PROJECT REPORT

Project: Al farjaan Market Market: 2

PIPING CABLE
SHOP
NUMBER 2 TONNES M
IN Nos G1 G2 1
1 3 ü ü ü ü ü ü
2 3 ü ü ü ü
3 3 ü ü ü ü ü ü
4 3 ü ü ü ü
5 3 ü ü ü ü ü ü
6 3 ü ü
7 3 ü ü ü ü ü ü
8 3
9 3 ü ü ü ü

1.5 PIPIN CABL


ROOM NO
TONNE G E
S IN Nos G1 G1
Pump
Room 1
Elect
rical
Room 1
Security
Room 1
Total 3

Remark:

 Shop 8 sleeve not ready.


 Shop2 ground floor pipe line sleeve concrete blocked.
 Shop 4 first floor pipe line sleeve concrete blocked.
 Shop 6 ground& first floor pipe line sleeve concrete blocked.
 Telecom, electrical and security room (1.5 tones) rooms not ready.