Professional Documents
Culture Documents
SECTION 03 05 00
PART 1- GENERAL
1.3 REFERENCE
1.4 SUBMITTALS
PART 2- PRODUCT
2.1 MANUFACTURERS
A. Performance Requirements:
1. Hydraulic Conductivity: Project specific maximum of 6.0 E-8 cm/s per
ASTM D 5084.
2. Toxicity: None.
3. Odor: None.
4. Flammability: None.
5. Volatile Organic Compound (VOC) Content: 0 grams per liter.
6. Freeze Temperature: 32 degrees F (0 degrees C).
7. pH: 11.3.
PART 3- EXECUTION
3.1 EXAMINATION
A. Do not begin installation until substrates have been properly constructed and
prepared.
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
3.2 INSTALLATION
C. Install, protect and repair sheet vapor retarder in accordance with to ASTM
E1643, ASTM F710, ACI 302.2R-06, and manufacturer's instructions.
D. Protect freshly placed concrete from premature drying and excessive cold or
hot temperatures. Comply with ACI 306R-10 for cold-weather protection and ACI
305R-10 for hot-weather protection during curing.
E. Curing.
B. Project team: Upon request, provide batch tickets indicating presence and
dosage of MVRA in mix.
END OF SECTION 03 05 00
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
SECTION 03 06 00
SCHEDULES OF CONCRETE
PART 1 – GENERAL
The WORK includes furnishing all labor, materials, equipment and incidentals necessary for
the construction of all concrete work.
1.3 REFERENCE
Except as otherwise indicated, the current editions of the following Standards apply to the
WORK of this Section:
1.4 SUBMITTALS
The Contractor is responsible for the performance of all tests and inspection required
by this Standard Specification. However, the owner reserves the right to perform any
or all prescribed tests and inspection where such is deemed necessary to ensure
that delivered materials conform to the specifications, and shall be paid for by the
Contractor. The Contractor shall furnish the owner certified copies of records
showing that each material has been pre-tested, and complied with all applicable
requirements of this Standard. The Contractor shall, at his own expense, replace all
rejected materials for failure to comply with this Specification.
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
PART 2 – PRODUCTS
2.1 MATERIALS
A. Cement: Cement shall be Portland Cement conforming to ASTM C150, Type II, as
follows:
Table 1- Physical Requirements of Cement
Test Requirement
Compressive Strength for ages indicated, min.
3 days 12.0 MPa
7 days 19.0 MPa
Time Setting by Vicat Method
Initial Set, minimum 45 minutes
Final Set, maximum 375 minutes
Fineness, by turbidimeter test, minimum 160 m²/kg
B. Aggregates
C. Admixture
3. The total air entrained measured at the discharge from the truck shall be 3.0
per cent maximum for finished slabs and 3.5 to 5.0 per cent for all other concrete.
A. Before placing any concrete, the Contractor shall discuss with the Engineer the source of
materials and concrete he proposes to use. Samples of aggregate and cement shall be
furnished to the Engineer for testing.
PART 3 – EXECUTION
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
A. All debris, dirt and water shall be removed from the forms. Forms, reinforcement
steel, pipes, conduits, sleeves, anchors and other embedded items shall be
inspected an approved by the Engineer before placing any concrete. The Contractor
shall advise the Engineer of his readiness to proceed at least 12 hours before each
placement of concrete.
B. Concrete shall be uniformly placed during the process of depositing until the
completion of the layer to maintain an approximately horizontal plastic surface. The
rate of placing concrete in forms shall not exceed o.60 meter of vertical rise not be
permitted.
C. Concrete shall not be placed in water or stay submerged within 24 hours after
placing except for curing nor shall running water be permitted to flow over concrete
surfaces within four days after the placing of concrete.
