Professional Documents
Culture Documents
SCHEDULES OF CONCRETE
PART 1 – GENERAL
The WORK includes furnishing all labor, materials, equipment and incidentals necessary for
the construction of all concrete work.
1.3 REFERENCE
Except as otherwise indicated, the current editions of the following Standards apply to the
WORK of this Section:
1.4 SUBMITTALS
The Contractor is responsible for the performance of all tests and inspection required
by this Standard Specification. However, the owner reserves the right to perform any
or all prescribed tests and inspection where such is deemed necessary to ensure
that delivered materials conform to the specifications, and shall be paid for by the
Contractor. The Contractor shall furnish the owner certified copies of records
showing that each material has been pre-tested, and complied with all applicable
requirements of this Standard. The Contractor shall, at his own expense, replace all
rejected materials for failure to comply with this Specification.
PART 2 – PRODUCTS
2.1 MATERIALS
A. Cement:
B. Aggregates
C. Admixture
3. The total air entrained measured at the discharge from the truck
shall be 3.0 per cent maximum for finished slabs and 3.5 to 5.0
per cent for all other concrete.
2.2 QUALITY OF CONCRETE
A. Before placing any concrete, the Contractor shall discuss with the Engineer the
source of materials and concrete he proposes to use. Samples of aggregate and
cement shall be furnished to the Engineer for testing.
PART 3 – EXECUTION
A. All debris, dirt and water shall be removed from the forms. Forms,
reinforcement steel, pipes, conduits, sleeves, anchors and other
embedded items shall be inspected an approved by the Engineer before
placing any concrete. The Contractor shall advise the Engineer of his
readiness to proceed at least 12 hours before each placement of
concrete.
END OF SECTION 03 06 00
SECTION 03 21 00
REINFORCEMENT BARS
PART 1 – GENERAL
1.3 SUBMITTALS
The Contractor is responsible for the performance of all tests and inspection
required by this Standard Specification. However, the owner reserves the right to
perform any or all prescribed tests and inspection where such is deemed
necessary to ensure that delivered materials conform to the specifications, and
shall be paid for by the Contractor. The Contractor shall furnish the owner
certified copies of records showing that each material has been pre-tested, and
complied with all applicable requirements of this Standard. The Contractor shall,
at his own expense, replace all rejected materials for failure to comply with this
Specification.
PART 2 – PRODUCTS
2.1 MATERIALS
2. Reinforcement steel shall bear a mill identification symbol, shall be tagged with
the size and mark number so that different types may be identified, and shall be
stored off the ground to protect the steel from moisture and dirt until placed in
final position.
3. Steel wire for tying reinforcing bars and water stops shall conform to ASTM
A82. Should the Contractor wish to use reinforcing steel bars having areas
different from those shown (with consequent different designations), the following
requirements shall apply:
b. Approval by the Engineer of bar size substitutions does not relieve the
Contractor of other specified requirements, including steel grade and bar
deformations.
PART 3 – EXECUTION
All reinforcing bars shall be bent cold around a pin with a free revolving collar
having a diameter of the bar of not less than the following:
1. Four times for stirrups
2. Six times for bars up to and including 25mm diameter
3. Eight times for bars over 25mm diameter
4. Ten times for bars 43mm and 57mm diameter
Reinforcement steel shall not be straightened nor rebent. Bars with kinks or bends
not shown on the Drawings will not be accepted.
All reinforcing bars shall be accurately placed as shown on the Drawings, and in
accordance with the shop drawings and bar schedules. The reinforcing bars shall be
secured against displacement with annealed iron wire ties of minimum GA#16 GI
Wire (i.e. 1.39mm diameter) or suitable clips at the intersections.
END OF SECTION 03 21 00
SECTION 03 31 00
STRUCTURAL CONCRETE
PART 1. GENERAL
A. CONTRACTOR shall furnish all labor, tools, and equipment for the
construction of reinforced cast-in-place concrete.
B. This section includes basic finishing and curing methods, accessory control,
and expansion and contraction joint devices.
