Professional Documents
Culture Documents
EAT 11-024
EXECUTIVE SUMMARY
The economic activity of the Salar de Uyuni does not focus only on tour- Introduction
ism but also on salt production realized by neighboring cities.
The Salar de Uyuni is considered the world's largest salt lake with an
extension of 10,582 km2 located 3,650 meters above the sea.
In the province of Daniel Campos department of Potosí in the southwest
of Bolivia, is one of the largest reserves of lithium, potassium, boron and
magnesium of the world.
Thus, after preliminary studies recently conducted, the Mining Corpora-
tion of Bolivia (GNRE-COMIBOL), responsible for the exploitation of min-
eral resources in the country, has decided to carry out the design and
planning of an industrial plant in the Salar de Uyuni for obtaining high
purity potassium chloride with a product quality of 95 %.
After processing, the brine collected will be used mainly as fertilizer.
Due to the large reserves of the Salar, the Mining Corporation of Bolivia
(GNRE-COMIBOL) raises a consistent industrial scale production by
700,000 t/y.
The natural brine from the Salar will be processed in different process
sections as explained in the following chapters of this document.
For the production of 700,000 t/y, the plant will work over 7,500 hours per
year with two independent lines producing 350,000 t/y each, working 24
hours per day in three shifts.
The remaining time of the year will be used for maintenance of equip-
ment in the plant.
For the design of the Industrial KCl Plant in Bolivia, the Mining Corpora- Project History
tion of Bolivia (GNRE-COMIBOL) published the bidding procedure called:
"FINAL DESIGN ENGINEERING INDUSTRIAL PLANT IN BOLIVIA KCl"
in the year 2011.
ERCOSPLAN has extensive experience backed by over 60 years of con-
tinuous work and good references in the potash and mineral salt indus-
try, has been awarded to make the carry out this project.
The contract between GNRE-COMIBOL and ERCOSPLAN was signed on
July 31, 2012 and on February 18, 2013 the ‘Document Verifying Readi-
ness for Activities’ was approved.
From this time, ERCOSPLAN had a period of 15 days to deliver the Pro-
ject Procedures Manual, which was accepted by the Authority.
The objective of this manual was to define the procedures and relation-
ships of the parts to be applied during the development of the contract.
ERCOSPLAN defined two phases for the project. The first phase called
Basic Engineering and the second phase called Detail Engineering.
The development of the Basic Engineering started with signature of the
‘Document Verifying Readiness for Activities’, in February 2013 and was
completed in July 2013.
During this period, project team members of ERCOSPLAN travelled on
several occasions to La Paz in Bolivia to present the state of the work.
Page 2 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
For the project, ERCOSPLAN has always worked with internationally rec- Nomenclature
ognized standards for rationalization and technical quality assurance
ERCOSPLAN dedicates the chapter 3 of the Detail Engineering report to
the explanation of the nomenclature.
In the preparation of drawings and other project documents it has been
followed the model of the Normative German DIN (German Institute for
Standardization).
Page 3 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
It is very important to note that in this project there are codes indicating
the name of each equipment necessary for the operation of the plant
based on the DIN EN ISO 10628.
Similarly there is another code indicating the name to each control points
in the process. It is governed by the German standard DIN 19227-2 and
this is being extended for both valves as pipes.
All belonging documents are listed in chapter 4 of the Detail Engineering Belonging Documents
report. The Design Base Document prepared at the beginning of the
project by ERCOSPLAN and later confirmed by GNRE-COMIBOL is at-
tached as Appendix A1.
For the mechanical engineering part, Quotations (Appendix Q1 – Q66) of
suppliers for plant equipment are attached as well as cost estimations for
Equipment (Appendix G1 and G1.1), Piping (Appendix G2 and G2.1) and
Valves (Appendix G3 and G3.1) which are necessary for plant operation.
In the Block Flow Diagram, which is indicated as Drawing A01, the single
processing stages from the evaporation ponds to the final product (KCl
with 95 % purity) are schematically shown.
Also included is the Equipment List (Appendix A2 and A2.1), Equipment
Data Sheets (Appendix A3 and A3.1), List of Drawings (Appendix A4), List
of Instruments (Appendix A5 and A5.1), Specification for Mechanical
Equipment (Appendix A6 and A6.1) as well as Pipe List (Appendix A8 and
A8.1), Valve List (Appendix A9 and A9.1) and Pipe Classification (Appen-
dix A10).
The Inquiry Specification (Appendix A7) was provided to potential equip-
ment suppliers within the request for proposal defining the essential fea-
tures for the proper design of the equipment.
ERCOSPLAN prepared a list with all valves used in the project as well as
a piping list and a list in which the leading suppliers of equipment are
reflected.
Finally, drawings of piping and instrumentation (PID), arrangement draw-
ings and isometric drawings for pipes exceeding 100 mm diameter are
attached to this Detailed Engineering.
Chapters 4.4 and 4.5 cover all belonging documents for the sections
Electrical Engineering and Civil/Building Engineering and the respective
documents are attached to this Detailed Engineering report as well.
Chapter 5 of the Detail Engineering report is referring to the meteorologi- Property Description
cal conditions, earthquake risk and soil conditions of the Salar de Uyuni.
The Salar de Uyuni is located at an altitude of 3,653 m above sea level.
The exact location of the plant has been defined by mapping and was
provided by the Mining Corporation of Bolivia (GNRE-COMIBOL) to ER-
COSPLAN along with the coordinates of the current evaporation ponds.
As for the weather, there is a stable average temperature with ranges
from 21 °C to 13 °C depending on the time of year. The nights are cold
with temperatures between -9 °C to 5 °C.
The relative humidity is quite low and precipitations are usually not great-
er than 13 mm per month between the months of April and November,
Page 4 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Chapter 6 of the Detail Engineering report describes the raw material Process Design for
used for production, its condition in the evaporation ponds and its com- Production MOP
position.
According to these data, ERCOSPLAN has selected the flotation process
for processing the raw material to final product.
The block flow diagram presents each of the processing stages where
the material is treated. Furthermore, tables defining the mass flow and
the composition at any process stage to become MOP product are in-
cluded in the report.
In Chapter 7 of the Detail Engineering report, all facilities inside and out- Production Facilities
side the production plant are described.
Thus ERCOSPLAN defines the following facilities in general:
• Bottom dump truck load out and further transportation to wet salt
storage.
• Wet salt storage with afterwards iron/non-iron metal detecting,
lump crushing and further transportation to process building.
• Processing plant for producing the final product (MOP).
• Tank farm for reclaim brine and process water with pumps and
thickeners.
Remark: For producing saleable MOP product it was mandatory to add
following facilities:
• Product drying section (as extension of processing plant)
• Product storage
• Product truck loading
Due to modification of the existing contract signed by GNRE-COMIBOL at
the Gate 3 Meeting, these facilities are considered in this revised docu-
mentation.
The processing plant is designed as two production line operation. The Production Plant
production lines are called "Line A" and "Line B". Regarding the capacity Description /
and type of equipment, the production lines are similar. Advantage of a Process Building
two line production is that there is a 50 % production guarantee even if
one line is disturbed.
The processing plant consists of following technological process sec-
tions:
Page 5 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Although the main processing facilities are located in the main buildings Outside Facilities
on the plant site, e.g. wet salt storage, process building, product storage
and truck loading, there are several and necessary facilities located out-
side of the main buildings:
• Trucks unloading
• Conveyors belts
Page 6 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
The KCl plant has to be designed to produce 700,000 t/y of MOP (KCl Design Criteria
95).
Design safety factor applied to the production rate will be 15 % in mini-
mum. ERCOSPLAN considered a design safety factor of 20 %.
The operation time of KCl production plant will be 7,500 hours per year.
Remaining time is envisaged for maintenance and repairs. The KCl plant
will be operated 24 hours per day.
There is a power line and water supply network coming from the west. Existing Services
Water supply:
For the processing plant approx. 300 m³/h of process water is required.
Process water is delivered in sufficient quantity to the plant site via pipe
line. Also for the staff potable water is required. Due to the total number
of persons at the plant site, the daily amount of potable water is estimat-
ed under consideration of the working shift factor with approx. 30 m³.
Power supply:
Energy is transported to the industrial complex via 230kV overhead line
which is not sufficient and the electrical energy distribution in the area of
the industrial complex Salar de Uyuni starts from a distribution station
that still has to be realized via local network with a voltage level of 24.9kV.
Finally a reliable interim solution for the energy supply will have to be
realized for the transitional period.
Roads:
There are also roads to the plant site that can be used by heavy trucks
(20 tons).
Consumables supply:
To keep the plant operational, supplies have to be brought to the plant
and stored accordingly. Lubricants and others consumables are packed
correctly and delivered to the production plant via truck.
Page 7 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Due to extensive technology and continuous issues of the client, chapter Technical Description
7.4.2 “Technical Description of Selected Main Equipment” has been in- of Selected Main
cluded to the Detail Engineering report. Equipment
In this chapter, not only the operating mode is described, but also the
most important dimensional characteristics for each equipment.
The main process equipment are such as portal scraper, centrifuges,
screening machinery, rod mill, flotation cells, vacuum band filter, dry-
er/cooler belonging to each of the processes.
After the performance of laboratory tests and calculation processes, ER- Equipment Test Work
COSPLAN researched and selected the main equipment based on the
specific demand.
Once selected, ERCOSPLAN requested quotations from different suppli-
ers. It should be noted, that some of the supplier have requested test
runs on site since the will work under special conditions due to the high
altitude of the Salar.
Note that some of the suppliers have requested test work for their
equipment because of the special conditions due to the high altitude of
the Salar.
ERCOSPLAN recommends that GNRE-COMIBOL takes these outstand-
ing test works into consideration during the purchase of equipment, so
that the delivered equipment by the supplier can meet 100 % of GNRE-
COMIBOL’s expectations.
Page 8 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
• Tails process
• Compressor plant
• Process water storage
• Reclaim brine storage
• Rinsing water system
• Sealing water system
• Drying section product storage
• Truck loading.
The control circuits are defined with the help of a table (Appendix E8) for
all single sections of the process.
ERCOSPLAN can only give a general description on operation manuals, Operation Manuals
since GNRE-COMIBOL was not in the position to specify any suppliers
and type of equipment during compilation of the Final Engineering report.
Anyway, ERCOSPLAN defines the preconditions for start-up process or
notice of start of operation.
For the production of 700,000 t/y an energy demand of 11.2MVA is re- Utilities
quired.
This energy will be produced by power generator. The generator station
will be installed in a 40 foot container attached to the process building.
Another material required for process operation is water which must have
a temperature in the range from 12 °C to 18 °C.
The treatment of wastewater is not included in ERCOSPLAN’s scope of
work.
A network of rainwater systems will collect and lead rainwater to retention
basins for evaporation.
Finally the management of waste or tailings generated in the process will
be stockpiled in a dump 500 meters to the east of plant site.
The civil and building engineering of the KCl plant is defined and de- Structural/ Architectural
scribed in detail in chapter 7.8. Systems
The civil engineering comprises the implementation of roads or streets
that provide vehicular and pedestrian circulation.
In the building engineering, buildings are described where some of the
equipment is accommodated as well as other buildings such as wet salt
storage, small workshops, generator station and transformer station.
Administration and other social buildings are not within ERCOSPLAN’s
scope of work.
Each of these main and secondary buildings is described in detail as well
as the materials used for construction. More details are referenced in the
construction drawings.
As for the civil works is included the belt conveyors, support pipelines
structures, network of water and paved streets.
Page 9 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Finally a description of the discharge area for trucks and the tailings pile
is provided.
This chapter provides the description of an execution procedure pro- Project Execution
posal, applicable for the execution structure of this project.
However, execution procedure is outside battery limits of ERCOSPLAN’s
scope and is in full responsibility of GNRE-COMIBOL:
The main objectives of the proposed project execution plan are to com-
plete the project:
• Within (or below) the budget
• On (or ahead of) schedule
• While meeting the quality requirements and constructing the
plant in the most efficient manner
• While ensuring that health, safety, environmental and social obli-
gations are adhered to.
The project execution philosophy adopted also complies with the follow-
ing criteria:
• Maximization of the sourcing of the equipment and materials from
Bolivian or South American Sources.
• Execution by a general contractor team owned by GNRE with the
capacity to manage and execute the full scope of work to be per-
formed.
• Training of local residents so that they can be productively em-
ployed during the construction phase.
• Establishment of a construction-driven schedule.
Page 10 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
In this project, a detailed schedule of the overall development of the pro- Project Schedule
ject including activities is attached as Appendix G6
• Basic Engineering
• Detailed Engineering
• Acquisition
• Construction
• Mounting
• Commissioning.
At the same time a timely supply of equipment, materials and accessories
is considered in order to minimize the time until the start of production.
The management is very important during the construction phase to co- Construction
ordinate, direct and supervise the work of contractors on site. Management
During this stage it is very important to locate aspects like temporary facil-
ities, machinery park which will assist in the execution of the work, mate-
rial stockpile areas.
On the other hand it is also important to exercise oversight of the con-
struction process and take steps to ensure the safety and health of work-
ers.
Performance tests and studying the technical specifications of the materi-
als put in work is also important, always under the control of activities at
the time reflected in the work plan.
Also for maintenance of the environment, it is necessary to manage
wastes generated on site, implanting during the construction phase and
marking guidelines for actions to be followed.
Before commissioning of the plant, test runs and several checks have to
be performed to control that all equipment and facilities work properly.
The necessary staff has been classified into different groups with different Personnel Require-
salary levels based on their qualifications. Shifts will be three a day, each ments
shift lasting eight hours.
Page 11 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
ERCOSPLAN developed a table with the three most important equipment Technical Evaluation
suppliers. Quotations
The table provides for each company contact person, date of request of
proposal, quotation number, the date of quotation and the number of
appendix where the quotation can be found.
Finally ERCOSPLAN show the quotations that have been considered in
the detail engineering. Attached to this final report are only quotations
that have been considered in the Detailed Engineering.
It defines the average consumption required for production of KCl at plant Media Consumption
site with respect to:
• Raw material is in the evaporation pools.
• Water consumption
• Power consumption
• Consumption of liquefied gas
• consumption of chemicals
• Fuel for trucks, cars, machinery
• Oils and lubricants.
In general, ERCOSPLAN propose ensuring the safety and health of work- Risk Analysis
ers as well as measures to ensure environmental protection.
Prior to the commencement of activities, a safety and health plan will be
presented showing risks and preventive measures based on the activities
as well as the made jobs.
Also risks for accidents caused by natural phenomena or fire are men-
tioned.
The basic structure of a plan of emergency must be defined and ap-
proved by the superiority during implementation and commissioning of
the plant site.
Environmentally it is referred to the various risks arising by water, atmos-
phere and soil. Therefore it is important to have a plan of environmental
protection where preventive measures as well as the regeneration or envi-
ronmental restoration of the area are indicated.
It should be noted that ensuring the safety and health of workers at the
Page 12 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
All machinery, materials and equipment that are within ERCOSPLAN’s Capital Cost Estimate
scope have been chosen according to the widespread experience of the
authors in potash processing operations worldwide.
Remarks: All equipment, buildings, devices that are outside battery limits
(especially water sewage, furniture, laboratory equipment, equipment for
office, administration building, laboratory, canteen, warehouse, work-
shop, fire station, hospital and vehicles such as fire ambulances, trucks,
cranes, buses, loaders, vehicles) have not been considered in this calcu-
lation.
Page 13 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
LIST OF CONTENTS
EXECUTIVE SUMMARY 2
LIST OF CONTENTS 14
LIST OF FIGURES 21
LIST OF TABLES 22
LIST OF ENCLOSURES 23
LIST OF APPENDICES 24
LIST OF DRAWINGS 28
LIST OF ABBREVIATIONS 50
1 Introduction 51
2 Project History, Database and Battery Limits 53
2.1 Project History 53
2.2 Database 54
2.2.1 Design Base 54
2.3 Battery Limits 55
2.3.1 Interface Delivery of Wet Crystallizate from Evaporation Ponds 55
2.3.2 Interface Product Truck Loading 55
2.3.3 Interface Debrined Tailings to Tailings Pile 55
2.3.4 Interface Brine Disposal 55
2.3.5 Interface Delivery of Process Media 55
3 Nomenclature 57
3.1 Indication Code for Devices and Equipment 57
3.2 Indication Code for Measuring and Control Points 58
3.3 Indication Code for Pipelines / Chutes 61
3.4 Indication Code for Valves 61
3.5 Overview of Media Codes (Can Be amended Anytime) 62
4 Belonging Documents 63
4.1 General Documents 63
4.1.1 Design Base Document 63
4.1.2 Equipment Quotations 63
4.1.3 Cost Estimation Equipment 63
4.1.4 Cost Estimation Pipes 64
4.1.5 Cost Estimation Valves 64
4.1.6 Cost Estimation Electrical Equipment 64
4.1.7 Cost Estimation Civil Works (Infrastructure, Buildings) 64
4.1.8 Project Schedule 64
4.2 Documents Processing Engineering 65
4.2.1 Block Flow Diagram 65
4.3 Documents Mechanical Engineering 65
4.3.1 Equipment List 65
4.3.2 Equipment Data Sheets 65
4.3.3 Drawing List 65
Page 14 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 15 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 16 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 18 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 20 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
LIST OF FIGURES
Figure 1 Block Flow Diagram (see also Drawing A01) Crystallisate Debrining 82
Figure 2 Cross Section of a Screen Worm Centrifuge CX 135
Figure 3 Overview of modules 137
Figure 4 Hydraulic diagram 7-138
Figure 5 Centrifuge characteristics and circumferential speed 7-139
Figure 6 RF-∆t-diagram 145
Figure 7 Working scheme wet screen 146
Figure 8 Vacuum belt filter 154
Figure 9 Capacities of Truck Loading 191
Figure 10 Organization Chart General Superintendent Process 240
Page 21 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
LIST OF TABLES
Page 22 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
LIST OF ENCLOSURES
Page 23 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
LIST OF APPENDICES
Mechanical Engineering
Appendix A1 Design Base Document
Appendix A2 Equipment List incl. Electrical Energy Consumption (Rev.01)
Appendix A3 Equipment Data Sheets (Rev.02)
Appendix A4 Drawing List (Rev.01)
Appendix A5 List of Instruments (Rev.01)
Appendix A6 Specification Mechanical Equipment (Rev.03)
Appendix A7 Inquiry Specification
Appendix A8 Pipe List (Rev.01)
Appendix A9 Valve List (Rev.01)
Appendix A10 Pipe Classification
Appendix A2.1 Equipment List incl. Electrical Energy Consumption
Appendix A3.1 Equipment Data Sheets (Rev.02)
Appendix A5.1 List of Instruments
Appendix A6.1 Specification Mechanical Equipment (Rev.02)
Appendix A8.1 Pipe List
Appendix A9.1 Valve List
Electrical Engineering
Appendix E1 Energy Consumer (Rev.01)
Appendix E2 Electrical Energy Demand (Rev.01)
Appendix E3 Utilized Capacity Power Supply System (Rev.01)
Appendix E4 Cable List / Power Supply Cable (Rev.01)
Appendix E5 Cable List / 0.69kV Cable (Rev.01)
Appendix E6 Cable List / Control Cable (Rev.01)
Appendix E7 Cable List / Lighting, Socket System (Rev.01)
Appendix E8 Control Circuits
Appendix E9 Interlocking System
Appendix E10 I/O-List (Rev.01)
Appendix E11 Short Circuit Calculation
Appendix E12 Voltage Drop Calculation
Appendix E13 Lighting Calculation
Appendix E14 Cable List / Information System (Rev.01)
Appendix E15 Requirements Rooms Power Station
Appendix E16 Cable List / Automation System
Page 24 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
General Appendices
Appendix G1 Cost Estimation Mechanical Equipment (Rev.01)
Appendix G2 Cost Estimation Pipes (Rev.01)
Appendix G3 Cost Estimation Valves (Rev.01)
Appendix G4 Cost Estimation Electrical Equipment
Appendix G5 Cost Estimation Civil Works (Infrastructure, Buildings) (Rev.01)
Appendix G6 Project Schedule
Appendix G1.1 Cost Estimation Mechanical Equipment
Appendix G2.1 Cost Estimation Pipes
Appendix G3.1 Cost Estimation Valves
Quotations
Appendix Q1 Overbelt Magnetic Separator / Eriez (Rev. 02)
Appendix Q2 Overbelt Magnetic Separator / Steinert (Rev. 01)
Appendix Q3 Flotation / FLSmidth
Appendix Q4 Quotation canceled
Appendix Q5 Pumps / KSB (Rev. 02)
Appendix Q6 Pumps / Allweiler
Appendix Q7 Quotation canceled
Appendix Q8 Belt Conveyor / SBM
Appendix Q9 Belt Conveyor / FAM
Appendix Q10 Belt Conveyor / Doubrava
Appendix Q11 Quotation canceled
Appendix Q12 Trough Chain Conveyor / Emde
Appendix Q13 Portal Scraper / FAM
Appendix Q14 Portal Scraper / Schade
