Professional Documents
Culture Documents
FOR
CIVIL AND STRUCTURAL WORKS.
GENERAL SCOPE
1.0 WATER
The Site-in-charge may require the Contractor to get the water tested
from an approved laboratory at latter's expense and in case the water
contains excess of acid, alkali or salt etc., the Site-in-charge may refuse
to permit its use.
2.0 AGGREGATE:
Coarse and fine aggregates for concrete shall conform in all respects to
IS:383.
The Site-in-charge may require the Contractor to carry out tests at the
Contractor 's expense, in accordance with IS : 516 (Methods of test for
strength of concrete )and IS:2386 (Methods of test for aggregates for
concrete.)
Sand for filling shall be medium coarse hard, strong free from any
organic and deleterious materials. Any sand (Fine/Coarse) proposed,
shall be used only after it is approved by the Site-in-charge.
4.0 CEMENT
5.0 STEEL
5.4 STORAGE
6.0 BRICKS
These shall be sound, hard, tough and rectangular in shape and size,
well burnt (not overburnt) of uniform deep red , cherry or copper
colour and shall conform to IS:1077 . These shall have plane
rectangular faces with parallel sides and sharp straight right-angled
edges.
The bricks shall be free from cracks, chips, flaws, stones or humps of
any kind. These shall not show signs of efflorescence.
Tile bricks shall conform to all the specification of 50A class bricks
except that the thickness shall be 4.4cm with permissible tolerance of
3mm.
7.0 ADMIXTURES
All materials not fully specified herein and which may be used in the
work shall be of quality approved by the Site-in-charge and he shall
have the right to determine whether all or any materials offered or
delivered for use in the work are suitable for the purpose. The
Contractor shall give the sample of materials and shall get those
approved before procurement and use.
SPECIFICATION FOR EARTHWORK
1.0 CLASSIFICATION OF SOIL
Generally any soil which yields to the ordinary application of pick and
shovel or to phawra or other ordinary digging implement; such as sand,
silt, loam, clay, peat etc.
Rock or boulder may be quarried or split with crowbar. This will also
include laterite & hard conglomerate.
Hard rock requiring blasting as described under 1.4 but where blasting
is prohibited for any reason and excavation has to be carried out by
chiselling, wedging or any other agreed method.
(i) Soil
(ii) Selected earth from heaps or brought from borrow areas.
(iii) Stone/gravel
(iv) Sand
(v) Lean concrete
The material shall be free from rubbish, roots, hard lumps and any
other organic material.
Excavated material shall not be deposited within 1.5M from the top
edge of the excavation.
The sides of the excavation may be cut sloping or shored and strutted
to hold the face of earth as per site requirements and as directed by the
BPCL's Site-in-charge.
3.1 The specification for earthwork shall also apply to excavation in rock
in general. The excavation in rock shall be done such that extra
excavation beyond the required width and depths as shown in drawing
is not made. If any extra excavation particularly in depth is made by the
Contractor during the excavation operation, the Contractor shall make
up such extra excavations with concrete 1:5:10 mix to the required
levels and shaped at no extra cost to the Owner.
The Contractor shall obtain license from the District authorities for
undertaking blasting work as well as for obtaining and storing the
explosive as per Explosive Rules. He shall purchase the explosives,
fuses, detonators etc. only from licensed dealer. He shall be responsible
for the safe custody and proper accounting of the explosive materials.
The Site-in-charge or his authorised representative shall have the
access to check the Contractor’s store of explosive and his accounts.
Proper precautions for safety of persons shall be taken. Red flags shall
be prominently displayed around the area to be blasted and all the
people at the works except those who actually light the fuses shall
withdraw to a safe distance of not less than 200 meters from the blast.
4.0 MEASUREMENT
Payment for earth work in excavation shall be made on cubic meter (m3
) basis on the measurement of volume of pit/trench of excavation as per
IS:1200 . The rate shall include cost of all the operations of blasting,
making all arrangements for dewatering, removal and disposal of
surplus earth.
If soil of any classification other than that specified in the SOR is met
with during the excavation, the decision of the Site-in-charge as to the
classification of the soil, levels of the strata and their location shall be
binding on the contractor.
Dumpy Level
For taking level of any point w.r.t. the known Bench Mark (BM), with
dumpy level, first take the height of B.M. reading, you get the level of
line of collimation and by reducing the height of particular point from
B.M's reading you get the level of that particular point.
Recording
A 0 1.164 289.902
10 1.329 289.737
20 1.429 289.574
30 3.792 287.274
point
50 1.629 286.173
60 1.836 285.966
70 0.925 286.877
0.634 287.168
BM-2
----------------------------------------------------------------------------------------------------
Check 1.723 4.478
---------------------------------
2.755
BM-1 = 289.923
BM-2 = 287.168
------------
2.755
-------------
In this method rise and fall of each point is added or subtracted from
B.M. reading to get the level of particular point e.g.
------------------------------------------------------------------------------------------------------
Stn. Chainage Reading Rise Fall Reduced
Remarks
------------------------------ Level
Back Inter Fore
Sight Sight Sight
--------------------------------------------------------------------------------------------------------
------------
0.535 232.280 BM-
1
A 0 2.145 1.608 230.672
2.435 0.292 230.380
0.56 1.875 232.255
1.583 0.731 0.171 232.084
Changing
Point
2.015 0.432 231.652
1.015 1.00 232.652
2.015 1.00 231.652 BM-
2
Before finally selecting the particular soil for filling from a quarry, the
properties of earth are tested to ensure its suitability.
(a) Procedure for Testing Soils
For selecting earth for earth filling following tests are conducted to
check the suitability of earth for filling purpose as per IS:2720 (Part-V)
1985.
Sands, gravel and peat do not possess plasticity and their PL is zero.
(iii) Soil having laboratory maximum dry density of less than 1.5
gm/cc shall not be used.
(e) Testing Frequency
One test for every 3000 m² of earth filled is required to be carried out.
(iii) Using sheep's foot Roller (can compress upto 35 kg/cm sq.)
As per practical experience, Sheep’s foot roller is best suited for earth
compaction, while rammer is best suited for sand. When areas are
large, road roller could also be used effectively in combination with
sheep's foot roller. It should be noted that water flooding should
always be avoided while compacting the earth.
The cutter containing the soil core shall be weighed to the nearest gram
(Ws)
The soil core shall be removed from the cutter and a representative
sample shall be placed in an air-tight container and its moisture content
(W) determined as per IS:2720 (Part-II) - 1964.
Note:
Calculations
The bulk density (Db), that is, the weight of the wet soil per cubic
metre shall be calculated from the following formula:
Ws - Wc
Db = ---------------- x 1000 Kg/m³
Vc
Where
The dry density Dd, that is, the weight of the dry soil per cubic metre
shall be calculated from the following formula:
1000 x Db
Dd = -------------------- Kg/m³
100 + w
Where
O1 O2 O3 O4 O5 O6 O7
L L L
Area of figure = L (Ol + On + O2 + O3 + O4 ...........................On-1)
2
O1 O2 O3
L L
This rule is applicable only when the number of divisions of the area is
even and total number of ordinates is odd. If there is an odd number of
divisions (resulting in even number of ordinates), the area of the last
division must be calculated separately and added to equation.
The results obtained by the use of Simpson's rule are more accurate
than trapezoidal rule.