1.3 REFERENCES
1.4 SUBMITTALS
2. Fly ash.
5. Bonding agents.
6. Grout.
B. Cement
1. Cement in bags shall be stored in a suitable weatherproof structure which
shall be as air-tight as practicable; floors shall be elevated above the
ground a distance sufficient to prevent the absorption of moisture.
2. Bags shall be stacked close together to reduce circulation of air but shall
not be stacked against outside walls; the manner of storage shall permit
easy access for inspection and identification of each shipment.
3. Bulk cement shall be transferred to elevated airtight and weatherproof
bins. At the time of use, all cement shall be free-flowing and free of
lumps.
4. Cement that has been in storage longer than 6 months will be tested by
standard mortar tests or other tests as deemed necessary by the Owner's
Representative to determine its suitability for use and such cement shall
not be used without approval of the Owner's Representative.
C. Aggregates
D. Reinforcement
PART 2. PRODUCTS
2.1 MATERIALS
A. General: Acquire cement and aggregate from the same source for all
work.
C. Aggregate:
1. Fine Aggregate: Fine aggregate shall consist of hard, strong, durable
particles complying with the provisions of ASTM C33.
D. Water: Water shall be clean and free from injurious amounts of oils, acids,
alkalis, salts, organic materials, or other substances that may be
deleterious to concrete or steel. Mixing water for prestressed,
pretensioned and prestressed post-tensioned concrete or for concrete
which will contain aluminum embedments shall not contain deleterious
amounts of chloride ion.
PART 3. EXECUTION
3.1 PREPARATION
B. CONTRACTOR shall use compressed air from an air compressor to blow out
construction debris and dirt at the bottom of members to be placed such as walls,
beams, and columns, prior to final placement of forms that may obscure any
joint. CONTRACTOR shall demonstrate to ENGINEER that all debris, such as
concrete particles, saw dust, loose tie wire, bar tags, tape, trash and dirt, have
been thoroughly removed.
C. All surfaces of forms and embedded materials that have become encrusted
with dried mortar or grout from concrete previously placed shall be cleaned of all
such mortar or grout before the surrounding or adjacent concrete is placed.
A. Placement shall conform to ACI 301, Chapter 8, ACI 304, ACI 306.1, ACI
305.1, and ACI 309. No concrete shall be placed in water except with the
written permission of ENGINEER. The surfaces of absorptive materials
against or upon which concrete is to be placed shall be moistened
thoroughly so that moisture will not be drawn from the freshly placed
concrete. The concrete shall be placed by equipment that will prevent
segregation or loss of ingredients. The stream of concrete shall not be
allowed to separate by permitting it to fall freely over rods, spacers or
other embedded materials.
E. All pipes shall be kept clean and free from coatings of hardened concrete.
END OF SECTION 03 31 00
SECTION 03 39 00
CONCRETE CURING
PART 1 ‐ GENERAL
1.3 REFERENCES
1.3 SUBMITTALS
A. Perform Work in accordance with ACI 301, ACI 302, ACI 308, ASTM C171,
ASTM C309.
1.7 COORDINATION
PART 2 ‐ PRODUCTS
2.1 MATERIALS
PART 3 ‐ EXECUTION
3.1 EXAMINATION
A. Protect freshly placed concrete from premature drying and excessive cold or
hot temperatures. In hot weather, provide windbreaks or fog spray to control
early concrete cracking.
B. Start initial curing as soon as free water has disappeared from concrete
surface after placing and finishing. Keep continuously moist for not less than 7
days.
C. Begin final curing procedures immediately following initial curing and before
concrete has dried. Continue final curing for at least 7 days in accordance with
ACI 308. Avoid rapid drying at end of final curing period.
3.3 CURING METHODS
\
3.4 CURING HORIZONTAL SURFACES
A. Protect finished Work from damage by using barriers, scaffolds, covers, work
directives, etc.
END OF SECTION 03 39 00
SECTION 03 47 00
PART 1 – GENERAL
C. The Project Architect/Engineer has not been retained to design the wall panels or
the floor slab to resist the stresses caused by erection of the wall panels, nor to
determine the means and methods to be used for erection and bracing until
permanent bracing is in place.