Appendix Q15 Quotation canceled
Appendix Q16 Quotation canceled
Appendix Q17 Quotation canceled
Appendix Q18 Screen / Siebtechnik TEMA-BV (Rev. 01)
Appendix Q19 Screen / Rhewum (Rev. 01)
Appendix Q20 Rod Mill / FAM (Rev. 01)
Appendix Q21 Mill / FLSmidth
Appendix Q22 Centrifuges / Andritz (Rev. 01)
Page 25 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 26 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Structural Engineering
Appendix S1 Structural Analysis Wet Salt Storage
Appendix S2 Structural Analysis Process Building. Building Stabilization Part 1
Appendix S3 Structural Analysis Process Building. Building Stabilization Part 2
Appendix S4 Structural Analysis Process Building. Platforms
Appendix S5 Structural Analysis Truck Unloading
Appendix S6 Structural Analysis Distribution Tower 1
Appendix S7 Structural Analysis Power Station
Appendix S8 Calculation of Rainwater Retention
Appendix S9 Rough Steel Lists, Technical Specifications for Construction
Appendix S10 Structural Analysis Truck Loading
Appendix S11 Structural Analysis Distribution Tower 2
Appendix S12 Structural Analysis Foundations (Process Building, Wet Salt Storage,
Truck Unloading, Distribution Tower 1, Outside Facilities)
Page 27 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
LIST OF DRAWINGS
Page 28 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 29 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 30 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
A1501 Parameter for Civil Engineering Process Building Platform +18.00m Part 1
A1502 Parameter for Civil Engineering Process Building Platform +18.00m Part 2
A1503 Parameter for Civil Engineering Process Building Platform +12.00m Part 1
A1504 Parameter for Civil Engineering Process Building Platform +12.00m Part 2
A1505/1 Parameter for Civil Engineering Process Building Platform +6.00m Part 1
A1506/1 Parameter for Civil Engineering Process Building Platform +6.00m Part 2
A1507/1 Parameter for Civil Engineering Process Building Ground Floor +/- 0.00m Part 1
A1508/1 Parameter for Civil Engineering Process Building Ground Floor +/- 0.00m Part 2
A1510 Parameter for Civil Engineering Process Building Drying Section
Ground Floor +/- 0.00m
A1511 Parameter for Civil Engineering Process Building Drying Section
Platform +4.00/+6.00m
A1512 Parameter for Civil Engineering Process Building Drying Section
Platform +9.00m
A1513 Parameter for Civil Engineering Process Building Drying Section
Platform +15.50m
A1514 Parameter for Civil Engineering Process Building Drying Section
Platform +18.00m
Page 32 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
E2216 Lighting system and Automation equipment / Distribution Tower 2 Ground floor,
+3,51m / Layout
Page 33 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
E2217 Lighting system and Automation equipment / Distribution Tower 2 +9,27m, Roof
/ Layout
E2218 Lighting – Socket system / Drying section Ground floor / Layout
E2219 Lighting – Socket system / Drying section +4,0/+6,0m / Layout
E2220 Lighting – Socket system / Drying section +9,0m /Layout
E2221 Lighting – Socket system / Drying section +15,5m / Layout
E2222 Lighting – Socket system / Drying section +18,0m / Layout
Page 34 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 35 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
E2389 Typical wiring diagram WD16.3 / Screw conveyor with Frequency converter
Page 36 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 37 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
E2664 Automation fire protection Video control system / Product storage / Page 1-2
E2665 Automation fire protection Video control system / Truck loading
E2666 Automation fire protection Video control system / Drying section Ground floor /
Layout
E2667 Automation fire protection Video control system / Drying section +4,0m / +6,0m
/ Layout
E2668 Automation fire protection Video control system / Drying section +9,0m / Layout
E2669 Automation fire protection Video control system / Drying section +15,5m /
Layout
E2670 Automation fire protection Video control system / Drying section +18,0m /
Layout
E2671 Access control system / Overview diagram
Page 38 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Process Building
3200 Ground Plan, Grid Line 1-9 / A-H
3201 Ground Plan, Grid Line 1-9 / H-O
3202/1 Ground Plan, Grid Line 10-20 / A-H
3203/1 Ground Plan, Grid Line 10-20 / H-O
3204 Platform +6.00 m, Grid Line 1-9 / A-H
3205 Platform +6.00 m, Grid Line 1-9 / H-O
3206/1 Platform +6.00 m, Grid Line 10-20 / A-H
3207/1 Platform +6.00 m, Grid Line 10-20 / H-O
3208/1 Service Platforms on Platform +6.00 m
3209/1 Platform +9.00 m
3210/1 Platform +4.00 m
3211 Platform +12.00 m, Grid Line 1-9 / A-H
3212 Platform +12.00 m, Grid Line 1-9 / H-O
3213/1 Platform +12.00 m, Grid Line 10-20 / A-H
3214/1 Platform +12.00 m, Grid Line 10-20 / H-O
3215/1 Service Platforms on Platform +12.00 m
3216 Platform +15.00 m
Page 39 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Product Storage
3300 Ground Plan Grid 1 – 13
3301 Ground Plan Grid 13 - 26
3302 Cross Section
3303 Longitudinal Bracings
3304 Conveyor Platform +22.80 m, Grid Line 1-15
3305 Conveyor Platform +18.10 m, Grid Line 1-26
3306 Roof Construction, Purlins Arrangement, Grid Line 1-13
3307 Roof Construction, Purlins Arrangement, Grid Line 13-26
3308 Front Wall Construction, Grid Line 1
3309 Front Wall Construction, Grid Line 26
3310 Stairs Tower
3311 Anchoring Plan, Anchor Detail, Grid Line 1-13
3312 Anchoring Plan, Anchor Detail, Grid Line 13-26
3315 Views
3320 Gate / Door Details
Page 40 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Truck Unloading
3400 Top View, Cross Sections
3401 Ground Plans
3402 Sections
3403 Bin Structure
3404 Abutments. Formwork Plan
Truck Loading
3500 Ground Plan -0.50 m, Platform +3.07 m, +4.87 m, +7.93 m
3501 Platform +12.61m, +14.95/17.11 m, +19.27 and Roof View
3502 Elevation on Grid Line 1, 2, and 3
3503 Elevation on Grid Line 4, 5 and 6
3504 Elevation on Grid Line A
3505 Elevation on Grid Line B
3507 Anchoring Plan, Anchor Detail
3510 Views
Power Station
3600/1 Ground Floor
3601/1 Level +6.00 m
3602/1 Level +8.55 m
3603/1 Level +12.60 m
3604/1 Level +16.00 m
3605/1 Cross Section A-A
3606/1 Longitudinal Section B-B
3607 Elevations
3608 Roof Steel Structure
Page 41 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Distribution Tower 1
3800/1 Ground Plan -0.50 m, Platform +4.05 m, +7.65 m
3801/1 Platform +13.59 m, 19.17 m, and Roof
3802/1 Elevation on Grid 1, 2, and 3
3803/1 Elevation on Grid 4 and 5
3804/1 Elevation on Grid A
3805/1 Elevation on Grid B
3806/1 Elevation on Grid C
3807/1 Anchoring Plan, Anchor Detail
3810/1 Views
Distribution Tower 2
3850 Ground Plan -0.50 m, Platform +3.51 m
3851 Platform +9.27 m and Roof View
3852 Elevation on Grid Line 1 and 2
3853 Elevation on Grid Line 3 and 4
3854 Elevation on Grid Line A
3855 Elevation on Grid Line B
3856 Elevation on Grid Line C
3857 Anchoring Plan, Anchor Detail
3860 Views
Outside Facilities
3900/1 Outside Process Area. Ground Plan
3901/1 Reclaim Brine Storage / Generator Station. Ground Plan
A4002/1 A02-RL-002-SP-125-GFK/PP
A4003/1 A02-RL-003-SP-300-GFK/PP
Page 42 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
A4005/1 A02-RL-005-SP-300-GFK/PP
A4006/1 A02-RL-006-SP-250-GFK/PP
A4007/1 A02-RL-007-SP-250-GFK/PP
A4008/1 A02-RL-010-SP-350-GFK/PP
A4009/1 A02-RL-015-SP-200-GFK/PP
A4002/1 A02-RL-002-SP-125-GFK/PP
A4003/1 A02-RL-003-SP-300-GFK/PP
A4005/1 A02-RL-005-SP-300-GFK/PP
A4006/1 A02-RL-006-SP-250-GFK/PP
A4007/1 A02-RL-007-SP-250-GFK/PP
A4008/1 A02-RL-010-SP-350-GFK/PP
A4009/1 A02-RL-015-SP-200-GFK/PP
A4010/1 A02-RL-016-FI-250-GFK/PP
A4011/1 A02-RL-019-SP-300-GFK/PP
A4012/1 A02-RL-020-SP-250-GFK/PP
A4013/1 A02-RL-023-SP-150-GFK/PP
A4014/1 A02-RL-024-SP-150-GFK/PP
A4015/1 A02-RL-025-SP-250-GFK/PP
A4016/1 A02-RL-026-SP-250-GFK/PP
A4017/1 A02-RL-027-SP-250-GFK/PP
A4021/1 A02-RL-045-SP-350-GFK/PP
A4022/1 A02-RL-046-SP-350-GFK/PP
A4024/1 A02-RL-050-SP-300-GFK/PP
A4025/1 A02-RL-055-SP-250-GFK/PP
A4026/1 A02-RL-057-SP-450-GFK/PP
A4027/1 A02-RL-058-SP-300-GFK/PP
A4028/1 A02-RL-059-SP-300-GFK/PP
A4029/1 A02-RL-060-SP-300-GFK/PP
A4030/1 A02-RL-066-SP-250-GFK/PP
A4031/1 A02-RL-069-SP-300-GFK/PP
A4032/1 A02-RL-070-SP-250-GFK/PP
A4034/1 A02-RL-080-SP-250-GFK/PP
A4036/1 A02-RL-092-SP-250-GFK/PP
A4037/1 A02-RL-095-SP-250-GFK/PP
A4038/1 A02-RL-110-SP-125-GFK/PP
A4040/1 A02-RL-112-SP-150-GFK/PP
A4041/1 A02-RL-115-SP-500-GFK/PP
Page 43 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
A4042/1 A02-RL-116-SP-450-GFK/PP
A4043/1 A02-RL-119-SP-450-GFK/PP
A4044/1 A02-RL-120-SP-500-GFK/PP
A4045/1 A02-RL-121-SP-150-GFK/PP
A4050/1 A02-RL-135-SP-400-GFK/PP
A4051/1 A02-RL-136-SP-400-GFK/PP
A4056/1 A02-RL-155-RW-150-GFK/PP
A4058/1 B02-RL-002-SP-125-GFK/PP
A4059/1 B02-RL-003-SP-300-GFK/PP
A4061/1 B02-RL-005-SP-300-GFK/PP
A4062/1 B02-RL-006-SP-250-GFK/PP
A4063/1 B02-RL-007-SP-250-GFK/PP
A4064/1 B02-RL-010-SP-350-GFK/PP
A4065/1 B02-RL-015-SP-200-GFK/PP
A4066/1 B02-RL-016-FI-250-GFK/PP
A4067/1 B02-RL-019-SP-300-GFK/PP
A4068/1 B02-RL-020-SP-250-GFK/PP
A4069/1 B02-RL-023-SP-150-GFK/PP
A4070/1 B02-RL-024-SP-150-GFK/PP
A4071/1 B02-RL-025-SP-250-GFK/PP
A4072/1 B02-RL-026-SP-250-GFK/PP
A4073/1 B02-RL-027-SP-250-GFK/PP
A4077/1 B02-RL-045-SP-350-GFK/PP
A4078/1 B02-RL-046-SP-350-GFK/PP
A4080/1 B02-RL-050-SP-300-GFK/PP
A4081/1 B02-RL-055-SP-250-GFK/PP
A4082/1 B02-RL-057-SP-450-GFK/PP
A4083/1 B02-RL-058-SP-300-GFK/PP
A4084/1 B02-RL-059-SP-300-GFK/PP
A4085/1 B02-RL-060-SP-300-GFK/PP
A4086/1 B02-RL-066-SP-250-GFK/PP
A4087/1 B02-RL-069-SP-300-GFK/PP
A4088/1 B02-RL-070-SP-250-GFK/PP
A4090/1 B02-RL-080-SP-250-GFK/PP
A4092/1 B02-RL-092-SP-250-GFK/PP
A4093/1 B02-RL-095-SP-250-GFK/PP
A4094/1 B02-RL-110-SP-125-GFK/PP
Page 44 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
A4096/1 B02-RL-112-SP-150-GFK/PP
A4097/1 B02-RL-115-SP-500-GFK/PP
A4098/1 B02-RL-116-SP-450-GFK/PP
A4099/1 B02-RL-119-SP-450-GFK/PP
A4100/1 B02-RL-120-SP-500-GFK/PP
A4101/1 B02-RL-121-SP-150-GFK/PP
A4106/1 B02-RL-135-SP-400-GFK/PP
A4107/1 B02-RL-136-SP-400-GFK/PP
A4112/1 B02-RL-155-RW-150-GFK/PP
A4114/1 A03-RL-003-SP-450-GFK/PP
A4115/1 A03-RL-004-SP-450-GFK/PP
A4116/1 A03-RL-005-SP-450-GFK/PP
A4117/1 A03-RL-010-LG-400-GFK/PP
A4118/1 A03-RL-011-LG-400-GFK/PP
A4119/1 A03-RL-012-LG-350-GFK/PP
A4121/1 A03-RL-016-LG-300-GFK/PP
A4122/1 A03-RL-020-SP-150-GFK/PP
A4123/1 A03-RL-021-SP-150-GFK/PP
A4124/1 A03-RL-024-SP-125-GFK/PP
A4125/1 A03-RL-025-SP-125-GFK/PP
A4126/1 A03-RL-026-SP-125-GFK/PP
A4127/1 A03-RL-030-SP-400-GFK/PP
A4128/1 A03-RL-033-SP-350-GFK/PP
A4130/1 B03-RL-003-SP-450-GFK/PP
A4131/1 B03-RL-004-SP-450-GFK/PP
A4132/1 B03-RL-005-SP-450-GFK/PP
A4133/1 B03-RL-010-LG-400-GFK/PP
A4134/1 B03-RL-011-LG-400-GFK/PP
A4135/1 B03-RL-012-LG-350-GFK/PP
A4137/1 B03-RL-016-LG-300-GFK/PP
A4138/1 B03-RL-020-SP-150-GFK/PP
A4139/1 B03-RL-021-SP-150-GFK/PP
A4140/1 B03-RL-024-SP-125-GFK/PP
A4141/1 B03-RL-025-SP-125-GFK/PP
A4142/1 B03-RL-026-SP-125-GFK/PP
A4143/1 B03-RL-030-SP-400-GFK/PP
A4144/1 B03-RL-033-SP-350-GFK/PP
Page 45 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
A4146/1 03-RL-150-EL-250-PE
A4147/1 A04-RL-001-SP-500-GFK/PP
A4149/1 A04-RL-003-SP-300-GFK/PP
A4151/1 B04-RL-001-SP-500-GFK/PP
A4153/1 B04-RL-003-SP-300-GFK/PP
A4155/1 A05-RL-001-SP-250-GFK/PP
A4156/1 A05-RL-004-SP-200-GFK/PP
A4157/1 A05-RL-006-SP-200-GFK/PP
A4158/1 A05-RL-007-SP-300-GFK/PP
A4159/1 A05-RL-012-VK-500-GFK/PP
A4160/1 A05-RL-013-SP-350-GFK/PP
A4161/1 A05-RL-014-VK-500-GFK/PP
A4162/1 A05-RL-015-SP-200-GFK/PP
A4163/1 A05-RL-018-SP-150-GFK/PP
A4164/1 A05-RL-019-SP-300-GFK/PP
A4165/1 A05-RL-020-SP-300-GFK/PP
A4166/1 A05-RL-021-SP-300-GFK/PP
A4167/1 A05-RL-022-SP-250-GFK/PP
A4168/1 A05-RL-026-SP-200-GFK/PP
A4170/1 A05-RL-035-SP-250-GFK/PP
A4171/1 A05-RL-040-SP-200-GFK/PP
A4172/1 A05-RL-047-SP-200-GFK/PP
A4173/1 A05-RL-050-SP-150-GFK/PP
A4174/1 A05-RL-051-SP-125-GFK/PP
A4175/1 A05-RL-055-LG-300-GFK/PP
A4176/1 A05-RL-057-SP-150-GFK/PP
A4177/1 A05-RL-059-LG-300-GFK/PP
A4178/1 A05-RL-060-LG-250-GFK/PP
A4179/1 A05-RL-063-LG-200-GFK/PP
A4180/1 B05-RL-001-SP-250-GFK/PP
A4181/1 B05-RL-004-SP-200-GFK/PP
A4182/1 B05-RL-006-SP-200-GFK/PP
A4183/1 B05-RL-007-SP-300-GFK/PP
A4184/1 B05-RL-012-VK-500-GFK/PP
A4185/1 B05-RL-013-SP-350-GFK/PP
A4186/1 B05-RL-014-VK-500-GFK/PP
A4187/1 B05-RL-015-SP-200-GFK/PP
Page 46 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
A4188/1 B05-RL-018-SP-150-GFK/PP
A4189/1 B05-RL-019-SP-300-GFK/PP
A4190/1 B05-RL-020-SP-300-GFK/PP
A4191/1 B05-RL-021-SP-300-GFK/PP
A4192/1 B05-RL-022-SP-250-GFK/PP
A4193/1 B05-RL-026-SP-200-GFK/PP
A4195/1 B05-RL-035-SP-250-GFK/PP
A4196/1 B05-RL-040-SP-200-GFK/PP
A4197/1 B05-RL-047-SP-200-GFK/PP
A4198/1 B05-RL-050-SP-150-GFK/PP
A4199/1 B05-RL-051-SP-125-GFK/PP
A4200/1 B05-RL-055-LG-300-GFK/PP
A4201/1 B05-RL-057-SP-150-GFK/PP
A4202/1 B05-RL-059-LG-300-GFK/PP
A4203/1 B05-RL-060-LG-250-GFK/PP
A4204/1 B05-RL-063-LG-200-GFK/PP
A4206/1 A07-RL-004-SP-350-GFK/PP
A4207/1 A07-RL-005-SP-300-GFK/PP
A4209/1 B07-RL-004-SP-350-GFK/PP
A4210/1 B07-RL-005-SP-300-GFK/PP
A4212/1 A08-RL-003-SP-400-GFK/PP
A4213/1 A08-RL-006-SP-350-GFK/PP
A4215/1 A08-RL-008-SP-400-GFK/PP
A4216/1 A08-RL-015-SP-450-GFK/PP
A4217/1 A08-RL-016-SP-150-GFK/PP
A4219/1 A08-RL-030-SP-350-GFK/PP
A4220/1 A08-RL-031-SP-350-GFK/PP
A4221/1 A08-RL-034-SP-300-GFK/PP
A4223/1 A08-RL-039-SP-125-GFK/PP
A4224/1 A08-RL-040-SP-350-GFK/PP
A4225/1 A08-RL-041-SP-125-GFK/PP
A4226/1 A08-RL-042-VK-500-GFK/PP
A4227/1 A08-RL-043-FI-300-GFK/PP
A4228/1 A08-RL-044-FI-300-GFK/PP
A4230/1 A08-RL-046-FI-300-GFK/PP
A4232/1 A08-RL-050-FI-250-GFK/PP
A4234/1 A08-RL-052-FI-300-GFK/PP
Page 47 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
A4236/1 B08-RL-003-SP-400-GFK/PP
A4237/1 B08-RL-006-SP-350-GFK/PP
A4239/1 B08-RL-008-SP-400-GFK/PP
A4240/1 B08-RL-015-SP-450-GFK/PP
A4241/1 B08-RL-016-SP-150-GFK/PP
A4243/1 B08-RL-030-SP-350-GFK/PP
A4244/1 B08-RL-031-SP-350-GFK/PP
A4245/1 B08-RL-034-SP-300-GFK/PP
A4247/1 B08-RL-039-SP-125-GFK/PP
A4248/1 B08-RL-040-SP-350-GFK/PP
A4249/1 B08-RL-041-SP-125-GFK/PP
A4250/1 B08-RL-042-VK-500-GFK/PP
A4251/1 B08-RL-043-FI-300-GFK/PP
A4252/1 B08-RL-044-FI-300-GFK/PP
A4254/1 B08-RL-046-FI-300-GFK/PP
A4256/1 B08-RL-050-FI-250-GFK/PP
A4258/1 B08-RL-052-FI-300-GFK/PP
A4259/1 B08-RL-055-SP-125-GFK/PP
A4263/1 A10-RL-68-LG-300-GFK/PP
A4264/1 A10-RL-98-LG-300-GFK/PP
A4265/1 A10-RL-125-LG-600-GFK/PP
A4266/1 A10-RL-128-LG-500-GFK/PP
A4267/1 A10-RL-156-LG-250-GFK/PP
A4268/1 10-RL-170-LG-250-GFK/PP
A4269/1 A10-RL-173-LG-125-GFK/PP
A4270/1 A10-RL-185-RW-200-GFK/PP
A4271/1 A10-RL-188-RW-125-GFK/PP
A4272/1 B10-RL-78-LG-300-GFK/PP
A4273/1 B10-RL-108-LG-300-GFK/PP
A4274/1 B10-RL-135-LG-600-GFK/PP
A4275/1 B10-RL-138-LG-500-GFK/PP
A4276/1 B10-RL-157-LG-250-GFK/PP
A4277/1 B10-RL-190-RW-200-GFK/PP
A4278/1 B10-RL-193-LG-125-GFK/PP
A4284/1 10-RL-008-LG-250-GFK/PP
A4285/1 10-RL-016-RW-500-GFK/PP
A4286/1 10-RL-017-RW-200-GFK/PP
Page 48 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
A4288/1 10-RL-021-RW-150-GFK/PP
A4289/1 10-RL-022-RW-700-GFK/PP
A4290/1 10-RL-023-RW-450-GFK/PP
A4291/1 10-RL-024-RW-500-GFK/PP
A4292/1 10-RL-032-RW-450-GFK/PP
A4279/1 10-RL-040-LG-700-GFK/PP
A4295/1 10-RL-043-LG-250-GFK/PP
A4296/1 10-RL-044-LG-250-GFK/PP
A4298/1 10-RL-046-LG-700-GFK/PP
A4299/1 10-RL-047-LG-700-GFK/PP
A4294/1 10-RL-050-LG-700-GFK/PP
A4302/1 10-RL-055-LG-250-GFK/PP
A4303/1 10-RL-058-LG-150-GFK/PP
A4304/1 10-RL-085-LG-250-GFK/PP
A4305/1 10-RL-088-LG-150-GFK/PP
A4306/1 10-RL-115-LG-250-GFK/PP
A4307/1 10-RL-118-LG-200-GFK/PP
A4309/1 10-RL-165-LG-200-GFK/PP
A4310/1 10-RL-168-LG-150-GFK/PP
A4315/1 A15-RL-020-PW-150-PE
A4316/1 A15-RL-050-PW-250-PE
A4317/1 A15-RL-053-PW-200-PE
A4318/1 B15-RL-002-PW-150-PE
A4319/1 B15-RL-030-PW-250-PE
A4320/1 B15-RL-033-PW-200-PE
A4321/1 15-RL-005-PW-300-PE
Page 49 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
LIST OF ABBREVIATIONS
Page 50 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
1 Introduction
The Salar de Uyuni is located about 3,650 m.s.n.m. in southwest Bolivia, in the Province of
Daniel Campos, Department of Potosi, in the Andean high plateau. It is the largest continuous
salt desert in the world with an area of 10,582 km².
The salt is formed in one of the largest reserves of lithium in the world and has significant
amounts of potassium, boron and magnesium.
The economic activity of the Salar does not focus only on tourism but also salt production real-
izes by neighboring cities as Colchani City.
The employed extraction method is traditional in which the salt is collected in small piles, facili-
tating the evaporation of the water and its optimizing transport.
Today it is possible to know the structure of the salt with the help of researches and the realiza-
tion of test drillings, knowing it that consists of approximately 11 overlapping layers of salt and
mud lake, with thicknesses ranging from less than 1 meter to 20 meters, and its depth of 120
meters and that its origin corresponds to the drought of an ancient salt lake.
Therefore, and according to official data of the Mining Corporation of Bolivia (GNRE-COMIBOL)
estimates that the Salar contains 10 billion tons of salt, of which only 25,000 tons are extracted
annually.
In view of the large reserve of material, the Mining Corporation of Bolivia expects to exploit on
an industrial scale and plans to build a production plant of 700,000 t/y of potassium chloride of
high purity (KCl 95) in the Salar de Uyuni.
Thus GNRE-COMIBOL currently starts a pilot plant that produces about 1,000 tons of potassi-
um chloride monthly supply the local market and to set basic parameters, for the design of the
plant.
In Bolivia, this industrial production of potassium chloride and other derivatives is operated
100 % by state administration using technologies always compatible with the preservation of
the environment.
It is the German company ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH as specialist in
the sector and with extensive experience in the design of the mining of salt guarantee for its
professional path over the years, which has carried out the development of the engineering
project.
One of the main premises on which it´s based ERCOSPLAN for industrial production is the
application of flotation process, which helps in the recovery of potassium chloride presents in
the brine (sylvite) and whose final destination is the production of fertilizer potash.
The processing plant designed by ERCOSPLAN will work continuously 24 hours a day, in three
shifts, seven days a week, with a total production of 7,500 hours per year. The remaining time
will be used a year in performing preventive maintenance.
Prior to processing the brine, it will be pumped from the salt and is led to a battery of ponds,
whose main function is water evaporation and crystallization of sodium chloride and potassium
chloride.
It then proceeds to supply the process plant through loaded brine in trucks with 20 tons of ca-
pacity that will work for 16 h/day and transport the material to a lump crushing that reduces its
initial grain size.
Then and, with the help of the belts conveyor, the material is divided into two production lines A
and B are exactly the same and that produce 350,000 tons/year respectively.
Page 51 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Each of these stages will be developed and explained in the different sections that make up
this project.
It is noted that all installations that make both lines (A and B) are accommodated in the pro-
cess building which have been designed in this project while all those needed installations but
larger are located in the proximity of the building.
The aim of this processing plant becomes the initial product or brine contents approximately
70 % of NaCl in a product with a purity of 95 % KCl, together with a recovery of over 80 % of
their tails.
Finally note that the implementation and processing of the brine in the Salar de Uyuni will con-
tribute to socio-economic development of the region, generating jobs, to will enable better liv-
ing conditions of its inhabitants of the area as well as positioning of the Bolivian country as one
of the leading producers of KCl worldwide.
Page 52 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
On January 17, 2012, the Mining Corporation of Bolivia awarded to the German company ER-
COSPLAN INGENIERURBURO ANLAGENTECHNIK GmbH, Contract No. CTTO: COMIBOL-
GNRE/AL-022/2012 consisting of the design and implementation of the project:
"ENGINEERING DESIGN INDUSTRIAL PLANT 700,000 Tn / Time OF KCl BASED PROCESS
SYLVINITE FLOATING IN UYUNI"
with a duration of 10 months from the date of signing of the minutes of the start of work.
The contract signing was on July 31, 2012 and the meeting minutes of the start of work are
dated February 18, 2013.
In the first ten days after the start date of the act, ERCOSPLAN achieved an initial document to
schedule the phases of project and work plan.
In February 28, 2013 ERCOSPLAN began with the basic engineering project.
In March, ERCOSPLAN sent a questionnaire to GNRE-COMIBOL to ensure the further possible
progress in the design of the project.
This questionnaire asked for a sample of brine from existing pools in the Salar de Uyuni, for
analysis by the company, as well as defining certain general criteria as general criteria for the
implementation of engineering project.
In this month, ERCOSPLAN made two more deliveries. The first one was a coordination proce-
dure establishing roles and routines that should be followed by both companies ERCOSPLAN
and GNRE-COMIBOL.
In the second delivery, ERCOSPLAN sent a report of the progress made so far, with the results
obtained in the flotation of the previously requested brine sample.
At the beginning of the following month, GNRE-COMIBOL answered to the questionnaire sent
by ERCOSPLAN days earlier.
Also during the month of April 2013, ERCOSPLAN sent the manual for the use of a data server
through which documents are delivered digitally, as well as a file with the functional require-
ments to prepare the subsoil, the specifications required for the basic and detailed engineering
and so far there was no geotechnical report endorsed by an expert.
From May 13 - 17, 2013 the first meeting (Gate 1) took place in La Paz and in these days, ER-
COSPLAN and GNRE-COMIBOL made a visit to the pilot plant located in the Salar de Uyuni.
Already in June, ERCOSPLAN, delivered the "Milestone 2" documents, a precursor to the final
Basic Engineering which was delivered on July 17, 2013. On July 5, 2013 ERCOSPLAN sent
addendum documents for the “Milestone 2” report
Between June 22 and July 24, 2013 there was a second meeting "Gate 2" in La Paz where ER-
COSPLAN, explained the basic engineering developed in the different sections that make up
the project: process, mechanical, electrical ,civil and finally the building engineering, getting
the confirmation from the GNRE-COMIBOL, assuming completion of the phase consisting of
basic engineering.
Page 53 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Since then, ERCOSPLAN has begun with the development of the detailed engineering, deliver-
ing on August 1, 2013 a Basic Addendum and on August 30, 2013 "Milestone 3" documents
which have been presented to GNRE-COMIBOL on September 23 – 25, 2013 during the "Gate
3" meeting in La Paz.
On October 1, 2013 GNRE-COMIBOL contracted ERCOSPLAN for a modification of the already
existing contract. The contract modification includes the Basic and Detail Engineering for prod-
uct drying, product storage and product truck loading at plant site. The final detail engineering
has to be delivered to GNRE-COMIBOL in March 2014.
Furthermore ERCOSPLAN delivered the final equipment data sheets, final equipment specifica-
tions and updated civil and electrical drawings at Milestone 4 on November 08, 2013 as agreed
on Gate 3 Meeting.
From November 13 – 15, 2013 an additional meeting in Erfurt took place. ERCOSPLAN held
presentations about the progress of works of all the involved departments.
ERCOSPLAN presented the final detail engineering (Milestone 5) at Gate 4 meeting in La Paz
on December 16. – 18, 2013.