Prismoidal formula
Trapezoidal Formula
V = L [A1+An + A2+A3+A4..................................An-1]
2
For Volume Calculation, we should use only Simpson's rule
(Prismoidal formula) as this is more accurate than Trapezoidal formula.
SAMPLE CALCULATIONS
QUANTITY SURVEY
AND
MEASUREMENT OF
EARTHWORK
SAMPLE AREA : 7 m x 9 m
GRID SIZE : 1m x 1m
CONTOUR PLAN :
SIMPSON RULE FOR AREA CALCULATION
A = Area of Section
O1 = First Ordinate
L = Interval (GRID)
If n is even number, then for the last two ordinates Area calculation to
be done by
V = Volume
Simillarly if n is even number then for the last two sections volume
calculation to be done by
V = L/3 x [ An + An + 1 + An + An + 1 ]
SECTION L - 1
CALCULATION SHEET
------------------------------------------------------------------------------------------------------
Sr. Chainage Initial Final Depth of Calculations
No. Level Level Cutting/Filing
-------------------------------------------------------------------------------------------------------------------------------------------------------------
-----------------------
01. 0m 107.520 107.700 0.180 Area of Section by Simpson
Rule
02. 1m 107.455 0.245
aL1 = 1/3 [0.180+0.250
03. 2m 107.420 0.280
+ 4 (0.245 + 0.295 +
04. 3m 107.405 0.295 0.275 + 0.255) +
AL1 = 2.388 m²
SECTION L - 2
01. 0m 107.500 107.700 0.200 aL2 = 1/3 [0.20 + 0.24 + 4
SECTION L - 4
01. 0m 107.540 107.700 0.160 aL4 = 1/3 [0.160 + .225 +
SECTION L - 6
01. 0m 107.560 107.700 0.140 aL6 = 1/3 [.140 + .250 +
SECTION L - 8
01. 0m 107.450 107.700 0.250 aL8 = 1/3 [.250 + .250 +
L1 A1 = 2.388 m 2
L2 A2 = 2.370 m 2
L3 A3 = 2.027 m 2
L4 A4 = 2.077 m 2
L5 A5 = 2.198 m 2
L6 A6 = 2.262 m 2
L7 A7 = 2.265 m 2
L8 A8 = 2.088 m 2
V1 = 39.939 m3
V2 = 1/3 x [ A7 + A8 + A7 x A8 ]
V2 = 2.176 m3
V = V1 + V2
V = 39.939 + 2.176
= 42.115 m3
SPECIFICATION FOR EARTH WORK
IN FILLING
1.3 The material (soil) used for filling shall be free from boulders lumps,
tree roots, rubbish or any organic deleterious matter.
1.4 Material (soil) having plasticity index less than 20 shall be used for
filling purpose.
1.5 Soil having laboratory maximum dry density of less than 1.5 gms/cc
shall not be used.
1.6 Care shall be taken to see that unsuitable waste material is disposed off
in such a manner that there is no likelihood of its getting mixed with
the material proposed to be used for filling.
2.1 All trees having girth between 30 cms and 120 cms and which are not
marked for preservation, shall be cut down and their roots dug up to a
depth of 1 metre from the existing ground level.
2.2 All holes or hollows produced by digging up roots shall be carefully
filled with approved material (soil) including all leads and lifts,
rammed and compacted to obtain 90% of maximum laboratory dry
density of soil and levelled as directed.
2.3 All uprooted trees shall be stacked or disposed off as directed by Site-
in-Charge.
2.4 Payment
Cutting of trees above 30 cms girth shall be paid per number. The rate
quoted shall include cutting, uprooting, removing the trees within plant
boundary as directed, including filling holes or hollows produced by
removal of roots etc. as per specifications.
3.3 Payment
The Contractor has to make his own approach and access roads from
the borrow area to the demarcated filling areas. BPCL does not
guarantee any passage way or right of way for the Contractor's work
other than available at site. No claim shall also be admissible to the
CONTRACTOR on account of his having to take longer leads or
routes for earth movement, than envisaged by him, either due to any
road cuttings, non-availability of routes, or any other grounds
whatsoever.
In case total filling required in any area consists of earth both from
borrow areas and available approved excavated material from within
plant area, then joint levels, shall be taken before commencing filling
with earth from borrow area.
However, earth from Borrow areas required for filling can be used only
after the available earth from excavation within demarcated area has
been utilised and clearance to this effect obtained from the Site-in-
Charge.
4.3 Successive layers of filling shall not be placed until the layer below has
been thoroughly compacted to satisfy the requirements laid down in
this specification.
4.5 After adjusting the Moisture Content as described the layers shall be
thoroughly compacted by either sheep foot roller or power driven roller
or vibratory roller as approved by Site-in-Charge till the specified
maximum laboratory dry density is obtained.
4.6 Each layer shall be tested in field for density and accepted by Site-in-
Charge subject to achieving the required density before laying the next
layer. A minimum of one test per 500 M2 for each layer shall be
conducted.
4.7 If the layer fails to meet the required density, it shall be reworked or the
material shall be replaced and method of construction altered as
directed by Site-in-Charge to obtain the required density.
4.8 The filling shall be finished in conformity with the alignment, levels,
cross-section and dimensions as shown in the drawing.
Earthen embankment shall be filled 300 mm more on both sides, where
height is more than 1M, and this extra filling shall be dressed, after
compaction, in conformity with alignment, level, cross-section and
dimension as shown in the drawing to achieve proper compaction in
the slope. No extra payment shall be made in this regard.
4.9 Extra Material shall be removed and disposed off as directed by the
Site-in-Charge.
4.10 Tolerances
4.11 Payment
M 15 15
M 20 20
M 25 25
M 30 30
M 35 35
M 40 40
-------------------------------------------------------------------------------------
M 10 480 " 34
M 15 350 " 32
M 20 250 " 30
-------------------------------------------------------------------------------------
The mix shall be designed to produce the grade of concrete having the
required workability and characteristic strength not less than
appropriate values given in para 2 above.
3.3 PROPORTIONING
Once a mix, including its water-cement ratio, has been determined and
specified for use by the Site-in-charge, the water-cement ratio shall be
maintained. The Contractor shall determine the water content of the
aggregates frequently as the work progresses, and the amount of
mixing water shall be adjusted so as to maintain the specified water-
cement ratio.
3.6 CONSISTENCY
3.7 WORKABILITY
The concrete mix proportion chosen should be such that the concrete is
of adequate workability for the placing condition and can be properly
compacted with the means available.
-------------------------------------------------------------------------------------
PLACING CONDITIONS DEGREE OF VALUES OF
WORKABILITY
WORKABILITY
------------------------------------------------------------------------------------
Concreting of shallow Very low 20-10 seconds, vee-bee
sections with vibration time or 0.75 - 0.80 ,
compacting factor
4.0 BATCHING
4.3 The amount of the added water shall be adjusted to compensate for any
observed variations in the moisture contents in both fine and coarse
aggregates. For the determination of moisture content in the
aggregates, IS : 2386 (Part-III) may be referred to. To allow for the
variation in weight of aggregates due to variation in their moisture
content, suitable adjustments in the weights of aggregate shall also be
made. In the absence of exact data, only in the case of nominal mixes,
the amount of surface water may be estimated from the values given in
Table below:-
5.1 MIXER
All records and charts for the batching and mixing operations shall be
prepared as specified and as per the instructions of the Site-in-charge.
