Professional Documents
Culture Documents
CONSTRUCTION]
Management Insider
Page 1 of 7
What is Disruption?
Disruption is loss of productivity, disturbance, hindrance or interruption to a
contractor’s normal working methods, resulting in lower efficiency.
Is Disruption Claimable?
If caused by the Employer, it may give rise to a right to compensation either under the
contract or as a breach of contract.
However, you should know that Disruption to construction work may lead to late
completion of the work, but not necessarily so.
In another meaning, it is possible for work to be disrupted and for the contract still to
finish by the contract completion date. In this situation, the Contractor will not have a
claim for an EOT, but may have a claim for the cost of the reduced efficiency of its
workforce.”
Causes of Disruption:
Some of the common and main causes of productivity loss:
Changes to working methods
Changes to working conditions and sequence
Ex. change in sequence or priority of work making some works more
onerous to perform
Adverse weather
Management characteristics
Project characteristics
Hereunder is an illustration showing example for factors affecting productivity
REGULATORY
CUMBERSOME
CHANGES
LOGISTICS OF PROCEDURES
LATE QC
TOOLS AND
OVERTIME INSPECTIONS
MATERIALS
TOOL
ACCELERATED REPAIR
WORKFORCE SCHEDULE
POOR SITE
ACCESS, LACK OBSERVATION
LACK OF SURVEY INADEQUATE
OF EATING OR AND
COMMUNICATION ALIGNMENT UNCLEAR, CONSUMABLES
TOILET MEASUREMENT
ELEVATION POORLY
FACILITIES MATERIALS,
MARKINGS MARKED TOOLS AND
WALKWAYS EQUIPMENT
LACK OF REMOTE
LARGE PROJECT RESPECT LOCATION ABSENTEEISM SQUAD
SMALL COG
TURNOVER COORDINATION
SYNDROME LATE START, POOR
OUTDATED EARLY SAFETY
PROTESTERS EQUIPMENT FINISH OVER
AT SITE, LOW MORALE CROWDING
PUBLIC NO MOTIVATION
LACK OF UNBLANCED
OPINION ACCIDENTS SQUADS
PRE-
LOW PLANNING SHIFT
TRADESMEN COORDINATION
NEGATIVE
SKILLS
LABOUR
MOBILISATION,
MOBILISATION
INFLUENCES PACING TRAVELLING RE-
MOBILISATION
LACK OF
VISABLE
WORK WAITING OR
ALCOHOL SLOW JURISDICTIONAL
, DRUGS WORK REDUCED IDLE STRIKES DISPUTES
PRODUCTIVITY
UNCLEAR CONTRACT
TECHNICAL COORDINATION
INFORMATION FATIGUE
REWORK TEMPORARY
START, STOP, INSTALLATION
INEFFECTIVE
MOVE AND
WORK RESTART
ADVERSE
WEATHER POOR QUALITY QC HOLD
WORKMANSHIP POINTS
WORK
SEQUENCING
ENGINEERING
POOR LACK OF
ERRORS, POOR
LIGHTING, ENGINEERING
DRAWINGS RESTRICTIVE
VENTILATION INFORMATION
WORK
DAMAGE SCOPE AND PRACTICES
DESIGN
JOINT LACK OF
SLOW DRAWING CHANGES
OCCUPANCY COMMUNICATION
REVISION
CUMBERSOME DISTRIBUTION CONSERVATIVE
PHASE OF
PROCEDURES DESIGN
THE
REGULATORY PROJECT
CHANGES
Page 3 of 7
Proving Disruption
It is not easy at all to prove disruptions especially without very detailed records as this
is your strongest method to prove disruption by keeping good records.
A side form keeping a good records, the contractor has to focus on the Cause by
identify and track through to the effect.
Disruption exists on the Micro level:
It takes place within the working day;
It may come down to lost hours or minutes within a day.
“There is no fixed calculation method. But the same principle applies, it is very much
dependent on the nature of the tasks as well as the data available”
Example:
Step 1: Identify Period of Impeded Performance
Actual Man-hours
= 2520+2150+1985 = 6655
Actual Man-hours
= 1950+2000+1800+1900+1950+1925
= 11,525
Performance Ratio
= 11,525 / 12,380 = 93%
I.e. if un-impeded, Contractor’s resources could have
been this efficient.
Increased Cost
= 1622 man-hours x $70/man-hour as determined
= $113,540
Then the contractor will claim a compensable claim with $113,540
About Us
PHONE +201004974771
Cairo - Egypt