Due to a contract modification, ERCOSPLAN furthermore provides the detail engineering for
drying section, product storage and truck loading. The revised detail engineering documents
including the contract modification will be delivered to GNRE-COMIBOL 90 days after finalizing
the main contract on March 14, 2014 and presented in La Paz subsequently.
Finally, it should be noted that the project manager belonging to ERCOSPLAN makes and de-
livers a monthly report which shows the progress of the project in all moment.
2.2 Database
ERCOSPLAN prepared a design base document for the project where all conditions by the
client and assumptions by ERCOSPLAN are listed. Assumptions were confirmed at
Gate 1 meeting. Conditions by the client are same as written in the contract. Furthermore
GNRE-COMIBOL submitted weather data and technical drawings regarding the location of the
plant site. Specific questions by ERCOSPLAN were answered almost promptly by GNRE-
COMIBOL via email. All information is considered in the following documents.
Page 54 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
ERCOSPLAN’s scope of works ends after dry standard product truck loading. Transportation of
dry standard product after truck loading is out of ERCOSPLAN’s scope of works.
During production of KCl 95, also NaCl is produced. This NaCl is envisaged to be stored on a
tailings pile. The tailings pile probably will be erected by GNRE-COMIBOL 500 meters to the
east of plant site. ERCOSPLAN’s scope of works ends with the conveyor belt for debrined tail-
ings at the border of plant site. The concept of erecting the tailings pile, the operation of the
tailings pile and necessary equipment for tailings pile is out of ERCOSPLAN’s scope of works.
During production of KCl 95, furthermore disposal brine is produced. It is envisaged to dispose
these brines into the salt lake. ERCOSPLAN’s scope of works ends with the pipes for disposal
brines at the border of plant site. The concept of disposing these brines, the operation of brine
disposal and necessary equipment for brine disposal is out of ERCOSPLAN’s scope of works.
Process water is required for operation of process plant. GNRE-COMIBOL delivered the chemi-
cal composition and ph-value of delivered process water at Gate 3 Meeting on 25th September
2013. GNRE delivers process water in sufficient quality and quantity into the process water
storage tank at plant site. ERCOSPLAN’s scope of work starts with the process water tank.
Page 55 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Heating media for building heating, drying plant and any other heating processes will be LPG
(liquefied petroleum gas). LPG will be delivered in sufficient quality and quantity by GNRE-
COMIBOL to plant site. ERCOSPLAN’s scope of work starts at the emptying flange of the LPG
tank.
Consumables for processing are chemicals for flotation, after treatment and flocculation. Fur-
thermore general consumables like working material, lubricants, etc. are delivered by truck to
plant site and stored in envisaged places. The delivery to plant site and storing of consumables
at plant site is out of ERCOSPLAN’s scope of work.
Page 56 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
3 Nomenclature
B 03 01 A/B . 1
Letter for production line (A, B or without letters if there is only one
plant line)
A Apparatus, machinery
As far as not classified in one of the following groups
B Vessel, tank, bunker, silo
C Chemical reactor
D Steam generator, gas generator, oven
F Filter apparatus, fluid filter, gas filter, screening apparatus,
screening machine, separator
G Gearbox
H Lifting device, conveying device, transporting device
K Column
M Electrical motor
P Pump
R Agitator, agitated tank, mixer
S Centrifuge
T Dryer
V Compressor, vacuum pump, ventilator
Page 57 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
W Heat exchanger
X Distributing device, splitting device, other devices
Y Drive device except electrical motor
Z Crushing machine, milling machine
The regulations of German standard DIN 19227-2 generally apply for the indication of measur-
ing and control points.
Regarding the subsequent letters I and R, the following is applied:
Subsequent letter I indicates the local indication of an analog measured value, subsequent
letter R indicates the transfer of an analog measured value to a control system (in normal case -
the PLS, for package units - the SPS). Therefore the letter sequence IR only appears it an addi-
tional local indication of measured data is required for transmitters.
The function of actuated OPEN/SHUT control valves (valves, ball valves, butterfly valves etc.) is
indicated with YV. Final position switches for tap position indication are indicated with GO fol-
lowed by the letters H for OPEN end position and L for SHUT end position.
Page 58 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
In case their separate presentation is required, control valves that are assigned to control cir-
cuits receive a function indication that consists of the code letter of the control variable and the
letter V for the actuator function. The measurement and control code is identical to the control
circuit code (for example: control valve PVB0902B-01 belongs to pressure control PRC-0001).
Remote-controlled control valves that are not assigned to a control circuit are indicated with
YC.
The measurement and control code numbers consist of:
LSA
B02-025
Letter for plant line (A, B or without letters if there is only one
plant line)
Double numbers with different first letters (not subsequent letters) are allowed.
Switching and alarm limit values of analog measured data have to be recorded in separate
lists. According to German standard, the code for measuring and control points has to be add-
ed by the subsequent letters A or S resp., limit values have not to be indicated.
Switching and alarm limit values of binary signaling devices have to be indicated clearly. The
measuring and control symbol – but not the measuring and control position indication - for eve-
ry limit indicators that generates an electrical signal has to be added by the relevant sign.
A manometer that is equipped with a lower and two upper switching or alarm limit indicators
receives the code PISA followed by the number; the letters L, H and HH have to be specified
next to the symbol in a smaller font type.
Following convention applies to the indication of single-signals from measuring and con-
trol points:
The signal names of analog input signals are formed by the functional letter of the measuring
and control point and the measuring and control number omitting the subsequent letters (with
the exception of C).
In case of speed or frequency of drives, analog feedback signals of frequency converters get
the functional letter S, otherwise the first letter E from measuring and control code (EU) is used.
Analog output signals are called like the corresponding input signals whereat an additional
secondary letter is inserted (for control valves: V, for set-point for frequency converter: W).
After the functional letter (L, P, F, …), the signals of the digital limit switch get the letter S as
code (but according to function also A or O) and, as far as required for distinction, the code for
switching status H, L, HH or LL. The position indicators at ball valves get the signal names
GOH plus a measuring and control number for the OPEN position and GOL plus measuring
and control number for the SHUT position. The operation signal of drives (main contactor ON
position) gets code NB plus measuring and control number and the common electrical fault
indication (over-current release, control fuse) the signal code NA plus measuring and control
number. Fault indications generated by other switch gears (e. g. frequency converters) get the
Page 59 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
code XA plus measuring and control number. An input signal that shows if a drive is switched
off on site or from PLS gets the code NU plus measuring and control number. Switch signals of
ball valves and drives are called Y plus measuring and control number. If ball valves have two
control pulses these are distinguished by secondary letters A (as code for input signal OPEN)
or Z (as code for input signal SHUT). That applies correspondingly for drives (YE for ON switch
signal; YA for OFF switch signal). Release and interlock signals respectively are named YF plus
measuring and control number.
If several signals of one measuring and control point have the same letter combinations ac-
cording to above described rules, they can be distinguished by a sequence number added to
the letters. In such a case, the sequence number is separated by an underline from the meas-
uring and control number (e. g. XA1_-01 and XA2_-01).
1
N.A. = Not Applicable
Page 60 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
A02-RL-025-SP-DN100-GFK/PP
RL for pipeline
SL for flexible line
SH for chute
Letter for plant line (A, B or without letter if there is only one plant line)
A02-S-025-SP-DN100
Page 61 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 62 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
4 Belonging Documents
Beside the report several documents are belonging to this detail engineering. The following
chapter gives an overview and explanation of all belonging documents.
Appendices which are associated with the contract modification, such as drying section, prod-
uct storage and truck loading, differentiate by “.1” after the appendix name.
Example: Appendix A2.1 for equipment list of contract modification (drying section, product
storage and truck loading)
The “Design Base Document” is the base of ERCOSPLAN’s work. It includes substantial re-
quirements to the processing plant, battery limits, boundary conditions, appropriated normative
as well as ERCOSPLAN’s assumptions.
The “Design Base Document” was created at the beginning of ERCOSPLAN’s work, presented
at the “Gate Meetings” and was confirmed by GNRE-COMIBOL.
The “Design Base Document” is attached as Appendix A1.
After calculating the process route and the designing of equipment, ERCOSPLAN made a pre-
selection of main equipment. Afterwards ERCOSPLAN sent inquiries for the main equipment to
suppliers which are familiar with the potash industry.
As response ERCOSPLAN received quotations for the specific equipment from the equipment
suppliers. The quotations are attached as Appendices Q. These individual quotations have to
be checked for up-to-dateness during equipment purchase phase by GNRE-COMIBOL and
appropriate equipment supplier.
The cost estimation for equipment was created under consideration of equipment quotations
sent by the suppliers and ERCOSPLAN’s data base. In this list the price for every main equip-
ment sorted into the belonging process section is easy to find.
The cost estimation for equipment is attached as Appendix G1 and G1.1.
Page 63 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
The cost estimation for pipes was created under consideration of price list (price per meter) of
pipe suppliers and ERCOSPLAN’s data base. In this list the price of pipes, sorted into the be-
longing process section and summed up to total piping length, is easy to find.
The cost estimation for pipes is attached as Appendix G2 and G2.1.
The cost estimation for valves was created under consideration of valves quotations sent by the
suppliers and ERCOSPLAN’s data base. In this list the prices of valves, sorted by process sec-
tion and the type of valve, are easy to find.
The cost estimation for valves is attached as Appendix G3 and G3.1.
The project schedule shows following process steps and its durations from the beginning until
the end of the project:
• Engineering phase
• Procurement / acquisition phase
• Delivery phase
• Building construction
• Civil construction
• Erection / assembly phase
• Commissioning / start-up phase.
Page 64 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
The “Block Flow Diagram” shows the complete process route as considered by ERCOSPLAN.
Each processing step is shown as block. Blocks are connected with arrows to define inputs,
outputs and the direction of flow.
The “Block Flow Diagram” is attached as drawing A01.
The “Equipment List” shows all main equipment necessary for production at plant site. In this
list the item number, item name, basic description of the item and electrical energy consump-
tion of the item of every main equipment, sorted into the belonging process section, is easy to
find.
The “Equipment List” is attached as Appendix A2 and A2.1.
ERCOSPLAN has prepared “Equipment Data Sheets” for each main equipment. The “Equip-
ment Data Sheets” include more detailed information in comparison to the overall “Equipment
List”.
“Equipment Data Sheets” are attached as Appendix A3 and A3.1.
The “Drawing List” gives an overview about all technical drawings belonging to this Detail En-
gineering report.
The “Drawing List” is attached as Appendix A4.
Page 65 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
The “List of Instruments” shows all measuring equipment in the process necessary for produc-
tion at plant site and its specific parameters. This list sorted into the belonging process section.
The “List of Instruments” is attached as Appendix A5 and A5.1.
ERCOSPLAN has prepared “Equipment Specifications” for each main equipment. The “Equip-
ment Specifications” include detailed information about main equipment necessary for produc-
tion at plant site. With these documents in addition to the “Equipment Data Sheets” GNRE-
COMIBOL is in the position to make specific inquiries to equipment suppliers respectively pre-
pare the public bidding phase.
The “Equipment Specifications” are attached as Appendix A6 and A6.1.
The “General Inquiry Specification” is the central and general document necessary for making
inquiries to equipment suppliers.
The “General Inquiry Specification” gives an overview about boundary condition around the
equipment, necessary to know for designing the equipment.
The “General Inquiry Specification” is attached as Appendix A7.
The “Pipes List” shows all main pipes installed in the processing plant. Pipes are listed belong-
ing to the process sections.
The “Pipes List” is attached as Appendix A8 and A8.1.
The “Valve List” shows all valves installed in the processing plant. Valves are listed belonging
to the process sections.
The “Valves List” is attached as Appendix A9 and A9.1.
Page 66 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Applied pipes at plant site are separated into different pipe classifications according to purpose
and application of pipes.
The “Pipe Classification” is attached as Appendix A10.
The “Equipment Supplier List” shows a selection of recommended equipment suppliers sorted
by the type of main equipment. Recommended suppliers possess long term experience and
various references in the potash industry.
The “Equipment Supplier List” is attached as Enclosure E1.
“Piping and Instrumentation Diagrams” (PIDs) created by ERCOSPLAN show detailed infor-
mation about the piping of the process flow together with the installed equipment and instru-
mentation.
The entire process is classified into two production lines (Line A&B) and several process sec-
tions. Hence, the single production lines and process sections are shown separately on PIDs.
Furthermore ERCOSPLAN added a table of all volume and mass streams shown on the PID.
PIDs are attached as drawings A 1350 – A 1374.
Page 67 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
“Piping Isometric Drawings” are generated for all main pipes necessary for processing. Main
pipes are pipes with a diameter > DN 100.
“Piping Isometric Drawings” show the details necessary for manufacturing and installing the
pipe.
“Piping Isometric Drawings” are attached as drawings A 4000 - A 4321.
4.4.1 Appendices
Appendix E1 includes all electrical details for the electrical energy consumer of the project.
Appendix E2 includes the electrical energy demand calculation, calculation of the power and
number of the necessary transformer.
Appendix E3 includes the calculation of the utilized capacity power of the transformer.
Page 68 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Appendix E8 is basis for the programming of the automation system. The document includes:
• List of all control circuits at the KCl plant
• Equipment measurement value logging
• Control device
• Description of the control process.
Appendix E9 is also basis for the programming of the automation system and includes:
• List of all interlocking requirements at the KCl plant
• Description of safety interlocking requirements
• Description of technologically-related requirements.
Page 69 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Appendix E10 is basis for the programming of the automation system as well and comprises
• Input contacts to the automation system
• Output contacts from the automation system to other control equipment.
Appendix E11 includes all results of the short circuit calculation which are represented in a sin-
gle line diagram of the power supply system.
Appendix E12 includes all results of the voltage drop calculation which are represented in a
single line diagram of the power supply system.
Appendix E14 includes all connection cables for following parts of the electrical system:
• Fire protection system
• Video control system
• Access control system
• Communication system.
Page 70 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Appendix E15 includes all technical requirements for the rooms of the power station:
• Floor load
• Liability of electrical power loss
• Necessary illumination level
• Minimal and maximal temperature inside the rooms.
Appendix E16 includes all cables for the connection of central control equipment for the auto-
mation system.
4.4.2 Drawings
Drawings E2000 – E2005 present the overview diagrams and assembly plans of the middle
voltage level (24.9kV, 6kV).
Drawings E2011 – E2038 present the overview diagrams and assembly plans of the 0.69kV
MCC (Motor control center).
Page 71 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Drawings E2071 – E2088 present the overview diagrams of 0.4kV main switch gear and the
0.4kV sub-distribution panel.
Drawings E20101 –E2106 presents all installation points of the electrical energy consumer.
Drawings E2121 – E2126 present the main cable trays on each platform of the production plant
and inside the power station.
Drawings E2201 – E2210 present the installation points of lightings and sockets on each plat-
form of the production plant, inside the power station and the outside facilities.
Drawings E2301 – E2351 present the wiring diagrams, terminal connection tables and assem-
bly plans of all control cabinets.
Drawings E2353 – E2386 present detailed wiring diagrams for all gear types within the techno-
logical process.
Drawings E2401 – E2404 present the installation points for the automation equipment on each
platform of the production plant.
Page 72 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Drawings E2501 – E2504 comprise the arrangement drawings for the power and generator sta-
tion.
Drawings E2501 – E2571 comprise all technical details for the lightning protection.
Drawings E2601 – 2671 comprise block diagrams and installation drawings for plant sections
communication, fire protection system, video control system and access control system.
Page 73 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
5 Property Description
The Salt Lake is found at an altitude of 3,653 meters above sea level and has an area of 10,000
km². It is the largest salt lake in the world en one of the most important reserves of various
chemical components.
The Uyuni Salt Lake basin forms part of the Southern Altiplano, bordering on the north with the
Intercalar mountain range, on the south by the San Cristóbal mountain range, on the east by
the Cordillera Oriental, and on the west by the Cordillera Occidental. In the eastern section are
found the peaks Jatum Mundi (5,348 m), Choque Huarani (5,388 m), Cuzco (5,386 m), Cosuño
(5,243 m). The Cordillera Occidental consists of a volcanic chain with a predominant north-
south direction and a maximum altitude of 5,600 m. The Salt Lake is 545 km from La Paz, 315
km from Oruro and 230 km from Potosí, which represents a justification for the investments
planned in transport infrastructure.
5.1 Location
ERCOSPLAN received maps from GNRE-COMIBOL (12.02.2013 / 08.04.2013 via mail and
05.06.2013 via email). Furthermore GNRE-COMIBOL handed over maps at the meeting in La
Paz 22.01.-24.01.2013. These maps are showing location of plant site and evaporation ponds
with coordinates. The area for erecting the production plant and storages will be approx. 500 x
500 meters. An extension of 500 x 500 meter area is possible, e.g. due to the huge buildings
and limited incline angle of conveying equipment. Evaporation ponds are located in the north
of plant site area.
The area has a relatively stable average temperature with a peak of 21 °C (70 °F) from Novem-
ber to January and a low of 13 °C (55 °F) in June. The nights are cold all through the year, with
temperatures between -9 and 5 °C (16 and 41 °F). The relative humidity is rather low and con-
stant throughout the year at 30 to 45 %. The rainfall is also low with1 to 3 mm (0.039 to 0.12)
per month between April and November, but it may increase up to 70 mm (2.8) in January.
However, except for January, even in the rainy season the number of rainy days is fewer than 5
per month.
GNRE-COMIBOL provided ERCOSPLAN with following climatic data in digital form (on CD-R):
• Relative humidity
• Precipitation
• Temperature
• Wind speed.
Page 74 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
These data represent measurements in the time from February 08, 2010 to December 16, 2012
at different locations (Coipasa, Piscinas de Evaporacion, Planta Piloto, UOP).
The extreme values are shown in Table 3.
Page 75 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Table 4 Overview of the Precipitation in mm from 2010 to 2012 (Data provided by GNRE-COMIBOL)
Piscinas de Evaporacion
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Sum/Year
2010 20.2 1.7 0.8 12.9 6.8 42.4
2011 54.3 142.1 27.4 6.1 3.6 11.6 3.3 53.3 301.7
2012 43.6 89.2 29.6 5.2 967.7 1135.3
Coipasa
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Sum/Year
2010 65.8 65.8
2011 192.3 535.9 96.3 11.2 21.1 39.1 4.1 136.4 1036.4
2012 188 242.6 173.7 20.3 624.6
Planta Piloto
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Sum/Year
2010 65.8 65.8
2011 192.3 535.9 96.3 11.2 21.1 39.1 4.1 136.4 1036.4
2012 188 242.6 173.7 20.3 624.6
UOP
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Sum/Year
2010 26.7 3.6 1.8 0.1 1.2 33.4
2011 48.3 108.7 32.1 4.5 4.4 68.9 266.9
2012 63.8 106 37.2 5.4 5 217.4
Page 76 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
For the plant site area a geological report including expert opinions is available. The following
soil layers were detected:
1. Salt crust thickness = 0.25 m
2. Peat clay thickness = 0.55 m
3. Rock salt I thickness = 4.30 m
4. Clay thickness = 18.35 m
The permanent brine level is close to the bottom edge of the salt crust layer.
For foundation of buildings and facilities layer 1 and 2 are not suitable. These layers have to be
cut and replaced by a good bearing material. The next layers are suitable for founding of all
buildings and facilities and the infrastructure.
For more information see the soil report (ENCLOSURE 3).
Page 77 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
6.1 General
The exploitation of the Salar de Uyuni will be carried out by salar brine processing. Hence, at
first there is saline (KCl containing) brine available for processing to a KCl product (MOP) with
95 % purity (equates a K60 product). The salar brine is led through a multistep solar evapora-
tion system. In the first evaporation pond water is evaporated until KCl saturation of the brine is
reached. Contemporaneously sodium chloride crystallizes. At the time when the brine is satu-
rated with KCl, the brine is pumped to a second evaporation pond where also water is evapo-
rated and a material crystallizes that mainly consists of NaCl and KCl. Regarding improvement
of total plant recovery rate the surplus reclaim brine from processing plant should also subject-
ed to a solar evaporation pond in order to recover the contained KCl as a KCl/NaCl bearing
crystallisate. These crystallisates are transported to the processing area. ERCOSPLAN is as-
signed to plan and design the processing of this material via flotation to a MOP product. The
dried MOP product will have a purity of at least 95 %. Following the flotation process is de-
scribed.
The process can be grouped in following sections:
• Crystallisate debrining
• Crystallisate treatment
• Rougher flotation
• Cleaner flotation and leaching
• Scavenger flotation
• Reclaim brine handling and tails handling
• KCl product debrining and drying.
The production capacity is envisaged with 700,000 t/y of MOP. It is assumed that the produc-
tion plant is run continuously 24 hours a day, seven days a week in total 7,500 hours per year.
The remaining time of one year is for scheduled maintenance.
By the reason that no data from the pilot plant at the Salar de Uyuni are available for ERCO-
SPLAN, the following process design (process description, block flow diagram and mass flow
balance) is only based on "test-size scale" test work (batchwise, 4 l volume flotation cell) with a
crystallizate from the evaporation of natural salar brine in evaporation ponds at the envisaged
plant area. When the existing pilot plant at the Salar de Uyuni run continuously, the gathered
data from its operation have to be compared with the test work results and the process design
should be refined if necessary.
Page 78 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
The analysis of the potash containing wet crystallisate from the second salar brine evaporation
pond that shall be processed to a MOP product shows following average composition:
KCl 27.04 %
K2SO4 0.30 %
NaCl 69.98 %
MgCl2 0.18 %
MgSO4 0.25 %
CaSO4 0.34 %
Insolubles 0.08 %
H2O 1.85 %
Lithium 31.27 mg/kg
Boron 62.49 mg/kg.
The analysis of the adhered brine at the crystallisate shows following brine composition:
KCl 39.20 g/l
NaCl 31.20 g/l
LiCl 23.76 g/l
MgCl2 237.00 g/l
MgSO4 67.40 g/l
CaSO4 bld.
H2O 899.7 g/l.
The expected crystallisate composition from surplus reclaim brine evaporation pond is as fol-
lows:
KCl 27.17 %
K2SO4 0.00 %
NaCl 69.02 %
MgCl2 0.00 %
MgSO4 0.00 %
CaSO4 0.51 %
Insolubles 3.30 %
H2O 0.00 %.
Page 79 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
The expected composition of the adhered brine at the crystallisate from surplus reclaim brine
evaporation pond is as follows:
KCl 89.46 g/l
K2SO4 6.91 g/l
NaCl 179.35 g/l
LiCl 7.27 g/l
MgCl2 72.53 g/l
MgSO4 23.19 g/l
CaSO4 2.00 g/l
H2O 876.75 g/l.
For the average production amount of 700,000 t/y MOP a representative process calculation
was accomplished considering the above mentioned crystallisate and adhered brine composi-
tion. Following amounts refer to this representative calculation. For the production amount of
700,000 t/y MOP, an amount of 3.4 mtpy wet crystallisate from second evaporation step and
0.7 mtpy wet crystals from surplus reclaim brine evaporation pond are required for the pro-
cessing plant. This corresponds to a production capacity of 93.3 t/h saleable product MOP and
for that 452.7 t/h wet crystallisate from second salar brine evaporation pond and 89.7 t/h wet
crystallisate from surplus reclaim brine evaporation pond are required. The KCl recovery rate of
the designed process route has been calculated to be 82.35 %.
The expected composition of dried product is as follows:
KCl 95.44 %
NaCl 3.79 %
MgCl2 0.01 %
CaSO4 0.00 %
Insolubles 0.56 %
H2O 0.2 %.
The flotation process requires certain amounts of water and produces certain amounts of saline
water (saturated with KCl and NaCl). In this case the surplus saline water (surplus reclaim
brine) is led to a surplus reclaim brine evaporation pond and a part of the contained KCl and
NaCl can be recrystallized and led to the flotation plant feed again. Here the advantage is that
most of the contained KCl in the surplus reclaim brine is recovered.
Besides the KCl product, also residue materials accumulate during processing the raw ore.
This residue materials are discharged from the process as wet salt (wet tailings). The residue
material consists mainly of NaCl.
Page 80 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
For production of 700,000 t/y MOP approx. 2.13 mtpy of wet tailings arise from the process.
This corresponds to an amount of approx. 283.51 t/h of wet tailings.
Beside crystallisate from second salar brine evaporation pond and crystallisate from surplus
reclaim brine evaporation pond, a main feed component to the processing plant is water. The
net feed charge of water direct into the process is approx. 270 m3/h for the production of
700,000 t/y MOP. This corresponds to an amount of 2.05 million m3 water per year. A large
amount of process water, 177.8 m3/h, is used for cold leaching in order to reach the product
quality of MOP.
The processing concept is illustrated in the block flow diagram in Figure 1. Explanations are
provided in the following subsections.
Page 81 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
It is supposed that the crystallisates from the second salar brine evaporation pond and the sur-
plus reclaim brine evaporation pond have 15 % adhered brine. Due to the fact that this brine
has a magnesium chloride content of approx. 237 g/l which will negatively influence the flota-
tion processes, the crystallisates have to be debrined. The combined crystallisates will be de-
brined with centrifuges. Therefor the crystallisate is mixed with filtrate from the centrifuges in a
repulping tank to adjust the correct solid content for the centrifuge inflow. The centrifuges de-
water the crystallisate to residual moisture of 3.8 %. The dewatered crystallisate is led to the
second process step, the crystallisate treatment. The filtrate is clarified in a thickener. Under-
flow of the thickener is led to rougher flotation. The main part of the overflow is led back to the
repulping tank to adjust the correct solid content. The leftover of the overflow has to be dis-
posed of to reduce the magnesium chloride amount in the flotation process.
The second step of plant processing is the screening of the crystallized material. For flotation it
is essential to mill the feed material to a certain grain size for an optimal flotation result. By
screening the loading of the mill is reduced and the generation of much additional fines by mill-
ing of the fine raw material can be avoided.