5.4 ADMIXTURES
5.5 TRANSPORTATION
All concrete shall be conveyed from the mixer to the place of final
deposit as rapidly as possible in suitable buckets, dumpers, containers
or conveyors which shall be mortar leak tight. Care shall be taken to
prevent the segregation or loss of the ingredients and maintaining the
required work ability.
Before placing concrete all soil surfaces upon which or against which
concrete is to be placed shall be well compacted and free from standing
water, mud or debris. Soft or yielding soil shall be removed and
replaced with lean concrete or with selected soils and compacted to the
density as directed by Site-in-charge. The surface of absorbing soil
(against which concrete is to be placed) shall be moistened thoroughly
so that moisture is not drawn from the freshly placed concrete.
Concrete shall be discharged by vertical drop only and the drop height
shall not exceed 1.5 M.
All struts, stays and braces (serving temporarily to hold the forms in
correct shape and alignment pending the placing of concrete at their
locations) shall be removed when the concrete placing has reached an
elevations rendering their service unnecessary. These shall not be
buried in the concrete. Concrete shall be thoroughly compacted with
vibrators and fully worked around the reinforcement, embedded
fixtures and into corners of form work before setting commences. In no
case this shall be subsequently disturbed. Methods of placing shall be
such as to preclude segregation. Care shall be taken to avoid
displacement of reinforcement or movement of formwork.
Unless otherwise approved, concrete shall be placed in single operation
to the full thickness of slabs, beams and similar members. Concrete
shall be placed continuously until completion of the part of the work
between construction joints or as directed by the Site-in-charge.
Concrete that has been left standing and become stiffened shall not be
deposited in the work.
In soil In Water
(%) (ppm)
-------------------------------------------------------------------------------------
7.2 In a column, the joint shall be formed about 100 mm to 150 mm below
the lowest soffit of the beams framing into it. Concrete in a beam and
slab shall be placed throughout without a joint but if the provision of a
joint is unavoidable, the joint shall be vertical and located within 1/3 to
1/4 of the span. This is to be done to ensure that joint is located at the
point of minimum shear.
7.3 When stopping the concrete on a vertical plane in slabs and beams, an
approved stop board shall be placed with necessary slots for
reinforcement bars. The construction joints shall be keyed by providing
a triangular or trapezoidal fillet nailed on the stop board. When
concrete is stopped on a horizontal plane, the surface shall be
roughened and cleaned after the initial set .
7.4 When the work has to be resumed on a surface, which has hardened,
such surface shall be roughened to expose the tips of the coarse
aggregate by hacking it. It shall then be swept clean and thoroughly
wetted. For vertical joints neat cement slurry shall be applied on the
surface before it is dry. For horizontal joints the surface shall be
covered with a layer of mortar about 10 to 15 mm thick composed of
cement and sand in the same ratio as the cement and sand in concrete
mix. This layer of cement slurry or mortar shall be freshly mixed and
applied immediately before placing the concrete.
7.5 Where the concrete has not fully hardened, all laitance shall be
removed by scrubbing the wet surface with wire or bristle brushes, care
being taken to avoid dislodgement of particles of aggregate. The
surface shall be thoroughly wetted and all free water removed. The
surface shall be coated with neat cement slurry. On this surface, a layer
of concrete not exceeding 150 mm in thickness shall first be placed and
shall be well rammed against old work, particular attention being paid
to corners and close spots , work thereafter shall proceed in normal
way.
11.0 CURING
The Contractor shall have all equipment and materials required for
curing on hand and ready for use before concrete is placed.
For curing the concrete in pavements, floors, flat roofs or other level
surfaces the ponding method of curing is preferred after the expiry of
first 24 hours during which (i.e. first 24 hours) the concrete shall be
cured by use of wet sacking, canvass, hessian etc. The minimum water
depth of 25 mm for ponding shall be maintained. The ponded areas
shall be kept continuously filled with water and leaks, if any , shall be
promptly repaired.
The Damp Proof Course shall be laid at plinth level of brick walls,
flush with the floor surface and shall not be carried across doorways.
Before laying, the top surface of wall should be thoroughly cleaned and
watered. The D.P.C shall be laid in layers of 20 mm thickness retaining
the edges by necessary formwork and shall be well tamped and
trowelled to smooth finish. The layer shall be cured by keeping the
surface wet for 40 hours and after it has dried, two coats of hot bitumen
of grade 85/25 conforming to IS:73 shall be applied over it at the rate
to 1.7 Kg/M2. Over this, the second layer 20 mm thick concrete shall
be laid and cured as described in case of the first layer and two coats of
hot bitumen at the rate of 1.7 Kg/M2 shall be applied again in a similar
manner. Over this, dry sharp sand shall be sprinkled evenly.
On striking the formwork, all surface defects such as bulges, ridges and
honey-combing etc. observed shall be brought to the notice of the Site-
in-charge. The Site-in-charge may, at his discretion allow rectification
by necessary chipping and packing or grouting with concrete or cement
mortar. However, if honeycombing or sagging are of such extent as
being undesirable, the Site-in-charge may reject the work totally and
his decision shall be binding. No extra payment shall be made for
rectifying these defects, demolishing and reconstructing the structure.
All burrs and uneven faces shall be rubbed smooth with the help of
carborandum stone.
Repairs shall be made as soon as possible after the forms are removed
and before the concrete becomes too hard. Stone pockets, segregation
patches and damaged areas shall be chipped out and the edges undercut
slightly to form a key. All loose material shall be washed out before
patching.
A good bond between the patch and parent concrete shall be obtained
by sprinkling dry cement on the wet surface or by throwing mortar with
force on to the wetted concrete, or by brush in a coat of thick cement
grout of about 1:1 (1 Cement:1 Sand) just before applying the patching
material. Before this has dried, the remainder of the patch shall be
filled with mortar or concrete, depending on the extent of the repair.
13.3 The use of an epoxy for bonding fresh concrete used for repairs shall
be permitted at the discretion of the Site-in-charge. Epoxy shall be
applied in strict accordance with the instructions of the manufacturer.
Form joints shall not permit any leakage. The formwork shall be strong
enough to withstand the effect of vibrations practically without any
deflection, bulging, distortion or loosening of its components. Forms
for beams and slabs (span more than 6.0 m) shall have camber of 1 in
500 so as to offset the deflection and assume correct shape and line
after deposition of concrete. For cantilevers, the camber at free end
shall be 1/100th of the projected length.
The surfaces of forms that would come in contact with concrete shall
be well treated with approved non-staining release agents such as soft
soap, oil, emulsions etc. Care shall be taken that such release agents are
kept out of contact with the reinforcement.
Forms and their supports shall not be removed without the approval of
the Site-in-charge. Methods of form removal likely to cause
overstressing or damage to the concrete shall not be adopted. Supports
shall be removed in such a manner as to permit the concrete to
uniformly and gradually take the stresses due to its own weight.
15.6 STAGING/SCAFFOLDING
All reinforcement shall be cleaned of mill scale, loose rust, oil, grease
or any other harmful material before placing them in position.
16.3 OVERLAPPING
Only bars of full length shall be used as shown in the drawings. But
where this can not be done, overlapping of bars shall be done as
directed by the Site-in-charge. Where practicable, the overlapping bars
shall not touch each other, but these shall be kept apart by 25 mm or
1.25 times the maximum size of the coarse aggregate whichever is
greater. But where this is not possible, the overlapping bars shall be
tied with two strands of 16 SWG black soft annealed binding wire. The
overlaps shall be staggered for different bars and located at points
along the span where neither shear nor bending moment is maximum.
