Professional Documents
Culture Documents
References
1. Reynold’s Reinforced Concrete Designer’s Handbook, 11th Edition by
Charles E.Reynolds, James C.Steedman and Anthony J. Threlfal
5. Design Codes:
BS 5400 Part 2: 1978 Steel, Concrete and Composite Bridges
Specification for Loads.
Table of Contents
Item Page
Introduction 1
Bridge Location 1
Soil Investigation 1
Locating Abutments and Deck Positions 1
Types of Bridge Decks
Reinforced Concrete Decks/Girder Bridges 1
Prestressed Concrete Bridge Decks 2
Composite Decks
Reinforced Concrete Deck and Steel sections 3
Prestressed Beam and Slab Composite Sections 3
Design Considerations
Loadings
I. Permanent Loads 7
ii. Transient Loads 7
HA Load 7
Carriageway 7
Notional Lanes 7
HA Load Intensity graph 8
Load Distribution
Nominal Loads 13
Partial Safety Factors 13
Design Loads 13
Load Combinations
Load Combination 1 13
Load Combination 2 13
Load Combination 3 13
Load Combination 4 14
Load Combination 5 14
Application of Loads 14
Loads Due to Movement Caused by Shrinkage(3),
Temperature (T), and Creep ( c ) 14
Stresses Due to Restrained Shrinkage 14-15
Example- Calculation of resulting stresses on a
composite section due to differential
shrinkage 15-17
Temperature Effects 18-20
Annual Temperature Variation 21
Example- Calculation of residual stresses
due to temperature effect 21-23
Abutment 39
Types of Abutment 39-40
Bridge Foundations
I. Spread Foundations 40
ii. Piled Foundations 40-41
Soil Investigation 41
I. Standard Penetration Test (SPT) 41
ii. Dutch Cone Penetration Test (CPT) 41
iii. Tests 41
Borehole Log 42
Bearing Capacity of Foundations 42
I. Spread Foundations 42
Application Example 43
a. Abutment Location 43
b. Pier Location 43
Forces on Abutment
Horizontal Forces 45
Vertical Forces 45
Abutment Design 47
Abutment on Spread Footing 47
Application Example 47-49 iii
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Pile Cap 50
Ultimate Limit State Considerations 50
Serviceability Limit State Considerations 50
Pile Cap, Sections and Pile Arrangements 51
Structural Design
a. Abutment with Ear 51
b. Abutment with Sidewall and Ear 51
Pile Design
Steps in Estimation of Deflection, Shear Force
and Bending Moment on the pile 53-55
Points to Note 55
Boundary Conditions 55-56
References 56
iv
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Bridge Design
Introduction:
The following which can generally serve as a guide should be considered in the
design of bridges. However more detailed guidance can be obtained in the
Codes of Practice and other references attached.
Bridge Location
There is need to get involved at an early stage in the determination of the
location of the horizontal alignment where the bridge is to be situated. This
involvement will influence the geometry and aesthetics of the proposed bridge
as large skew of the bridge can be avoided, adequate longitudinal and
transverse gradients necessary for storm water disposal from the bridge deck
can be incorporated in the design.
Soil Investigation
Soil investigation at locations of piers and abutments of the proposed bridge
must be done to determine the soil strata type, load bearing capacities of the
strata, the suitable foundation types and their location in the ground.
Solid Slab
Voided Slab
Composite Decks:
Composite deck construction usually refers to the interaction between insitu
reinforced concrete deck and structural steel used (as replacement for the
reinforced or prestressed concrete girder) to carry the deck . Composite
deck construction can also refer to the interaction between insitu reinforced
concrete deck and reinforced concrete precast planks and/or beams.
Steel Girder
In situ cast
Prestressed
Y-Beam
reduction of the bridge. High fabrication cost for the truss and maintenance
has however made this type of bridge less popular.
Through Truss
Suspension Bridges:
Suspension bridges are used for spans in excess of 350m. The suspension
bridge is essentially a catenary cable prestressed by dead weight. The cables
are guided over the support towers to ground anchors. The stiffened deck is
supported mainly by vertical or inclined hangers.
4
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
The following are to serve as a rough guide for selecting type of construction
for various span ranges.
Design Considerations
Bridges in Nigeria are currently generally designed to the UK Code BS 5400
supplemented by the Department of Transport Memoranda BD 37/01 and BD
44/95. It is expected that Eurocode, the most advanced design code to date
will be adopted in the near future by Nigeria for bridge design, in line with
5
best practices. BS 8110 is also incorporated in the design of bridges where
information from BS 5400 is lacking.
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Loadings:
Whether the bridge carries a road, railway, waterway or just pedestrians,
it will be subjected to the following load types:
Ÿ self weight (sw) and loads from surfacing , parapets and walkway
referred to as superimposed dead loads(SDL)
Ÿ Environmental loads which included the effects of wind , temperature
and snow, for cold regions.
Ÿ Traffic which included HA and HB loads also referred to as standard
loadings in BS 5400.
Ÿ Accidental loads such as impact
Ÿ Temporary loads during construction and maintenance.
These loads can be separated into two groups; Permanent and Transient
Loads.
I. Permanent Loads
This includes the dead weight of the structure and the superimposed dead
weights (parapet, asphalt and walkway) and filling soil materials. The effects
of differential settlement of supports are also to be included as permanent
load.
ii. Transient Loads
The transient loads are all other loads expected on the bridge structure
and excludes the permanent loads. This includes the HA and HB loads and
the effect of temperature.