Milling of the solid material is necessary in order to ensure an optimal flotation process. The
KCl crystals which shall be floated are mostly intergrown with other crystals mainly with NaCl,
the main component of the crude salt. To assure good contact of collector molecules with KCl
crystals during flotation the liberation of KCl crystals by crushing has to be ensured. The milled
material is mashed with reclaim brine.
From the repulping tank the suspension is conducted to wet screening. There, the solids are
divided in two fractions: overflow and underflow. The coarse overflow is subjected to wet mill-
ing and subsequently led back to wet screening. The solids in the fine underflow fraction have
the appropriate grain size below 0.8 mm and are conducted to the rougher flotation.
The rougher flotation is the first flotation step and occurs as sylvite flotation. Herein mass flows
are processed which contain approximately 20 – 30 % KCl in the solid. The KCl content of the
crystallisate from solar evaporation is approx. 27 %. Aim of the rougher flotation is to enrich the
KCl in one mass flow and to separate most of the non-KCl solids. The concentrate will have a
KCl content of around 55 % in the solid.
The rougher flotation concentrate is given to the cleaner flotation. Tailings of the rougher flota-
tion are given to the scavenger flotation.
Page 83 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
The cleaner flotation occurs as sylvite flotation. Mass flows which possess a relatively high KCl
percentage in the solids are given to the cleaner flotation for further enrichment of KCl in the
solid phase. The KCl content of the solids in the flotation concentrate will amount to 70 %. The
rougher flotation concentrate and scavenger flotation concentrate are led into the cleaner flota-
tion cells combined with an aqueous solution of flotation reagents and reclaim brine for ad-
justment of solid content in the feed suspension. Tailings of the cleaner flotation exhibit KCl
content in the solids of almost 30 %. This makes it appropriate for re-usage in the rougher flota-
tion. The cleaner flotation concentrate is subsequently leached with leaching water. KCl-dust
from drying is dissolved in the leaching water before it is used for leaching. Cleaner concen-
trate leaching is performed in two steps with that amount of leaching water which is necessary
for dissolution of most of the solid sodium chloride to reach the envisaged quality of the dried
product. In the first step of cold leaching the solids will be treated with low concentrated brine
from the second cold leaching step. Thereby a moderate increase of KCl content is achieved.
In the second cold leaching step the wet solid will be treated with leaching water. Thereby the
KCl content increases to approx. 96.3 % in the centrifuged solids, which finally results in the
envisaged product quality of at least 95 % KCl after de-brining and drying. The suspension
from leaching is then conducted to the product centrifuge for debrining.
The scavenger flotation is fed with the rougher flotation tails. Indeed the KCl content in the sol-
ids is relatively low but the amount is absolutely worthwhile to be recovered. The scavenger
flotation is also a sylvite flotation. The scavenger flotation concentrate is conducted to the
cleaner flotation process. The scavenger flotation tailings are subjected to the tails leach tank
where it is leached with process water to dissolve a certain amount of the remaining KCl.
Suspension from tails leach tank is thickened with hydrocyclones and thickeners. The thicken-
er overflow is re-used as reclaim brine, a NaCl and KCl saturated solution for mashing, trans-
portation and solid content adjustment in flotation processes. There are three main sources for
the reclaim brine, the overflow of the thickener prior rougher flotation, the overflow of the thick-
ener after first product cold leaching step and the overflow of the tails thickener. These over-
flows are led to an additional reclaim brine thickener to ensure that there are as less as possi-
ble solids in the reclaim brine. The underflow of this thickener is led to tails leach tank. Clarified
reclaim brine is permanently distributed to many different process parts. But there is more re-
claim brine generated than needed for the process. The surplus is discharged to the surplus
reclaim brine evaporation pond where the contained KCl and NaCl can crystallize again and is
then given back to the flotation process.
The tails thickener underflow is given on a belt filter for further debrining. The filtrate is led back
to the tails thickener. The filter cake is washed with process water to replace the adhered po-
tassium chloride rich brine. The remaining wet solid consists mainly of NaCl. With this mass
flow the main amount of NaCl and high amounts of insolubles are discharged from the pro-
cess. The solid tailings have to be stockpiled.
Page 84 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
The KCl product suspension from leaching is conducted to hydrocyclones to adjust the right
solid content for feed into the product centrifuges. In the product centrifuges the product is
further debrined up to a remaining water content of max. 6 % in the wet solid. The filtrate is giv-
en into first step of cold leaching. The de-brined solid is then led to a dryer and dried to mois-
ture of 0.2 %. Dust from the drying is dissolved in cold leaching water and so reused in the
process. Dry solids are led to product storage. The dried product is led to the product treat-
ment (anticaking mixing vessel), where it is treated with an aqueous solution of Potassium Fer-
rocyanide and Sodium Chloride to avoid product caking.
The following Table 5 presents the calculated mass flows of the process which are shown in
the process flow scheme in Figure 1. The following mass flow numbers are not used in the
process calculation: 15, 19, 20, 23, 24, 25, 26, 52. During progression of process development
these mass flows were omitted.
The numbers in the shown mass balance are calculated values. Due to the fact that this is an
iteration process by several thousands of calculation steps, it is normal that there will be slight
changes in the single numbers within every iteration step. So it is not worrying if there are mar-
ginal differences, in the range of ± 0.2 %, between the numbers shown in the mass flow table
and the numbers shown e.g. in the datasheets and PIDs. For the same reason it is not worry-
ing, that there are marginal differences in the whole mass balance between the respective de-
sign work milestones.
The mass flow table refers to 7,500 operating hours per year. The MOP production amounts
700,000 t/y. This means approx. 93.34 t/h of saleable product.
Page 85 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 86 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 87 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 88 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 89 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 90 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 91 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 92 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 93 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 94 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 95 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 96 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 97 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 98 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Page 99 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
to
71
Repulping b) Water for Flocculant 95 kg/h 0.096 m³/h
Thickener
a) Collector 31 kg/h
Reagents b) Water for Collector 1,505 kg/h 1.540 m³/h
c) Hydrochloric Acid (37%) 12 kg/h 9.89 l/h
to
18
Scavenger d) Frother 12 kg/h
Flotation e) Water for Frother 813 kg/h 0.814 m³/h
f) Reclaim Brine for Frother 11,528 kg/h 19 kg/h 9.296 m³/h
a) Collector 34 kg/h
b) Water for Collector 1,658 kg/h 1.696 m³/h
Reagents c) Hydrochloric Acid (37%) 13 kg/h 10.89 l/h
37 to
d) Frother 10 kg/h
Cleaner Flotation
e) Water for Frother 640 kg/h 0.640 m³/h
f) Reclaim Brine for Frother 0 kg/h 0 kg/h 0.000 m³/h
a) Collector 63 kg/h
b) Water for Collector 3,065 kg/h 3.136 m³/h
Reagents c) Hydrochloric Acid (37%) 24 kg/h 20.13 l/h
50 to
d) Frother 21 kg/h
Rougher Flotation
e) Water for Frother 1,380 kg/h 1.381 m³/h
f) Reclaim Brine for Frother 19,564 kg/h 32 kg/h 15.777 m³/h
Sodium
Carbonate
82 to Na2CO3 5 kg/h
Anti Caking
Reagent Mixer
to
Application c) Na2CO3 5 kg/h
In flotation processes always certain reagents are used for separation of substances and
therefore, for Sylvite flotation process several reagents are required, too. The most essential
reagent is the collector. The collector molecules adhere to the KCl crystals and effect the
accumulation of the KCl in the concentrate. Additionally, also frothers and stabilizer oils are
used for flotation. These reagents are responsible for formation of a stable froth on the liquid
surface in the flotation cell. Moreover, further reagents are used such as flocculants for op-
timal settlement of solids during thickening.
Requisite for Sylvite flotation is a collector which will be in every case an organic amine. Typ-
ical products are for example Armeen® from AKZONOBEL or Genamin® from CLARIANT. In
this case we used for the testwork Genamin SH 100 from CLARIANT. It can be expected that
approx. 280 g of collector are needed per ton processed raw ore. It is recommended to
have approx. 130 t of the collector reagent in stock. The wet tailings can contain 20 – 25 g/t
collector.
Hydrochloric Acid is always added to a Sylvite flotation because it is necessary for formation
of alkylammonium ions from the collector amine which is the particle interacting with the
Sylvite crystals. It can be expected that approx. 90 ml conc. Hydrochloric Acid are needed
per ton of processed raw ore. It is adequate to keep approx. 41 m³ of the Hydrochloric Acid
in stock. The Hydrochloric Acid will be discharged as Chloride salt with the Alkylamine col-
lector (as alkylammonium chloride salt).
For optimal flotation process a frother agent is needed. This will be an organic alcohol, e. g.
a polypropylene glycol. There are several stabilizer oils which are used for Sylvite flotation.
In this case we used for the testwork MIBC from AKZO NOBEL. It can be expected that ap-
prox. 95 g of frother reagent are needed per ton of processed raw ore. It is adequate to
store the frother reagent with an amount of approx. 43 t. The frother is mainly contained in
the adhering brines after flotation and thus in the process brines. It is discharged from the
process with the wet tailings. It can be assumed that the frother is contained with 20 – 25 g/t
in the wet tailings.
Which reagents will be used for Sylvite flotation has to be decided finally in large scale test
works (pilot plant operation). There is a wide variety of collector and frother reagents and
which combination of reagents is in this case most appropriated for the raw ore will be a
result of these test works.
In order to ensure a fast and effective settlement of fine particles flocculating agents are
used, which often is polyacrylamide. It can be expected that approx. 1.5 g flocculant are
needed per ton processed raw ore. It is recommended to have approx. 1 t of the flocculant
in stock. Nearly all of this flocculant will be discharged with the wet salt tailings, hence 5 –
10 g per ton of wet tailings are expected to be disposed.
In order to avoid product caking, Potassium Ferrocyanide and Sodium Chloride are used for
final product treatment. It can be expected that approx. 120 g Potassium Ferrocyanide and
50 g Sodium Chloride are needed per ton product. It is recommended to have approx. 10 t
of Potassium Ferrocyanide and 5 t of Sodium Chloride in stock. Nearly all of this anticaking
reagents will be discharged with the wet product.
Page 110 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
7 Production Facilities
Production facilities at plant site are in general:
• Bottom dump truck loadout and further transportation to wet salt storage
• Wet salt storage with afterwards iron / non-iron metal detecting, lump crushing and
further transportation to process building
• Processing plant for producing MOP
• Tank farm for reclaim brine and process water with pumps and thickeners.
Remark: For producing saleable MOP it was mandatory to add following facilities:
• Product drying section (as extension of processing plant)
• Product storage
• Product truck loading.
Processing plant is designed as two production line operation. Production lines are called
“Line A” and “Line B”. Regarding the capacity and type of equipment production lines are
similar. Advantage of a two line production is the guarantee of 50 % production even if there
is on line disturbed.
Processing plant consists of following technological process sections:
• Wet screening and milling
• Rougher flotation
• Cleaner flotation
• Cold leaching and product dewatering
• Scavenger flotation
• Tails process
• Compressor plant
• Reagent dosing plant
• Rinsing water system
The building height will be in average approx. 30 meters. The highest part of the building will
be approx. 36 meters. The building consists of two areas, one for production line A and a
second for production line B. These both areas are connected by a free passage for repair
and maintenance reasons.
Five overhead cranes are installed above selected areas of process building to ensure hoist-
ing of huge equipment in case of repairs and maintenance. One additional overhead crane
is installed above both rod mills.
KCl plant has to be designed to produce 700,000 t/y of MOP (KCl 95).
Design safety factor applied to the production rate will be 15 % in minimum. ERCOSPLAN
considered a design safety factor of 20 %.
Operation time of KCl production plant will be 7,500 hours per year. Remaining time is en-
visaged for maintenance and repairs. KCl plant will operate 24 hours a day.
As first step of the engineering ERCOSPLAN designs the process and customizes a process
calculation. Due to this process calculation ERCOSPLAN knows about mass, volume
streams and all other relevant parameters all over the process.
Under consideration of all the parameters ERCOSPLAN’s experts estimate the main equip-
ment by use of long lasting experience in potash processing and also ERCOSPLAN’s data
base.
Parallel to this, ERCOSPLAN’s estimation is confirmed by the knowhow of contacted suppli-
ers of potash equipment.
Necessary parameter for designing of all major equipment can be found in the equipment
data sheets (Appendix A03) and in the equipment specifications (Appendix A06).
Pipeline for process water (average temperature 12 … 18 °C) and power line for electrical
energy comes from West direction into plant site area in sufficient quality and quantity. Bat-
tery limit for process water used in the process is the filling flange of process water tank.
Solid and liquid disposal from processing will be transferred by belt conveyor and pipeline
into East direction (distance approx. 500 m) out of plant site area.
Battery limit for LPG as heating media for building heating and drying section is the empty-
ing flange of LPG tank. On the layout plan a delivery area with LPG tank is envisaged.
7.3.1 Road
Plant site is accessible on public roads by huge vehicles (e.g. 20 tons trucks). A map show-
ing road connections to plant site from Oruro City was delivered by client.
For processing at plant site approx. 300 m³/h of process water are required. Process water
is delivered in sufficient quantity to plant site by pipe line.
Process water is mainly required to keep the amount of flotation brine constant as part of
this brine has to be disposed of to keep the MgCl2 content low.
Process water temperature is in a range from 12 to 18 °C.
For staff potable water is required. The estimated amount of potable water per person is
calculated with 120…160 liters per day. Due to the total number of persons at plant site, the
daily amount of potable water is estimated under consideration of the working shift factor
with approx. 30 m³.
Potable water is delivered in sufficient quality and quantity to plant site by GNRE-COMIBOL.
To keep the plant operational supplies have to be brought to the plant and stored accord-
ingly. Lubricants and other operational consumables are packed in adequate packages and
delivered to the production site via truck. All these are stored in provided storages on the
production site.
The complete industrial complex on Salar de Uyuni is supplied with electric energy from the
communal network.
Energy is transported to the industrial complex via 115kV overhead line. The electric energy
distribution in the area of the industrial complex Salar de Uyuni starts from a distribution
station (that still has to be realized) via local network with a voltage level of 24.9kV.
Two 24.9kV feedings are planned for the energy supply of the potash plant.
Since the 230kV overhead line and the local 24.9kV network will be only finished after erec-
tion of the potash plant, a reliable interim solution for the energy supply has to be realized
for the transitional period.
For that purpose, a generator power station has to be installed in the area of the KCl plant at
the same time as the erection of the flotation plant.
The plant capacity will be designed for average 700,000 t/y production.
In order to minimize unscheduled shutdown, critical equipment will be equipped with 100 %
installed spare, e.g. 1 operating and 1 stand-by.
This applies to critical process equipment identified as such on the PFD’s and P&ID’s. Criti-
cal process devices will be equipped with by-pass facilities.
The specific capacity for each section and equipment is mentioned in the process calcula-
tion and in the single equipment data sheets and equipment specifications.
The product storage and all conveyor belts are protected by automatic dry chemical sys-
tems discharging at the head end of the conveyor belt.
Adequate clearances shall be made around mechanical equipment to ensure no interfer-
ence during detail design phase, in the event that final selected equipment varies dimen-
sionally compared to that used prior to equipment purchase.
All plant equipment and materials shall be new and of best quality. No welding, fitting or
plugging of defective parts are permitted without prior written approval by the engineer.
All equipment and materials shall be suitable for the specified general site conditions and for
any specific conditions of exposure to dust, temperature variations, moisture and humidity
as specified in the individual technical specifications and drawings. The equipment shall
function reliably and achieve the specified performance throughout the specified range of
the above conditions.
Design service factors for all equipment shall equal or exceed such factors as are specified
in the appropriate technical specifications. These factors shall take into account duration
(i.e. intermittent, 12 hours, 24 hours, duty, etc.) and the nature of the loading (i.e. steady,
surge, reversing, shock, etc.).
Equipment selections shall be based on the maximum design loading conditions taking into
account the appropriate service factor.
The make and model of all components shall be such that replacement components are
readily available and shall include all wearing and small mechanical parts, valves, piping,
fittings, instruments, etc.
Selection of component parts shall be standardized to optimize the requirement for stocking
spare parts. This principle shall be applied to large components and assemblies of compo-
nents to the best possible advantage.
All equipment, equipment parts, piping with a temperature of more than 45 °C are provided
with a protection against direct contact by the personnel.
Provision shall be made for the reduction of vibration transmitted to the covers and cladding
of any equipment or any structure that is liable to radiate noise due to the vibration.
All items of equipment weighing more than 40 kg shall be provided with a convenient ar-
rangement for slinging or handling during maintenance.
King lugs shall be provided and located so that the equipment can be lifted in balance with-
out the use of wrap around slings.
Instruction plates, name plates and labels shall be fitted to all equipment requiring identifica-
tion and instructions for operation. Where possible, they shall be fitted to equipment before
packing for transit. Where this is not practical they shall be supplied loose for fitting during
erection, but great care shall be taken in identification and packing to minimize the chance
of misplacement or loss.
The construction, location, size and engraving of all nameplates and labels shall be such
that they are easily readable from equipment operation levels. Materials used for nameplates
and labels that remain as part of the permanent work shall be corrosion resistant.
Electric motors and electrical equipment shall be located above the maximum flooded level
of the dyked area.
Ladders shall not be used where frequent access is required.
Stairs shall be designed with a minimum width inside stringers of 750 mm. The optimum
riser to tread ratio shall be 7.5:10.
All ladders, stairs, handrails and platforms shall be designed in accordance with the OSHA
and applicable codes.
In high corrosion area, such as in potash processing, the material of construction of equip-
ment shall be selected to be compatible with the process solution, Titanium, Monel, thermo-
set material (FRP), thermoplastic material (PVC, CPVC, PP, HDPE, Kynar, Teflon, etc.) will
be considered.
7.4.1.4 Welding
All welding shall be in accordance with DIN, EN, CSA W59 or ASME IX or equivalent.
All welders shall be qualified for the type of welding they are engaged.
Gears and gear type speed reducers shall be of standard manufacture, designed, rated and
fabricated in accordance with the latest standards published by the DIN or American Gear
Manufacturer's Association (AGMA) or equivalent.
Speed reducers shall be supplied complete with inspection covers, multi-labyrinth seals or
double lip seals, filtered air breathers, oil drain plugs, and oil dip sticks.
Chain drives shall be designed and supplied in accordance with EN or ANS1 Standard for
Transmission Roller Chain and Sprocket Teeth.
Adequate adjustments shall be available to install and take up chain slack. Where take up
allowance is not possible, due to fixed sprocket centers, an adjustable chain wheel idler
shall be fitted.
The minimum chain drive service factor shall be 1.5.
All sprockets shall be attached to the shafts using "QD" type hubs with standard keyway.
V-belt drives shall be designed and supplied in accordance with RMA standards or equiva-
lent. Belts shall be provided in matched sets.
The arc of contact on the smaller sheaves shall be at least 120". Belt sheaves shall be accu-
rately balanced.
Drive motors and intermediate speed reducers shall be mounted on pivoted bases or slide
rails, allowing sufficient adjustment for correct belt tensioning. Bases shall incorporate jack-
ing screws with lock nuts.
Page 118 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
7.4.1.8 Couplings
Couplings shall be of the horizontal split cover flexible type unless otherwise approved.
The minimum service factor shall be 1.5 based on the motor nameplate rating.
The tolerance limits and fits of shafts and coupling bores shall be in accordance with the
coupling manufacturer's recommendations. Light interference fits without set screws over
the keyways are preferred.
Fluid couplings shall be fitted to the motor shaft of conveyor drives and other mechanical
equipment only where designated by the Engineer.
Fluid couplings shall be of the delayed fill type to provide soft starting capabilities. All fluid
couplings shall be provided with thermal trip plugs and limit switches to prevent oil losses.
Do not use lubricated coupling for low speed shaft (less than 1,500 rpm).
7.4.1.9 Bearings
For arduous duties and continuous service, self-aligning double row spherical roller type
bearings with seals on both sides are preferred.
Ball bearings may, subject to the approval of the engineer, be acceptable for lighter duties.
Shafts supported by two or more bearings shall have bearing housings capable of accom-
modating expansion and contraction with only one bearing being fixed.
Where brinelling of rolling element bearings could occur (e.g. equipment subjected to vibra-
tion while stationary), plain bearings with non-ferrous bushes or linings (e.g. gun metal,
phosphor bronze, white metal, etc.) should be provided. However, the supplier may submit
alternative types of bearings to the engineer for approval.
Provision shall be made for removing the bearing by split pillow blocks, removable end co-
vers on housings, etc.
Pillow blocks shall be mounted to avoid direct static tension loads on the holding down
bolts and cap bolts. However, the pillow block units shall be designed to withstand any form
of loading imposed upon them during normal operation of the plant.
Pairs of pillow blocks shall be fully self-aligning with one "fixed" and one "free" type for each
shaft.
When pillow blocks are mounted at shaft ends, covers shall be supplied.
Plain bearings are not preferred, but if used, they must be designed to have adequate oil
film lubrication and the bearing length should be at least one and a half times the diameter.
On vertical shafts, thrust and guide bearings shall be provided.
7.4.1.10 Seals
Seals for shafting shall be of the heavy duty "rubbing" type (i.e. felt or spring steel washers
and lip seals), or the "non-rubbing" type (labyrinths) suitable for dusty and wet environ-
ments. Seals shall be selected for each application so as to preclude the ingress of dust,
moisture and other contaminants and to retain lubricants (grease or oil) used within the
housing.
Felt seals shall not be used when dusty and abrasive materials are to be handled. Their use
shall be restricted to shafts with peripheral speeds less than 3.65 m/s and temperatures be-
low 100 °C.
Lip seals, either in rubber or plastic, shall be used for peripheral speeds in excess of
3.65 m/s. The double lip type is preferred.
For high temperature applications, suitable special materials (e.g. Teflon, carbon, etc.) shall
be used for the seal surfaces.
Where corrosive gases or liquids are being handled, seal materials shall be corrosion re-
sistant.
Where wet and extremely dirty conditions prevail, a thrower shall be provided additionally to
seals.
A thrower shall also be provided above the upper bearing seal on all vertical shafts.
7.4.1.11 Lubrication
Provision shall be made for suitable lubrication wherever necessary to ensure smooth oper-
ation and freedom from undue wear.
Gearboxes and oil baths shall be provided with filling and drain plug or valves, both of ade-
quate size and shall be provided with an approved means of oil level indication, e.g. dip-
sticks or constant level oilers.
Lubrication of ball/roller bearing pillow blocks may be by:
• Grease packing for life
• Periodic grease lubrication by nipple
• Oil lubrication
• Periodic automatic lubrication.
All hazardous revolving or reciprocating parts not guarded by the frame of the machine or
by remote location shall be guarded in conformance with the part 1910219, sub-part "O”,
Page 120 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
"Machinery and Machine Guarding" of the Occupational Safety and Health Standards of the
OSHA or equivalent.
Base plates shall be robustly and rigidly constructed generally of fabricated steel or cast
steel.
Mounting pads and base plate feet shall be machined true and parallel.
Shims shall be provided for final adjustment of alignment. All packing pieces and shims
shall have an effective loading area approximately equal to that of the foot.
Screw conveyors shall be designed and supplied in accordance with CEMA Standard 350 or
equivalent.
Screw conveyors shall be of heavy duty construction with minimum 4 mm trough plate
thickness fitted with angle flange and with trough supports independent from the end flang-
es.
The clearance between the flight and the trough shall be 12 mm.
Flights shall be made of abrasion resistant carbon steel, or hard surfaced if required, sec-
tionalized, minimum 5 mm plate.
Screw conveyor sizing shall be based on 30 % trough loading for granular non-abrasive
material and 15 % for fluidizing materials using the flow sheet tonnage per hour.
Trough end packing shall be externally mounted and easily replaceable.
The drag conveyor shall be of heavy duty type equipped with one or multiple inlets and mul-
tiple outlets.
The drag conveyor will be of horizontal or inclined, bottom flight conveying type.
Flights should be of rectangular type, driven by double strand chain for slug services.
The casing shall be rectangular with removable covers. The casing shall be dust tight and
weatherproof for outdoors installation and to prevent cross contamination.
The drag conveyor shall be sized to operate at less than 60 % of recommended maximum
speed.
The chain speed shall be limited to 0.15 m/s.
The chain shall be protected from the material flow as much as possible with deflector for
double strand chain in slug services
7.4.1.16 Chutework
All chutework and hoppers shall be structurally designed for full plugged operating condi-
tions of the material they are conveying.
Chutes and hoppers shall be fabricated from 6 mm minimum thickness steel plate suitably
stiffened and supported to deal with the loads and forces imposed on them.
All chutework and hoppers shall be structurally supported independently of equipment un-
less noted otherwise.
Unless otherwise specified or approved in writing by Engineer, all chutework and hoppers
shall maintain a minimum slope of 60° or better from horizontal.
7.4.1.17.1 General
• Shaft sealing
Shaft sealing in each application shall be as nominated on the relevant "Pump Data
Sheet", either:
– Packing with full flow gland, with PTFE lantern ring
– Packing with restricted flow gland, with metal lantern ring.
Replaceable shaft sleeves of hardened and ground, abrasion resistant alloy steel shall
be provided at the gland area where the duty demands it.
Mechanical seals shall be of single or double, used only for clean liquid services com-
plete with appropriate seal flushing as required. Single external mechanical seal may be
used for crystallizing fluid, only with written approval from the engineer.
7.4.1.18 Tanks
a) Mixing Tanks
b) Storage Tanks
Large storage tanks will be provided with one manhole on the side wall near the bottom lev-
el. One additional manhole will be provided on the roof of the tank for closed tanks.