D. It shall be the Contractor’s responsibility to erect the panel in a manner that will
be both safe for personnel and property, and to brace and otherwise protect the
panels against wind and other forces that may occur during construction and until
connections to the permanent structural system are completed.
E. It shall be the Contractor’s responsibility to ensure that a suitable slab has been
prepared to provide for the level of finish that has been established within this
specification.
B. Section 07920 – Sealants and Caulking: Fire-resistant Blanket and Sealant Materials.
1.3 REFERENCES
1.4 SUBMITTALS
B. Shop Drawings: Submit Panel Shop Drawings and Erection Drawings detailing all
work of this section, including temporary bracing. Reinforcing bars shown on the
project drawings do not allow for lifting and erection stresses.
D. Material Submittals:
1.6 TOLERANCES
A. Dimensions of the finished panels, at the time of erection in the structure, shall
conform to the casting tolerances stated below, unless otherwise specified or
approved by the Project Architect/Engineer.
B. Dimensions of the erected panels shall conform to the erection tolerances stated
below unless otherwise specified or approved by the Project Architect/Engineer.
3. Joint Taper
5. Panel Alignment
A. Job Conditions: The provisions of this section are supplemental to the scope of
ACI 305 and 306.
C. For cold weather conditions, adequate equipment shall be provided for heating
concrete materials and protecting concrete during freezing or near-freezing
weather. Concrete materials and reinforcing steel, forms, fillers and ground with
which concrete is to come in contact shall be free from frost. If shelters are used,
the type of fuel used for heating shall not weaken the concrete surface. Frozen
materials or materials containing ice shall not be used. Also refer to ACI 306 -
Specification for Cold Weather Concreting.
D. For hot weather conditions, proper attention shall be given to concrete materials,
production methods, handling, placing, protection, and curing to prevent
excessive concrete temperatures or water evaporation that may increase
shrinkage and impair required strength or serviceability of the member or
structure. Also refer to ACI 305 - Specification for Hot Weather Concreting.
PART 2 – PRODUCTS
A. Lifting hardware, inserts, braces and related embedded and attached items
shall be manufactured specifically for site-cast Tilt-Up construction.
A. Forms:
B. Reveal Materials: All material used for creating reveals or relief in the
exterior face of the panel must be of adequate strength to withstand
construction traffic/loads without damage.
C. Concrete Materials:
4. Mixing water shall be free of any acid, alkali, oil or organic material
that may interfere with the setting of the cement.
D. Quality of Concrete
H. Fibers:
I. Miscellaneous Metals:
3. Concrete Curing of Casting Beds: All concrete in and around those areas
to be used for casting shall be cured after finishing, as soon as the free
water on the surface has disappeared and no water sheen is visible, but
not so late that the liquid curing compound will be absorbed into the
concrete. The cure and/or bond-breaking compound should be applied at
the manufacturer’s recommended coverage to achieve minimum moisture
loss.
2. Product must comply with AASHTO Specification M-171 for reflection and
moisture retention.
5. The bond breaker used must be compatible with any coating specified for
interior or exterior concrete panels and slab.
PART 3 – EXECUTION
3.1 GENERAL
A. Coordinate site-cast Tilt-Up operations with Work of other trades in order that
Work may be expedited and omissions and delays avoided.
D. After placing reinforcing steel for panels, check casting slab surfaces for
continuity of film. Touch up or recoat worn or damaged areas, taking care to
prevent application of coating on reinforcing steel and inserts.
F. Where reveals are specified in panels, ensure that forming strips are straight and
securely fastened to prevent movement or floating during placing operations and
that alignment between adjacent panels is correct. Reveal tolerances shall
comply with the provisions of Section 3.7 of this document.
A. The Contractor shall lay out the panels for casting in a manner that minimizes the
locations of floor joints, column isolation joints and other construction joints in the
panel faces. The Contractor shall prevent the layout of the panels over
temporarily poured casting surfaces such as pre-formed columns and pits unless
deemed absolutely necessary.