16.5 SUBSTITUTION
When specified diameter of reinforcement bars is not available, the
Contractor shall use other diameter of reinforcement bars on written
approval of the Site-in-charge.
16.6 COVER
18.0 PAYMENT
Payment for plain and reinforced cement concrete (cast in-situ) shall be
made on cubic meter basis of the volume of the actual finished work
done or as per approved construction drawings, whichever is less and
shall be inclusive of providing pockets, openings, recesses of all sizes,
chamfers, fillets construction joints, cement wash, curing etc. The rates
shall be deemed to include complete cost of taking and testing concrete
cubes and carrying out other tests as per specifications and as directed
by Site-in-charge.
Payment shall be made on square meter basis of the area laid inclusive
of formwork, curing, providing and applying bitumen, supplying and
spreading sand over bitumen etc.
SPECIFICATION FOR
BRICK MASONRY
1.0 CLASSIFICATION OF BRICK WORK
2.1 PROPORTIONING
2.2 MIXING
B) Hand mixing
Bricks shall be thoroughly soaked in clean water before use for at least
two hours and until air bubbles cease to come out. The soaked bricks
shall be kept on wooden planks or bricks platform to avoid earth being
smeared on them. At the time of placing the bricks, they should be
bone-dry.
3.2 LAYING
Brick shall be laid with frogs upward. While laying, bricks shall be
thoroughly bedded and flushed in mortar and tapped into position with
a wooden mallet and the superfluous mortar removed.
All iron fixtures, pipes, conduits, holdfasts of doors and windows etc.
which are required to be built in walls, shall be embedded in cement
mortar or in cement concrete as specified, in their correct position as
the work proceeds.
3.3 JOINTING
3.4 CURING
4.0 SCAFFOLDING/STAGING
5.2 LAYING
6.0 PAYMENT
6.1 Payment for brick masonry work (of one or more brick thickness) shall
be made on cubic metre basis on the volume of actual work done.
6.2 Payment for half brick masonry work shall be made on square meter
(M2) basis on the area of actual work done and shall include cost of
supplying and fixing reinforcement in position.
6.3 The rate of brick masonry work shall be inclusive of all labour,
material, sampling and testing, scaffolding/staging, soaking of bricks
raking of joints, curing, providing recesses and openings, embedding
fixtures etc.
SPECIFICATION FOR
STONE MASONRY
1.1 STONE
1.2 DRESSING
Stone shall be hammer-dressed on the face, the sides and the beds. The
"bushing" (projection) on the face shall not project more than 40 mm
on an exposed face and 10 mm on the face to be plastered.
1.3 LAYING
All stones shall be wetted before use. The wall shall be carried up truly
plumb or to specified batter. Every stone shall be carefully fitted to the
adjacent stones so as to form neat and close joints. Stones may be laid
at random without being brought upto any level courses except at
plinth, window sills and roof level. The bond shall be obtained by
fitting in closely the adjacent stones and by using bond stones. Face
stones shall extend and bond well into the backing. These shall be
arranged to break joints as much as possible and to avoid long vertical
lines of joints. Hearting (interior filling) of the wall face shall consist
of rubble stones with thickness not less than 100 mm in any direction,
carefully laid, hammered down with a wooden mallet into position and
solidly bedded in mortar. Chips and spawls of stones shall be used
wherever necessary to avoid thick mortar beds or joints and at the same
time ensuring that no hollow spaces are left anywhere in the masonry.
The masonry in a structure shall be carried regularly. Where the
masonry of one part has to be delayed, the work shall be raked back at
an angle not steeper than 45 degree.
Bond or through stone running right through the thickness of wall shall
be provided in the walls having thickness upto 600 mm. If the walls are
thicker than 600mm, two or more bond stones overlapping each other
by at least 150 mm shall be provided in a line from face to back.
Atleast one bond stone or a set of bond stones shall be provided for
every 0.5 sq.m. of wall surface
1.5 JOINTING
Stones shall be so laid that all joints are fully packed with mortar. Face
joints shall be 20 mm thick. The joints shall be struck flush and
finished at the time of laying when plastering and pointing is not
required. If walls are to be plastered or pointed, joints shall be raked to
a depth of 20 mm (minimum) during the progress of work when the
mortar is still green. For the faces of walls that are not to be plastered,
stone surfaces shall be cleared of mortar splashing to give uniform
appearance.
1.6 PAYMENT
Payment for stone masonry work shall be made on cubic metre (M3)
basis on the volume of actual work done and the rates shall be
inclusive of all labour, material, scaffolding/staging, wetting out of
stones, raking out joints, curing, providing recesses and openings,
embedding fixtures etc.
2.1 STONE:
2.2 DRESSING:
Face stones shall be hammer dressed and to be squared on all sides and
joints so as to give them approximately rectangular block shape. The
bed joint shall be rough chisel dressed, true and square for at least 60
mm back from the face and the side joints for at least 40 mm, such that
no portion of the dressed surface is more than 6 mm from a straight
edge placed on it. The remaining portion of stones shall not project
beyond the surface of the bed and side joints. The "Bushing" on the
face shall not project more than 40 mm on exposed face and 10 mm on
the face to be plastered.
2.3 LAYING:
All stones shall be wetted before use. The walls shall be carried up
truly plumb or to specified batter. All courses shall be laid truly
horizontal and all vertical joints shall be truly vertical. The stones shall
be laid in horizontal courses and each course shall be of equal height.
The height of each course shall not be less than 150 mm and not more
than 300 mm.
Same as for random rubble masonry except that a bond stone or a set of
bond stones shall be inserted 1.5 to 1.8 m apart, in every course.
2.5 JOINTS
All bed joints shall be horizontal and all side joints vertical. All joints
shall be full of mortar. Face joints shall not be more than 10 mm thick.
When plastering or pointing is not required to be done, the joints shall
be struck flush and finished at the time of laying. Otherwise the joints
shall be raked to a minimum depth of 20 mm during the progress of
work when the mortar is still green. The joint shall be either flush or
struck. Raised or cut-pointing, shall be done with cement mortar 1:3
using wooden mould/template of minimum 12 mm depth for
uniformity.
SPECIFICATION FOR
PLASTERING AND POINTING
1. CEMENT PLASTERING
1.2 MORTAR
Plaster shall be started from top and gradually worked down towards
floor. It shall not, at any place be thinner than specified. To ensure even
thickness, plaster of about 15cm x 15cm shall be first applied
horizontally and vertically at not more than 2 metre interval over the
entire surface to serve as gauges. The surfaces of these gauged areas
shall be truly in the plane of finished plaster surface. The mortar shall
then be laid on the wall or other surfaces between the gauges and
finished even. All corners shall be rounded to a radius of 25 mm unless
otherwise specified. The Contractor shall not be paid for any extra
thickness of plaster done than as specified. The plastering thickness
shall generally be as under unless otherwise specified.
1.4 CURING
Curing shall start 24 hours after the plaster is laid. It shall be kept were
for 7 days.
During this period it shall be suitably protected from all damages at the
Contractor's expenses by such means as approved by the Site-in-
charge.
1.5 Any cracks which appear in the surface and all portions which sound
hollow when tapped, or are found to be soft or otherwise defective,
shall be cut out in rectangular shape and redone as directed by the Site-
in-charge.