HA load:
BD 37/01 Loads for Highway bridges states that HA loading is the normal
design loading in the UK and this adequately covers the effect of all
permitted normal vehicles other than those used for abnormal indivisible
loads. The normal vehicles are vehicles up to 44 tonne gross weight.
HA load is a formula load and consists of a uniformly distributed load
(HA UDL) and a knife edge load(HA KEL) ; this adequately covers the
effect of these vehicles on highway bridges. The HA load which has been
enhanced includes the effect of:
I. Impact load(caused when the wheel ‘bounce’ in the course of striking
potholes or uneven expansion joints)
ii. Overloading
iii. Lateral bunching ie more than one vehicle occupying the width of a lane.
The magnitude of the HA load depends on the loaded length of the bridge
as determined from influence line for the member being considered. For
simply supported decks the loaded length is the span of the bridge.
To obtain the magnitude of the HA load, the carriageway is divided into
notional lanes and the UDL and KEL values given for one notional lane are 6
multiplied by the appropriate lane factors as given in BD 37/01.
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
The loads so obtained are termed nominal loads. The UDL varies with the
loaded length and the KEL extends over a length equal to the width of the
carriageway. An alternative single wheel load (SWL) can be placed at any
point on the carriageway and applied over a circular (340mm diameter) or
square equivalent to 1.1 N/mm2 pressure on the surface of the deck.
The dispersal of this SWL may be taken at spread to depth ratios of 1
horizontal to 2 vertical through asphalt or similar material and 1 horizontal
to 1 vertical down to the neutral axis of structural concrete.
Carriageway:
The carriageway width in the standard is defined as the part of the running
surface which includes all traffic lanes, hard shoulders, hard strips and
marker strips. It is the width between raised kerbs. In the absence of
raised kerbs it is the width between safety fences, less the amount of set-
back required for the fences. The carriageway width is measured in the
direction at right angles to the line of the raised kerbs, lane marks or edge
markings.
Notional Lanes:
These are parts of the carriageway width for deriving the intensity of the
HA live load. They have a maximum width of 3.65m and minimum of 2.50m.
The carriageway shall be divided into an integral number of notional lanes,
have equal widths .The number of notional lanes is based on the carriageway
width (b) and is given by Int[(b/3.65)+1].
Alternatively refer to Clause 3.2.9.3.1 BD 37/01 Vol 1.
The carriageway shall be divided into an integral number of notional lanes,
have equal widths as follows:
7
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
w=336(1/L)0.667KN
w=36(1/L)0.1KN
24.4
17.2
Multiple Lanes:
HA is applied to every notional lane across the carriageway attenuated by
factor β as defined in Table 14 BD 37/01 reproduced below. The attenuation
8
takes account of vehicle bunching along and across the bridge.
Generally β=1.0 for the first two lanes and β=0.6 for the remainder.
Nominal HA load =βHA UDL + βHA KEL
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Loaded length First lane Second lane Third lane Fourth &
(m) Factor factor factor subsequen
t
β1 β2 β3 lane
Note 1:
α1=0.274bL and cannot exceed 1.0
α2=0.0137[bL (40-L) + 3.65 (L-20)]
where [bL is the notional lane width (m)
Note 2:
N shall be used to determine which set of HA lane factors is to be applied for
loaded lengths in excess of 50m. The value of N is to be taken as the total
number of notional lanes on the bridge (this shall include all the lanes for dual
carriageway roads) except for a bridge carrying one-way traffic only, the
value of N shall be taken as twice the number of notional lanes on he bridge.
9
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
HB Load:
BD 37/01 Loads for Highway Bridges states that the Type HB loading
requirement derives from the need to transport exceptional loads e g
electrical transformers, generators, pressure vessels etc which are
indivisible loads on vehicles likely to use the roads in the area. The vehicle is
therefore exceptional and is represented by a four axle vehicle with four
wheels spaced on each axle. The load on each axle is defined on the number
units which is dependent on the class of road. 1 unit = 10KN and one wheel
weighs 2.5KN. In the UK motorways and trunk roads require 45 units,
principal roads require 37.5 units and other public roads require 30 units. In
Nigeria FMW specifications require that all public highway bridges be
designed to 45 units.
The design procedure is to analyze the bridge for HA and HB load effects
applying the appropriate load factors. The member is then designed for the
more onerous of the effects of these two types of loads.
1 unit 1 unit
Axle Axle
1 unit 1 unit
1 4
Axle Limit of vehicle Axle
0.25m 0.25m
2 3
0.25m
1.0m
3.5m
overall 1.0m
width
1.0m
0.25m
I unit HB Vehicle
1.8m 6m, 11m, 16m, 21m, 26m 1.8m
Whichever dimension gives the most severe effect on the member under consideration.
11
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
β2[HA]
a1 β1[HA UDL]
HB Vehicle 3.5
β33[HA UDL] a2 β3[HA UDL]
Central reserve No loading for global analysis
βn[HA]
[HA UDL + HA KEL]
βn[HA]
[HAUDL + HA KEL]
βn[HA]
[HA UDL + HA KEL]
HA UDL
Load Distribution:
The application of traffic load on any area of the deck causes the deck to
bend transversely and twist, thereby spreading the load to the other side.