B. Forms shall be designed to maintain the perimeter of the panel as shown on the
project drawings within 1/4” maximum deflection during pouring.
C. All formed blockouts for openings in the panels shall be designed to limit the
deflection during pouring to a maximum of 1/8”.
A. Protect freshly placed concrete from premature drying and excessive cold or hot
temperatures, and maintain without drying at a relatively constant temperature for
the period of time necessary for hydration of the cement and proper hardening of
the concrete.
A. Design panels for erection stresses. Selection of lifting system and hardware
shall be by the Contractor.
C. It is recommended that the Contractor take extra test specimens and field cure to
verify concrete strength of panels.
D. Before starting erection operations, Contractor shall check relevant job site
conditions to ensure they are ready for the erection of panels. Each element shall
be properly marked to correspond with the designation indicated on the approved
Shop Drawings.
H. Set panels in the position assigned. Place panels evenly on prepared setting
pads or proper capacity shims. Grout space under panels for full bearing or
provide additional support until grouting takes place.
I. Panels not attached to the building frame at the time of erection shall be braced
in position using a bracing system designed to resist wind and other loads that
may reasonably be determined until all structural connections have been made.
There shall be a minimum of two braces per panel. Design of bracing shall be the
responsibility of the Contractor. Panel bracing connection shall be maintained
daily by Contractor to assure tightness.
J. After panels are erected, Contractor shall check all connecting bolts at the floor
and panels daily to ensure tightness.
K. Dry-pack grout installation and preparation for weld pockets and other panel
blockouts not cast in during pouring shall be performed as follows:
6. Remove free water from concrete and bolt holes immediately before
grouting.
N. After the panels are erected, dismantle panel erection devices and patch panels
as required for a uniform appearance.
O. After panels are erected, patch holes or other blemishes in casting slab that were
caused by the panel casting and erection processes in a manner acceptable to
the Project Architect/Engineer.
A. The Contractor shall consult with the Project Architect/Engineer and the Owner
prior to initiating the project to determine the expectations for the project
appearance.
a. All panel surfaces will be free of all voids, holes, pockets and
other surface deformations greater than 1/8”.
b. Surfaces of panels must not project reinforcing patterns, floor
joints or other projections or voids from the casting surface.
a. All panel surfaces will be free of all voids, holes, pockets and
other surface deformations greater than 1/4”.
D. Install back-up rod, primer, paint and sealant in accordance with Section 07920 –
Sealants and Caulking.
A. Testing:
1. Take not less than four cylinders and four beams for each class of
concrete, for each 150 cu. yd. (114.7 cu. m.) or fraction thereof, for each
day concrete is cast, or not less than once for each 5,000 sq. ft. (464.5
sq. m.) of panel area. The specimens shall be field cured.
2. Of each set of four beams, at least two shall be tested prior to panel
erection. The average of the two beam results shall be the tested flexural
strength. Ensure that the specified flexural strength has been met. The
other beams shall be kept in reserve if additional testing is needed.
4. Of each set of four cylinders, two shall be tested at 7 days and two at 28
days.
5. Casting and curing of test cylinders shall be in accordance with ASTM
C31.
6. Test cylinders and test reports shall accurately indicate in which panel, by
number and concrete delivery tag, the concrete represented by each test
cylinder was placed.
1. In the event that concrete tests indicate a 7-day or 28-day strength below
that which was specified, the Contractor, with the agreement of the
Project Architect/ Engineer, shall have the mix adjusted so that
subsequent concrete will comply with the minimum strength
requirements. The owner may require core specimens to be taken and
tested, at the Contractor’s expense. If core tests fall below minimum
requirements, as determined by the Project Architect/Engineer, the
concrete in place will be deemed to be defective. This concrete shall be
removed and replaced or strengthened in a manner acceptable to the
Owner and Project Architect/Engineer, at the Contractor’s expense. Any
demolition or repair of other materials or systems as a result of repair or
replacement of defective concrete shall be at the Contractor’s expense.
