You are on page 1of 6

NOT

IN
A N Y O N E ' S
K Y A R D ?
BAC
BY CARRIE BLACKMORE SMITH ILLUSTRATION BY DANTE TERZIGNI

A new pressurized natural gas pipeline pitted


DUKE ENERGY against HAMILTON COUNTY RESIDENTS
who didn’t want it running under their streets
or near their schools. With construction completed,
the focus now shifts to safe operations.
60
P H OTO G R A P H S BY J O N AT H A N W I L L I S M A R C H 2 0 2 2 C I N C I N N AT I M A G A Z I N E . C O M 6 1
THE

J
PIP E L I N E USTIN AND ANN FELDMAN USED TO LOVE
their home in Reading, until Duke Energy construct-
ed a high-pressure natural gas pipeline under Mar-

T I M E L I N E ket Street in front of it. “The scariest part is that if


that line was cracked and would catch fire and would
explode,” says Justin Feldman, his voice rising, “we
could be incinerated.” The Feldmans’ daughter and
grandchildren also live on the pipeline route, deepening their fears.
FEBRUARY 2016: Duke Energy For nearly six years, the Feldmans fought Duke Energy over
Ohio sends its first letter to Hamilton
County property owners who might be the construction of the C314V Central Corridor Pipeline. Many in
impacted by a new high-pressure Hamilton County did, from local high schoolers to seniors to poli-
natural gas pipeline. ticians. Nearly every community on the route intervened. But the
fight came to an end in September, with a decision by the Supreme
SEPTEMBER 2016: Duke
Energy submits an application to the Court of Ohio to side with the Ohio Power Siting Board and grant
Ohio Power Siting Board (OPSB) for a Duke a certificate to build.
Certificate of Environmental “The decision is a disappointment,” said a statement from city
Compatibility and Need to build C314V
leaders in Blue Ash, who, along with the municipalities of Read-
Central Corridor Pipeline.
ing and Evendale and a grassroots opposition group, argued their
AUGUST 2017: Duke Energy case to the state supreme court. “The City put up a strong fight to
asks the OPSB for additional time to protect the community and its residents.”
examine site-specific matters. Nearly
all communities along the route have
asked to intervene in the upcoming
state hearing, as well as school districts,
including Sycamore; environmental
groups; and business and religious
leaders.

STREET FIGHTERS
ANN AND JUSTIN FELDMAN
PHOTOGRAPHED IN FRONT OF
THEIR HOUSE IN READING ON
JANUARY 31, 2022.

62
PHOTOGRAPH BY DYLAN BAUER
Now it’s done. The final weld of the ap- “THIS WHOLE PROCESS
proximately 13-mile pipeline was made on
December 14, and it now lies a minimum HAS DESTROYED MY FAITH
of four feet underground from the south-
ern border of Butler County through the IN GOVERNMENT,” SAYS
Hamilton County communities of Syca-
more Township, Blue Ash, Sharonville, JUSTIN FELDMAN.
Evendale, Reading, Amberley Village, Golf
Manor, and Cincinnati, ending at Duke’s

