STUDY - III
LIFE EXTENSION OF 110 MW TG SET BASED ON LIFE EXTENSION OF 110 MW TG SET BASED ON
RESIDUAL LIFE ASSESSMENT RESIDUAL LIFE ASSESSMENT
$ LE Based on overall performance of $ General Performance after 20 years :
& Maximum Load - 90 MW (Derated)
equipment, auxiliaries, systems and sub & PLF - 55 %
systems. & Overall heat rate - 3050 KCal / KWHr
$ Typical life history & Turbine heat rate - 2440 KCal / KWHr
& Rated parameters :
Load - 110 MW $ Salient points from residual life assessment
MS pressure - 130 ata tests :
MS temperature - 530 ° C
Condenser vacuum - 0.9 kg/cm2 & HP rotor cracks in fillet & heat relieving grooves.
Overall heat rate - 2537 KCal/ KWHr & HP blades - mechanical hits and erosion.
Turbine heat rate - 2153 KCal/ KWHr & C1 & C2 shrouds damaged - mechanical rubbing
& Commissioned - Early 70s & Sealing fins uprooted.
& Operational Hrs - More than 2 Lakhs & Coupling bolt holes enlarged due to repeated
reaming.
& LP rotor
# Erosion and corrosion in blades.
# Repeated blade failure in 3 & 3A stages.
# Stress corrosion cracking in shrunk fit Corrosion & Erosion of Moving Blades
moving wheels.
8
Shearing off of Blades due to stress corrosion
9
CASE STUDY - III CASE STUDY - III
LIFE EXTENSION OF 110 MW TG SET BASED ON LIFE EXTENSION OF 110 MW TG SET BASED ON
RESIDUAL LIFE ASSESSMENT RESIDUAL LIFE ASSESSMENT
HP TURBINE
CASE STUDY - III
LIFE EXTENSION OF 110 MW TG SET BASED ON
RESIDUAL LIFE ASSESSMENT
LIFE EXTENSION PROPOSALS :
$ PROPOSALS
& Keeping outer casings as it is, replace the liners,
diaphragms and rotors with a new inner casing and
rotors with reaction blading for HP, IP and LP
cylinders.
IP TURBINE LP TURBINE
10
CASE STUDY - III FEATURES OF CARTRIDGE DESIGN
LIFE EXTENSION OF 110 MW TG SET BASED ON
RESIDUAL LIFE ASSESSMENT
LIFE EXTENSION PROPOSALS :
The Boiler Feed Pump Cartridge is a
completely shop assembled Pump except
$ PROPOSALS FOR AUXILIARIES the barrel (casing).
& State of art U-tube HP heaters in place of Coil This does not involve extensive assembly
type HP heaters . and skilled centering at site
& LP heater I&II are removed.
& SS tubes for Condenser and Ejector.
& New piping for Vacuum system.
& Repair of LP casing by metal stitching.
& Cartridge design BFPs with better efficiency in Total replacement of the cartridge can be
place of 200KHI BFPs. completed in a maximum of two shifts.
• PICK UP
• EH CONVERTOR ' Governing console
• WOOD WARD GOVERNOR ' Servomotor/ control valve actuator
' Yoke assembly
' Control valves
' Trip solenoid valve
' Governor impeller
' Mechanical tripping device
' Overspeed governor
11
HYDRODYNAMIC GOVERNING SYSTEM HYDRODYNAMIC GOVERNING SYSTEM
• Oil filter
• Accumulator SPEED SENSOR
• Overspeed tester
• Automatic low load limiting device
• Axial shift protection
• Pressure gauges
• Starting device
PRIMARY OIL
12
WOODWARD GOVERNOR
ELECTRONIC GOVERNORS
13
THANK YOU
14