END OF SECTION 03 06 00
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
SECTION 03 11 00
CONCRETE FORMING
PART 1 GENERAL
A. CONTRACTOR shall supply all labor, tools, equipment and materials to set
forms for the proper placement of concrete for structures. It is CONTRACTOR’s
responsibility to design and build adequate forms and to leave them in place until
the forms can be safely removed. CONTRACTOR is responsible for damage and
injury caused by removing forms carelessly or before the concrete has gained
sufficient strength. Means and methods of repair shall be reviewed by
ENGINEER prior to performing the WORK.
1.03 REFERENCES
1.04 SUBMITTALS
A. General:
1. Design, placement and maintenance of formwork and form systems is
the responsibility of CONTRACTOR. Submittals other than those listed
are not required nor will they be reviewed.
2. Alternate form system configurations require preparation by a licensed
Professional Engineer and submittal to ENGINEER for review and
approval.
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
PART 2 PRODUCTS
2.01 GENERAL
A. Walls:
1. APA PS 1-07, B-B Plyform Class I, exterior. The plywood shall be mill
oiled and edge sealed.
2. Symons hand set steel-ply forms, or equal.
C. Grade Slabs:
1. APA PS 1-07, B-B Plyform Class I, exterior. The plywood shall be mill
oiled and edge sealed.
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
D. Columns:
PART 3 EXECUTION
3.01 GENERAL
A. Forms shall be used, wherever necessary, to confine the concrete and shape
it to the specified lines and grades as shown on the DRAWINGS.
CONTRACTOR shall set and maintain concrete forms so as to ensure completed
WORK is within all applicable tolerance limits. If a type of form does not, in the
opinion of ENGINEER, consistently perform in an acceptable manner, the type of
form shall be changed and the method of erection shall be modified by
CONTRACTOR, subject to the review of ENGINEER.
B. Forms shall have sufficient strength to withstand the pressure resulting from
placement and vibration of concrete, and shall be maintained rigidly in position.
The design of formwork and placing rate of concrete with medium and high-range
water reducing agents shall be adjusted to compensate for the greater hydraulic
pressures exerted on the forms by concrete of high fluidity.
C. Forms shall be clean and free from mortar and other foreign material from
previous use prior to being placed.
A. Prior to placing reinforcing steel, coat the forms with a non-staining release
agent that will effectively prevent the absorption of moisture and prevent bond of
the concrete to the form. Contact with hardened concrete against which fresh
concrete is to be placed is prohibited. All bond breaking materials or processes
shall be used only after acceptance by ENGINEER. Care shall be taken in
applying form oil to avoid contact with reinforcement steel. Embedded material
which becomes coated with form oil shall be thoroughly cleaned or replaced at
the expense of CONTRACTOR.
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
3.03 TOLERANCES
Column Footings:
a. Lateral Alignment: Variation less than or equal to 50 mm.
b. Level Alignment: Variation from specified elevation more than
10 mm, less than 50 mm.
c. Relative Alignment: Variation less than or equal to 25 mm in
300 mm (variation between specified plane and as built surface).
.
b. Lateral Alignment:
1) Maximum in Any Bay: Variation less than or equal to 12
mm
2) Maximum in Any 6 meter: Variation less than or equal to
12 mm.
3) Maximum for Entire Wall Length: Variation less than or
equal to 25 mm.
4) Floor and Wall Opening Locations: Variation less than or
equal to 12 mm.
5) Saw cuts and Joints: Variation less than or equal to 20
mm
c. Level Alignment:
1) Top Elevation of Slabs: Variation less than or equal to
20 mm.
2) Lintels, Other Lines Exposed to View: Variation less
than or equal to 20 mm.
A. Forms that prohibit visual review of items such as reinforcing steel, and
bearing pads by ENGINEER, shall not be placed until ENGINEER has performed
a final review of the reinforcing steel.
B. CONTRACTOR shall use compressed air from an air compressor to blow out
construction debris and dirt at the bottom of sections or members to be placed
such as wall, slabs, beams and columns, prior to placing forms or concrete.
A. The forms for any portion of a structure shall not be removed until the
concrete has reach sufficient strength with a factor of safety of 2.0, to
withstand applied loads such as self-weight and wind loads or withstand
damage when the forms are removed.