1.7 PAYMENT
2.2 Sand face plaster shall consist of two layers. The first layer generally
7mm average thick cement plaster with cement mortar of 1:4 mix (1
cement : 4 sand) shall be rough finished. Over this a second layer of
average 13 mm thick of cement sand plaster in the proportion of 1:2
mix shall be applied. The second layer of plaster shall be laid only after
first layer has sufficiently dried.
2.3 CURING
The plaster shall be thoroughly cured for 7 days as directed by Site-in-
charge.
2.4 Any cracks which appear in the surface and all portions which sound
hollow when tapped, or are found to be soft or otherwise defective,
shall be cut out in rectangular shape and redone as directed by the Site-
in-charge.
2.5 PAYMENT
Payment for plastering shall be made on square metre basis, for the
particular thickness of plaster. Deduction shall not be made for Jambs,
Sills and soffits measured for opening of area less than 0.5 sqm. each.
For opening of area between 0.5 sqm. and 3.0sqm. each, deduction
shall be made at 50% of the opening area and no payment made for
jambs, soffits, sills etc. For openings of area above 3 sqm. each,
deduction shall be made for full area of opening but jambs, soffits and
sills shall be measured. All measurements shall be separately made for
each face. The rate shall include the cost of providing drip
moulds/bands, scaffolding and swing etc., needed for the work with
labour and material all complete.
3.1 The surface shall be prepared as for cement plaster and then 2 cm
backing coat of cement mortar 1:3 (1 cement:3 sand) shall be applied.
Subsequently a top coat, 13mm average thick of cement and stone
chips mixture in proportion 1:3 (1 cement : 3 stone chips 10mm size
and below) shall be applied by throwing the mixture on top with trowel
to produce uniform rough texture.
3.2 PAYMENT
Payment shall be made on square metre basis. The rate shall include
the cost of scaffolding, swing etc. With labour and material all
complete.
4.0 POINTING
4.3 MORTAR
The mortar shall be pressed into raked out joints with pointing trowel
and finished either flush, sunk or raised according to type of pointing
specified in the drawings or as directed. The superfluous mortar shall
be cut off from the edges of the lines and the surface of masonry shall
be cleaned of all mortar finish to be free of slack spots, cut faces and
other blemishes. Finished work of pointing shall be to exact size and
shape stipulated and edges shall be straight, neat and clean.
4.5 CURING
The pointing shall be kept wet for 7 days. During this period it shall be
suitably protected from all damages.
4.6 PAYMENT
In recessed pointing, the mortar shall be simply struck off with a trowel
and the work left showing the natural irregularities in line and surface
of the stones themselves. Other specification shall remain as above for
pointing.
In case of raised pointing, it shall project from the well facing with its
edges cut parallel so as to have a uniformly raised band about 6mm
raised and width 10mm or more as directed showing the natural
irregularities in line and surface of stones themselves. Other
specifications shall remain same as per above specifications of
'Pointing'.
4.8 PAYMENT
SPECIFICATION FOR
FLOORING
1. SCOPE
1.2 The materials and workmanship shall conform to the provisions of the
following codes and standard specifications in particular and with such
other standards as are mentioned here in after. IS : 269, 515, 653, 712,
809, 1077, 1195, 1196, 1197, 1198, 1237, 1344, 1443.
2. GENERAL REQUIREMENTS
2.1.1 GENERAL
2.1.2 FILLING
The bed for Flooring shall be prepared either level or sloped as per
relevant drawings or as instructed by Site-in-charge. Care shall be
taken that there are no roots, Vegetation, foreign matter etc.
2.1.4 SUB-BASE
The finished work shall be of uniform depth over the whole floor with
surface even and parallel to the prepared bed as per drawing or as
directed by Engineer-in -Charge
b) Sand Layer
Sand for sand layer to be laid over the prepared bed shall be
clean, free from admixture and shall be as per specification.
Sand layer shall be spread in one or more layers to the thickness
as indicated in drawings or schedule of rates, watered and
rammed.
2.1.5 PAYMENT
Payment for sub base course shall also be made on cubic metre basis of
gross volume.
2.2 BASE-COURSE
2.2.1 CEMENT-CONCRETE
2.2.2 PANELS
2.2.3 SHUTTERING
The panels shall be bonded by wooden battens or flat iron having the
same depth as the concrete floor. These shall be fixed in position, with
their top at proper level, giving slope, where required. The surface of
battens or flats, to come in contact with concrete shall be smeared with
soap Solution or non-staining oil before concreting. The flooring shall
butt against masonry of wall, which shall not be plastered.
2.2.4 CONCRETING
The shuttering shall be removed next day. Care shall be taken to see
that edges are not damaged and fresh mortar from adjacent panel is not
splashed over them. The joints between panels shall come out as fine
straight line.
2.2.5 PAYMENT
Base course shall be measured on cubic metre basis and the rate shall
include shuttering but exclude reinforcement unless otherwise
specified. Payment for MS reinforcement where used shall be made
under the item of MS reinforcement irrespective of the size of MS rods
used.
It shall be pressed twice by mans of iron floats, once when the slurry is
applied and second time when cement starts setting.
2.3.1 CURING
2.3.2 PRECAUTIONS
2.3.3 PAYMENT
Payment shall be made on square metre basis. Rate shall include costs
of all materials, shuttering and labour involved in all the operations but
shall not include the cost of sub-base and base course-concrete under
the finishing layer.
The bottom layer of concrete shall be laid with 10mm to 6mm graded
aggregate and well compacted. Within 15 minutes of laying this course,
the top layer of 6 mm thickness shall be laid. The cement and aggregate
for top layer shall be mixed dry. After mixing, sufficient quantity of
washed sand and water shall be added to make the mix plastic but not
flowing. The mixture shall be laid on the under layer so that the two
layers firmly grip together. The top layer shall be well tamped, spaded,
trowelled and finished with a neat cement punning or with non-skid
finish as required. At the junction of adjoining panels a thin string shall
be given.
3.3 CURING
3.4 PAYMENT
Payment shall be made on square metre basis. Rate shall include cost
of all materials, Shuttering and Labour involved in all the operations
but shall not include the cost of sub-base and Base Course Concrete
under the finishing layer.
4.1 The requirements of filling, preparation of bed, sub base and base
course concrete shall be same as in clause 2.0 above.
4.2.1 MORTAR
4.2.2 LAYING
The top plaster shall be laid a day after the base course concrete has
been laid. The plaster shall be done to a uniform thickness of 10mm or
as specified and finished smooth with floating coat (In floating coat 2.2
Kg. of cement per sq.m. of floor area shall be mixed with red oxide in
the same ratio as the cement to red oxide ratio used for the plaster).
4.3 CURING
The curing shall be done for a minimum period of 7 days. Curing shall
not be commenced until the floor finish has hardened. Covering with
empty cement gunnies shall be avoided, as the scour is likely to be
blotched with the remnants of cement mortar sticking these bags.
4.4 PAYMENT
Payment shall be made on square metre basis. Rate shall include cost
of all materials and labour involved in all the operations but shall not
include the cost of sub-base and base course concrete under the
finishing layer.
5.1 The requirement for filling, preparation of bed, subbase and base
course concrete shall be same as in clause 2.0 above.