The assessment of how much of the load is shared in this way and the extent
to which it spreads across the deck depends on the bending, torsion and shear
stiffness of the deck in the longitudinal and transverse directions and is
referred to as the load distribution. Computer method are generally used to
analyze the structure for this load effect, a versatile procedure uses grillage
analysis which treats the deck as a two dimensional series of beams elements
in both orthogonal x, y directions. Guyon, Massonnet and Bares have also
developed a method, referred to as Method of Distribution Coefficient to
obtain this load distribution; the method simplifies this analysis and lends
itself to hand or computer solution when the skew of the bridge is not
o
greater than 20 . The procedure recommended in BS 5400 specifies that the
deck HB load be moved to different positions on the deckThe author has
developed a computer program for this method and an extensive application of
the method can be seen in the attached Bridge Design Project Example. The
distribution analysis procedures are referred to as rigorous analysis methods.
The method has also been codified in the USA by AASHTO. Clause 6.1.3 of
BS 5400: Part 2: 1978 specifies that where appropriate the effects of design
standard loadings be distributed in accordance with a rigorous distribution
analysis or from data derived from a suitable test.
Nominal Loads:
Where adequate statistical distribution are available, the nominal loads are
those appropriate to a return period of 120 years. In the absence of such
statistical data, the nominal load values considered to approximate to a 120-
year return period are given.
For foot/cycle bridges, the only secondary live loads to be considered are
the vehicle collision loads on the bridge supports and superstructures.
Combination 5: For all bridges the loads to be considered are the permanent
loads together with the loads due to friction at the bearings.
Application of Loads:
Each element and structure shall be examined under the effects of loads
that can coexist in each combination.
Generally the stresses are low and are considered insignificant in most cases.
Where a concrete deck is cast in situ onto a prefabricated member (whether
steel or concrete) the amount of differential shrinkage and thus the
shrinkage stresses can be significant.
The figure below illustrates how the shrinkage of the in situ deck affects the
composite section.
In composite construction using precast reinforced beam or prestressed units
in combination with in situ concrete slab, a considerable proportion of the
total shrinkage would have taken place in the precast unit before casting and
hardening of the in situ concrete.
Due to the high w/c ratio used in the in situ concrete, there will be
considerable shrinkage of the concrete of this part in the composite section.
Consequently the differential shrinkage between the precast unit and in situ
cast slab will result in stresses in both units.
The magnitude of the differential shrinkage is influenced by the composition
of the concrete and environmental condition to which the composite member is
exposed.
-6
In absence of exact data, a general value of 200x10 for concrete strain is
applied in computing the shrinkage stresses..
Reasonable estimation of the stresses developed due to differential shrinkage
can be made using the following assumption:
Shrinkage is uniform over the in situ part of the section;
Effect of creep and increase of modulus of elasticity with age over the
shrinkage developed by the component units is negligible.
An illustration of the design procedure for the reinforcement to resist shear
forces at the interface of insitu slab and precast longitudinal beam is given
below. A further practical illustration of interface shear design is given in
the Bridge Design Project Example.
15
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
2200 2200
1400 Precast
Y8 beam
Deck cross-section
Solution
I. Calculation of section properties of composite section
Differential shrinkage Ɛs = 200x10-6
Modular ratio = 50/28=1.786
Effective width of the in situ slab =2200/1.786=1232.0mm
Effective area of the in situ slab =1232.0x230=283360.0mm2
3 9
Ix (slab) =1232.0x230 /12=1.24915x10 mm2
2200
4.27 Compression
230 In situ cast slab 5.07 -
6.24
705
NA +
1400
Precast
Y8 beam
2.54 -
Resultant stresses due to differential shrinkage
Deck cross-section (N/mm2)
17
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Temperature Effect
Daily and seasonal temperatures of the bridge and environment have a
considerable effect on the stresses within the bridge structure.
Changes in effective temperature of the deck will cause it to expand or
contract while differential temperature gradients through the concrete will
result in stresses that need to be considered in prestress design.
Where a deck is free to expand or contract, the overall change in effective
temperature will not give rise to any forces in the structure, although the
movement does need to be allowed for in the bearing and expansion joint
design.
When a restraint exists that restricts free movement, such as integral decks
or multiple fixed piers, forces and stresses are set up throughout the
structure which must be taken into account in prestress design.
The daily variation of temperature also gives rise to temperature variations
within the depth of the superstructure and varies depending on whether the
bridge is cooling or heating, the form of construction( concrete slab,
composite deck etc) and black top surface thickness.
The temperature variation is caused by the position of the sun, the intensity
of the sun’s rays, thermal conductivity of the concrete and surfacing, the wind
and the cross-sectinal make-up of the structure.
The temperature gradient results in self equilibrating internal stresses.
Two types of stresses are induced; primary and secondary stresses.
The primary stress is due to temperature differences throughout the
superstructure; whether simply supported or continuous.
The secondary stresses is due to the continuity of the superstructure.
Both stresses are determined and catered for in design.
The effects are complex to evaluate but guidance is given by the UK Dept of
Transport and Research laboratory.
The critical parameters are the thickness of the deck slab and the nature of
the beam.
Concrete construction falls within Group 4.
The distribution of thermal gradients can be idealized for different group of
structure as in Fig 9 BD 37/01 Cl 5.4.
Primary Stresses
Ÿ Primary stresses occur in both simply supported and continuous bridges.
Ÿ They are observed as stress variation with depth caused by redistribution
of restrained
temperature.