B. For post-tensioned concrete slabs and beams, formwork shall not be removed
until the entire slab or member has been stressed and stressing records
accepted.
SECTION 03 15 00
CONCRETE ACCESSORIES
PART 1 - GENERAL
1.04 REFERENCES
1. ASTM C272 Test Method for Water Absorption of Core Materials for
Structural Sandwich Constructions
1.05 SUBMITTALS
B. Shop Drawings: Submit drawings showing locations of all joints to be filled and
sealed.
D. Samples: Submit 300 mm long sample of joint filler and elastomeric joint seals
and one pint can of sealing compound.
PART 2 - PRODUCTS
2.01 MATERIALS
PART 3 - EXECUTION
3.01 EXAMINATION
A. Verify that joint surfaces are dry to the extent necessary for successful
sealant application and long service life as recommended by the sealant
manufacturer.
B. Verify also that ambient and concrete-surface temperatures and humidity are
within the ranges recommended by the manufacturer for successful sealant
application.
3.02 PREPARATION
3.03 INSTALLATION
B. Plastic Pads, Spacers, and Fillers: Install as indicated over or against clean
surfaces. Apply adhesive where required to hold material in place.
END OF SECTION 03 15 00
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
SECTION 03 21 00
REINFORCEMENT BARS
PART 1 – GENERAL
1.3 SUBMITTALS
The Contractor is responsible for the performance of all tests and inspection
required by this Standard Specification. However, the owner reserves the right to
perform any or all prescribed tests and inspection where such is deemed
necessary to ensure that delivered materials conform to the specifications, and
shall be paid for by the Contractor. The Contractor shall furnish the owner
certified copies of records showing that each material has been pre-tested, and
complied with all applicable requirements of this Standard. The Contractor shall,
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
at his own expense, replace all rejected materials for failure to comply with this
Specification.
PART 2 – PRODUCTS
2.1 MATERIALS
2. Reinforcement steel shall bear a mill identification symbol, shall be tagged with
the size and mark number so that different types may be identified, and shall be
stored off the ground to protect the steel from moisture and dirt until placed in
final position.
3. Steel wire for tying reinforcing bars and water stops shall conform to ASTM
A82. Should the Contractor wish to use reinforcing steel bars having areas
different from those shown (with consequent different designations), the following
requirements shall apply:
b. Approval by the Engineer of bar size substitutions does not relieve the
Contractor of other specified requirements, including steel grade and bar
deformations.
PART 3 – EXECUTION
All reinforcing bars shall be bent cold around a pin with a free revolving collar
having a diameter of the bar of not less than the following:
1. Four times for stirrups
2. Six times for bars up to and including 25mm diameter
3. Eight times for bars over 25mm diameter
4. Ten times for bars 43mm and 57mm diameter
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
Reinforcement steel shall not be straightened nor rebent. Bars with kinks or bends
not shown on the Drawings will not be accepted.
All reinforcing bars shall be accurately placed as shown on the Drawings, and in
accordance with the shop drawings and bar schedules. The reinforcing bars shall be
secured against displacement with annealed iron wire ties of minimum GA#16 GI
Wire (i.e. 1.39mm diameter) or suitable clips at the intersections.
END OF SECTION 03 21 00
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
SECTION 03 31 00
STRUCTURAL CONCRETE
PART 1 GENERAL
A. CONTRACTOR shall furnish all labor, tools, and equipment for the
construction of reinforced cast-in-place concrete.
B. This section includes basic finishing and curing methods, accessory control,
and expansion and contraction joint devices.
1.3 REFERENCES
1.4 SUBMITTALS
2. Fly ash.
5. Bonding agents.
6. Grout.
A. The ready-mixed concrete truck driver shall provide the batch ticket to
ENGINEER at the time of concrete delivery. The ticket shall summarize the
following information legibly in an easily discernible table:
5. Time of batching.
7. Gallons of water that may be added at the site without exceeding the
permissible W/C ratio.
