Scheme-
Amaravati
19ARIN025 - SYED ABDUR RAHMAN
19ARIN028 - LAASYA VEMAVARAPU
19ARIN030 - HARI PRIYA CHOWDARY ANNABATHUNI
19ARIN036 - KOTHA AKSHITH
18ARIN002 - D SAI KIRAN REDDY
18ARIN005 - M V V SAI RAM REDDY
TABLE OF CONTENTS
01 Introduction 02 Key Success factors in
Master Plan
Implementation
07 Schedules
01 Introduction
Background on Master Plan - Amaravati
Existing Settlements 25
● The land pooling program went into effect on January 1st, 2015.
● Agreements from more than 25000 farmers covering an area of more than 30000
acres were obtained within 60 days of operation.
● Strong implementation guidelines, a grievance procedure,and prompt benefit
distribution.
● Returnable plots, a clear strategy for plot allocation by lottery, 5000
possibilities to choose returnable plots,and the LPS returnable layout have
increased LPS farmers trust and their involvement in the process at every level.
Integration of existing villages into Amaravati development
The new land pooling scheme projects have been smoothly integrated with all of the
existing communities in the Capital city as part of the master planning goal to
preserve and strengthen them. Using common social and economic infrastructure
(neighbourhood centres, town centres, etc.) and land use planning, this has been
handled.
Social Inclusion:
This would promote social integration and inclusive planning principles in terms of
urban design guidelines, town planning concepts, and zoning regulations that target
population of various age groups as well as social class structure. This would aim to
achieve seamless integration of the neighbourhood level local community/ village
planning unit with the larger city level unit.
Way forward and
03 Challenges in
Implementation
Way forward and Challenges in
Implementation
Policy Framework related Actions
● Enforcement of Amaravati Zoning Regulations, will ensure to safeguard the
health, property and public welfare by controlling the design, location, use or
occupancy of all buildings and structures through the regulated and orderly
development of land and land uses within this jurisdiction.
● Formulation of Urban Design Guidelines (with focus on urban design elements).
Administrative Actions
● Land Management System - Development of Land Management System for CRDA lands
● Organization setup- Formulation of Zonal Offices
Challenges
● How to support Affordable housing?
● How to cope with proposed high Density in Amaravati?
● How to promote orderly development of periphery areas of capital city?
● How to encourage to use Non-Motorized transport and Public Transport?
04 Land Pooling
Scheme
Land Pooling Scheme
Land Pooling Scheme is intended for Land Owners volunteering to offer their land
against a guaranteed return of developed and reconstituted plot and other benefits.
Under land pooling scheme, landowners voluntarily sign ownership rights over to a
single agency or government body. This agency develops the land by developing public
infrastructure like roads, sewage lines, ICT etc.
Andhra Pradesh Capital Region Development Authority (APCRDA), a government body was
constituted under the APCRDA Act 2014 (vide GO No 255) on 30th Dec 2014 of MA&UD
Department, GoAP. The Government vide G.O.Ms.No.257 M.A.& U.D.(M2) Department,
dated 30.12.2014 have issued authorization orders to APCRDA to undertake development
scheme as provided in Chapter IX of Andhra Pradesh Capital Region Development
Authority Act,2014, through voluntary Land Pooling Scheme in the Capital City area.
The final Master plan of the Capital City was notified on 22nd February 2016 after due
consideration of objections and suggestions made. The broad structure for the LPS
layouts was prescribed in the Master plan with the distribution of Town Centres,
Neighbourhood Centres and Community Centres. With this framework, the preparation
of LPS Layouts was initiated.
A multi department team within CRDA has evaluated every possible scope for
refinement of the process at every stage from concept to lottery, all of which made
this exercise a thumping success and the best possible alternative for new large
scale developments in the country.
Land Pooling Scheme Social Benefits:
● Consultation with Land Owners over Draft Plan After Draft Notification
of LPS Plan, Consultations are held with Land Owners in Villages to
gather their objections and suggestions over the Draft Plan. There is a
specified period of 30 days for objections and suggestions after ‘Draft
Notification’.
● Final LPS Development Plan Notification After assimilation of
suggestions from Land Owners in Villages, the Final LPS Development Plan
is prepared, incorporating these requirements. Then, the Finalized plan
is notified. After notification, the finalized layout is relayed on
ground, by peg-marking. Then, the Land Owners are allotted their
returnable plots by means of a digital lottery. Along with the Lottery
allotment, the Land Owners are given their Land Pooling Ownership
Certificate (LPOC).
Plot Allotment Strategy
b) the Authority shall take over all lands allotted to it and shall enter the
details of all such lands in Form 9.27 register.
3)Within one year from the date of notification of final LPS, the Authority shall
complete the basic formation of roads and physical demarcation of plots in the
Final LPS.
(4) Within twelve months of the date of notification of final LPS, the
Authority shall handover physical possession of reconstituted plots in Form
9.28 to the land owners.
(5) The Commissioner shall ensure that LPOCs granted under section 51 and
sub-section (4) of section 57 of the Act are in accordance with the
provisions of the Registration Act, 1908 without charging registration fee
from the land owners.
(6) Within three years from the date of final LPS the Authority shall develop
the infrastructure in a phased manner.
Completion of final LPS
(2) The Commissioner shall also publish in Form 9.30, the details of
reconstituted plots with in thirty days after mutations are carried out in
land records.
(3) On verification of the above details, the Commissioner shall issue the
Completion Certificate in Form 9.31 along with layout of Final LPS.
(4) The owners shall be responsible for the following, namely,
(a) all the required infrastructure within the Final Plot;
(b) obtaining all ‘No Objection Certificates’ required for the development
of the reconstituted plot and following the prevailing Development
Promotion Regulations and Building Regulations / Rules depending on the
type of development proposed; and
(c) payment of necessary fees and charges as per the rules for the
sanction of development permission.
07 Schedules
SCHEDULE 1
Process of the scheme:
(a) finalise the LPS area after calling for objections and suggestions.
(b) prepare draft LPS, invite objections and notify final LPS.
(c) transfer ownership rights to the Authority from willing landowners for the
purpose of development and reconstitution.
(d) assemble original plots and reconstitute the plots on ground after ear
Marking.
(e) transfer ownership rights to the land owners through issue of land pooling
ownership certificates to the land owners.
(d) to return land to the land owners near pooled land / within 5 km radius
of pooled land subject to other planning requirements.
(c) to demarcate all the roads as per layout plan and sector plan within
the assembled area and give approval of layout plans/detailed plans.
(d) to develop of sector roads/internal roads/ infrastructure/services
(including water supply lines, power supply, rain water harvesting,
sewage treatment facilities, water treatment facilities, etc. falling in
the share of the land guaranteed to the land owners.
(f) allot the prescribed built up space/ dwelling units for economically
weaker sections.
(g) to develop identified land in time bound manner with master plan
roads, provision of physical infrastructure, and traffic and transportation
infrastructure inclusive of metro corridors.
(b) to provide one time exemption from stamps and registration fee,
Non-Agricultural Land Assessment and development fee.
(e) to provide interest free loan of up to 25 lakhs to all the poor families
for self employment.
(d) to enhance the limit under NREGA up to 365 days a year per family.
(d) not to create any encumbrances after entering into agreement with
the Competent Authority for Land Pooling.