Ÿ They are determined by balancing the restrained stresses with an
equivalent system of a couple and direct force acting at the neutral axis
position. 18
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Ÿ The section is divided into slices and restraint force in each slice is
determined
Ÿ The sum of the moments of each force about the neutral axis and sum of
the forces across the section give the couple and direct force
respectively.
Secondary Stresses
Ÿ Secondary stresses occur in continuous bridges only and are due to
change in global reactions and bending moments.
Ÿ They are determined by applying the couple and force at each end of the
continuous bridge and determining the resulting reactions and moments.
Ÿ These are the added the self weight and live load reactions and moments.
Ÿ They are included in combination 3 refer to cl 4.4.3 BD 37/01
0 0 0
h3 F3
T3 σ3
h4 T4 σ4 F4
Equivalent Stresses:
M/z=∑(Fe)/Zb
b. Moment release
∑F/A
iv. Balancing stresses 19
a. Axial stress
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
+ + =
Stress Relieving axial force from Relieving moment from Resultant stress
from (ii) (iv)(a) (v) distribution
∑F ∑F
20
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
100
Deck cross-sec on
Solu on
Consider 1m wide strip of deck sec on:
Apply the temperature difference given for group 4 in Fig 9 in BD 37/01.
Coefficient of thermal expansion = 12 x 10-6/oC (Cl 5.4.6 BD 37/01)
From BS 5400 Part 4
Elas c modulus of the concrete Ec=19+0.3fcu=24N/mm2
o 3 -6
Restrained temperature stress per C= 34x10 x12x10 =0.408N/mm2
h=700mm
21
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Reverse Temperature:
h1=h4=0.2x700=140≤250mm
h2=h3=0.25x700=175≤200mm
T1=7.05oC T2=1.75 oC T3=1.5oC T4=5.5oC
1000
13.25oC 7.05oC
150 140
1.75oC
2.0oC 175
350
210
175
350
1.5oC
200 140
2.25oC 5.5oC
0.82 -1.73
210
-0.07
+0.29
200
+2.84 +2.83
0.92
Axial release Moment release Residual
Restrained stress
=F/A =M/Z stress due to
=0.408xT
22
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Leaf Pier
Ÿ Leaf pier is used in modern bridge construction.
Ÿ It is usually designed as a solid reinforced concrete wall.
Ÿ The overall length of the pier is equal to the transverse width of the
bridge.
Ÿ A typical leaf pier supporting a single carriageway of a bridge can be 4 to
10m in length and the least lateral dimension may be 0.5 to 1.0m in width.
Ÿ Common practice is to taper the pier dimension from base up to the deck.
Ÿ The greatest transverse dimension is required at the top to provide
sufficient support for the superstructure.
Ÿ Vertical and horizontal loads transmitted from the superstructure
disperse rapidly from the top of the pier.
Ÿ The overall design of the leaf is normally conducted on a metre strip basis
assuming a uniform distribution of axial and bending effects.
Columns
Ÿ Individual concrete columns are often used to support footbridges and
bridge decks with high skew or greater height than minimum headroom
clearance
Ÿ Columns may be vertical, inclined or even curved in shape to produce a
greater aesthetic appeal.
Ÿ Column sections are usually required to resist biaxial bending and significant 23
axial loading.
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Example - Bridge pier rectangular column design with sidesway, and with no
sidesway
Consider a pier column shown with loads indicated at ULS. Design the
reinforcement for the column having the characteristic strengths of
reinforcement and concrete as 410N/mm2 and 40N/mm2 respectively. Assume
that the articulation of the deck is such that a) sidesway is prevented and b)
sidesway can occur.
3000KN
Y
280KN Bearing which 600mm
permits
rotation only 1500m
X X
9.0m
A A
Y
25
Bridge Col section A-A
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
A/Sidesway prevented
I. Hand calculation
N=3000KN
fcu=40
fy=410
With sidesway prevented, the column can be considered to be braced.
From the given Table in the Code
Take effective length le=lo=9m
Slenderness ratio le/b=9.0x103/600=15>12 therefore slender col
Min eccentricity =0.05h=0.05x600=30mm>20mm (min allowed)
Initial moments:
At top of colM1=0
At bot of col M2=280x9+3000x0.03=2610KNm
Col is braced Mi=0.40M1+0.60M2
= 0+0.6x2610=1566KNm
Additional moment Madd=Nau
where au is the deflection of the col.
The deflection of a rectangular or circular column au=BetaaKh
and Betaa=(1/2000)(le/b’)2
where b’ =smaller dimension of the column except for biaxial bending where le
and b’ are always in the plane considered.
2
Betaa=(1/2000)(9.0/0.6) =0.1125
Take K=1 initially
au=0.1125x1x0.6=0.0675
Madd=3000x0.0675=202.5KNm Y
Total Moment Mt=Mi+Madd=1566+202.5=1768.5KNm<M2
600mm
Therefore Design moment M=2610KNm
M/(bh2fcu)=2610x106/(1500x6002x40)=0.1208 9T40
3
N/(bhfcu)=3000x10 /(1500x600x40)=0.0833
Assume 40mm dia main bars 1500mm
Take 40mm cover to main bars
X X
d=600-40-20=540mm
d/h=540/600=0.90
B/ With sidesway
I. Hand calculation
With sidesway occurring, consider the col to be a cantilever with effective
height equal to twice the actual height.
le=2x9=18m
Slenderness ratio=18/0.6=30
The initial and additional moments are both maximum at the base.