PART 2 PRODUCTS
2.1 MATERIALS
A. General: Acquire cement and aggregate from the same source for all work.
B. Cement: Cement shall be Portland cement Type II, unless otherwise indicated
on the DRAWINGS.
C. Aggregate:
D. Water: Water shall be clean and free from injurious amounts of oils, acids,
alkalis, salts, organic materials, or other substances that may be deleterious to
concrete or steel. Mixing water for prestressed, pretensioned and prestressed
post-tensioned concrete or for concrete which will contain aluminum
embedments shall not contain deleterious amounts of chloride ion.
PART 3 EXECUTION
3.1 PREPARATION
B. CONTRACTOR shall use compressed air from an air compressor to blow out
construction debris and dirt at the bottom of members to be placed such as walls,
beams, and columns, prior to final placement of forms that may obscure any
joint. CONTRACTOR shall demonstrate to ENGINEER that all debris, such as
concrete particles, saw dust, loose tie wire, bar tags, tape, trash and dirt, have
been thoroughly removed.
C. All surfaces of forms and embedded materials that have become encrusted
with dried mortar or grout from concrete previously placed shall be cleaned of all
such mortar or grout before the surrounding or adjacent concrete is placed.
3.2 PLACEMENT
A. Placement shall conform to ACI 301, Chapter 8, ACI 304, ACI 306.1, ACI
305.1, and ACI 309. No concrete shall be placed in water except with the written
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
E. All pipes shall be kept clean and free from coatings of hardened concrete.
END OF SECTION 03 31 00
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
SECTION 03 39 00
CONCRETE CURING
PART 1 ‐ GENERAL
1.3 REFERENCES
A. ACI 301 – Structural Concrete for Buildings.
B. ACI 302 – Recommended Practice for Concrete Floor and Slab Construction.
C. ACI 308 – Standard Practice for Curing Concrete.
D. ASTM C171 – Sheet Materials for Curing Concrete
E. ASTM C309 – Liquid Membrane‐Forming Compounds for Curing Concrete
1.4 SUBMITTALS
A. Product Data: Provide data on curing compounds, product characteristics,
compatibility and limitations.
B. Shop Drawings and Product Data: Submit under the provisions of Section 01
33 00.
1.7 COORDINATION
A. Coordinate work under provisions of Section 01 31 00.
PART 2 ‐ PRODUCTS
2.1 MATERIALS
PART 3 ‐ EXECUTION
3.1 EXAMINATION
A. Protect freshly placed concrete from premature drying and excessive cold or
hot temperatures. In hot weather, provide windbreaks or fog spray to control
early concrete cracking.
B. Start initial curing as soon as free water has disappeared from concrete
surface after placing and finishing. Keep continuously moist for not less than 7
days.
C. Begin final curing procedures immediately following initial curing and before
concrete has dried. Continue final curing for at least 7 days in accordance with
ACI 308. Avoid rapid drying at end of final curing period.
A. Protect finished Work from damage by using barriers, scaffolds, covers, work
directives, etc.
END OF SECTION 03 39 00
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
SECTION 03 47 00
PART 1- GENERAL
A. Work Included: Provide labor, materials and equipment necessary to complete the
work of this Section, including but not limited to the following.
B. Site-cast tilt-up insulated sandwich concrete panels. Related Work: The following
items are not included in this Section and are specified under the designated
Sections:
1.2 SUBMITTALS
B. Shop Drawings: Submit panel shop drawings and erection drawings detailing the
Work of this Section including temporary bracing. Reinforcing bars shown on the
project drawings are not checked for lifting and erection stresses. Shop drawings
shall be reviewed by a licensed design professional Include the following:
1. Product Data: For each product, including bond breakers, joint sealants,
insulation, connection devices.
F. Job Mock-up Panel for Architectural Finishes: Prepare one panel using forming
technique and construction methods to be used on the project for each level of
finish shown on the drawings according to the following:
3. For abraded or exposed colored concrete finishes: Utilize full range size
and colors in aggregate. Utilize full range of color in grout. Match the
degree of abrasion (e.g. sand-blast, water-blast, retarder, acid etch, etc.)
specified.