Tanks larger than 15 m in diameter may require additional manholes in the side wall and/or
roof.
For classification of pipes applied in the potash plant please see Appendix A10.
The pipelines are described in the pipe classification (Appendix A10) that provides an over-
view on all pipelines required for the project and in the isometric drawings (A4002 ff.).
The planning of pipelines and pipeline routes is based on the basic engineering. The iso-
metric drawings indicate the course of pipelines for the fitting and installation companies but
do not substitute the installation planning. At any rate the executing companies have to
check the course of pipelines given in the isometric drawings for practicability and have to
arrange for the necessary pipeline elements. The material for supporting structures for pipe-
line elements is given as all-inclusive rate.
The pipelines of the plant serve for the transport of different media. According to their sub-
stances of content and the material requirements for pipelines and fittings, these media were
divided into different groups that have been provided with medium codes.
All pipelines have been uniformly planned with nominal pressure 10, even if the operating
pressures in part are clearly under that value.
All pipelines containing salt solutions or suspensions have to be laid with continuous slope
to the deepest point. At the highest points the pipeline has to be provided with ventilation
devices.
The suspension of pipelines is arranged at the pillars or platform structures of the particular
platforms. For that the pipeline installation companies possibly have to install additional
supporting structures to keep the maximum possible distances between supports and to
exclude line sway.
As part of the technological steel construction, relocation constructions for fittings have to
be provided by the pipeline construction companies. During installation, it is important to
pay attention to good accessibility of fittings and measurement instruments for operation
and maintenance. Attention should also be paid to the required build-in conditions of the
manufacturers for this equipment.
Secondary steelworks are necessary for erection and installing of technical equipment in the
process building and also for equipment belonging to the outside facilities.
After handing over of the final Detail Engineering report, GNRE-COMIBOL will start the pur-
chase phase of technical equipment. Due to the Bolivian regulations, GNRE-COMIBOL
needs to start the purchase phase with a public bidding. Due to the necessity of the public
bidding, GNRE-COMIBOL was not in the position to fix suppliers and type of the technical
equipment during ERCOSPLAN’s engineering phase, so that ERCOSPLAN had to make
assumptions. Hence, the chapter of “Secondary Steelworks” can only have a general char-
acter.
Remark:
Secondary steelworks for piping and piping construction is in the scope of work of the com-
pany which installs the pipes at plant site.
GNRE-COMIBOL needs to define an erection company for built up buildings and equipment
at plant site. Activities at plant site should follow the erection schedule of the erection com-
pany.
Maintenance shop
For erection and assembling it is necessary to build up a maintenance resp. work shop at
plant site at first. Work shop should be equipped according to the requirements of the erec-
tion company. Special tools for equipment (e.g. tools for centrifuges) should be included
with the equipment delivery.
Equipment storage / warehouse
During erection phase, delivered equipment should be stored dry in warehouse. Afterwards
the equipment should be installed step by step according to the installation schedule of the
erection company. A central place for storing empty packaging material has to be defined.
Assembling of huge equipment at plant site
Huge equipment is transported in segments to plant site. The maximum dimensions of sin-
gle segments must be according to Bolivian regulations for transportation of goods.
For assembling of huge equipment, which cannot transported in one piece to plant site, e.g.
thickeners, mounting areas resp. erection places have to be prepared at plant site. At
mounting areas huge equipment is then assembled.
For erection of huge equipment at mounting areas mobile cranes are necessary.
Assembling and installation of special equipment
General equipment should be installed by the overall erection company. For the assembling
and installation of special equipment (e.g. centrifuges), representatives of the supplier com-
panies are managing at plant site as supervisor.
Due to the extensive technology and continuous issues of the client at the Gate Meeting, the
project manager has decided to add a chapter regarding selected main equipment to the
Detail Engineering report.
Operation method
To reclaim the stored bulk material the reclaimer travels along a pre-selected working dis-
tance on rails arranged parallel to the stockpile with a constant boom inclination preset be-
fore starting the operation. At each end position the travelling direction is reversed after low-
ering the boom by one cutting depth. The material will be pulled down the face of the pile
and into the discharge chute and the impact roller table. The material is deposited onto the
reclaim conveyor.
The relocation of the reclaimer into a different working position is effected by manual opera-
tion with the booms retracted.
Modes of operation
The reclaimer can be operated in three different modes:
C) Automatic mode
In this mode the reclaimer is electrically interlocked with all receiving conveyors. All operat-
ing conditions are visually indicated. The reclaimer operates automatically until the stock-
piled material is completely reclaimed or until the operator stops the automatic operation.
Reclaiming in automatic operation mode requires the following pre-conditions:
• Pile is dressed by the operator (plan surface)
• Working range is set by the operator to limit the reclaimer travel.
Malfunctions
Malfunctions at any drive will be indicated as follows:
• Acoustical signal by means of alarm horn
• Signal lamp on the panel.
Component description
The reclaimer consists of the carriage made of sectional steel and sheet metal in welded,
torsion resistant and rigid design, with pedestals for the boom, rope pulleys and lifting winch
with connecting flanges for the bogies as well as pedestals for catwalk and stairway.
The travel mechanism, consisting of bogies, idler wheels, driven wheels, drive units, buffers,
etc., is fitted on the carriage. The reclaimer will traverse the pile on two runway rails, which
are arranged outside of the pile section. The booms are arranged laterally to the supporting
structure. The boom is supported by cables from the overhead suspension structure, and is
lifted and lowered by means of an electric hoist. The scraper booms are equipped with
chain drives, chain guides, scraper blades and hoist etc. Walkways and work platforms will
be provided for access to rope sheaves and hoists at top the suspension structure.
• Bevel gearbox with shrink disk, hollow-shaft connection and protective cover.
Scraper Blades:
• Scraper blades are bolted to the chain
• Blades will be equipped with hard faced cutting edges scraping teeth
• Blades will be bolted to the blade holders / chain for easy replacement and be
equipped with locknuts
• Blades will be designed for best flow characteristics.
Portal
The portal will be of the enclosed box-girder design. The portal includes all required beams
and brackets to fix and operate the boom, the operator's cabin as well as staircases, lad-
ders, catwalks and platforms to provide access for maintenance.
Travelling gear
The truck assemblies will be rigid structural steel frames of welded and bolted construction.
The assembly shall be connected to each leg of the carriage.
Fixed side:
• Head (cross) beam of sectional welded steel
• Double flanged wheels of cast steel with wheel shafts supported in antifriction bear-
ings
• Guide roller units supported in antifriction bearings to transfer the horizontal forces
into the rail on the fixed side only
• VFD controlled travel drives to regulate travel speeds and maintain synchronized (an-
ti-skew) positioning.
Floating side:
The travelling gear at the floating side consists of the same design as described for the fixed
side.
The only difference is the floating bearing between carriage and head (cross) beam to com-
pensate the rail tolerances and the deformation in the structure due to loads and tempera-
ture.
Operator's cabin
The operator's cabin with E-house is mounted on the operating platform of the portal and
accommodates the switching cabinets and the control panel.
The cabin will have wide safety glass windows giving the operator an unobstructed view of
the working area. The cabin will have adequate space for an operator and all required
equipment.
The cabin will be of sheet steel construction, complete with wall and ceiling insulation. The
operator’s seat shall have an adjustable backrest. The cabin will be complete with air condi-
tioning, heating and lighting.
Control system
The machine is controlled and monitored by a SIEMENS S7-300 programmable logic con-
troller (PLC). The PLC is located in the respective control cabin.
Lighting
Illumination to ensure safe working conditions will be provided at the portal and walkways.
Sufficient floodlights are mounted at top of the cabin or boom. All stairs and ladders are pro-
vided with sufficient illumination by means of fluorescent lighting.
The cabin, electrical equipment room and machinery platform will be illuminated by means
of fluorescent lighting fixtures.
Portable emergency hand lamps with battery chargers are supplied for operator cabin in
order to leave the machine in case of power loss.
Cables
Flexible cables will mainly be provided. Distinctive numbering or colors will identify multi-
conductor cables. A separate earth conductor will protect all electrical life parts.
7.4.2.2 Centrifuges
Machine Description
The construction and functional principles of the versatile screen worm centrifuge
KONTURBEX are shown in the sectional drawing. The drive and bearings, the rotating parts
in the fluid area and the solid matter discharge are arranged synoptically and maintenance
friendly.
The centrifuge is driven by V-belts. The rotational speed of the rotating parts is matched to
the process engineering requirements. The solid matter retained by the screen coating is
conveyed by the drum inclination and by a worm with slightly different rotational speed from
small to large diameter and there thrown off into the product housing. Thus with respective
drum inclination matched to the input feed material, various products of different origin and
consistency can be separated most successfully from the suspension fluid and, if neces-
sary, cleaned by washing.
A centrifuge gearbox ensures the required differential rotational speed between the drum
and the worm even in the case of high friction of the material on the screen coating. An over-
load fuse protects the gearbox to prevent damage. The gearbox and the bearings are
equipped with oil circulation lubrication, except for the H 200 which is equipped with a gear-
box with oil filling.
The machine and drive motor are connected as a unit to the substructure via rubber buffers.
Thus even large centrifuges do not require any special foundations or steadying masses.
The relative movement of the worm prevents unbalance due to uneven distribution of the
material in the drum. No product residues leading to unbalance remain in the machine after
switch off.
The screen drum is equipped - depending on the wear stress - with perforated sheets or
with wedge wire screens.
Construction
The name "screen worm centrifuge" specifies the chief features of this kind of centrifuge:
• Screening element for retaining the solid matter in the centrifuge drum,
• Feed worm for continuous feed of the solid matter.
The drum and the worm rotate in the same direction with high centrifugal force, but with a
slight mutual rotational speed difference resulting from the conveying effect of the worm.
The rotating parts, carried by the cantilevered shafts of the drive, project onto the product
area. This arrangement has the advantage of clear separation between the oil-lubricated
drive and the process space, so that only a fast running component has to be sealed
against the product housing.
An over dimensioned gearbox guarantees a constant speed difference between worm and
screen drum and thus constant results.
The centrifuge is driven by an electric motor with V-belts. Depending on the process re-
quirements, it is also possible to use frequency converters to achieve a variable control of
the main speed and/or differential speed. For purposes of vibration absorption, the machine
stands on rubber buffers.
The centrifuge features a wedge wire basket with special profile. Depending on the applica-
tion, a special screening plate can be used alternatively. In every case the screening ele-
ments can be replaced very easily.
If required, the centrifuge casing can be equipped with rinsing fittings that allow cleaning the
parts coming in contact with the product.
The largest fluid portion is separated on the small drum diameter in the area of low circum-
ferential speed and small centrifugal acceleration.
Towards the large diameter the small amount of residual fluid is flung off with increasing
centrifugal acceleration.
The rotating parts usually have conical shape. Inclination angles of the drum basket jacket
with respect to the rotation axis in the range from 10° to 20° have proved to be successful
because the friction coefficients of nearly all products correspond to the tangential values of
these angles.
With ideal choice of drum angle the solid matter slides without significant intervention of the
feed worm from the input area on the small diameter of the drum along a mantle line to the
large diameter and thus to the exit. The worm must perform a regulating function during the
residence time of the solid matter. In the initial phase it prevents too rapid slide down of the
wet solid matter and later, when the friction coefficient has become greater due to the cen-
trifugal drying, it pushes the solid matter towards the removal discharge.
Materials
The parts in contact with the product are made of special steel 1.4571 / 81 for normal appli-
cations. If necessary, a highly abrasion proof coating can be applied to the worm volutions.
Alternatively, higher material grades up to Hastelloy or Titanium can be used depending on
the process.
Due to the tendency of any centrifuge to convey air, a pressure difference of approx. 1 mbar
(=10 mm water column) will build up between filtrate and solid matter space, i.e. a very
small overpressure of approx. 1 mbar will occur in the filtrate space!
If it should be impossible to lead the air flow generated in the filtrate space outside, an air
recirculation is required in the solid matter space of the product housing.
This ensures pressure compensation between the filtrate space and the solid matter space
and prevents penetration of moisture fog into the solid matter space.
If the centrifuge is a gastight model (version K), a special sealing may cause internal pres-
sures of up to 0.2 bar. In this case, the gases and vapors can directly be exhausted sepa-
rately which prevents the dehumidified solid matter from getting moistened.
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
The compromise to be found in a specific case must ensure that the screening element will
keep clear during continuous operation because screen worm centrifuges work continuously.
• The production cannot be interrupted due to regular reverse flow rinsing processes or
the replacement of filter layers that are required on machines which work discontinu-
ously.
• The discharge area of the screen depends on spacing and dimensions of the apertures
and ranges between 4 % and 10 %.
Since the filtration resistance in the solid matter is in most cases higher than the residual flow
resistance the liquid must overcome on its way to the one or other screen aperture, the size of
the discharge area is of minor importance to the residual moisture. In combination with aper-
ture shape and aperture size, the discharge area of the screen is however decisive for the
amount of fine particles entering the filtrate and which quantities of liquid can be separated in
the feed zone, i.e. it determines the swallow volume of the machine.
Layer thickness
The dehumification process commences at the instant when the cake of solid matter has
formed. Dehumification of grainy solid matters is performed by filtration. Sufficiently large parti-
cle diameters and appropriate centrifugal forces permit a dehumidification by spontaneous
drainage of the liquid from the cake capillary system and, as far as possible, by the filtering
away of the cuneal and film liquid adhering to and enveloping the particles of solid matter.
The grain size and consistency of the solid matter substantially determine the extent to which
the layer thickness affects the residual moisture.
Very coarse incompressible solid matters facilitate filtration so that the residual moisture de-
creases only slightly when the layer thickness increases. In contrast to this, very fine-grained
incompressible solids have such a high filtration resistance that any increase in the layer thick-
ness will cause a considerable decrease in the residual moisture due to the longer filtration
distance if this is not compensated by a longer residence time.
Fine grained incompressible particles of solid matter have a high degree of filtration resistance.
Large layer thickness significantly impairs the residual moisture because of the longer filtration
path.
Through the machine geometry (drum inclination, slot width of the screening element), choice
of rotational speed, residence time, grain geometry, input feed concentration and input feed
quantity
n Tr − n Exz
n Schn = n Tr + = n Tr + ∆ n
i
If the drum speed is higher than the excenter shaft speed, the value of the differential speed
turns positive; this means the worm rotates slightly faster than the drum. In this case, the worm
is said to be advancing.
In contrast to this, the value of the differential speed is negative if the drum speed is lower than
that of the excenter shaft; this means the worm rotates slightly slower than the drum. In this
case, the worm is said to be lagging. However, lagging operation is not practicable with the
Conthick due to the short decanter section.
The differential speed with the excenter shaft at standstill results directly from the transmission
gear ratio and the drum speed; the transmission gear ratio and accordingly, the differential
speed can be varied by exchanging some gearbox parts.
To ensure a precise tuning of the centrifuge at high speeds, the excenter shaft is driven in this
case. If the gearbox type is the same, the excenter shaft is driven by the main motor via a sec-
ond motor belt pulley.
Accordingly, the differential speed in case of double transmission is calculated as follows:
n Tr − n Exz
∆n =
i
Overload protection
The centrifuge will hardly suffer overload during the processes that usually run continuously at
constant product flow. Notwithstanding that, the admissible maximum suspension flow must
not be exceeded.
Malfunctions may however occur during restarting after production stops if the machine is
jammed due to insufficient rinsing, or due to a feed flow surge.
In order to protect the gearbox from such overload, the torque is limited by different mecha-
nisms on the excenter shaft that prevent inadmissible gearbox overload by disengaging the
shaft. Furthermore, they generate an electric signal to close the suspension feed and discon-
nect the main motor.
Sealing
The protruding design requires only one part rotating at high speed, the neck piece of the
drum hub, to be sealed against the rear wall of the product housing.
The absolute rotational speed of the worm hub may be even higher. But thanks to the low dif-
ferential speed between worm hub and drum hub, this sealing point can be mastered easily
with standard shaft seal rings.
The neck of the drum hub requires the use of non-contact labyrinths because the circumferen-
tial speed is high and there is the risk of impairment by the product.
If the production system is self-contained, then contacting seals like chamber packings or axial
face seals need to be used.
Solids discharge
Crystals that could be smashed by the impact onto the housing wall, or solids that tend to ad-
here, are caught in a gutter that envelops the drum discharge and are discharged tangentially
downwards through a gutter aperture. Metal wings fixed to the drum that rotate at high speed
in the internal space support the flow of solid matter by their ventilating effect.
But the gutter would clog despite the high speed and the flat angle of impact if a product is
sticky.
Therefore, the machine must be operated without discharge gutter in such cases and the solid
matter space needs to be lined with PTFE or similar suitable material to avoid incrustations and
machine jamming.
Ventilation
The tendency of centrifuges to convey gas may cause an overpressure in the filtrate space and
a filtrate fog may be pressed through all existing apertures. In this way, the filtrate fog may
moisten the dried solid matter another time.
To achieve effective deairing of the filtrate space, at least one large-dimensioned deairing con-
nection must be installed on top of the filtrate discharge, or even better a filtrate cyclone that is
open on top, to separate fine droplets.
Self-enclosed production systems require an air extraction of a pressure equalizing pipe be-
tween filtrate space or cyclone and solid matter space.
Thousand crystals with a diameter of 0.1 mm have even ten times the surface of one crystal
with a diameter of 1 mm.
Due to their large surface, very fine particles will bind particularly much liquid and deteriorate
the residual moisture that can be achieved.
If a solid matter is provided in two fractions with significantly differing grain sizes, it may be
economical to discharge the very fine particles along with the filtrate and process them in an-
other way so that the coarser solid particles will contain so little residual moisture that they can
be stored and possibly even packed as a finished product without need for further dehumidifi-
cation.
The centrifuge is to discharge the supplied solid matter despite fine-grained constituents with-
out significant screening loss at the lowest possible residual moisture.
To this end, the following conditions should be given if possible:
• Highest possible feed concentration
• Low revs, tuned to the required residual moisture
• Thick layer on the screening element
• Small screen apertures
• Optimized discharge area of the screen.
The higher the feed concentration is, the better will the process efficiency of the screen worm
centrifuge normally be because small suspension volumes with high solid content require a
minimum of acceleration energy and a maximum discharge rate of solid matter can be
achieved.
Residual moisture
The residual moisture depends on the following influence factors:
• Grain size, grain size distribution, grain fracture
• Grain shape and surface structure of the solid matter
• Permeability of the solid matter layer on the conical drum section
• Viscosity
• Adhesion characteristics between solid matter and liquid
• Feed concentration
• Inclination of the cone
• Residence time
• Centrifugal factor
• Layer thickness of the solid matter on the conical drum section.
As the retention time ∆t increases, the residual moisture RF initially decreases fast but then
only slowly so that very long retention times do not result in any economic advantage but on
the contrary limit the throughput without necessity.
If the centrifuginal factor z increases, the graph largely maintains its shape but is shifted to-
wards lower residual moisture and shorter residence time. The zone of transition between
steep decrease and flat branch indicates which residence time should be selected.
Figure 6 RF-∆t-diagram
At the same time, the parameters wear, grain fracture and loss of fine particles must be consid-
ered, too.
Very coarse incompressible solids facilitate filtration so that the residual moisture increases
only slightly when the layer thickness increases.
In contrast to this, very fine-grained solid matter has such a high filtration resistance that any
increase in the layer thickness will cause a considerable rise in the residual moisture due to the
longer filtration distance if this is not compensated by a longer residence time.
Machine lubrication
According to standard all Centrifuges should be equipped with an integrated recirculating oil
lubrication system.
At the base frame an oil reservoir is attached, in which the oil pump aggregate is integrated.
From here the oil is fed to the lubrication system.
From this pressure line the supplies the gearbox and all antifriction bearings are supplied via
individual throttling ports with oil. Thus the temperature development is affected at high num-
bers of revolutions as well as a contamination of the antifriction bearings is prevented to the
best advantage.
The recirculating oil is supplied to the oil reservoir and will be filtered. Control devices belong to
the scope of supply. This perfect lubrication system guarantees high life span for gear and
bearings with smallest maintenance costs.
From this pressure channel, the gear unit and all roller bearing are supplied specifically with oil
via single throttling bores.
This has a positive influence on the development of temperature even at high rotation speed
and contamination of the roller bearing is prevented as well.
Wet screens as considered in the project have various fields of applications such as:
coal, raw and washed iron and copper ores, minerals, granular material, pellets, potash and
halite, aggregates, limestone, sand and gravel, building materials.
Operational characteristics
“Banana“ screens are high speed screening machines. Due to the steep screen inclination,
high transport speeds are achieved. A very fine layer is formed and a large proportion of the
fines pass through the elongated apertures. The inclination is less in the middle and discharge
sections, which reduces the transport speed. In these sections a good separation, even of
marginal particles, is achieved.
"Banana" screens achieve a very accurate separation, even with extremely high feed rates and
difficult material. Originally “Banana“ screens were developed for two separations and have
proved themselves in that field. However they have also been used successfully many times on
multiple separation applications.
Machine details
Considered "Banana" screens are double counterweight screening machines. These screens
are manufactured as single or double deck machines, of two to five sections with gradually
flattening inclination. E.g. In the steep part it might be 25° - 40°, in the middle sections 15° - 25°
and 0° - 15° towards the discharge. The effective screening areas can be up to 50 m². The
quantity of inclination sections and their degree of slope can be designed according to specific
requirements (e.g. restrictions in height of the steel structure of the processing plant).
The Rod Mill should been manufactured to the latest state of the art and under consideration of
the FEM Codes and Standard (Fédération Européenne de la Manutention), ISO und DIN
standards and the acknowledged rules of safety engineering. Nevertheless, use of this equip-
ment might involve risks to life of operators or third parties or damage to equipment, its com-
ponents or other property.
Therefore, the operator of the Rod Mill shall prepare job-specific instructions on the basis of the
intra-company occupational safety and accident prevention codes and declare them obligatory
so that accident-free operation, repair and maintenance of this equipment can be ensured.
The Rod Mill should be used only in technically perfect condition and in full accordance with
the intended purpose, with safety awareness and under strict adherence to the operation and
maintenance instructions so that accidents can be excluded. Troubles that might impair opera-
tional safety must be immediately eliminated.
The Rod Mill shall be used only for the application parameters. Use of equipment for other pur-
poses and/or different application parameters is considered as not in accordance with the in-
tended purpose.
The crystallizate grinding system described herein is designed to mill in continuous wet grind-
ing process for the use in further process.
The plant is equipped with instruments to provide the necessary signals and contacts. The im-
plementations of controls will be accomplished in the DCS system.
Mill Components
Mills are O' flow type and have central drive consisting of a squirrel cage motor, mechanical
starter coupling with entrainment charge of oil and steel rods, a speed reducer and toothed
coupling connected to the rod mill’s central drive trunnion. An inching drive is installed on each
mill at the high-speed shaft of the speed reducer side opposite to the mill main E-motor.
The mill trunnion bearings are of bush type with lead bronce inserts with large oil bags. Self-
aligning swivelling rollers support the bush body. Mill trunnion bearings are provided with au-
tomated low pressure oil lubrication sets each comprising motor gear-pump set and gap filter
at suction side, oil flow switch and thermocouples transmitting the oil gap temperature signal 4-
20mA to the DCS system permissions, feedback and alarms.
Trunnion bearing housing contains also its own oil tank in bottom section. To ensure dust &
water tightness of bearing housings, each housing is sealed off by a grease lubricated double
lip seals clamped to the bearing housings and fed with grease by a timer controlled grease
pump one for each mill.
To ensure proper grinding kinetics of the grinding rod charge - mill liners of lifter bar type made
of solid rubber are installed inside the mill body.
The grinding rod charges are composed of steel rods.
The mill slurry is gravity discharged through the discharge trunnion carrying a return spiral of
solid PU lining, in order to prevent grinding parts from being flushed out into the mill tank with
the mill discharge slurry. Return spiral is followed by a discharge liner with outlet slots - both
items installed on inside diameter of discharge trunnion.
Mill Body
The mill body is composed of a shell and two heads screwed to the shell.
Both mill heads consist of a conical casted head part.
The shell carries in that case peripheral outlet slots at its discharge end - without a discharge
chamber.
The three main parts are made of heavy gauge steel plate or forged parts and are annealed
before machining.
The body is supported by two bearings.
Trunnion Bearings
Self-aligning bush bearing lined with high-grade babbit, under dust-tight housing, with auto-
matic lubrication set.
Floating bearing drawing and fixed bearing version.
Roller-Bearing Block
Heavy-duty, self-aligning roller bearing carried in sealed mounting with grease lube-plug and
grease discharge valve.
Feed Arrangement
Rod mill has a conical feed cone.
A feed box with spout feeder and wear part, the entire arrangement removable, ensures a save
flow into the grinding chamber for the mill new feed.
The feed box further carries:
• One flanged rectangular opening for mill new feed.
• Flanged connections for grinding water.
• One inspection flap on top.
Discharge Arrangement
Central Discharge
• Overflow
Mill Liners
The following mill liner system is used:
• Rubber liners of the lifter bars type, for wet fine grinding as in the subject case.
The liners are fastened by special fine-threaded bolts with leak proof washer, nut and lock-nut.
This operation is carried out at the site or in the shop after mill assembly or installation respec-
tively.
For certain materials it is usual to apply the HARDGROVE index to define the grindability.
If a product is harder its HARDGROVE index is lower- what is inversely proportional to the Wi
figure.
The supplier should be in the position to carry out the HARDGROVE tests.
Particle size distribution of product ground
In order to define a product before and after grinding, the granular curves of this product are
plotted, based on the screen analysis.
A representative screen analysis is carried out under defined conditions on a range of standard
screens.