Initial moment Mi=2610KNm at base
Y
From equation
Mt=Mty+Madd 600mm
Madd=Nau
12T40
au=Betaakh
Betaa=(1/2000)(18/0.6)2=0.45
Take k=1 initially
au=0.45x1x0.6=0.27
Madd=3000x0.27=810KNm X X
Mt=2610+810=3420KNm 1500mm
3
N/(bhfcu)=3000x10 /(1500x600x40)=0.0833
2 6
M/bh fcu=3420x10 /(1500x6002x40)=0.1583
From Chart 151 RCDH
ρfy/fcu=0.31818 12T40
ρ=0.31818x40/410=0.03142
100ρ=3.142>0.4 (min allowed) Y
<6.0 (max allowed)
Bridge Col section A-A
Asc/bh=0.03142
2
Asc=0.03142x1500x600=28278mm
Asc/2=28278/2=14139mm2
2
Provide 12T40 (As=15080mm ) each face
or Provide 24T40 (As=30160mm2) in col
27
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
3000KN
280KN
Bearing which permits Y 950mm Dia
rotation only
12.0m X X
A A
N=3000KN
fcu=40
fy=410
With sidesway prevented, the column can be considered to be braced.
From the given Table in the Code
Take effective length le=lo=12m
Slenderness ratio le/b=120x103/950=1263>12 therefore slender col
Min eccentricity =0.05h=0.05x9500=47.5mm>20mm (min allowed)
Initial moments:
At top of colM1=0
At bot of col M2=280x12+3000x0.0475=3502.5KNm
Col is braced Mi=0.40M1+0.60M2
= 0+0.6x3502.5=2101.5KNm
Additional moment Madd=Nau
where au is the deflection of the col. 28
The deflection of a rectangular or circular column au=BetaaKh
and Betaa=(1/2000)(le/b’)2
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
where b’ =smaller dimension of the column except for biaxial bending where le
and b’ are always in the plane considered.
Betaa=(1/2000)(12.0/0.95)2=0.0798
Take K=1 initially
au=0.0798x1x0.95=0.0758
Madd=3000x0.07581=227.4KNm
Total Moment Mt=Mi+Madd=2101.5+227.4=2328.9KNm<M2
Therefore Design moment M=3502.5KNm
3 6 3
M/(h fcu)=3502.5x10 /(950 x40)=0.102
2 3 2
N/(h fcu)=3000x10 /(950 x40)=0.083
Assume 40mm dia main bars
Take 40mm cover to main bars
hs=950-40-20=890mm
hs/h=890/950=0.937
From Chart 90 of Manual for the Design of Reinforced Concrete Building
Structures published by the Institution of Structural Engineers.
ρfy/fcu=0.37
ρ=Asc/Ac=0.37x40/410=0.0361
100ρ=3.61>0.4 (min allowed)
100ρ<6 (maximum allowed)
Asc/Ac=0.0361
2 2
Asc=0.0361x22/7x950 /4mm =25588.5mm2
Provide 22T40 (As=27646mm2)
Y
950mm Dia
22T40
X X
29
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
d’
dc
d a’
h
As(area of steel in
S Φ
Ɛs
30
acr Cnom Ɛm
Section Cracked elastic
Strain
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
(0.4fcu)bx
x>0.5d
|
d Z=(d-0.5x)
h
As(area of
steel in tension)
(0.87fy)As
Stress diagram 31
Taking moment about the centre of compression for the tensile reinforcement
Mu=(0.87fy)Asz (1)
Taking moments about the centre of tension steel for the compressive force
Mu=(0.4fcu)bxZ=(0.4fcu)bx(d-0.5x) (2)
The maximum moment of resistance is obtained when x=0.5d and so subs tu ng for x
we obtain
2
Mu=0.15fcubd (3)
The depth to the neutral axis depends on the reinforcement provided and is obtained by
equa ng forces thus
(0.87fy)As=(0.4fcu)bx
Rearranging and dividing both sides by d
<Z/d={1-[1.1fyAS/(fcubd)]}<0.95d (4)
b
A’s(area of steel in
compression)
0.4fcu
d’ (0.72fy)A’s
x=0.5d (0.4fcu)bx
d Z=(d-d’)
h Z=0.75d
As(area of
steel in tension)
(0.87fy)As
Taking moment of the compressive forces about the centre of tension steel
Mu=0.15fcubd2 + (0.72fy)A’s(d-d’) (5)
Equating tensile and compressive forces
2
(0.87fy)As=0.2fcubd +(0.72fy)A’s (6)
Equations (5) and (6 ) are based on value of d’/d<0.20
For values of d’/d>0.20 the use of design stress 0.72fy in compression steel is
not valid. This stress has to be determined from the design stress strain
curve of the steel in compression as the steel has not yielded.