5. For cast-in-brick or stone finishes: Utilize full range of color sampling for
brick specified. Sample shall consist of one repaired brick in field of
display.
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
6. Cast mock-up over slab joint or column joint if actual panels will be
affected by these conditions.
1.5 COORDINATION
A. Coordinate site cast tilt-up operations with Work of other trades in order that Work
may be expedited and omissions and delays avoided.
PART 2-PRODUCTS
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
A. Forms:
2. Panel boundary forms shall be rigidly constructed and well braced steel or
wood forms, straight and with precise corners. Design to withstand
stresses resulting from the casting process. Consideration should be
given to exposed formed surfaces. Forming surfaces shall be smooth
and clean prior to pouring of concrete.
5. When panels are stack cast, maintain a continuous sound and smooth
casting to match the finish of the original casting surface.
B. Reveal Materials: Materials used for creating reveals or relief in the exterior face
of the panel shall be of adequate strength to withstand construction traffic/loads
without damage.
C. Concrete Materials:
2. Fine and coarse aggregates shall consist of clean, hard strong, and
durable inert material, free of injurious amounts of deleterious
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
4. Mixing water shall be free of any acid, alkali, oil or organic material that
may interfere with the setting of the cement.
E. Sacking Materials: Portland cement and water, mixed to a uniform creamy paste.
G. Steel Reinforcement:
H. Lifting Hardware: Lifting hardware, inserts, braces, and related embedded and
attached items shall be manufactured specifically for site cast tilt-up construction.
I. Randomly-Mixed Reinforcing Elements (Fibers): The use of materials mixed with the
concrete for reinforcement are commonly applicable for reduction of plastic
shrinkage and thermal expansion/contraction. They shall not be used as flexural
reinforcement in structural panels unless approved by a licensed design professional
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
and reviewed by the Architect. Consult the manufacturer’s literature for proper
material quantities and application procedures.
J. Supports for Steel Reinforcement: Supports may consist of metal, all-plastic and
concrete materials.
2.5 SEALANTS
2.6 BONDBREAKER
2. The bond breaking compound shall be applied with adequate time to dry prior to
placement of reinforcing steel.
3. The bond breaking compound shall dry in 30-minutes or less at 100°F to reduce
panel clean up.
5. The bond breaker used shall be fully removed from the slab surface or shall be
compatible with any curing compound.
PART 3-EXECUTION
1. Casting slab shall be cured. Saw cuts, cracks, joints or defects in the casting bed
shall be filled so as to minimize transfer of the joint line to the panel face.
2. Waste slabs, if used, shall be of sufficient thickness and strength so as not to crack
with the weight of the panels.
4. Isolation pockets shall be formed in such a manner as to minimize the transfer of the
pocket to the finished appearance of the panel.
C. Locate and install all inserts and anchorages required for the panels prior to casting of
any concrete. When approved by the engineer of record, embedded items such as
dowels, inserts or anchorages, that either protrude from the concrete or remain exposed
for inspection, may be installed while the concrete is in a plastic state. This is provided
the item(s) is not required to be hooked or tied to the reinforcement within the concrete
and are maintained in the correct position until the concrete hardens. Such items shall
be properly anchored to ensure full development of the design load. The concrete
surface adjacent to the embedded item shall be properly finished for correct interfacing.
D. After placing steel reinforcement for panels, check casting slab surfaces for continuity of
bondbreaker. If touch-up or recoating of worn, damaged or missing areas is required,
the Contractor shall remove the steel reinforcement entirely prior to re-application of the
bondbreaker unless approved by the Architect.
A. Layout the panels for casting in a manner that minimizes the locations of floor
joints, column isolation joints and other construction joints in the panel faces.
Prevent the layout of the panels over temporarily poured casting surfaces such
as pre-formed columns and pits unless deemed absolutely necessary.
B. Forms shall be designed to maintain the perimeter of the panel as shown on the
project drawings within 6mm maximum deflection during pouring.