It is most popular to express a certain fraction in mesh, or microns, which is a concrete term
avoiding confusion.
Number for the grain size
The results of the screen analysis expressed per passing or per retained cumulated at 100 %
one wt. % and mesh permit to plot the granular curve.
Specific surface of a particle size distribution
The result of a grinding operation can be checked by measuring the specific surface of the
product.
The specific surface is expressed by cm²/g. It is the surface of one gram of product with all
grain sizes contained.
Amongst the usual methods & instruments we like to mention the permeability meter acc. to
Blaine.
Critical speed of a mill
It is usual to express the rotating speed of a mill as percentage of its critical speed. The critical
speed is the speed at which the outermost layer of mill rods starts centrifuging.
It is calculated by: Nc=42.3/√Dil (2)
whereas Dil (m) is the mill diameter, inside liners.
The rotating speed of the mill in % of the critical speed is chosen as function of the dimensions
of the mill and its application.
L/D - ratio of mills
It is the ratio of the length to the useful diameter of the mill. It is defined primarily at an optimum
value according to the kind of operation, open or closed circuits, reduction ratio, etc.
Charge of the mill
This is the percentage of the useful volume of the mill filled with grinding rods and material to
be ground.
It is generally equal or less than 30 % according to the applications.
Page 150 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
d-l d-1
v = dm-l
(5); and v= d (5a)
m-1
When we consider the most usual case where the liquid is cold water and where l = 1, then we
obtain (5a).
The solids concentration by weight / wt % is then:
dm൫d-1൯ d
S= d൫d = v ˙ dm (6) S=s˙100 (6a)
m-1൯
Our diagrams and flow sheets of wet-process installations contain the following terms to de-
scribe the different mass flows:
Total mass flow (M) (kg/h)
Solids flow (Sm) (kg/h)
Water flow (W) (m³/h)
Density (d) (kg/m³)
Volume flow (Q) (m³/h)
Solids wt% (S) (wt.%)
Grinding Circuits
Open Circuit
Rod mills operate with open or with closed circuit.
With open circuit grinding, it is intended to obtain by only one passage through the mill a cer-
tain granulometry that is characterized by a maximum percentage of remainder admissible at a
certain mesh size.
If the remainder has to be strictly limited, the working in open circuit will result in excessive
power consummation because of the surface increase involved.
This increase of power consumption can reach 1.3 to 2 times to energy theoretically required.
Closed Circuit
In ore processing, mostly try to liberate the mineralogical components without going beyond
this mesh called liberation size.
This can be reached by working in closed circuit, either in dry grinding on air-separators or in
humid process on hydro cyclones, curved sieves, screen panels and mechanical classifiers.
This classification allows to work on comparatively short mills with circulating loads varying
from 100 to 500 % and more.
The efficiency of the work can be considerably improved and optimum adjustments for the
product particle size distribution are possible.
• Proportional to the filling rate of the mill as indicated by the curves here-after (c-factor
for the calculation of the mill power).
7.4.2.5 Flotation
In the designed process for producing KCl 95, several steps of flotation for concentrating the
ore are necessary. These flotation steps are rougher flotation, cleaner flotation and scavenger
flotation. The consultant decided to consider agitated flotation machines within the detail engi-
neering. The consideration of pneumatic flotation machines was evaluated. During this evalua-
tion the focus was set on operational requirements of the flotation machine in the overall pro-
cess, operational safety, references in the potash industry, capital costs and operational costs.
The consultant came to the conclusion to prefer agitated flotation machines under considera-
tion of the requirements of this special project.
Agitated flotation machines feature a unique design that is demonstrably superior to other flota-
tion systems. In direct comparisons by major mining companies, the considered flotation ma-
chines in this detail engineering, have repeatedly delivered higher recovery and grade with
easier start-up, simpler operation, lower reagent consumption, longer mechanism life and less
required maintenance. The considered flotation machine is the world leader in large cell tech-
nology with the greatest installed capacity of any other flotation machine.
At the heart of each cell is a rotor-disperser that delivers intense, mixing and aeration. Ambient
air is drawn into the cell and uniformly distributed throughout the pulp, providing optimum
air/particle contact. In larger cells a false bottom and draft tube channel flow, ensuring high
recirculation and eliminating sanding. The combination of efficient aeration and optimum solids
suspension gives these machines the highest specie recovery and concentrate grade perfor-
mance available, and reduces reagent consumption.
Air flow into the pulp is induced by the turning rotor. No forced air supply is required, eliminat-
ing the capital and operating costs of blowers and distribution piping. Air flow compensation
for varying feed densities is automatic, minimizing the operator attention required. An additional
benefit is that one mechanism can be removed for service without interrupting production, un-
like forced air systems which require shut down of an entire cell bank for service access to a
single mechanism.
To reduce wear on rotor and disperser surfaces, the aeration mechanism is positioned above
the tank bottom, eliminating contact with abrasive, oversize tramp material. After a shutdown,
the elevated rotor allows cells to be restarted instantly, unlike conventional designs with rotor
and floor-mounted stator located in the zone of heaviest solids accumulation.
Aerator mechanism erosion is further reduced by large design clearances between rotor and
disperser. Normal wear life of the considered mechanism is 2-4 times that of closely spaced
conventional rotor/stator designs. Because the mechanism stay with design tolerances longer,
peak metallurgical performance is maintained over a longer period, further enhancing profitabil-
ity.
For reasons of productivity the superior air dispersion and high slurry recirculation ensures
adequate residence time for optimum recovery and concentrate grade. In regard to economy
the simple induced aeration reduces both capital and operating cost. Furthermore the efficient
air dispersion reduces frother consumption and the reduced mechanism erosion slashes
maintenance costs.
Description of Operation
The horizontal belt filter dewaters thickener underflow slurry by applying a vacuum to the un-
derside of a filter cloth moving across the filter bed. The filter cloth is transported by a rubber
transporter belt, which is also grooved and holed to allow liquid runoff under the cloth. Filtrate
and air are mixed in the vacuum box, which is spaded internally to separate the flow streams.
Slurry is fed onto the filter at ambient temperatures. The filter can be equipped with one (or
more) wash stages. The dewatered slurry cake is discharged from the end of the horizontal belt
filter into a cake discharge system
The filtrate and wash water from the stages are drawn off into filtrate receivers each filtrate re-
ceiver and moisture trap can be equipped with NPSH pumps, which pumps away the accumu-
lated filtrate. Each vessel is connected through a common vacuum system to a moisture trap
and then to a vacuum pump.
Process Description
FEED
Slurry is fed onto the horizontal belt filter via an agitated/flocculated tank and onto a fishtail
feeder. The feeder ensures even product distribution over the cloth width. This is important for
uniform washing and drainage.
FORM ZONE
The form zone is the area of the belt visible from the feed dam roller to the point where no sur-
face liquid is visible. The feed rate must be such that a uniform layer of material covers the en-
tire width of the belt.
WASH ZONE
The wash zone is the area of the belt after the form zone where wash liquid on the filter forms a
dam covering the filter cake. The wash liquid will be drawn through the filter cake displacing
residual filtrate and washing the filter cake.
DRYING ZONE
The drying zone is the area of the belt where the filter cake is further dewatered. In the drying
zone, no surface moisture will be visible and during the last stages of drying, air will be drawn
through the filter cake.
DISCHARGE ZONE
At the discharge zone, the filter cloth is separated from the carrier belt by passing over a sepa-
rate roller. This has the added function of breaking the cake prior to discharge. The filter cloth
then wraps around cake slide roller or discharge slide through an angle of 90°. At this point that
the wet filter cake and the filter cloth are separated by gravity.
VACUUM SYSTEM
Vacuum is applied to the horizontal belt filter via a vacuum system connected to filtrate receiv-
ers where the filtrate is separated from the airblow. The vacuum pump vents into atmosphere
and the mine water is passed once through the vacuum pump as seal water.
Operating Strategies
There are two variable in the control of the horizontal belt filter, with the aim being the dis-
charge of a uniform filter cake having a minimum liquid content.
Feed Rate: The feed rate should be controlled such that the filter cake thickness on the belt at
the drying zone is uniformly thick with no openings or wet patches.
Cycle time: The cycle time is the time taken for a known point of the belt to pass over the vacu-
um boxes along the length of the belt and is directly related to belt speed.
Operating Instructions
FILTER DESCRIPTION
The horizontal belt filter comprises the following:
Filter Frame
This is a painted mild steel structure for pre-leach filters and stainless steel for acid. The frames
are manufactured from angle and channel sections with welded and/or bolted construction.
The unit is designed for delivery to site in small pieces.
Head Pulley
This is an oversized mild steel pulley with corrosion resistant shafting and rubber lined with a
grooved diamond pattern. It is located at the filter cake discharge end, and is also known as
the drive pulley.
Tail Pulley
This is similar to the head pulley but is fitted at the feed end of the filter, i.e., the idler pulley.
The pulley is fitted with take-up bearings to facilitate belt tracking and tensioning.
Drive Unit
The filter drive comprises an AC motor, fixed ratio gearbox and pulleys driven by a variable
speed drive.
Transporter Belt
The main transporter belt is manufactured from neoprene rubber reinforced with a polyester
fabric carcass. The belt has regularly spaced sloped grooves cut at right angles to the direction
of travel and has drainage holes punched in the center for filtrate extraction into the vacuum
box. The belt is delivered unspliced and must be spliced, tracked, drilled and have curbing
added on site.
Belt Support
The transport belt is supported by a system if airboxes supplied with low-pressure air from a
single fan. The rubber transport belt slides on an aircushion over perforated stainless steel
plates. Guide rollers are fitted along the length of the filter to assist with guiding the transport
belt along the top deck of the filter.
Vacuum Boxes
The stainless steel vacuum box is made up from a set of flanged fabricated high-grade stain-
less steel box construction. Wear belts slide in machined plastic sliding strips mounted on top
of the vacuum box, and are lubricated by injecting seal water. The vacuum box is connected by
large bore hoses to the vacuum manifold and then by rigid piping to the filtrate receivers.
Filter Cloth
An endless length Needlefelt cloth is carried along the main transporter belt. After the filter cake
discharge, the cloth and the transport belt separate and both return to the tail pulley via a sys-
tem of return rollers. The cloth has a pneumatically controlled tracking system. Tensioning is
achieved by a weighted gravity tensioned roller. A bowed roller is fitted to the head of the filter
and acts to prevent the cloth from creasing.
Bearings
The head and tail pulleys have sealed plumber blocks on the shaft ends. The DE bearing is
static while the NDE bearing is floating. All bearings are lubricated with the aid of a dual line
lubrication system. The tail pulley is equipped with take-up bearings. All other rolls are fitted
with high quality double spherical roller bearings.
Slurry Feeder
The feeder consists of a dual fishtail feed distributor to regulate and evenly distribute the slurry
onto the filter cloth. All slurry feeders are rubber lined.
Wash Distributors
The wash distributors are designed to ensure that wash water is evenly distributed over the
entire cake.
FILTER PLANT
The filter plant can be viewed as three sections:
• Filter feed
• Horizontal belt filter
• Washed cake disposal.
FILTER FEED
An ultrasonic level sensor mounted over the form zone measures feed dam level. The PID con-
trol loop either stands alone or in the client PLC controls the modulating flow control valve in
the feed line to ensure a constant cake thickness.
BELT FILTER
Slurry is distributed over the width of the belt in the formation zone by the fishtail feeder. The
length of the formation zone is the distance from the feed dam roller to the point where no sur-
face liquid is visible. The filter cake bed thickness is dependent on the following:
• Feed flow rate
• Feed density
• Belt speed.
Strong filtrate extracted from the form zone and wash filtrate extracted from the wash is
pumped away by the filtrate pumps and not recycled on the belt filter. An overflowing cake
wash distributor distributes wash water over the wash area. A second ultrasonic level detector
is mounted above the wash zone on the acid filters, to alarm high and low dam levels for preset
levels. Level switching is carried out in client PLC. The belt filter transport speed is controlled
by a frequency inverter coupled to the filter drive. The belt speed is visually monitored and is
set manually during commissioning and adjusted during filter operation as required.
Cake Disposal
The cake produced by the filter plant is discharged off the end of the belt into cake discharge
system and disposal to a plant supplied by others.
A shaking fluid bed dryer is used for continuous drying of powders, crystals and granulated
materials. Drying is achieved by the transfer of heat from a fluidizing air stream as it comes into
contact with the material.
Working Principle
Centrifuge wet material is continuously fed in to the dryer. In the shaking fluid bed is a perforat-
ed stainless steel plate (air distributor) through which the drying air flows. The air is of sufficient
volume that it lifts or fluidizes the bed of material allowing intimate contact between drying air
and each particle. The shaking action of the fluid bed assists in the transportation of the mate-
rial over the length of the dryer and improves the fluidization of the wet material. Moisture is
carried away with the air and fine particles into a dust recovery system, an exhaust air fan
transport the cleaned air to ambient. The flow of air is controlled along the length of the dryer to
maximize fluidization enabling wet and sticky materials to be handled. As the material passes
along the length of the dryer it gradually loses moisture until the target dryness is achieved at
which point it passes into a cooling zone. In the cooling section the product is fluidized with
cool ambient air which reduces the product temperature to the requested value. Cooling of
product is required to allow further product handling on bucket elevators, belt conveyors etc.
The exhaust air from the cooling section is also de-dusted in a filter installation and recycled to
the drying section.
Air Heating
Air is pumped by a fan into a burner housing which is fuelled by liquefied petroleum gas. The
flue gasses from the burner and process air are mixed in the burner chamber to an even tem-
perature. The heated air is then blown into a chamber under the perforated bed from which air
passes into the material bed. De-dusted exhaust air from the cooling section is recycled to the
burner for fuel efficiency. The burner capacity is adjusted to control the final product moisture
content depending on the measured exhaust air temperature and product temperature; this is
a fully automated system that requires no adjustments from the process operators.
De-dusting System
The entrained fine particles in the exhaust air from the dryer and the cooler are separated from
the air stream in separate filter sections. The filter is equipped with a filter material (polyester
needle felt) supported by stainless steel cages. The dust is collected on the filter material and
the air permeates though the filter cloth. In regular intervals compressed air is used to remove
the dust from the filter cloth. The dust is collected in a screw conveyor and removed from the
filter through a rotary airlock valve.
After laboratory test work, process calculation, pre-selection of equipment ERCOSPLAN made
inquiries for main equipment. Afterwards equipment suppliers sent quotations for main equip-
ment. Along with the quotations, some suppliers asked for equipment test work due to the
specific high altitude of installation of equipment. Equipment test work is necessary e.g. for
vacuum belt filters and settling tests for thickeners.
ERCOSPLAN recommends that GNRE-COMIBOL takes these outstanding test works into con-
sideration during the purchase phase of equipment, so that the delivered equipment by the
supplier can meet 100 % of GNRE-COMIBOL’s satisfaction.
The overall process is divided into following technological process sections. For details see
Piping & Instrumentation Diagrams (PID).
• Wet salt storage including truck loadout
• Wet screening and milling
• Rougher flotation
• Scavenger flotation
• Cleaner flotation
• Cold leaching and product dewatering
• Reagent dosing plant
• Tails process
• Compressor plant
• Process water storage
• Reclaim brine storage
• Rinsing water system
• Sealing water system
• Drying section
• Product storage
• Truck loading.
The truck loadout is constructed as a ramp from compacted salt. The ramp has two parallel
lanes upwards the ramp, two parallel openings for discharging the crystallizate from trucks and
two parallel lanes downwards the ramp. So a parallel loadout of two trucks is possible. Due to
this construction, backwards driving and shunting of trucks is not necessary and a quick
loadout cycle is ensured. Once the truck has reached the top of the ramp, the truck has to stop
and to open the bottom valve. When the crystallizate is discharged, the truck drives down the
ramp back to the crystallizate pond. In the center of the ramp the crystallizate bunker is in-
stalled. The level indication of the bunker prevents overfilling. In case of a high level inside the
bunker, a traffic light signals the truck driver to wait until the bunker level has been sunk. Inside
the bunker a rotating beater crushes possible crystallizate lumps coming from the ponds. Un-
derneath the bunker a discharge conveyor, equipped with speed control, is installed. A belt
conveyor transports the crystallizate from truck loadout ramp to a two-way distributor.
Due to a liquid content up to 15 % in the crystallizate, the adhered brine from crystallizate is
collected in a low point next to the bunker. The collected brine in the low point is then pumped
to disposal. The low point is equipped with a level indicator which lets the pumps start when
the upper level is reached.
The crystallizate arriving the two-way distributor has the possibility to be transported to the wet
salt storage, to bypass the wet salt storage by going directly to processing plant, or to be dis-
tributed between wet salt storage and processing plant.
Wet crystallizate to be stored in the wet salt storage is done by an increasing belt conveyor.
Afterwards a moveable and reversible conveyor belt generates the longish storage. Wet salt
storage’s capacity is designed with 30,000 tons of wet salt. Discharging of wet salt into pro-
cessing plant will be done by automatic scraping technology. The scraper feeds a conveyor
belt leading out of the wet salt storage. Discharge capacity will be approx. 650 t/h.
Wet crystallizate stored in the wet salt storage has an adhered brine content of approx. 15 %.
During storage time these moisture will flow out of the bulk and will settle on the ground floor of
the storage. On ground floor there is a drainage system (channels) which lead the adhered
brine to a central low point where brine is collected. From there adhered brine is pumped to
disposal. The low point is equipped with a level indicator which lets the pumps start when the
upper level is reached.
Lump crushing and iron / non-iron metal detecting is necessary for trouble-free operation. Af-
terwards lump crushing a two-way distributor distributes crystallizate to conveyor belt including
belt weigher leading to production line A and B. At these conveyor belts it is envisaged to take
samples for controlling crystallizate quality. Furthermore a K2O measurement device and mois-
ture measurement device is installed at these conveyor belts.
Chutes afterwards belt conveyor drops are generally equipped with overfilling detectors (LSA).
Wet salt storage will be a closed building, so that there is no bad influence due to precipitation
and contamination.
Main equipment in wet salt storage will be:
• Crystallizate bunker
• Discharge conveyor
• Belt conveyors
• Scraper
• Iron / Non-iron detector
• Lump crusher
• Belt weigher
• Low point pumps.
The wet screening and milling process section is executed in two parallel production lines (line
A & B). In case of disturbance due to the delivered crystallizate, a connection between both
lines is envisaged after the first suspending step of crystallizate. So there is a possibility to
switch between both production lines. A second connection between both lines is before the
wet screens.
Wet crystallizate coming from wet salt storage is suspended with reclaim brine in an agitated
vessel. The amount of brine to be used for suspending is monitored with flowmeters. From
there suspension is pumped to a distributor tank and from there it flows to 3 parallel installed
centrifuges to separate adhered magnesium brine. The volume flow of suspension to distribu-
tion tank is monitored by flowmeter. Furthermore the correct distribution between the 3 centri-
fuges is monitored by flowmeters and valves. The centrifuges are equipped with an oil cooling
circuit. The cooling media is process water (average 15 °C).
The adhered brine has to be separated because of the high content of magnesium chloride.
Magnesium chloride makes the recovery in flotation go down.
Liquid fraction of centrifuges flows into a central vessel. From there it is pumped to a thickener
to separate the fine remaining particles. The thickener overflow is collected in a tank and then
Page 162 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
pumped to the suspending vessel in the beginning of the process section. Here it is used for
suspending the crystallizate coming from wet salt storage. In case of a surplus of suspending
brine, the brine can be disposed to disposal. The thickener underflow is pumped directly to
rougher flotation because of the particles containing KCl.
Solid fraction from centrifuges is collected on centrifuge discharge conveyor and is conveyed
to agitated vessel. Solid fraction is there suspended with reclaim brine. Afterwards suspension
is pumped to 3 parallel installed vibrating wet screens together with cleaner flotation tailings.
The correct distribution between the screens is monitored by flow meters and valves. Split cut
will be at 0.8 mm because of the results of laboratory flotation tests. In the flotation tests was
manifested that the liberation grade, the grade where almost all KCl and NaCl particles are
separated from each other, is at a maximum grain size of 0.9 mm. Each screen is charged by
its own pump, so that an independent operation is ensured.
Screen overflow bigger than 0.8 mm is milled in a rod mill, collected in agitated vessel and then
pumped back to screen. By pumping back the milled fraction to screens, the operator has the
guarantee that all the particles are smaller than 0.8 mm.
Screen underflow is collected in an agitated vessel and is then pumped to rougher flotation.
The volume stream is monitored by flowmeter.
An overhead crane is installed above wet milling and screening process section to ensure
hoisting of huge equipment in case of repairs and maintenance.
The rod mill including its grinding media (rods) is one of the heaviest equipment in the process
building. So, above the rod mills an extra overhead crane is installed.
Generally all tanks in this process section are equipped with a level indication. The level inside
the tank is regulated by the afterwards installed pumps with speed control. Furthermore tanks
are equipped with an overflow pipe leading to central drainage system on platform 0.00 m.
The underflow of thickeners is monitored by checking the density. Chutes afterwards the centri-
fuges leading to centrifuge discharge conveyor are generally equipped with overfilling detec-
tors (LSA). Afterwards all pumps a pressure indicator is installed to ensured correct working of
pumps.
Centrifugal pumps in this process section are supplied with sealing water from sealing water
system.
Main equipment in wet screening and milling section will be:
• Centrifuges
• Centrifuge discharge conveyor
• Thickener
• Vibrating screens
• Rod mills
• Agitated tanks
• Pumps
• Overhead cranes.
Details regarding the wet screening and milling section are set in:
• PID Wet screening and milling (Drawing No. 1351 and 1352)
• Equipment list (Appendix A02)
• Arrangement drawings
• Equipment data sheets (Appendix A03)
• Equipment specifications (Appendix A06).
The rougher flotation process section is executed in two parallel production lines (line A & B).
Wet screened crystallizate from wet screening and milling process section is fed to hydro cy-
clones battery for generating flotation solid content. Hydro cyclone underflow is then collected
in an agitated vessel and flows from there via agitated conditioning vessel to rougher flotation.
The density of hydro cyclone underflow is monitored by density measurement. Conditioning
tank additionally receives reclaim brine in dependence of density of flotation feed. Correct den-
sity respectively solid content of flotation feed is important for flotation results.
Collector reagent from central reagent dosing plant is added by dosing pumps to agitated
conditioning vessel in front of flotation, so that 1 minute reagent resident time is guaranteed.
When dosing the collector agent reagent directly to rougher flotation (without conditioning)
floating of KCl will not work well in the first rougher flotation cells. After conditioning density and
volume flow of rougher flotation feed is monitored. Rougher flotation is designed as 8 cell agi-
tated flotation machine with a single cell volume of approx. 8 m³. Flotation machines are
equipped with its own level regulation. Flotation machines are self-aerating, due to the generat-
ing of under pressure by the agitators. Surrounding air flows into the cell through a hollow
shaft. So, no external supply of compressed air for flotation is needed. Flotation time will be
according to flotation test work in laboratory 6 minutes. Rougher flotation is furthermore fed by
frother agent from central flotation reagent plant. Frother reagent is mixed with flotation feed in
static mixer directly before flowing into flotation cell. Rougher flotation concentrate flows to
cleaner flotation. Rougher flotation tailings flow to scavenger flotation.
Hydro cyclone overflow flows freely to thickener. The thickener feed is monitored by flowmeter.
The thickener separates fine particles from hydro cyclone overflow. Generated solid free thick-
ener overflow is pumped to reclaim brine storage. Thickener underflow is pumped to condition-
ing vessel in front of rougher flotation. The thickener receives optional flocculant reagent, which
supports settling of fine particles in the thickener.
An overhead crane is installed above rougher flotation process section to ensure hoisting of
huge equipment in case of repairs and maintenance.
Generally all tanks in this process section are equipped with a level indication. The level inside
the tank is regulated by the afterwards installed pumps with speed control. Furthermore tanks
are equipped with an overflow pipe leading to central drainage system on platform 0.00 m.
The underflow of thickeners is monitored by checking the density. Afterwards all pumps a
pressure indicator is installed to ensured correct working of pumps.
Centrifugal pumps in this process section are supplied with sealing water from sealing water
system.
7.4.4.4.1 General
Chemical reagents are required for potash flotation processing. These reagents help to enable
separation processes respectively to increase recovery. Chemical reagents are delivered highly
concentrated and are transported in industrial common packages. For processing needs, rea-
gents have to be conditioned and almost diluted with process water. Conditioning can be a
melting of solid reagents in heated vessels to realize the subsequent dilution with process wa-
ter. The dilution takes place in agitated vessels. The finished reagent solution is then stored in a
next vessel, ready to be added into the process. Adding to the process is done with special
dosing pumps to guarantee exact dosing. Processing inside the reagent dosing plant runs au-
tomatically, feed vessel for delivered reagents however has to be filled from time to time.
In general, dosing means adding of highly effective substances (e. g. polymers, additives etc.)
to a given media (e. g. water). Control processes in dosing technology base on short-term add-
ing of high or small amounts of these substances according to requirements.
Purposes of dosing are for example:
• Exact keeping of mixing proportions (e. g. polymers and water as flocculants) under in-
fluence of disruptions
• Adding of active media into fixed quantities (e. g. water stabilizing substances) in peri-
odic times
• Adding of active media into fixed quantities, triggered by special events (e. g. filling of
tanks or vessels).
Many dosing processes base on adding of fixed quantities of a substance after occurrence of
specific incidences. For example, such an incidence can be the new-filling of a tank or vessel,
when a fixed quantity shall be charged at a time. As on the one hand the fixed quantity shall be
adjustable (selectable) and on the other hand it cannot understandably be added all at once at
the time of the incidence, adjustable time relays are used for such tasks. For instance: if 450 ml
of a product shall be dosed after occurrence of an incidence, the time relay of a pump with a
flow rate of 150 ml/min is set at 3 minutes. That means the dosing quantity results from the
product of flow rate and elapsed time. Based on that setting procedure, the term "time-
controlled dosing" has become common in dosing technology.