32
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
surfacing
100
Deck cross-section
From BS 8500:
Exposure class is XD1 - moderate humidity
Maximum water/cement ratio=0.55
Minimum cement content=320Kg/m3
Minimum strength class for cement type group 4=C32/40
Minimum cover=30mm
Nominal cover=40mm
No of notional lanes=Int[(b/3.65)+1]=3
Width of notional lane=8/3=2.667m
HA Load:
L=13.0m
0.67
HAUDL=336(1/L) =60.3KN/m/lane
X 13.0
centre of gravity of loads
Centreline of span
Combination 1 Loading
Dead=369.7x1.15+1.75x50.7=513.9KNm
Design HA SLS moment=ɣFL x M=1.2 x 455.5=546.6KNm
Design HB SLS moment=ɣFL x M=1.1 x 435=478.5KNm<546.6KNm HA is critical 34
Total Design SLS Moment (Dead + Live) =430.5+ 546.6=977.1KNm
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Combination 3 Loading
Design HA SLS moment=ɣFL x M=1.0 x 455.5=455.5KNm
Design HB SLS moment=ɣFL x M=1.0 x 375=375KNm<455.5KNm HA is critical
Case 2 - When creep and shrinkage in the bridge are substantially complete
For long term loading Youngs Modulus of elasticity=Ec/2=15.5KN/mm2
Combination 1 SLS Design Moment=430.5DL+ 546.6LL=977.1KNm
0 16+35=51
+4
r
ac 36
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
37
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
0.64m
13m
Nominal:
Due to HA Vx=138.5KN
Due to DL(concrete) =17.5x13/2KN=102.4KN
Due to SDL(surfacing)=2.4x13/2=14.0KN
X 13.0
HB:
38a
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Abutment
Abutment lies at the two extremities of the bridge. They serve to support the
superstructure, serve as retaining wall as well as transfer the vertical and
horizontal forces to the foundation. Recesses are provided at the top of the
retaining wall to support the transition slab sometimes referred to as apron or
approach slab. The function of the approach slab is to bridge the gap between
the bridge and the approach road.
Types of Abutment
The types of abutment depend on a number of factors such as the height of
the retained soil, the strength of the underlying soil strata and the slope of
the embankment across the return walls. The different types are discussed
below:
I The Cantilever Abutment - There are three forms of this namely:
a. The Wingwall Abutment- This consists of a front cantilever wall with
splayed wingwalls. The splayed wingwalls may be supported on extended
footing from the main front wall or may be cantilevered as a projection
from main stem wall. In this case no footing is required for the
wingwalls.
b. The Returnwall Abutment - This is sometimes referred to as the
U-Abutment. Here the wings become returnwalls parallel to the
longitudinal profile. It consists of a side wall and a cantilevered ear wall.
c. The Ear Abutment - This is another form of a Returnwall which
consists purely of the ear cantilevered wall.
ii. The Bank Seat Abutment - These are pseudo abutments which do not consist
of retaining wall. There are two main types:
a. The Skeleton (Spillthrough) type - This is used where the rock
bearing material is within about four metres from the existing ground
level. In this case the footing rest on rock while the skeleton columns
transfer load from the bridge to the underlying footing. The abutment is
then regarded as a buried abutment, and the forces on both sides are
taken as active. Since the columns will not be visible, pipe culvert precast
concrete rings are usually employed as permanent formwork.
b. Piled type - The bank seat may be supported on piles in poor ground.
iii. The Counterfort Abutment- This form of Abutment which is now obsolete
consists of counterfort walls placed to support the front wall at right angles.
The difficulties arising from compaction of the materials between the
counterfort walls contribute to its dislike by contractors and designers. It is
now replaced with the ReturnWalll Abutments with the side walls acting as end
counterforts. 39
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Determination of the horizontal forces induced by the backfill soil are based
on the coefficient of active earth pressure at the serviceability limit state
while at the ultimate limit state, the determination is based on the coefficient
of earth pressure at rest.
Well graded granular soil material, Class 6N is recommended as backfill soil.
The provision of weepholes at the front wall and wingwalls of the abutment
including french drain at bottom are required to prevent accumulation of
water behind the abutment and the consequent hydraulic forces.
Bridge Foundations
The foundations for bridges may be classified into two categories- spread and
piled foundations.
I. Spread Foundations
This category covers the strip foundation, pad and combined footings. The
strip footing is mostly used for abutments while piers are normally placed by
on either pad footing or combined footing. Leaf piers rest on strip footing.
Stability checks on the abutment resting on this category of foundations is
required.
The first three stated types are known as displacement piles and the problem
of calculating the load carrying capacity and settlement require a different
approach to that of the bored piles. Depending on the soil strata, driven piles
can either be end bearing or friction piles, sometimes a combination of both.
Bored piles are generally end bearing and are often of large diameter, 600mm
and above. To increase the bearing capacity, the bottom can be under-reamed
to produce greater bearing area. Additional safety precautions are required 40
with larger diameter piles.
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
All foundations must satisfy two criteria, no shear failure in the soil and no
excessive settlement. There are well established method for ensuring that the
criteria of no shear failure is met. The criteria of no excessive settlement is
met using the following methods:
I. Through soil parameters ie summing the shaft friction and bearing capacity .
ii. By means of test piles.
iii. By means of dynamic formulae ie Hiley formulae which equates the energy
required to drive the pile with its ultimate bearing capacity.
iv. Piling contractors ‘Know how’.
Soil Investigation
The foundation design requires knowing the characteristics of the underlying
strata. This is obtained by use of the Penetration Tests.
The two most common penetration tests in use are the Standard Penetration
Test and the Dutch Cone Penetration Test.
iii. Tests
a. Insitu tests are performed during the borehole operation. They are
i. The Vane Test
ii. The Standard Penetration Test
b. Disturbed and Undisturbed Samples are taken from the borehole at speific
locations for tests in the Laboratory.