C. Formed blockouts for openings in the panels shall be designed to limit the
deflection during pouring to a maximum of 4 mm.
D. Where reveals are specified in panels, assure that forming strips are straight and
securely fastened to prevent movement or floating during placing operations and
that alignment between adjacent panels is correct. Reveal tolerances shall
comply with requirements specified in this Section.
2. Cold joints shall not be permitted in an individual site cast tilt-up panel.
A. Field Testing:
3. Test specimens and test reports shall accurately indicate in which panel,
by number and concrete delivery tag, the concrete represented by each
test specimen was placed.
B. Deficient Compressive Strength: In the event that concrete tests indicate a 7-day
or 28-day strength below that which was specified, the Contractor with the
agreement of the Architect shall have the mix adjusted so that subsequent
concrete will comply with the minimum strength requirements.
1. The Owner may require core specimens to be taken and tested, at the
Contractor’s expense. If core tests fall below minimum requirements, as
determined by the Architect, the concrete in place will be deemed to be
defective.
1. Protect freshly placed concrete from premature drying and excessive cold
or hot temperatures and maintain without drying at a relatively constant
temperature for the period of time necessary for hydration of the cement
and proper hardening of the concrete.
A. Dimensions of the finished panels, prior to erection in the structure, shall conform
to the casting tolerances stated below unless otherwise specified or approved by
the Architect.
C. Deviation from Specified Panel Thickness: Note the tolerance listed is for the
average variation of panel thickness through any cross-section of the panel.
1. Panel surfaces shall be free of voids, holes, pockets and other surface
deformations greater than 1/8 inch.
1. Panel surfaces shall be free of all voids, holes, pockets and other surface
deformations greater than 1/4 inch.
3. Cracks are permissible as naturally resulting from curing. Cracks are not
permissible as caused by erection forces.
4. Surface repairs shall improve the appearance of the panels within the
descriptions above provided they do not result in additional blemishes
that are visible within the distance set.
D. Grade C - Utility: Projects designed for remote areas with little or no public
interaction and/or projects designed specifically for interior use with little or no
emphasis towards the exterior design.
1. Consult with the Architect and the Owner prior to initiating the project to
determine the expectations for the project appearance.
3. Cracked surfaces are permissible provided the cracks are not resulting
from structural weakness or failure and provided they do not present the
potential for failure of the finish over the life of the building.
A. Engineer panels for erection stresses and selection of lifting system and
hardware.
2. It is recommended that the Contractor take extra test specimens and field
cure to verify concrete strength of panels or demonstrate the acceptable
strength through maturity prediction of calibrated mix designs.
B. Set panels in the position assigned. Place panels evenly on prepared setting
pads or proper-capacity shims. Grout space under panels for full bearing or
provide additional support until grouting takes place.
C. Panels not attached to the building frame at the time of erection shall be braced
in position using a bracing system designed to resist wind and other loads that
may reasonably be determined until structural connections have been made.
There shall be a minimum of two braces per panel. Engineering of bracing shall
be the responsibility of the Contractor. Panel bracing connection shall be
maintained daily to assure tightness.
D. Dry-pack grout installation and preparation for weld pockets and other panel
block outs not cast in during pouring shall be performed as follows:
6. Remove free water from concrete and bolt holes immediately before
grouting.
1. Check connecting bolts at the floor and panels daily to ensure tightness.
3. After panels are erected, patch holes or other blemishes in casting slab
that were caused by the panel casting and erection processes in a
manner acceptable to the Architect.
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1
A. Clean the panel joints of contaminants, including form release agents and
concrete laitance. Dust and loose particles shall be blown out or otherwise
cleaned to provide proper bond. Apply sealants in accordance with
manufacturer’s recommendations.
C. Install back-up rod, primer, paint and sealant in accordance with Section 079200
– Sealants and Caulking.
A. Remove trash, debris, surplus materials, tools and equipment from site on a
regular basis.
END OF SECTION 03 47 00
MCL Architects and Design Section 030000
BID SET – March 2021 Concrete
Development Project No. 1