G
C350 Norwood Station. LENN ROSEN COULDN’T BELIEVE WHAT HE WAS READING. IT
Safety has always been opponents’ biggest concern. An average was February 2016, and one of Duke’s first pipeline letters
of 11 people die each year in pipeline incidents, according to 10- had arrived at his Blue Ash home on Bleuwing Terrace—one
year tracking by the U.S. Department of Transportation’s Pipeline of hundreds of households to receive the notice. “We are writing
and Hazardous Materials Safety Administration. to inform you of a proposed natural gas pipeline project being de-
Duke plans to have the pipeline operational by early March, signed in order to increase the reliability and dependability of the
with restoration projects along the route wrapping up this spring. natural gas delivery system in the area,” the letter read. “Providing
Company leaders reiterate that they’ve exceeded federal safety re- safe, reliable natural gas is a responsibility we at Duke Energy take
quirements and have the track record to operate the pipeline safely. very seriously. This pipeline will ensure natural gas reliability for
Statistically, now that the pipeline is in the ground, the biggest the next generation in Hamilton County.”
danger may be, well, the rest of us. Rosen began googling 30-inch pipelines, as described in the let-
ter, and soon landed on news articles about explosions, including
one in 2010 in San Bruno, California, that leveled a residential neigh-
borhood, killed eight people, and injured 58. Federal investigators
APRIL 2018: Duke asks the determined the utility company, Pacific Gas and Electric, caused
OPSB to restart the process of approval. the explosion with flawed record-keeping and sloppy maintenance.
APRIL 2019: The OPSB holds a “I realized this was a huge deal,” Rosen says, recalling his initial
three-day hearing on the application. thoughts. He began going door to door to consult his neighbors
and became one of the founding members of the grassroots orga-
NOVEMBER 2019: The OPSB nization Neighbors Opposing Pipeline Extension (NOPE), which
approves the project but throws in a bit
of a curveball, selecting an alternative fought Duke to the Ohio Supreme Court. NOPE’s membership
route, not Duke’s preferred route in its grew into the hundreds, and it organized public forums to rally
application. regional politicians, school and business leaders, academic experts,
environmentalists, and others who opposed the project. It helped
JANUARY 2020: Opponents file
for a rehearing, arguing Duke did not get more than 1,000 letters of opposition filed against Duke’s ap-
perform due diligence in plotting the plication for a Certificate of Environmental Compatibility and
alternative route before the OSPB gave Public Need from state regulators. There are no local votes taken
the green light. The board denies the
on these matters.
appeal.
In general, NOPE believed the pipeline was unnecessary and
SEPTEMBER 2020: Duke files a irresponsible. Many saw the plan as a money-making deal for Duke
199-page amended application, granted and not a benefit to the people it endangered. NOPE worked with
permission to do so by the OPSB.
experts to calculate a “blast zone” to qualify and quantify what
MARCH 2021: The OPSB accepts was at stake, pointing out that all of the proposed pipeline routing
the amended application. Construction options went by schools, churches, work, and business centers.
begins. Blue Ash, Reading, Evendale, and One jogged right by Jewish Hospital and Kenwood Towne Centre.
NOPE appeal the Ohio Power Siting
The route Rosen’s house was on would get dropped early in the
Board’s decision to the Ohio Supreme
Court, which accepts the case but does process, but he and others continued to fight. It wasn’t a “NIMBY”
not require Duke to stop construction. (not in my backyard) issue, but a not-in-anyone’s-yard one, he says.
The Central Corridor Pipeline was constructed to move natural
SEPTEMBER 2021: The Ohio gas to customers in Hamilton County from a northern pipeline in
Supreme Court issues a unanimous
opinion acknowledging the OSPB didn’t Butler County. Duke officials said the company needed to build the
follow its own administrative rules but pipeline, originally estimated to cost $110 million, in order to retire
concurring with the OPSB’s decision to two propane caverns and not risk putting some customers out of
grant a certificate to build.
service. The pipeline must be pressurized to move and balance gas
DECEMBER 2021: Duke through the system, though the amount of pressure necessary was
completes the last weld on the Central always part of the public debate. CONTINUED ON PAGE 86
Corridor Pipeline.
P H OTO G R A P H S BY J O N AT H A N W I L L I S
NOT IN ANYONE’S BACKYARD?
CONTINUED FROM PAGE 63