Such tests include:
Ÿ the Triaxial Compression Test
Ÿ the Unconfined Compression Test
Ÿ the Direct Shear Test
41
Ÿ the Consolidation Tests
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
0
Made up ground
1.0
5.0 WL
Rock
Application:
a. Abutment Location:
A borehole is provided for a proposed Abutment location. At depth 2m, the
cohesion=65KN/m2 and angle of internal friction=20o. To obtain the net bering
capacity of the foundation
Terzaghi’s equation for strip footing is applied.
qult=c’Nc + ɣz(Nq-1) +(0.50)(ɣ)(B)(Nɣ)
=65x17.7 +18x2x7.4 +0.5x5x5=1606KN/m2
q(safe)=1606/2.5+18x2=678KN/m2
b. Pier Location
This location requires a rectangular footing.
qult(net)=cNc(1+0.3B/L) + ɣz(Nq-1) + (0.5)(ɣ)(B)(Nɣ)(1-0.2B/L)
The net bearing capacity is multiplied by a correction factor where the water
table is located within the vicinity of the foundation.
Cohesionless Soils:
Design parameters for soils in granular soils are usually obtained from results
of insitu penetration tests because of the difficulty involved in obtaining
undisturbed samples. In 1953 Peck et al proposed the relationship between the
uncorrected N-value from SPT and the angle of friction of the soil.
Berezantzev showed the relationship of Nq with Q.
The ultimate bearing capacity for piles considering end bearing only is the
volume of displaced soils x density of the soil x Nq
2
ie πd /4.ɣ.H.Nq
where d=diameter of piles
H=depth of penetration of piles
ɣ= density of soils 43
Nq=bearing capacity factor.
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
The author has developed a program called PileBeaCapa which uses the
Berezantzev’s method to compute the bearing capacity of a pile embedded in
sands and other granular soils at various depths based on the correlations
between the Berezantsev’s bearing capacity factor Nq and the angle of
shearing resistance of the soil.
Meyerhof Correlations:
Here the ultimate load is given by
Qf=Abqf + AsFs
where qf=40ND/B KN/m2 <=400N KN/m2
N=No of blows from SPT
and fs=2Navg KN/m2
Navg=average number of blows for the soils.
The safe ultimate load, Qf(safe)=Qf/2 for factor of safety of 2.
The author has developed a program called PileBeaMeyerhof which utilizes the
empirical correlations between the SPT-N values to determine the shaft and
base resistance of the pile in a soil stratum.
The author has developed a program called BeaPen which plots the Dutch Cone
Penetrometer readings against depth in the soil and determines the bearing
capacity of piles using Meyerhof’s, De Beer’s and Tomlinson’s methods.
Piles on Rock
These piles depend on their structural strength, and are desiged as columns.
The ultimate load that can be supported by the pile is
N=0.4fcuAc + 067fyAc
where the minimum are of steel, As depends on the L/D ratio.
For L/d<=30, use 1.25% of area of pile.
30<L/D<=40, use 1.5%
Application Example
Determine the required set for a pile driving operation utilizing a Model D-36
Delamg Diesel Hammer for an allowable pile load of 600KN.
Using the Engineering News formula, we have
S+2.54=166.64E/R
=166.64x47.2/600
=13.1
S =10mm per blow
Hence the refusal value of 10mm per blow subject to a minimum of 1.25mm per
blow for the final 150mm of driving is adopted within the minimum length of
pile shown on the drawings, It is essential to test a few selected piles to
confirm agreement with design parameters.
Forces on Abutment
Horizontal forces:
Ÿ Earth pressures
Ÿ Live load surcharge created by either HA ornHB loading
Ÿ Braking forces
Ÿ Temperature forces acting through bearings
Vertical Forces:
Ÿ Abutment self weight
Ÿ Superstructure dead load 45
Ÿ Superimposed dead load (parapets, asphalt and walkway)
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
6
9
7
5
3
1 8
Abutment Typical 2
4 2
Arrangement
GL
1
1 = Strip footing or pile cap
2=Abutment stem
3=Bbackwall or ballast wall
4=Side wall
5=cantilevered returnwall or EAR
6=Run on slab or Approach slab or Transition Slab
7=Superstructure
8=Plinth or Bearing Support
9=Curtain wall
Haunched Abutment
46
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Abutment Design
The design consists of evaluation of
I. Stability of the Abutment
Ÿ Overturning stability
Ÿ Sliding stability
ii. Bearing capacity checks
The author has developed a program called winAbutPiler which determines the
resultant forces and their point of application at the base of the abutment.
The program also determines the pressure distribution beneath the spread
footing of the abutment at serviceability and ultimate limit states.
Application Example
Bearing Pressure calculations for an EAR Abutment at SLS load combination 4.
The Ear is 0.4m thick.
700 300
6 DL= 1782 KN
1500 4 1000
7 LL= 1823 KN 3
8
225KN
5 2000
3850
2 2218KN
3000
9
1000 1
47
A 600
1900 1000
3500
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Ecce=1.75-1.28=0.47m
2756KNm
P1 P2
5864KN Pressure distribution
beneath the spread footing.
3
P1=5864/(3.5x12)+(2756x1.75)/(12x3.5 /12)
=139.6+112.5=252KN/m2
P2=27KN/m2
Compare these two figures with bearing capacity of the underlying soil strata.
Abutment on Piles
Consider the same abutment under LC4.