5.2.1 MORTAR
Unless otherwise specified, one part of ironic and four parts of ordinary
Portland cement by weight shall be mixed dry thoroughly on a clean
and dry platform. This dry mixture shall be mixed with stone grit 6 mm
and down size in the ratio of 1:2 (1 ironic cement mixture: 2 stone grit)
by volume or as otherwise specified and well mixed over. Just enough
water shall then be added to this dry mix for laying.
5.2.2 LAYING
5.2.3 CURING
5.2.4 PAYMENT
6.2.1 MORTAR
6.2.2 LAYING
The topping shall then be laid over the wet base course concrete and
finished in the same manner as in sub-para 5.2.2.
7.1 The requirements for filling, preparation of bed, sub-base and base
course concrete shall be same as in clause 2.0 above.
Base course concrete on which the tiles are to be laid shall be cleaned,
wetted and mopped.
7.3.1 LAYING
The bedding for the tiles shall be with either lime Mortar 1:2 (1 lime
putty: 2 coarse sand) or cement mortar mix as directed by Site-in-
charge. Lime or cement mortar setting shall be spread, tamped and
corrected to proper levels and allowed to harden for a day before the
tiles are set.
Over this bedding neat cement slurry of honey like consistency shall be
spread at the rate of 44 kg. Of cement per square metre. Tiles shall be
soaked in water for 20 minutes and allowed to drain out for 20 minutes
before laying. Tiles shall be damp but not wet when they are laid. Tile
shall be laid in the mortar bedding from centre to outwards to obtain a
symmetrical pattern, each tile being gently tapped with wooden mallet
till it is properly bedded and is in level with adjoining tiles. The surface
of the flooring during laying shall be frequently checked with a straight
edge at least 2m long, so as to obtain true surface with required slope.
Fractional tiles shall be used where full tiles cannot be used in the extra
space. When extra space left out is less than 25 mm, it shall be filled
with coloured Mortar and finished to match tiled floor.
7.3.2 JOINTS
The joints shall be uniform and as thin as possible and run in straight
lines or to suit the required pattern. Where full size tiles cannot be
fixed, these shall be cut to the required size and their edges rubbed
smooth to ensure straight and true joints.
Tiles that are fixed on the floor adjoining the wall shall enter not less
than 13 mm under the plaster, skirting or dado. The junction between
wall plaster and tiled work shall be finished neatly and without waving.
After the tiles have been laid surplus cement grout that may have come
and of the joints shall be cleaned off.
The day after the tiles are laid, all joints shall be cleaned with wire
brush to the depth of 5mm. And all dust and loose-mortar removed.
Joints shall then be grouted with grey or white cement mixed with or
without pigment to match the shade of the topping of the wearing-layer
of the tiles. Pigment shall conform to IS :459.
The floor shall then be kept wet for a minimum period of 7 days. The
surface shall there after be ground evenly to the satisfaction of Site-in-
charge with machine grinders in 3 phases with grade stones from
coarse to fine grade. The surface shall receive a wash of neat cement
mixed with or without pigment and cured before every grinding
operation.
After final polish, surface shall be cleaned and oxalic acid shall be
dusted over the surface wiped and dried with soft cloth. Finally the
finished Terrazzo surface is to be rendered with the wax mixed with
turpentine or similar approved material. The surface after polishing
shall present a glossy appearance. Where machine polishing cannot be
done, because of small areas, the surface shall be hand polished. In all
other respects the process shall be similar as per machine polishing.
7.4 PAYMENT
Payment shall be made on square metre basis of the finished work. The
rate shall include the cost of all material, labour involved in all the
operations described above.
8.1 The requirements for fittings. Preparation of bed, sub-base and base
course concrete shall be same as in clause 2.0 above.
8.2 MATERIAL
Best quality marble chips of uniform tint and colour, 6mm maximum
and 3mm mini mum size, as approved by Engineer-in -Charge shall be
used. They shall be machine crushed free from foreign matters and of
approved quality.
The cement and marble chips including powder shall be mixed dry.
Water shall then be added gradually after thorough mixing until the
mix become plastic but not flowing.
Within one hour of laying of the bottom layer of cement mortar, the
upper layer of marble chips and cement shall be laid over a coat of
cement slurry and the surface tamped lightly and finished to the
required level and slope.
After two hours of laying, the surface shall be covered with wet bags
and left undisturbed for six days and then the surface shall be ground
with carborandum stones of different grades starting with coarse one
and successively with finer one, by machine/hand cutting and the
rubbing continued until the entire surface shows uniform appearance.
Finally, oxalic acid powder shall be well rubbed on the surface with
pieces of felt with a few drops of water and this operation shall be
repeated until the surface becomes smooth and glossy.
For Skirting and Dado the brick work or concrete surface shall be
raked or hacked as the case may be and shall be well watered. A
dubbing coat of cement mortar 1: 3 (1 Cement: 3 sand) of specified
thickness shall be applied so as to bring the surface in line with the
plastered surface. The surface shall be scarified by lines with trowel so
as to receive the top layer of cement and marble chips in proportion of
1 : 1/2 : 2 (1 cement : 1/2 Marble powder : 2 Marble chips ) of 7mm
thickness with 3.5 mm size chips and shall be laid, polished etc. as
described above for flooring including glass dividing strips ( 20 mm x
4 mm) @ 600mm c/c or as specified in schedule of rates.
8.2.4 PAYMENT
Payment shall be made on square metre basis of the finished work. The
rate shall include the cost of all material and labour involved in all the
operations described above.
9.1 The requirements for filling, preparation of bed, sub-base and base
course concrete shall be same as in clause 2.0 above.
All glazed tiles will be immersed in water for atleast 12 hrs prior to
use.
Base course concrete or R.C.C. slab on which tiles are to be laid shall
be well cleaned, wetted and mopped. The bedding for the tiles shall be
with cement mortar 1 :3 or as specified. The average thickness of the
bedding shall be 12mm while minimum under any portion of tile shall
be not less than 10mm.
Over this mortar bedding neat grey cement slurry of honey like
consistency shall be spread, at the rate of 3.3 Kg per square metre, over
an area such that approximately 20 tiles can be accommodated. Tiles
being gently tapped with a wooden mallet till it is properly bedded in
level with adjoining tiles.
9.2.2 JOINTS
The Joints shall be cleaned of the grey cement grout with a wire brush
or trowel to a depth of 5mm and all dust and loose mortar removed.
Joints shall then be flush pointed with white cement.
Flooring shall be kept wet for 7 days. The tiled surface shall then be
finished with a 3% solution of oxalic acid, duly waxed and polished as
directed by Site-in-charge.
9.2.4 PAYMENT
Payment shall be made on square metre basis of the finished work. The
rate shall include the cost of all material, labour involved in all the
operations described above.
10.2 MATERIALS
PVC (Poly Vinyl chloride) tiles shall be 3mm thick. These shall be of
approved make conforming to IS : 3461 or 3462 as shown in the
drawing.
10.3 LAYING
10.3.1 The bedding for the tiles shall be M- 15 grade cement concrete
flooring. The thickness of flooring shall be 25mm. The cement
concrete floor shall be well cured and thoroughly dried and shall be
cleaned well.
A coat of approved base binding agent shall be applied evenly over the
bedding. The tiles shall be sufficiently dried before fixing to the floor.
The tiles shall be joined with binding pressure until it adheres well to
the bed material. In case the binding agent raises from the joints it shall
be removed. The tile floor shall be cleaned with the tile finish wax and
polished with the muslin cloth. The binding material shall be of
approved manufacturer.