nity rallied, Duke scaled down the size of says. “Without this kind of pipeline down
the pipeline from 30 inches to 20, pressur- the backbone of the county, we wouldn’t
izing it up to 400 pounds per square inch have been able to do that.”
instead of its initial 600 psi maximum. The Ohio Power Siting Board, too, placed
The company’s then-president of Ohio retiring the 60-year-old propane peaking
and Kentucky, Jim Henning, announced stations—another name for the caverns—
that “based on the 2,900 comments we re- at the top of its reasons for approval. Thelen
ceived, we think we have put forth the best says Duke has operated the stations, which
solution for the community.” are located hundreds of feet underground,
Newman says the Ohio Power Siting about 10 days each year to supplement the
Duke initially estimated the project Board got a slap on the wrist from the state region’s natural gas supply—usually on the
would be completed by 2018, but com- supreme court for not following its own coldest days when natural gas demands are
munity backlash held it up, with a drawn- rules, which perhaps will improve the pro- high. “We would lose 50,000 customers if
out application process that involved the cess for future pipeline applications. He’s we were to lose a propane cavern,” she says.
community clamoring for more public par- talking about the segment of Chief Justice “These are antiquated technology that we
ticipation and an eight-month delay at the Maureen O’Connor’s opinion that agreed need to get off of our system so we aren’t
company’s request. with NOPE, Reading, and Blue Ash. (Even- reliant, frankly, on something we don’t have
After a three-day hearing in Columbus, dale exited the case before the court made a lot of control over.”
the Ohio Power Siting Board granted Duke a its ruling.) She said Duke had not provided If something went wrong with one of the
certificate to build in November 2019. The all of the materials required in the state ap- limestone caverns, it would need to be re-
board included the chair of the Public Utili- plication to prove it had fully investigated tired immediately, Thelen says, which could
ties Commission of Ohio, Sam Randazzo, the route ultimately chosen by the Ohio cause long outages. “I wouldn’t want to be
who stepped down in 2020 after becom- Power Siting Board. “While an agency has the somebody who has to figure out which
ing ensnared in the House Bill 6 bribery a certain amount of discretion in adopting 50,000 customers aren’t going to get gas.”
As for safety measures on the pipeline
itself, Thelen says Duke has gone beyond
THE PIPELINE, SAYS DUKE ENERGY’S SALLY THELEN, IS what’s required, including doubling the
thickness of C314V’s steel walls. The com-
ABOUT “HAVING THE ABILITY TO UPGRADE INFRASTRUCTURE pany X-rayed every weld and will monitor
the pipeline 24/7 with scheduled inspec-
WITHOUT TAKING PEOPLE OUT OF SERVICE.” tions, she says. In its initial application to
the state, the public utility company prom-
ised to keep records for all repairs, inspec-
scandal; FirstEnergy Corp. admitted to giv- rules to carry out the legislative objective, tions, and patrols.
ing him millions of dollars in consulting agencies should not be permitted to ‘pick In addition, Thelen says, Duke installed
fees and bribes. and choose’ which rules they will follow,” remote control shut-off valves every 2.5
NOPE and others responded with a for- her opinion reads. “Failing to be consistent miles along the pipeline and in strategic
mal request for a rehearing, arguing that in the execution of administrative rules af- locations to be able to shut it down more
Duke hadn’t done its due diligence related fects the citizens of our state and does a quickly in case of a leak. The pipeline will
to required details of the pipeline route disservice to our system of government.” be marked as close to the ground as is prac-
OPSB selected—not Duke’s preferred Still, the court decided that Reading, tical, which is standard, but the company
route, but an alternate one. The OPSB said Blue Ash, and NOPE had not proven they also installed warning strips in the dirt
no to a new hearing, and NOPE members were harmed by the state agency’s error above the pipeline so that anyone who
and the communities of Blue Ash, Reading, and concurred with its decision that Duke might dig should hit the warning strip first.
and Evendale appealed that decision to the should be granted a certificate to build. Pipelines are quite safe in the U.S., says
Ohio Supreme Court. The court accepted Michelle Michot Foss, a fellow in energy,
the case but did not put a stay on construc- DUKE’S REASONS FOR NEEDING TO minerals, and materials at Rice Universi-
tion, so Duke kept building. build the Central Corridor haven’t changed ty’s Baker Institute for Public Policy. Be-
In September 2021, the court concurred since the beginning, says Sally Thelen, the ing underground, for one, protects them
with the Ohio Power Siting Board that company’s longtime local spokesperson. “It better than other forms of our energy in-
Duke proved it needed to build the pipeline. has always been about us needing to retire frastructure.
NOPE may have lost the pipeline war in the propane caverns and needing to balance “For the most part, all of our system is
the end, but group member Jared Newman, our supply in our system and to have the state of the art,” Foss says, explaining that
a Blue Ash resident, says the movement ability to upgrade infrastructure without the U.S. began regulating public utilities
prevailed in a few ways. After the commu- having to take people out of service,” she early on and the result was a fairly stan-

8 6 C I N C I N N AT I M A G A Z I N E . C O M M A R C H 2 0 2 2
dardized and regulated industry. If you
look hard at the data, she says, ruptures
or explosions usually occur because of
an outside force like construction or an
earthquake. It’s almost never a failure of
the pipeline itself. “It is always, always
injury to the pipeline, and homeowners
are some of the worst,” says Foss. “That
campaign to Call 811 Before You Dig was
one of the best inventions ever.”

NONE OF THESE STEPS REALLY BRING


any comfort to the Feldmans, who live on
the pipeline route and spent six months
of 2021 dealing with construction noise
and dust. By the pipeline’s mid-Decem-
ber wrap-up, nine months into construc-
tion, 40 complaints had been logged, in-
cluding litter from construction workers
and air quality concerns.
The Feldmans say it wasn’t just the
love for their home that they lost. “This
whole process has destroyed my faith in
government and destroyed my faith in
democracy,” says Justin Feldman.
His community of Reading did fight
all the way to the Ohio Supreme Court,
but in the end Feldman says he feels like
the entire process was rigged. He was a
little guy, powerless to stop any of it. It
drives him nuts, too, that as a Duke cus-
tomer he’ll help pay for the project.
Duke originally estimated the project
would cost $110 million, though Thelen
says the company will have a final figure in
the spring when all work is completed; she
doesn’t yet know how much of the cost
will start showing up on customers’ bills
or when. Duke will submit its total project
costs to the Public Utilities Commission
of Ohio, which will determine what is re-
coverable for company. That amount will
then be spread out over months or years
to customers, Thelen says.
Rosen, from NOPE, says nothing will
convince him that the Hamilton County
outcomes weren’t predetermined despite
the hearings and court consideration.
But both he and Newman say they’d lead
the fight again. “If somebody sent me a
postcard telling me a pipeline was going
through my backyard, I’d do the same
thing again,” says Rosen. “It’s about pro-
tecting yourself and protecting others
around you.”

M A R C H 2 0 2 2 C I N C I N N AT I M A G A Z I N E . C O M 8 7

You might also like