Assume pile capacity of 900KN
Load on an extreme pile=V/n+My/I
where V=Vertical load on pile group
y=distance from entre of pile to extreme piles
n=no of piles
2
I=Σd =sum of the square of the distance of the centre of the pile from the 48
centroidal axis.
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
N1 N2
0.75 2.0 0.75
1.20
2.40
12.00
3.50
Pile Cap
2
N1=V/n+-(M)(x1/Σd
I=Σd2=10x(1.0)2=10
N1 =5864/10+2756x1/10
=586.4+275.6=862KN
N2 =586.4-275.6=310.6KN
According to Berezantsev
o
Ÿ no raking for α<5
o o
Ÿ raking is provided for α between 5 and 15 , and deadman piles should be
o
provided for angles greater than 15 . For α of 22.7o, deadman piles are
required and back row piles will be utilized for this purpose. 49
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
However the use of raked piles is no longer fashionable due to the difficulty
involved in achieving the angle of raking at the site; bored cast in-situ piles
are currently in use.
Pile Cap
Pile cap serves to transmit the total load from the pier or abutment to the
piles below. The pile cap can be designed when the total number of piles
required at serviceability limit state and their arrangement below the pile cap
have been determined.
The piles should extend at least 75mm into the pile cap for adequate fixity
while the reinforcement from the piles should extend at least an anchorage
length into the pile cap.
50
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Pier col
150mm minimum Pile cap
150mm Pile
minimum
A A
Abutment stem
150mm minimum Pile cap
150mm Pile
minimum
A A
Abutment stem
51
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Structural Design
a. Abutment with Ear
This is treated as cantilever wall subjected to earth pressure, self weight
forces and forces from the superstructure. Moments can be taken about the
centre of gravity of the stem wall to obtain the resultant moment and
forces acting and thereby obviate the difficulty of lengthy calculations.
10
6
7 3 4
8
5
The design of the structural elements is based on ultimate limit state and
coefficient of earth pressure at rest is used to calculate the horizontal
forces due to earthfill and surcharge load. The Ear will be subjected to
vertical and horizontal forces which are statically determinate.
Pile Design
The piles should extend at least 75mm into the pile cap for adequate fixity
while the reinforcement from the piles should extend at least an anchorage
length into the pile cap. The geotechnical design of the pile precedes the
structural design of the pile and is required at the onset of design to obtain
the allowable pile load to avoid shear failure of the embedment soil and
52
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Step 2: Assuming that the soil contact pressures act at the nodal points,
express the reactive forces Q in terms of the soil pressure on the area of the
slice multiplied by the area of the slice thus
Q1=q1xarea=ks1xBxa/2
Q2=q2xarea=ks2xbxa
Q3=q3xarea=ks3xbxa
..
.
Qn=qnxarea=Ksnxbxa
where
Ks1,ks2,ks3..... Ksn are the modulus of subgrade reactions at node points 1,2,3,4
...n in MN/m3
B=diameter of the pile in m
a=thickness of the slice in m
53
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Pile Cap
F KN
b
Q1 NGL
1
Q2 a Slice No 1
2
Q3 a
3
Q4 a Node 3
4
Q5 a
5
Q6 a pile
6
a
Q7
7
Q8 a
8
a
Q9 9
B
Step 3: Write the expression for the bending moment at each nodal point in
terms of the shear force Q1,Q2,Q3.... Qn as follows
M1=Fxb
M2=(Fxb)-(Q1xa)
M3=(Fx(b+2a))-(Q2xa)-(Q1x2a)
M4=(Fx(b+3a))-(Q3xa)-(Q2x2a)-(Q1x3a)
.
.
Thus
M1=F1xa
-M2=(EI/a2)(y1-2y2+y3)
2
-M3=(EI/a )(y2-2y3+y4)
-M4=(EI/a2)(y3-2y4+y5)
where
54
E=modulus of elasticity of the pile material
I=2nd moment of area of the pile cross-section
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
Points to Note
Programmable calculators or Excel Spreadsheet program can be used to solve
the simultaneous equations obtained in step 5 when the unknowns
y1,y2,y3,y4........yn in the simultaneous equations are somewhat not more than 9.
For large number of unknowns say 15 occasioned by large number of slices say
14, it becomes imperative to get a special program to solve the simultaneous
equations.
Boundary conditions
The following boundary conditions are important in the solution of the
simultaneous equations
a. Base of the Pile: the bottom of the pile can be displaced and suffer a
rotation but for all practical purposes it can be assumed that the moment at
that point is zero.
b. The boundary condition at the top of the pile depends on the form of fixity
of into the structure it is supporting. If there is a large pile cap at the top, it
can be assumed that there is no rotation and moment will develop.
For a pile whose top is only lightly held, it can be assumed that there will be
rotation and therefore no moment is developed.
It is generally simplest to ignore the boundary condition at the top of the pile.
Reinforcement Design
Having determined the pile length and diameter and obtained the axial forces,
bending moments and shear forces acting on the pile, the pile is designed as
column.
It is to be noted that the pile is supported at the top and bottom. It is in a
55
very severe environment and minimum concrete strength applicable is
Project Job No
IDOLOR-VOB KONSULT Made by Date Sheet No
CONSULTING CIVIL & STRUCTURAL ENGINEERS
Checked Section Made by
A comprehensive design example for pile can be seen in the Bridge Design
Example Project included with this write up.
56