10.3.2 The pattern and colour arrangement for the flooring shall be as
indicated on the drawing or as approved by Engineer - in- Charge. The
Contractor shall assume full responsibility for any failures and defects
in tile finish work.
10.3.4 All flooring shall be thoroughly cleaned to full satisfaction of the Site-
in-charge.
10.3.5 The tiles shall be inspected after 30 days and the adjustment, repairs or
replacement of any tile showing loose edges, breaks, chipped corners,
cracks, discoloration or similar defects shall be done by the Contractor
at his own cost. Any replaced tile shall be of the same kind, colour,
size and finish.
10.4 PAYMENT
11.1 Precast RC floor panels of approximately 1.0 x 1.0M shall be cast true
to dimensions as shown on drawing. The concrete grade shall be as
specified on the drawing. The top surface of the precast slabs shall be
finished rough and hardened with sodium silicate solution. The sodium
silicate solution shall be diluted with four times its volume of water,
well stirred and sprayed over the surface with a watering can and
brushed evenly with a soft broom. The solution shall be applied in
three coats, each coat shall be allowed to dry for 24 hours before the
next coat is applied. Each coat shall be scrubbed with water after it has
hardened for a better condition for the application of succeeding coats.
The surface of concrete to be treated shall be thoroughly cleaned of any
grease or dirt and dried after completion of the curing period before the
solution is applied. The floor panels shall be laid over a compact layer
of and cushion and keyed together. The joint between two panels shall
be filled with bitumen sealing compound.
11.2 PAYMENT
12.1 For brick Soling only well burnt or slightly over burnt 2nd class bricks
conforming to specification shall be used. Soling shall be laid on flat or
on edge as shown on drawing. The laying shall be done in a
workmanlike manner starting from one end of the area and staggering
the joints and using cutbricks as and when necessary. The joints shall
be properly blended with sand of approved quality or cement pointed
as per specification or direction of Site-in-charge.
12.2 PAYMENT
Payment for brick soling shall be made on square metre basis. Rates
quoted shall include all labour, material and watering if necessary or as
directed by Site-in-charge at site.
The slabs shall have the top (exposed) face polished before being
brought to site. Before starting the work, Contractor shall get the
samples of slabs approved by the Site-in-charge.
Every slab shall be cut to the required size and shape and fine chisel
dressed on the sides to the full depth so that a straight edge laid along
the side of the stone shall be in full contact with it. The sides (edges)
shall be table rubbed with coarse sand or machine rubbed before
paving. All angles and edges of the slabs shall be true, square and free
from chippings and the surface shall be true and plane. For staircase
treads, single piece slab to full length and width of treads shall be
provided. The nosing shall be rounded off and two parallel grooves ten
by ten (10 mm x 10 mm) immediately behind the nosing edge shall be
provided as per drawing to avoid skidding.
Sub-grade concrete or the RCC slab on which the slabs are to be laid
shall be cleaned, wetted and mopped. The bedding for the slabs shall
be with cement mortar 1 : 3 ( 1 Cement :3 Coarse Sand ) the average
thickness of the bedding mortar under the slab shall not be less than
twelve (12) mm.
Mortar of the specified mix shall be spread under the area of each slab,
roughly to the average thickness specified in the item. The slab shall be
washed & cleaned before laying. It shall be laid on top, pressed, tapped
with wooden mallet and brought to level with the adjoining slabs. It
shall be lifted and laid aside. The top surface of the mortar shall then
be corrected by adding fresh mortar at hollows. The mortar is allowed
to harden a bit and cement Slurry of honey like consistency shall be
spread over the same at the rate of 4.4 kg of cement per sqm. The slab
to be laid shall be lowered gently back in position, bedded in level.
Subsequent slabs shall be laid in the same manner and joints between
adjacent slabs shall be as thin as possible and run in straight line. After
each slab has been laid, surplus cement grout coming out of the joints
of the slabs shall be cleaned off. The surface of the flooring as laid
shall be true to levels, lines and shapes as instructed by the Site-in-
charge.
The slabs shall be matched as shown in drawings or as instructed by
the Site-in-charge.
Slabs that are fixed in the floor adjoining the wall shall enter not less
than twelve-(12) mm. under the plaster skirting or dado. The junction
between wall plaster and the floor shall be finished neatly and with out
waviness.
The floor shall be kept wet for a minimum period of seven (7) days.
The surface shall there after be ground evenly with machine fitted with
fine grade grit blocks (No. 120). The final grinding with machine fitted
with the finest grade grit blocks (N0. 320) shall be carried out the day
after the first grinding described above or before handing over the
floor, as ordered by the Site-in-charge.
After the final polish, oxalic acid shall be dusted over the surface at the
rates of thirty-three (33) gms per square metre sprinkled with water and
rubbed hard with pad of wooden rags. The following day the floor shall
be wiped with a moist rag and dried with a soft cloth and finished
clean.
13.5 PAYMENT
The stone flooring shall be measured in square metre (M2). Length and
breadth shall be measured between the finished faces of skirting, dado
or wall plasters as the case may be, correct to a cm. No deduction shall
be made upto 0.050 sq.m. No extra shall be paid for laying the floor at
different levels in the same room. Steps and treads of stairs paved with
stone slabs also be measured under the item of "Stone Flooring. The
rate shall include the cost of all materials and labour involved in the
operations described above.
SPECIFICATION FOR
WHITE WASHING AND PAINTING
1. WHITE WASHING
PREPARATION OF SURFACE
Surface shall be thoroughly cleaned of all dust, dirt, mortar drops and
loose plaster. All holes shall be filled with gypsum and surfaces made
even and smooth.
SCAFFOLDING
Where ladders are used, pieces of old gunny bag shall be tied on their
tops to avoid damage or scratches to walls.
The wash shall be prepared from fresh and pure fat lime. It shall be
thoroughly slaked, mixed and stirred with sufficient water to attain a
consistency of thin cream. This shall be allowed to stand for a period of
24 hours and then shall be screened. The approximate quantity of water
to be added to pure fat lime for making the cream shall be 5 litres to 1
Kg of lime. Clean gum at the rate of 0.5 kg to 100 kg of cream,
dissolved in hot water and ultramarine blue of approved quality and
quantity as directed by Site-in-charge, shall be added and thoroughly
mixed.
APPLICATION
The wash shall be applied with moonj brushes. Three number of coats
or as specified shall be applied. One coat means painting the surface
first with vertical stroke, followed by horizontal stroke. Each coat shall
be allowed to dry before next one is applied. Further each coat shall be
inspected and approved by the Site-in-charge before the subsequent
coat is applied.
The finished dry surface shall be of even shade, without any brush
marks and shall not show any sign of cracking and peeling nor shall it
come off readily on the hand when rubbed.
PROTECTIVE MEASURES
Doors, windows, floors. etc. and such other parts of building shall be
protected from being splashed upon. Splashing and dropping if any,
shall be removed by the Contractor at his own cost and the surfaces
cleaned.
PAYMENT
Payment shall be made on Square Metre basis and rate shall include
cost of all material, Scaffolding and labour involved in all the
operations. Voids shall be measured as per clause for plastering given
under specification.
2. COLOUR WASHING
PREPARATION
APPLICATION
The finished dry surface shall not be powdery and shall not come off
on the hand when rubbed.
All other specification and mode of measurement & payment for white
washing shall be applicable.