A. Panel damage that occurs during erection, cracks readily visible per the
requirements specified in Section 03470.3.6.2, permanent bowing occurring from
erection, and spalls, shall be repaired or replaced to the satisfaction of the
Project Architect/Engineer, appropriate to the type and location on the building.
3.11 CLEANING
A. When Work of a Section has been completed, remove trash, debris, surplus
materials, tools, and equipment from site.
3.12 PROTECTION
A. During the period after this Work has been completed, the General Contractor
shall protect finished site-cast Tilt-Up concrete surfaces from damage by
subsequent construction operations.
END OF SECTION 03 47 00
SECTION 07 92 00
JOINT SEALANTS
PART 1-GENERAL
1.1 SCOPE
The publications listed below form a part of this specification to the extent
referenced.
1.3 SUBMITTALS
Submit certificates from the manufacturers attesting that materials meet the
specified requirements.
Clearly mark data to identify material type provided. Submit complete descriptive
data for:
a. Sealants
Data for sealant and caulking shall include application instructions and
precautions, self-life, mixing instructions for multi-component sealants
and recommended cleaning solvent. Silicone sealant should not be used i
n all the buildings.
b. Primers
c. Backstop Materials
1.3.3 COLORS
Submit one sample of each color for each sealant type to verify that
products match the colors indicated. Where colors are not indicated,
submit not less than 3 different samples of manufacturer's standard
colors.
Before sealant work is started, provide a sample of each type of finished joint
where directed. Sample shall show the workmanship, bond, and color of sealant.
The workmanship, bond, and color of sealant work throughout the project shall
match the approved sample joints.
The ambient temperature shall be within the limits of 40 and 100 degrees F when
the sealant is applied.
2.1 MATERIALS
Products shall conform to the reference documents listed for each use. Provide
sealant that has been tested and found suitable f or the substrates to which i t will
be applied.
For joints in vertical surfaces, provide ASTM C 920, Type S or M, Grade NS,
Class 25, Use NT. For joints in horizontal surfaces, provide ASTM C 920, Type S
or M, Grade P, Class 25, Use T.
LOCATION COLOR
Provide the type and consistency recommended by the sealant manufacturer for
the particular application.
2.5 BACKSTOPS
Surfaces shall be clean, dry to the touch, and free from dirt, frost, moisture,
grease, oil, wax, lacquer, paint, or other foreign matter that would tend to destroy
or impair adhesion. When resealing an existing joint, remove existing caulk or
sealant prior to applying new sealant.
3.2 PRIMER
Immediately prior to application of the sealant, clean out all loose particles from
joints. Where recommended by sealant manufacturer, apply primer to joints in
concrete masonry units, wood, and other porous surfaces in accordance with
sealant manufacturer's instructions. Do not apply primer to exposed finish
surfaces.
3.4 SEALANTS
Provide a sealant compatible with the materials to which it is applied. Do not use
a sealant that has exceeded shelf life or has become too jelled to be discharge in
a continuous flow from the gun. Apply the sealant in accordance with the
manufacturer's instructions with a gun having a nozzle that fits the joint width.
Force sealant into joints to fill the joints solidly without air pockets. Tool sealant
after application to ensure adhesion. Sealant shall be uniformly smooth and free
of wrinkles. Upon completion of sealant application, roughen partially filled or
unfilled joint, apply sealant, and tool smooth a s specified.
3.4.1 PROTECTION
Protect areas adjacent to joints from sealant smears. Masking tape may
be used for this purpose if remove 5 to 1 0 minutes after the joint is filled.
Sealant and Caulking s hall not be measured and p aid f or separately, but the
cost thereof s hall be considered as included i n the contract unit price of the
Items where called for.
PART 1 ‐ GENERAL
1.2 REFERENCES
(v) Crane hooks with deformations or cracks. For hooks with cracks or having
more than 15 percent in excess of normal throat opening or more than 10° twist
from the plane of the unbent hook.
PART 2 – PRODUCTS
PART 3 – EXECUTION
A. Verify sufficient hook coverage for each application to ensure each system is capable of
lifting all loads intended.
END OF SECTION 41 22 00