In some dosing processes (e.g. for flotation), a mixing ratio as exact as possible of two media
(main medium, dosing medium) shall be set up. That is called proportional dosing. One me-
dia often is water (e. g. process water) to which a chemical shall be proportionally added in an
exact ratio. If the flowing-in water flow is constant, the mixing ratio can be adjusted during
active filling-in via dosing device with adjustable flow rate (e. g. magnetic valve). In that case
the dosing device is switched on or off by the magnetic valve.
With unsteady water flow the flowing-in has to be measured, mostly by contact water flow
meter installed in the flowing-in flow. Contact water flow meters emit a fixed number of impuls-
es per liter so that the run-through volume can be measured exactly. Dependent on the num-
ber of impulses (of the actual water in-flow) a conveying device (e. g. pump) can be switched in
such a way by special equipment for contact water flow meters that an exact proportion of dos-
ing substance and flowing-in water is reached.
Numerous tasks require a continuously controlled dosing to keep a fixed concentration or mix-
ing ratio of dosing substance and base product (e. g. hydrochloric acid / process water). If a
physical or technical variable is a function of the concentration, that variable can be used to
control the concentration and disturbances can be "compensated". The most important con-
trolled process variables in dosing technology are:
• Electrical conductivity
• Flow rate (see also section 7.4.4.4.4)
• Redox potential
• pH value.
For process water and hydrochloric acid there is a functional correlation between electrical
conductivity and process water mixed with hydrochloric acid. If a certain concentration is
reached, this concentration represents the nominal value of the application. That amount of
concentration corresponds to a certain electrical conductance on which the control device is
adjusted (mostly at a trimm potentiometer or by keyboard and display). If hydrochloric acid is
spent during the process, the electrical conductivity decreases. In accordance with the differ-
ence, hydrochloric acid is gradually added by a conductivity control unit till the nominal value
of electrical conductivity is reached again.
Remark:
As written in the MOM of Gate 2 Meeting, GNRE-COMIBOL made no decision about package
sizes of delivered chemicals used in reagent dosing plant. ERCOSPLAN designed the reagent
dosing plant under making assumptions regarding the package sizes.
In reagent dosing plant a fork lifter for handling collector barrels, big bags and IBC is neces-
sary.
The reagent dosing plant is executed as central dosing plant for production line A & B. The
reagent dosing plant consists of a dosing plant for flocculation reagent for thickeners and a
reagent dosing plant for dosing frother solution and collector solution to flotation.
MIBC, used for flotation frother preparation, is delivered in IBC (Intermediate Bulk Container).
The capacity of an IBC is 1 m³. The agitated vessel is filled with process water. The capacity of
the agitated vessel is approx. 1 m³.
The frother is pumped by barrel pump (explosion preventing equipment) to the agitated vessel
and mixed with the process water. Afterwards the mixed solution flows into a storage vessel.
The capacity of the storage vessel is approx. 3 m³. The storage tank can feed the process for 1
hour, within this time a new batch for frother preparation has to be produced. From the storage
vessel the frother mixture is pumped by dosing pumps to flotation.
The frother reagent dosing plant is equipped with level indicators in tanks and flowmeters af-
terwards the pumps to monitor the frother reagent preparation and dosing.
Remark:
The reagent dosing plant as offered in quotation App. Q34 includes listed goods. These goods
are listed “dual-use-goods” according to EG-VO 428/2009, 2B350i. The supplier’s export con-
trol manager may support GNRE-COMIBOL at generating a request of an export license at the
BAFA (Federal Office of Economics and Export Control). Before shipping the goods, GNRE-
COMIBOL needs to show a positive BAFA approval.
The cleaner flotation process section is executed in two parallel production lines (line A & B).
Rougher flotation concentrate, scavenger flotation concentrate, reclaim brine and flotation rea-
gents flow into cleaner flotation. The cleaner flotation consists of five flotation cells installed in
line. From there a stepwise concentration of concentrates is realized due to the interconnection
of cleaner flotation cells. Final concentrate flows into leach tank. Final cleaner flotation tailings
are pumped back to rougher flotation.
Cleaner flotation is designed as 5 cell agitated flotation machine with a single cell volume of
approx. 8 m³. Flotation machines are equipped with its own level regulation. Flotation machines
are self-aerating, due to the generating of under pressure by the agitators. Surrounding air
flows into the cell through a hollow shaft. So, no external supply of compressed air for flotation
is needed. Flotation time will be according to flotation test work in laboratory 6 minutes. Clean-
er flotation is furthermore fed by frother reagent and collector reagent from central flotation re-
agent plant. Frother reagent and collector reagent are fed into the hollow shaft of the first flota-
tion cell.
An overhead crane is installed above cleaner flotation process section to ensure hoisting of
huge equipment in case of repairs and maintenance.
Centrifugal pumps in this process section are supplied with sealing water from sealing water
system. Afterwards all pumps a pressure indicator is installed to ensured correct working of
pumps. Flow rates are monitored with flow meters. Flotation tailings are monitored by K2O
measurement.
Cold leaching and product dewatering section contains generally following processing steps:
• Two step cold leaching to generate product quality
• Dewatering of suspension by vacuum belt filter
• Generation of solid free reclaim brine in thickener
• Dewatering of KCl product in centrifuges
• Conveying of wet KCl product via belt conveyors to drying section.
The cold leaching and product dewatering process section is executed in two parallel produc-
tion lines (line A & B).
First of all it has to be explained that the usage of term “dewatering” is a common household
name in potash processing. Of course, the usage of the term “debrining” would be more appli-
cable when handling with brines.
Cleaner flotation concentrate’s K2O value will be checked by K2O measurement. Cleaner flota-
tion concentrate is cold leached (cold leaching first step) together with thickener underflow and
hydro cyclone overflow as well as fugate from product centrifuges in agitated vessel. The tem-
perature measurement in agitated vessel (cold leaching tank 1) was included in the Detail En-
gineering documents according to MOM of Gate Meeting 13.-15.11.2013. Cold leached sus-
pension is then pumped to vacuum belt filter for dewatering purposes. The flow rate is checked
by flow meter. Belt filter’s filtrate is collected in vessel and pumped to thickener for generation
of solid free reclaim brine. The flow rate is monitored by flow meter, too. Filter cake from belt
filter is cold leached a second time (cold leaching second step) in agitated vessel and pumped
for pre-dewatering to hydro cyclone. The flow rate is monitored by flow meter. Hydro cyclone
underflow flows to product centrifuges. Liquid fraction’s flow rate of product centrifuges is mon-
itored by flow meter and is collected in vessel and pumped to cold leaching first step. De-
watered solids from product centrifuges (moisture 6 % or less) are conveyed to drying section.
Conveyor belts leading to drying section are equipped with K2O measurement and belt weigh-
er.
Furthermore there is envisaged that there is a possibility to bypass first cold leaching step. In
this case cleaner flotation concentrate is sent directly to second cold leaching.
Generally all tanks in this process section are equipped with a level indication. The level inside
the tank is regulated by the afterwards installed pumps with speed control. Furthermore tanks
are equipped with an overflow pipe leading to central drainage system on platform 0.00 m.
The underflow of thickeners is monitored by checking the density.
The thickener receives optional flocculant reagent, which supports settling of fine particles in
the thickener.
An overhead crane is installed above cold leaching and product dewatering process section to
ensure hoisting of huge equipment in case of repairs and maintenance.
Centrifugal pumps in this process section are supplied with sealing water from sealing water
system. Afterwards all pumps a pressure indicator is installed to ensured correct working of
pumps. Flow rates are monitored with flow meters.
Furthermore a K2O measurement device and moisture measurement device is installed at vac-
uum belt filters.
Chutes afterwards belt conveyor drops are generally equipped with overfilling detectors (LSA).
Main equipment in cold leaching and product dewatering section will be:
• Vacuum belt filters
• Thickeners
• Centrifuges
• Agitated tanks
• Pumps
• Belt conveyors
• Hydro cyclones.
Details regarding the cold leaching and product dewatering section are set in:
• PID Cold leaching and product dewatering (Drawing No. 1357 and 1358)
• Equipment list (Appendix A02)
• Arrangement drawings
• Equipment data sheets (Appendix A03)
• Equipment specifications (Appendix A06).
The scavenger flotation process section is executed in two parallel production lines (line A and
B).
Scavenger flotation is charged with rougher flotation tailings, flotation reagents from central
flotation reagent dosing plant (into first scavenger flotation cell) and reclaim brine for genera-
tion of necessary solid content. Scavenger flotation concentrates flow directly to cleaner flota-
tion. Scavenger flotation tailings are pumped to tails leach tank.
The scavenger flotation consists of nine flotation cells installed in line. From there a stepwise
concentration of concentrates is realized due to the interconnection of scavenger flotation cells.
Scavenger flotation is designed as 9 cell agitated flotation machine with a single cell volume of
approx. 8 m³. Flotation machines are equipped with its own level regulation. Flotation machines
are self-aerating, due to the generating of under pressure by the agitators. Surrounding air
flows into the cell through a hollow shaft. So, no external supply of compressed air for flotation
is needed. Flotation time will be according to flotation test work in laboratory 6 minutes. Scav-
enger flotation is furthermore fed by frother reagent and collector reagent from central flotation
reagent plant. Frother reagent and collector reagent are fed into the hollow shaft of the first
flotation cell.
An overhead crane is installed above scavenger flotation process section to ensure hoisting of
huge equipment in case of repairs and maintenance.
Centrifugal pumps in this process section are supplied with sealing water from sealing water
system. Afterwards all pumps a pressure indicator is installed to ensured correct working of
pumps. Flow rates are monitored with flow meters. Scavenger flotation feed and flotation tail-
ings are monitored by K2O measurement.
The tails process section is executed in two parallel production lines (line A & B).
Scavenger flotation tailings are collected in agitated vessel and mixed with process water to
leach remaining KCl out of the solid fraction. From there the suspension is pumped to hydro
cyclone for pre-dewatering reasons. Hydro cyclone underflow is collected and then free flowing
to vacuum belt filter for dewatering. Hydro cyclone overflow flows to thickener to separate re-
maining solids. Thickener overflow is used for reclaim brine generation and is pumped to re-
claim brine storage. Thickener underflow is dewatered together with hydro cyclone underflow
on vacuum belt filter.
Thickener underflow and hydro cyclone underflow is collected in vacuum belt filter feeding
tank. Filtrate from belt filter is collected and pumped back to thickener. Filter cake from belt
filter is washed with process water to leach remaining KCl solids and is then conveyed on belt
conveyors out of process building to tailings pile.
Conveying equipment to generate tailings pile and to distribute solid tailings on the tailings pile
is not considered.
Generally all tanks in this process section are equipped with a level indication. The level inside
the tank is regulated by the afterwards installed pumps with speed control. Furthermore tanks
are equipped with an overflow pipe leading to central drainage system on platform 0.00 m.
The underflow of thickeners is monitored by checking the density.
The thickener receives optional flocculant reagent, which supports settling of fine particles in
the thickener
An overhead crane is installed above tails process section to ensure hoisting of huge equip-
ment in case of repairs and maintenance.
Centrifugal pumps in this process section are supplied with sealing water from sealing water
system. Afterwards all pumps a pressure indicator is installed to ensured correct working of
pumps. Flow rates are monitored with flowmeters.
Furthermore a K2O measurement device and moisture measurement device is installed at vac-
uum belt filters.
Chutes afterwards belt conveyor drops are generally equipped with overfilling detectors (LSA).
The compressor plant is a central unit which serves production line A and B.
The compressor plant is required to supply dedusting filters in the drying section and pneumat-
ic valves in the entire plant with compressed air.
Compressed air needs to meet the requirements of DIN ISO 8573-1 – class 3.
Continuous process water supply to process plant is essential for stable production of KCl.
Hourly demand of process water will be approx. 270 m³/h (without design safety factor of
20 %). The process water storage tank is designed with a capacity of 2,000 m³. This amount of
process water is able to feed the processing plant for approx. one working shift. Process water
storage will be located outside of process building to save building construction cost.
Process water storage generally consists of an insulated tank and two redundant process wa-
ter pumps. These pumps supply the process with process water for sealing water system, cold
leaching, tails leaching and dilution of flotation reagents. Later on process water is needed for
drying section (not considered at the moment).
The distribution of process water to process is realized by two circular pipelines. Each circular
pipeline will be fed by a redundant process water pump.
Remark:
Process water storage tank is equipped with a level indication. Feeding pumps have to switch
off when maximum level of tank is reached (out of ERCOSPLAN’s scope of works).
Storage tank is equipped with an overflow pipe leading to central drainage system.
Afterwards all pumps a pressure indicator is installed to ensured correct working of pumps.
Flow rates are monitored with flow meters.
Optionally a water softening system for sealing water purposes is considered.
Details regarding the process water storage section are set in:
• PID Process water storage (Drawing No. 1364)
• Equipment list (Appendix A02)
• Arrangement drawings
• Equipment data sheets (Appendix A03)
• Equipment specifications (Appendix A06).
Page 177 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Reclaim brine storage consists of reclaim brine storage tanks, thickeners and centrifugal
pumps.
Thickener overflows from process are sent to an additional thickener, belonging to the reclaim
storage, because of certainty reasons. The generated thickener underflow is pumped back to
tails process section. The generated thickener overflow flows into two parallel reclaim brine
storage tanks. The reclaim brine storage tanks are operated intermitted, due to the fact that the
solid content inside the tank rises long term, even if there are only a few grams of solid in the
overflow of the process thickeners. Hence, the tanks are operated intermitted, so that from time
to time solid sediments on tank bottom can be emptied. From the storage tanks the process is
supplied with reclaim brine.
The supply of the overall process with reclaim brine is envisaged with an optimized system of
pumps feeding single consumers and pumps feeding several consumers to decrease the
number of pumps necessary for supply of process.
A second thickener is envisaged for the case of shutdown of operation of process sections,
e.g. in the situation of repairs or frequent maintenance. Process sections will be emptied by
leading thickener’s volume flows to this “shutdown” thickener. This thickener’s underflow is
then sent to wet milling and screening process section or to disposal. Thickener overflow is
pumped back to process or to evaporation pond.
As a third thickener in the reclaim brine storage a thickener for rinsing water purposes is envis-
aged. Due to the necessity of rinsing and cleaning the process plant and its equipment, con-
taminated rinsing water is generated. Collected rinsing water from drainage system will be sent
to this thickener. Underflow will be disposed. The generated overflow feeds the rinsing water
system line A & B. Hence the rinsing water has a recycling philosophy.
Furthermore there is a surplus of brine generated in the process, so that reclaim brine partially
has to be sent to evaporation pond. So leached KCl in the brine is recycled and will be fed
again to the process in form of crystallizate.
The storage tanks are located outside to save building construction cost. The storage tanks
don’t need to be insulated due to the salt concentration. Generally all tanks in this process sec-
tion are equipped with a level indication. The level inside the tank is regulated by the afterwards
installed pumps with speed control (partial). Furthermore tanks are equipped with an overflow
pipe leading to central drainage system.
Thickeners are supplied with flocculation agent to improve settling of fine particles (option).
The underflow of thickeners is monitored by checking the density.
Centrifugal pumps in this process section are supplied with sealing water from sealing water
system. Afterwards all pumps a pressure indicator is installed to ensured correct working of
pumps. Flow rates are monitored with flow meters.
Details regarding the reclaim brine storage section are set in:
• PID Reclaim brine storage (Drawing No. 1365)
• Equipment list (Appendix A02)
• Arrangement drawings
• Equipment data sheets (Appendix A03)
• Equipment specifications (Appendix A06)
Page 179 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
The rinsing water system is a central unit which serves production line A & B.
During maintenance and repair cycles it is necessary to clean pipes and equipment by rinsing.
Furthermore the production plant needs to be cleaned from time to time. Hence, a rinsing wa-
ter system should be installed inside the process building.
The rinsing water system consists of a fix installed piping system. In relevant areas of produc-
tion line A and B, flanges to install flexible pipes are envisaged. In the necessity of cleaning,
flexible pipes can be installed at these flanges to clean desired areas respectively desired
equipment and pipes.
The rinsing water system includes butterfly valves from where the supply of rinsing water can
be realized. Furthermore the rinsing water system includes pressure measurement to monitor
sufficient pressure for all places of consumption. Used rinsing water is collected at ground floor
in low points. From there the used rinsing water is pumped to a thickener for rinsing water pur-
poses.
The sealing water system is a central unit which serves production line A & B.
By sealing water, the control leakage shaft seals of the pump shaft bearings are sealed against
the aggressive agent inside the pump.
Remark:
The adding of chemicals is optional, due to the fact that there is no specific information about
the leached oxygen in the process water available.
The central sealing water system works as dynamic pressurize system with pumps.
The sealing water central unit consists of following equipment:
• Mixing vessel B1201 with storage volume of 25 m³
• Dissolution vessel B1202 with a content of 1200 l for the dilution of 25 % so-
lution zinc complex of oxyethylidene-diphosphonic acid (Zn-OEDF)
• Dosing pump P1201 – arranged as completely piped unit next to the mixing
vessel
• Centrifugal pump P1202A for central sealing water supply of line A.
Centrifugal pump P1202B for central sealing water supply of line B.
• Standby centrifugal pump P1202 – applied in case of damage of the pumps
for line A or B.
Control Circuits
Within the framework of planning for KCl production plant Salar de Uyuni, six control circuits
have been integrated into the sealing water system.
Control circuits 1 and 3 control the maintenance of constant pressure in sealing water lines A
and B.
Control circuit 2 controls the process water supply from the network to mixing vessel B1201
with engine valve for compensation of sealing water losses.
In control circuit 4, 1 % solution zinc complex of oxyethylidene-diphosphonic acid is conveyed
with dosing pump P1201 – depending on the discharge measurement of the process water –
from dissolution vessel B1202 into mixing vessel B1201 in a ratio of one part of 1 % solution to
two thousand parts of process water.
Control circuits 5, 6 and 7 are differential pressure control circuits used to discover the filters’
degree of soiling and to perform the automatic backflush during operation, guaranteed by a
two-chamber reversible flow filter.
The purpose of the drying section is to dry wet KCl from flotation process with residual mois-
ture of 6 % but with H2O content of approx. 4.5 % and convert it into a saleable product of in-
ternational standard with a requested quality of at least 95 % KCl and minimized amount of
0.3 % H2O or less.
Drying and subsequent cooling of KCl is envisaged in a vibrating fluid bed dryer/cooler unit.
Advantages in comparison to a separate arrangement of dryer and cooler are opposed at the
end of this chapter. In the following paragraphs, there is a description of the principle of fluid
bed dryer/cooler.
Inside vibrating fluid bed dryer/cooler the product is treated by causing it to vibrate on a perfo-
rated surface where air is blown in. Continuous air flow and vibration are separating and fluidiz-
ing individual particles and maximizing the surface area of material. In accordance, the rate is
increased at which heating and drying but cooling as well will occur. The vibration of the pro-
cessor also serves for uniform and continuous transportation of the material along a defined
pathway according a "first in/first out" method.
This equipment has two processing zones. In the first zone of the dryer/cooler moisture is re-
moved from KCl by blowing in hot air which is heating the product. Hot air has a high potential
for dehumidifying the product down to 0.2 % H2O. Hot air is generated by gas burners. There-
for cleaned but still hot exhaust air from cooling is reused and blown with recirculation fan
through gas burner where it is indirectly heated up to 450 °C. As heating media for burners
liquefied petroleum gas (LPG) and additional ambient air is applied. LPG is stored outside pro-
cess building in a tank. A pipeline is connecting the tank with the burners. The LPG tank is not
in the scope of work of ERCOSPLAN.
During the drying process KCl is heated up to approx. 120 °C and so it needs to be cooled to
get the optimal temperature for conditioning with anticaking agent and to reduce risk of injury.
For that reason in the second zone of the dryer/cooler heated fluidized product is cooled down
to 60 – 70 °C by blowing ambient air from the bottom into the equipment.
In order to prevent the uppermost layers of fluid bed particles from being pulled into the ex-
haust stream, the fluid bed exhaust ducts have large diameters to reduce air velocity. However,
fine particles are entrained in the exhaust air from drying and cooling. Therefor fluid bed appli-
cations are requiring a de-dusting system.
According to the flotation process the drying section is arranged in two lines each with a ca-
pacity of 47.5 t/h of KCl and designed for parallel but independent and continuous operation
(regular operation mode). But design capacity per drying line is approx. 80 t/h of KCl. So in
case of disruption in one drying line it is considered to dry the entire product from flotation in
the other line of drying section (emergency operation mode). Under this exceptional circum-
stance the production in the flotation department is reduced to 80 %. The anticaking agent dos-
ing system, as part of the drying section, is executed as central facility which serves both dry-
ing lines. The drying section contains generally following processing steps:
During the process of drying and cooling exhaust gas is generated that contains a certain
amount on fine KCl dust. The dust needs to be separated from exhaust air by filters comply
with environmental regulations and standards and to minimize product losses. Therefor per line
are installed two bag filters for the dryer/cooler and one for conveying equipment of dried KCl.
Exhaust air is sucked inside the filter with a fan what causes negative pressure inside the bag
house filter. The bag filter housing is generally designed for a low-pressure of 50 mbar whereas
low-pressure of maximum 30 mbar is available during normal operation. All the air taken in is
forced to stream through the filter tubes toward the upper exit. These bags are holding the dust
back and therefor need to be cleaned regularly. The cleaning is carried out via compressed air
(6 bar). Here electrically controlled compressed air pulses are provided section-wise (e.g. filter
tubes 1-3-5-x and in the next step 2-4-6-x) in a predefined timing.
Pulse duration is about 60 ms and is gauged such that the filter area is cleaned sufficiently.
Nevertheless, cycle and break times are variable and can be adapted to operating conditions.
It should be added that cleaning can be carried out via vibration as well. However, this method
is not recommendable especially in the potash field due to various disadvantages.
In case compressed air is used, it is differentiated between time-controlled, differential pressure
controlled and pre-pressure controlled operation mode. All three modes are considered to be
continuous processes.
Cycle times and compressed air are defined for time-controlled cleaning.
During pure differential pressure control the cleaning is carried out with fixed compressed air
depending on differential pressures measured in the filter sections.
For the pre-pressure controlled cleaning the compressed air demand is regulated via continu-
ous adaption of the cleaning pressure depending on the operating conditions.
Thereby the compressed air demand is minimized, amount of dust is more even, capacity of
dust discharge can be better utilized and finally mechanical stress including abrasion of bag
filters is minimized.
An exhaust fan is transporting filtered air from drying zone of dryer/cooler to environment
though filtered air from cooling zone of dryer/cooler is sent back to drying with recirculation fan
to save thermal energy. KCl dust is discharged from bag filters into a vessel where it is dis-
solved and pumped back to cold leaching step. Hence, product will be saved.
Generally all tanks in this process section are equipped with a level indication. The level inside
the tank is regulated by afterwards installed pumps with speed control. Afterwards all pumps
pressure indicators are installed to ensure correct working of pumps. Centrifugal pumps in this
process section are supplied with sealing water from sealing water system.
An overhead crane with a lifting force of 200 kN is installed above drying section to ensure
hoisting of huge equipment in case of repairs and maintenance.
Potassium chloride is a hygroscopic material. Especially after drying and cooling KCl has high
affinity to absorb water. Therefor application of anticaking agent is necessary to avoid agglom-
eration and clumping of product.
After the product has left the cooler it is fed to a mixer. Anticaking agent solution is also
sprayed into the inlet of the mixer to optimize pre-distribution in product stream. During mixing
process the anticaking solution is coating KCl crystals on the surface and prevents a water ad-
sorption from ambient.
The anticaking agent dosing system is executed as a central facility for drying line A & B.
The required reagents are delivered to plant site by truck. The anticaking agent dosing system
consists of:
• Big-bag discharge system consisting of two big-bag discharge stations
• Anticaking solution dosing station
Anticaking agent dosing system is located in the process building in the drying section on plat-
forms +9m and +18m.
The anticaking agent dosing system is operating automatically and consists in general of two
big-bag discharge stations, two agitated vessels and three dosing pumps.
Two anticaking reagents are required for the conditioning of KCl. They are delivered and stored
in big-bags. For application of these two reagents two discharge stations are necessary.
The big-bags are lifted by crane in the discharge station. These big-bags are automatically cut
by knives and emptied into buffer container.
The anticaking reagents are added by screw conveyors into the repulping tank and dissolved
with water. After the dissolving process the anticaking solution flows into the agitated vessel
from which the solution is continuously delivered to the mixers in both drying lines by dosing
pumps.
Potassium ferrocyanide (K4[Fe(CN)6]) and sodium ferrocyanide (Na4[Fe(CN)6]) are very similar
molecules with similar mode of action. Application of both chemicals is possible.
In order to avoid an additionally contamination of the product with Na+ ions, we decided to use
potassium ferrocyanide.
For the selection between K4[Fe(CN)6] and fat alkylamine, it is important to compare the differ-
ent solvents.
Potassium ferrocyanide (K4[Fe(CN)6]) and sodium carbonate (Na2CO3) solve optimally in water
at 40 °C. It forms a homogeneous liquid mixture. It is necessary to temper the solution at 40 °C.
The optimum KCl temperature (after cooling) for coating process is circa 60 °C.
Variant 1 was dismissed because exact dosing of the solid and an optimal mixing process are
difficult to realize. Furthermore, the pre-mixing with the product before the mixer is not good.
Variants 2 and 3 require delivery of gas-oil to the production plant and appropriate storage as
well. Gas-oil consumption is approximately 265 l/h.