3. DISTEMPERING
TYPE
The dry distemper shall be stirred slowly in clean warm water using 0.6
litre of water per kg. of distemper or as specified by the approved
makers. The mixture shall be well stirred before and during use to
maintain an even consistency.
The surface shall be thoroughly brushed free from mortar dropping and
other foreign matter and sand papered smooth.
APPLICATION
After the primer coat has dried for at least 48 hours, the entire surface
shall be coated uniformly with proper distemper brushes in horizontal
strokes, immediately followed by vertical ones which together shall
constitute one coat.
Subsequent coats shall be applied in the same way and only after the
previous coat has dried.
The finished surface shall be even and uniform and shall show no
brush marks.
After each day's work, the brushes shall be washed in hot water and
hung down to dry. Old brush that is dirty or caked with distemper shall
not be used.
PAYMENT
The payment shall be based on per square metre of finished area and
shall include cost of all materials and labour involved in all the
operation. Voids shall be measured as per clause given under
specification for plastering.
SURFACE PREPARATION
PAYMENT
Payment shall be made on square metre basis. Rate shall include cost
of all material and labour involved in all the operations. Voids shall be
measured as per clause given under specification of plastering.
5. PAINTING
MATERIAL
COMMENCEMENT OF WORK
Painting except priming coat shall generally be taken in hand after all
other building work is practically finished. Approval of Site-in-charge
shall be sought before commencing the work.
PREPARATION OF SURFACE
The surface shall be thoroughly cleaned. All dirt, dust, scales and
grease shall be removed before painting is started. The surface shall be
perfectly dry to permit good absorption. The prepared surface shall
receive approval from Site-in-charge for commencing the painting
work.
Specially for wood surfaces knots, if visible, shall be covered with red
lead conforming to IS: 103. Holes and indentation on the surface shall
be filled with good putty and rubbed smooth. Surface should be
thoroughly dry.
APPLICATION
The finished surface shall be free from hair or brush marks, clogging of
paint, puddles in the corners of panels angles of moulding etc.
PAYMENT
MATERIAL
Painting shall be done after the surface to be painted is made free from
dirt, dust and foreign matter and all rough spots, sand papered and
cleaned. The surface must be perfectly dry before painting is
commenced.
APPLICATION
The preservative shall be applied liberally with a stout brush. It shall be
applied with pencil brush at the joints of woodwork. The first coat
shall be allowed at least 24 hours to soak in before the second coat is
applied. The excess of preservative, which does not soak into the
wood, shall be wiped off with a clean dry piece of cloth.
PAYMENT
MATERIAL
PREPARATION OF SURFACE
The surface shall be thoroughly cleaned. All dirt, dust scales and grease
shall be removed before painting is started. The surface shall be
perfectly dry to permit good absorption. The prepared surface shall
receive approval from Site-in-charge for commencing the painting
work.
Holes and indentation on the surface shall be filled with wood putty
and rubbed smooth. Surface should be thoroughly dry.
APPLICATION
UNDER COAT
One coat of the specified paint of shade matching with the shade of the
top coat shall be applied and allowed to dry overnight. It shall be
rubbed next day with the finest grade of wet abrasive paper to ensure
smooth and even surface, free from brush marks and all loose particles
dusted off.
TOP COAT
GENERAL
The surface shall be thoroughly cleaned off dust, old white or colour
wash by washing and scrubbing. The surface shall then be allowed to
dry for at least 48 hours. It shall then be sand papered to give a smooth
and even surface. Any unevenness shall be made good by applying
putty, made of plaster of paris with water on the entire surface
including filling up the undulation and then sand papering the same
after it is dry.
APPLICATION
The number of coats shall be as stipulated in the item. The paint shall
be applied in the usual manner with brush or roller over the prepared
surface.
As soon as water has evaporated, the film gets hard and the next coat
can be applied then. The time of drying varies from one hour on
absorbent surfaces to 2 to 3 hours on non-absorbent surfaces.
The thinning of the emulsion is to be done with water and not with
turpentine. Thinning with water will be particularly required for the
under coat which is applied on the absorbent surface. The quantity of
thinner to be added shall be as per approved manufacturer instructions.
PRECAUTIONS
Splashes on floors etc. shall be cleaned out without delay, as they will
be difficult to remove after hardening.
PAYMENT
8. VARNISHING
MATERIAL
PREPARATION OF SURFACE
APPLICATION OF VARNISH
The number of coats shall be as stipulated in the item. The under coat
shall be given with a flatting varnish. This dries hard and brittle and
when rubbed down produces a smooth surface and enhances the gloss
of the finishing varnish.
The top coat shall be given with approved brand of finishing varnish.
The varnish shall be applied liberally with a full brush and spread
evenly with short light strokes to avoid frothing.
Rubbing down with fine sand paper and flatting the surface shall be
done after each coat except the final coat.
The work shall be allowed to dry away from damp air. Finished surface
shall then present a uniform appearance and a fine glossy free from
streaks, blisters etc.
PAYMENT
9. COAL TARRING
MATERIAL
Coal tar of approved quality and manufacture shall be used. The tar
with the addition of 0.2kg of unslaked lime per litre shall be heated till
it begins to boil. Then the heating will be stopped and kerosene oil
added to it slowly at the rate of 1 part of kerosene oil to 6 or more parts
of tar by volume and stirred thoroughly. The addition of lime is for
preventing the tar from running.
PREPARATION OF SURFACE
The surface shall be thoroughly cleaned and dusted. All dust, dirt,
scales, smoke and grease shall be thoroughly cleaned before painting is
started. Where form work is to be painted it shall be free from scales
and rust. The prepared surface shall be approved by Site-in-charge
before the painting is commenced.
APPLICATION
PAYMENT
1.1 MATERIAL
All steel Doors, Windows and Fixing & Glazing of Metal Ventilators
shall conform to IS : 1038, IS : 1361, IS : 1081 or Equivalent as
mentioned in specification and on drawings and as approved by the
Site-in Charge.
1.2 WORKMANSHIP
Doors, Windows and Ventilators etc. Shall be truly square and flat, free
from twist and warp. They shall be constructed of sections, which have
been cut to the required lengths, riveted or welded at the corners. The
general fabrication shall conform to IS : 1038 & 1361.
1.3 GLAZING
FIXING
Doors, Windows and ventilators shall not be built in at the time the
walls are constructed but shall be fixed into prepared openings, as laid
down in the code. Holes for fixing lugs are to be left or cut out, and the
door/window fixed after all the rough masonry and plasterworks have
been finalised. The MS lugs shall be jammed in cement concrete (M-
15) grade in proper position, line and level.
The width of the clear unfinished opening in the wall should be about
25mm. More than the overall width of the frame to facilitate erection.
The height of unfinished opening shall depend on whether threshold is
required or not.
FITTINGS
2. MS ROLLING SHUTTER
PAYMENT:
The glazing shall be 5.5 mm th. toughened glass fixed with necessary
gaskets and aluminium beading at the strip. The door shall be provided
with one security lock. The shutters shall be provided with anodised
aluminium door handles. The average thickness of anodic coating shall
not be less than 15 microns (IS:1948).
PAYMENT
Payment shall be made on sq.m basis of finished work. The rate shall
include providing all necessary materials, fittings, fixtures fixing in
position, breaking concrete or brick masonry walls to receive frames
and hinges etc. and making good the same.