Additionally, there are safety concerns for handling with gas-oil at temperatures of 50 °C –
60 °C. Therefore, increased safety standards are necessary.
Furthermore, variant no.3 requires constant stirring for emulsification.
Fat alkylamine is generally sensitive to high temperatures and tends to stick during transporta-
tion and storing.
After these considerations, the combination of potassium ferrocyanide and sodium carbonate
was preferred as anticaking agent. Water with a temperature of 40 °C is used as solvent.
Safety note
The handling of Potassium ferrocyanide (K4[Fe(CN)6]) and sodium carbonate (Na2CO3) has to
be under consideration of available material safety data sheets. According to these data
sheets, the both chemicals can be hazardous.
Table 8 Water and Anticaking Reagent Consumption for 3 Hours Operating Time
Remark:
The supplier of anticaking agent dosing system, considered in the detail engineering docu-
ments, cannot have any knowledge about the finally applied chemicals by GNRE-COMIBOL.
Finally applied chemicals by GNRE-COMIBOL still need to be surveyed and tested on chemi-
cal's product quality and pourability by GNRE-COMIBOL together with the supplier of anticak-
ing agent dosing system after the detail engineering phase to guarantee optimum design and
proper functioning of this facility.
Based on supplier’s quotation installation of fluid bed dryer and cooler as separate equipment
and as combined equipment including peripheral equipment have been evaluated.
In respect to the two-line process design of the flotation and due to the product volume two
drying lines with one combined dryer/cooler aggregate per line is installed. Combined dry-
er/cooler aggregate occupies less space inside the process building than separate devices
and transportation is more easy. Instead of static equipment we recommend equipment with
vibration drive to make sure product will pass the dryer/cooler in any case, even when agglom-
erates occur.
Sending back filtered but still hot exhaust air from the cooler section to the burner saves fuel
and reduces demand on thermal energy by approx. 20 %. A positive side effect is the demand
on electrical energy can be further reduced because of the recirculation fan at the same time is
feeding the drying section and one big electrical consumer per line can be saved.
For feeding of product to the dryer installation of vibration feeder is recommended. Compared
to a trough chain conveyor a vibrating conveyor assures optimal distribution of wet KCl inside
the dryer/cooler and needs less energy.
For the filter system we recommend to use separate bag house filters for drying and cooling
section instead of arrangement of cyclone-scrubber-droplet separator plus bag house filter. In
general combination of cyclones and bag house filters is proven technology but has several
disadvantages compared to application of only bag house filters. While influence to investment
costs is insignificant operating costs for bag house filters are lower and further peripheral
equipment such as pumps and tanks is not required, just as there is no demand on additional
water. Last but not least content of dust in the exhaust air from bag house filter can be reduced
to one fifteenth compared to a cyclone. In the end content of dust in the exhaust air will be less
than 10 mg/m³.
Page 188 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Regarding the equipment of drying section including anticaking details are set in:
• PID Drying / Anticaking (Drawing No. A 1370 / 1371 / 1374)
• Equipment list (Appendix A02.1)
• Arrangement drawings
• Equipment data sheets (Appendix A03.1)
• Equipment specifications (Appendix A06.1)
• Quotations App.Q53
• Quotations App.Q63
The product storage is a central unit which serves production line A and B.
Product comes from drying line A & B, each on its own conveyor belt. If there is a malfunction
of one of these conveyor belts, product can be transported on a redundant conveyor. Hence,
no shutdown of drying because of conveyor belts is necessary. Conveyor belts are equipped
with belt weigher, so that the product leaving the drying section can be registered.
The dried product arriving from the drying section has the possibility to be transported to the
product storage, to bypass the product storage by going directly to truck loading, or to be dis-
tributed between product storage and truck loading.
Product to be stored in the product storage is done by an increasing belt conveyor. Afterwards
a moveable and reversible conveyor belt generates the longish storage. Product storage’s ca-
pacity is designed with 30,000 tons of wet salt. In case of empty product storage, approx. 322
hours of production can be charged into the storage until the full capacity is reached. Hence,
the storage capacity is approx. 14 days respectively 2 weeks.
Discharging of product to truck loading will be done by automatic scraping technology. The
scraper feeds a conveyor belt leading out of the product storage. Discharge capacity will be
approx. 320 t/h.
Afterwards product storage discharge the product is transported to truck loading on conveyor
belt. The conveyor belt is equipped with K2O measurement, moisture measurement and belt
weigher to register the final product leaving the product storage.
Chutes afterwards belt conveyor drops are generally equipped with overfilling detectors (LSA).
Product storage will be a closed building, so that there is no bad influence due to precipitation
and contamination.
The truck loading is a central unit which serves production line A and B.
Design Criteria
The truck loading section is designed for loading 12 h/d and 5 d/w. It consists in general of
4 silos (2 silos charging – 2 silos discharging and reverse). The truck loading section is de-
signed with a necessary minimum loading capacity of approx. 320 t/h. Hence, at two silos eve-
ry 7.5 minutes a truck needs to be loaded to transport all the product which is produced in the
potash plant (16 loading cycles per hour are necessary).
Dry product from product storage is conveyed to truck loading section. Truck loading will take
place in an additional building. Dry product is split by two-way distributor to two conveyor
belts. Chutes afterwards belt conveyor drops are generally equipped with overfilling detectors
(LSA). At conveyor belt drops fine dust is generated. Dust will be separated by dedusting de-
vices, executed as bag filters including air ventilators. Separated dust is led back to conveyor
belt. Bag filters are equipped with pressure measurement to indicate filter charge.
Alternated feeding principle of silos is done because of charging one silo by conveyor belt and
discharging of second silo into truck at the same time. The truck loading capacity is designed
with 20 tons, hence the capacity of each silo is > 20 tons due to possible plugging of product
inside of the silos.
Silos are equipped with dedusting device on top of the silo. Bag filters are equipped with pres-
sure measurement to indicate filter charge.
Furthermore silos are equipped with weighing cells, so that exact loading of trucks is guaran-
teed. Each silo discharge flange is equipped with five pneumatic sliders which are opening in
case of loading one after another. Hence the truck doesn’t need to change its position during
loading. Before and after truck loading it is recommended to install a truck scale.
For detailed logical description of control loops (control circuits) please see Appendix E8 –
Control Circuits.
After handing over of the final Detail Engineering report, GNRE-COMIBOL will start the pur-
chase phase of technical equipment. Due to the Bolivian regulations, GNRE-COMIBOL needs
to start the purchase phase with a public bidding. Due to the necessity of the public bidding,
GNRE-COMIBOL was not in the position to fix suppliers and type of the technical equipment
during ERCOSPLAN’s engineering phase, so that ERCOSPLAN had to make assumptions.
Hence, the chapter of “Operation Manual” can only have a general character.
The start of the test-run and in particular start-up process is a critical interface during the com-
missioning phase. Safety risks but also risks regarding costs, schedule and quality increase
considerably once more. For all parties involved, the „moment of truth“ starts during the hot
phase of commissioning. Before the plant is started “on the push of a button”, all preconditions
should be checked minutely again and be analyzed and confirmed by the commissioning
team. This chapter provides a checklist for the pre-commissioning inspection and especially
pre-start-up inspection.
For the intended normal operation of the production plants, independent single plants will be
installed by suppliers to realize several performance steps.
Start-up of the single plants is carried out under the responsibility of the respective suppli-
er/installation company and in cooperation with GNRE-COMIBOL employees.
The supplier is also responsible for the provision of the operating material and input/raw mate-
rial.
Focal points for commissioning preparation:
1) Assembly/Maintenance
• Units installed; mechanics/technicians and operators briefed
• Spare parts and consumables available in the store-room
• Special tools and operating instructions available
• Inspection and maintenance instructions for equipment announced
• Input/raw material available
• Requirements of equipment manufacturers/suppliers catalogued (documentation)
• Inspection protocol is available.
4) Operating Materials
• Electricity
• Inspection of constant availability
• Overload setting for redistributions
• Insulation and safety regulations
• Samples from transformer oil analyzed
• Compressed air
• Compressed-air pipeline cleaned by blowing-out
• Water from equipments removed
• Drying plant filled with adsorption agent and compressed-air pipeline dried-out.
5) Laboratory
• Laboratory furnished, laboratory staff trained
• Sampling schedule published
• Specifications for all products and input/raw materials available
• Analysis of samples in the laboratory defined.
8) Safety
• Protective clothing, helmets, work gloves, lamps
• Safety regulations for power blackout, fire etc. available
• First-aid and medical care/treatment guaranteed
• First-aid-kits, blankets, portable stretchers, medicine, reanimation devices ready for use.
9) Fire Protection
• Portable fire extinguishers ready for use
• Fire extinguishing procedure planned
• Fire brigade informed/organized.
7.6 Utilities
The amount of electrical energy demand is required for the production of 700,000 t/y KCl,
based on a flotation process.
The calculation is based on following basic information/assumptions:
• Calculated installed electrical power for flotation process, wet salt storage, product
storage and truck loading
• Factor for coincidence, working load and power factor (experienced data from analog
plants)
• Energy demand for drying equipment (experienced date from analog plants)
• Energy demand for necessary plant parts outside of ERCOSPLAN battery limits (experi-
enced data from analog plants).
The calculation of the electrical energy demand is attached to this report in Appendix E2. For
the KCl plant a total electrical energy demand of
Ptotal = 11 MVA
is required.
The power supply of the KCl plant will be realized in two phases:
- Phase 1: Without connection to the local grid via generator power station
- Phase 2: Electrical power supply via local grid (final variant).
The generator power station has to be erected in modules with units of 8 pcs. en-
gines/generator. Each unit is provided with a power of 1.9 MVA, they are each installed in a
separate 40-feet-container and delivered in bloc to the building site.
Following plant units are arranged in the individual containers:
• Diesel engine
• Generator 1.9MVA / 6kV
• Day fuel tank for diesel
• Control system for complete unit
• Engine cooler (will be installed on the container roof).
7 pcs. engine/generator units are required for the running operation of the production plant.
One additional unit is permanently maintained rotational.
The energy of generators is fed into a 6kV generator switch gear which is installed in a sepa-
rate container.
According to the planning, diesel is stored in two supply tanks. Both tanks are also installed in
separate 40-feet-containers and are delivered to the building site en bloc.
Electrical energy is fed via cable to the 6kV switch gear SM which is installed inside the power
station.
The generator power station should be set up as turnkey system. It is only used up to the
commissioning of the electrical power supply via local grid.
Arrangement of the power generator station is presented in drawing E2504.
The final electrical energy supply of the KCl plant is made from the Bolivian energy supply net-
work. Energy supply of the industrial plants within the Salar de Uyuni shall be made via 230kV
overhead line.
An electrical power transformer substation 230kV/24.9kV is built in the Salar de Uyuni area as
central supply station from where energy is fed via two cable systems into the 24.9kV switch
gear within the power station of the KCl plant.
Power supply terminals of the 24.9kV switch gear of the power station KCl plant are defined as
power limit.
Delivery, installation and connection of both 24.9kV cable systems between central electrical
power transformer substation 230kV/24.9kV and power station KCl plant is not scope of the
present Detail Engineering.
Delivered process water temperature is between 12 and 18 °C. Process water must have suffi-
cient quality for processing needs.
Waste water treatment is osbl (outside battery limits). A waste water treatment plant should be
installed by GNRE-COMIBOL.
The rain water from the roofs of the production building and from the wet salt storage will be
collected in separate retention basins, where the rain water will evaporate. The relative low pre-
cipitation allows such simple solution.
For the roofs of the production building two basins of approx. 400 m³ will be enough; for the
wet salt storage two basins of approx. 200 m³ will be enough. For the drainage of in-plant
roads several basins will be arranged.
8 generator systems, each with a power of 1,900kVA, are installed in the power station for the
energy supply of the KCl plant.
Considering that one generator system is permanently switched-off for maintenance purposes,
a maximum continuous power of 13,300kVA is available. Only for a short time, e.g. for activa-
tion operations, generator can be overloaded up to 10 %.
Connection and disconnection of the diesel/generator units is manually depending on the re-
quired power of the entire plant. The associated control system is included within the scope of
delivery of the generator power station.
Electrical energy is fed into the 6kV switch gear SG which is installed inside the container of the
generator power station. This switch gear is also included in the turnkey scope of supply of the
generator power station.
Energy transport from 6kV switch gear SG to 6kV main switch gear SM in the power station at
the process building is made via two separate cable systems. Each of the cable systems has to
be designed for transfer of the entire generator power.
This type of energy supply is the final version and will be put into operation as soon as follow-
ing upstream plant units are ready-to-operate:
• 230kV overhead line
• 230kV/24.9kV power transformation substation
• 24.9kV cable connection between substation and power station KCl plant.
Energy is fed via two separate cable systems into the 24.9kV switch gear of the power station
KCl plant.
This switch gear consists of 6 cabinets (see drawing E2001 and E2004):
• Cabinet 1: Feed 1 from 230kV/24.9kV substation
• Cabinet 2: Feed 2 from 230kV/24.9kV substation
• Cabinet 3: Coupling
• Cabinet 4: Measuring cabinet
• Cabinet 5: Outgoing 1 to transformer 1.01 (12.5MVA 24.9kV/6kV)
• Cabinet 6: Outgoing 2 to transformer 1.02 (12.5MVA 24.9kV/6kV).
Energy supply of the 6kV main switch gear SM is made via transformer 1.01 and 1.02.
Considering a power demand of 11MVA for the entire plant, energy supply of the KCl plant
shall be realized via 2 transformers each with a total power of 12.5MVA.
Thus, following requirements are guaranteed:
• During normal operation with two transformers, these work in a low-loss operating
range.
• In case of failure of one transformer, the operation of the entire plant is possible via the
second transformer.
• When operating the plant with two transformers, enough power reserves for a possible
increase of the production capacity are available.
7.7.1.3.1 General
Main system for power distribution in the KCl plant is the 6kV main switch gear. All electrical
energy consumers of the KCl plant are directly/indirectly supplied via this switch gear.
• Supply 6kV level: In the KCl plant, altogether 7 motors with a power of 350kW respec-
tively 500kW are installed. The motors are directly connected to the 6 kV main switch
gear SM.
• Supply 0.69kV level: Supply of the 0.69kV consumer is made from 6kV main switch
gear SM via transformers 1.6MVA...6kV/0.69kV. These transformers supply the 0.69kV
motor control center MCC.
• Supply 0.4kV level: Supply of the 0.4kV consumer is made from 6kV main switch gear
SM via transformer 1.6MVA 6kV/0.4kV. These transformer supply 0.4kV main switch
gear.
(Power supply system see drawing E2000)
This switch gear is divided into two sections that are connected via cable-coupling:
Section 1
• Feed of transformer 1.01 (24.9kV / 6kV)
• Feed1 of 6kV Generator switch gear SG
• Outgoings transformers 6kV/0.69kV
• Outgoings motors
Section 2
• Feed of transformer 1.02 (24.9kV / 6kV)
• Feed 2 of 6kV Generator switch gear SG
• Outgoings transformers 6kV/0.69kV
• Outgoings transformer 6kV/0.4kV
• Outgoings motors
The switch gears are placed at the ground level in the power station.
During planning phase of which gear has to be connected with which MCC, affiliation of gears
to both technological production lines A and B has been considered. For increasing the supply
guarantee it is possible to connect the MCC for example via coupling switches and mounted
busbars in case of failure of one transformer.
With this type of operation, two transformer maximum are allowed to feed into the MCC for rea-
sons of short circuit protection. This has to be ensured via interlocking system between feeding
switches and coupling switches.
The switch gears are placed on the +12.60m platform in the power station.
7.7.1.3.5 Transformer
Transformer 3.01
• Primary nominal voltage: 6kV +/- 2 x 2.5 %
• Secondary nominal voltage: 0.4kV
• Max. power loss: 18.5kW
• Short circuit voltage: 6 %
• Vector group: Dyn5.
The transformers are located at the ground level in the power station.
All buildings have to be equipped with a separate grounding system which consists of follow-
ing subsystems:
• Foundation earth electrode
• Band iron loops from stainless steel, which are installed under the foundations of the
buildings.
• The ends of these foundation earth electrodes are led un-insulated out of the foundation
and are connected with the steel construction of the building and the remaining ground-
ing system.
• Depth earth electrode
• Components of the grounding system of the single buildings have to be interconnected
(intermeshing).
In order to avoid unduly high touch voltages for the operating staff, all continuous metallic parts
of the production plant have to be connected among each other and in addition with the
grounding system. That regards following parts of the plant:
• Building construction
• Pipelines
• Frames of plant equipment
• Cable trays
• Control cabinets
• Substructures (e. g. belt conveyor systems, pipelines).
The buildings and plant facilities have to be equipped with a lightning protection system that
consists of following components:
• Outside lightning protection system
For that system, lightning arresters have to be installed on the roofs of the buildings and
conveyor bridges as well as on the chimneys. These arresters have to be connected
with the metallic roof constructions and, via down conductor lines, with the grounding
system.
• Overvoltage protection
All over-voltages induced into the cable by a lightning strike are directly diverted to the
grounding system via lightning arresters.
For the entire production process, three different control options have to be realized for all
gears, which can be optionally activated.
• Interlocked central control (selected from operator station central control room)
All processes run fully automated. Abnormalities from standard operation conditions are
visually and acoustically displayed at the operator station of the central control room. In
case critical conditions occur, endangered plant components are switched-off automat-
ically.
This type of control is the preferred option.
• Un-interlocked central control (selected from operator station central control room)
This type of control shall only be used in exceptional cases and only for limited opera-
tional areas. All system conditions are displayed in the central control room. Necessary
switching operations are carried out manually by the operator.
• Local control (selected from local control box)
This type of control is only for test purposes after repairing works. Corresponding gears
are activated via local control boxes. The control is carried out without interlocking sys-
tem.
During development of software for plant control, Appendices E8 and E9 (control circuits and
interlocking system) have to be considered.
7.7.2.2.1 Architecture
Information about the process flows and process status in the potash plant as well as their
manual influence is carried out by operator stations assigned to the individual production sec-
tions according to the requirements.
The exchange of data with the automation stations AS well as the manual access to the opera-
tion stations is organized by redundant route control servers.
Actual control of the process is made via automation stations AS1 (PLC1) to AS4 (PLC4).
Via the programmable CPU’s installed in these automation stations, processing of data and
realization of control tasks is performed according to the control philosophy. The inputs and
outputs of the signal units are logically linked.
Data transfer from the peripheral control units ET from the field level is made via Profibus DP
cables.
All technical details for the four automation stations are presented in drawings E2301 – E2304.
In the field level, data and test results of following plant components are recorded:
• Local control boxes
• Measurement equipment
• Limit switches
• Sensors
• Operating conditions of the technological equipment.
Following plant equipment are activated via control equipment in the field level:
• Contactors MCC
• Magnetic valves
• Frequency converter
• Separate control cabinets for technological units (thickener, portal scraper).
Information transfer towards this plant equipment is made via multi-core copper cables or Pro-
fibus DP cables.
Local control tasks are realized via peripheral control units ET (remote input/output RIO). In-
formation transfer towards this plant equipment is made via multi-core copper cables or Profi-
bus DP cables.
All technical details for automation stations ET are presented in the drawings E2305 – E2349
and E2393 – E2400.
7.7.2.3 Instruments
The continuous production process of the potash plant requires the installation of extensive
measurement equipment in all areas of the plant. That measurement equipment is basis for the
realization of following tasks:
• Manual monitoring of processes
• Realization of control circuits
• Realization of interlocking systems
• Safety measures
• Evaluation/archiving of production data.
According to the P&ID drawings of mechanical and mining engineering, the following continu-
ous measurement devices are intended in the production process:
• Temperature measuring device
• Pressure measuring device
• Density measuring device
• Flow rate measuring device
• Level measuring device
• Conductivity measuring device
• K2O measuring device
• Bulk measuring device (belt weigher).
These measurement devices are implicated in the process control by digital signals, 4-20mA-
analog signals or Profibus DP (belt weighers).
The complete list with all required instruments is attached as Appendix A5 and A5.1.
7.7.3.1 Communication
For the communication in the area of the potash plant a uniform Ethernet-network has to be
realized. This network consists of intermediate distribution frames (including active and passive
components) and their connection via fiber optic cable. The communication system consists of
following main components:
• Communication server
• Main intermediate distribution frame (MIDF)
Page 208 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 370 Fax: +49 361 3810 403 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
b) Communication System
According to the present planning, the communication center consists of following main func-
tion blocks:
• Redundant server system
• Monitor workstations that can control all communication devices
• VoIP-system telephones
• IC-telephone-stations for the operation of EA/IC systems
• VoIP-telephone gateway for the transition from the internal network to the local tele-
phone provider
• EA/IC basis station (EA/IC electro-acoustic/intercom) for the connection of EA/IC sub-
stations on the site
• Internet service purchased from an Internet service provider (ISP).
c) Telephone System
The telephone system has to be designed as VoIP-system (Voice over Internet Protocol).
For the selection of telephone types, the local operating conditions have to be considered.
The telephones are connected to the intermediate distribution boxes via copper-data-cable.
d) Radio-Communication
It is planned to use a DMR-system (digital mobile radio) as radio system. According to present
planning, the radio system operates in the 4 m-band.
For a comprehensive site supply (exclusive of guaranteed indoor supply) on the surface it is
assumed that four DMR basis stations are sufficient.
The cross-linking of stationary radio stations is carried out by Ethernet-network.
Following function can be realized by DMR-system:
• Direct communication of handheld and
• Car radio transceivers among each other (exclusive of stationary radio station).
• Process building
• Power station
• Generator station
• Wet salt storage
• Product storage
• Truck loading.
The system is expandable for further buildings or plants.
The central fire alarm system is accommodated in the power station. Here the central alarm is
given if the system is triggered.
On the site, there are planned substations that are connected to the central fire alarm system.
Automatic detectors, manual alarms and signaling devices are installed in areas with extended
endangerment as well as in relevant rooms.
In order to increase the functional reliability, detectors and signal transmitters are connected
via ring-bus-system to the respective substation.
Via corresponding fire service indicator panel and fire service operator panel in the substations,
the action force can catch up on the position of the triggered detector and purposively investi-
gate the reason of triggering, and if necessary initiate the firefighting.
A flash light at the outside front of the respective building, already visible over a long distance,
informs about the triggering place.
Relevant areas at plant site are monitored by video cameras. Therefore IP-Cameras (internet
protocol cameras) with ingress protection rating 66 (IP 66) are used. The data transfer is real-
ized by Ethernet. Displaying of video camera data is available at all working station computers.
Process water must have sufficient quality and quantity and is delivered to plant site from West
direction. For processing needs an insulated process water storage tank is envisaged. The
process water tank is located in front of the process building to save building cost.
Firefighting is outside battery limits.
At plant site processing and sanitary waste is produced. Processing waste consists of solid,
liquid and other waste. Solid processing waste is conveyed to tailings pile approx. 500 meters
away from process building. Liquid processing waste is pumped back to evaporation pond
respectively is pumped to disposal.
Sanitary waste and other waste management is outside battery limits.
7.8.1 General
7.8.1.2 Buildings
Buildings for maintenance, storages for spare parts, workshops, administration, social func-
tions, security, etc. are not included in the scope of work of ERCOSPLAN.
For arrangement of buildings, facilities and infrastructure on plant site see drawing 3001_Site
Layout Plan.
7.8.1.3 Facilities
7.8.1.4 Infrastructure
The process building has a length of approx. 115 m (including drying) and a width of approx.
85 m. The process equipment is supported on the ground floor and on three technological
main platforms. There are additional technological platforms arranged. The height of the build-
ing is up to approx. 31 m on average, in an elevated part approx. 36 m.
For access to the technological platforms, seven stairways are installed, which will also be
used for evacuation in case of fire. The walls of the stairways are constructed as masonry walls
for fire protection. The way to reach a stairway from any point inside the building may not be
longer than maximum 70 m. Because of the minimal number of persons inside the building,
minor fire load density, big height between main technological platforms and big platform
openings, the size of the fire battle block and the length of the evacuation way of 70 m are suf-
ficient.
For maintenance the whole area of the process building is provided with indoor-cranes.
The process building is a conventional braced-steel structure of standard rolled sections and
welded wide flanges supported on a foundation slab. High-strength structural bolts are used
for all connections of beams, columns and bracings.
Due to the big size of the structure an expansion joint in the steel structure between the grid
lines 9 and 10 will be arranged.
The platform covering is made of wooden floorboards of 50 mm thickness, or steel plates, or in
exceptional cases of concrete slabs. Elevated concrete slabs will be constructed in process
areas only if essential. In wet areas, the covering of steel plates and concrete slabs is equipped
with formed soffits.
Horizontal bracing of floors and roofs is provided by open structural sections. Generally, dia-
phragm capability of floors and roofs is not utilized as primary bracing in process areas. Dia-
phragm contributions from concrete decks and floors are utilized as primary load-carrying
components in office areas and roofs over electrical rooms, pump houses and similar installa-
tions. Concrete floors, roofs and checkered-plate floors are utilized for stiffness if essential.
Vertical bracing is located in exterior walls where possible.
In general, hollow structural sections are not used in areas of severe and extreme corrosion.
The roofing system consists of trapezoidal cross sections with thermal insulation and roof seal-
ing. Generally, the roof is sloped and provided with gutters and downspouts.
The process building will get siding of trapezoidal cross sections or bi-stretched PVC sheets in
the high resistance range (RENOLIT ONDEX HR) with thermal insulation. All flashing and fas-
teners are stainless with sealing washers. Inside, the wall will get a siding with wooden panels.
Windows with wooden frames will be used for lighting and natural air ventilation.
The steel structure and dado walls will be based on a foundation slab of approx. 1.0 m thick-
ness. All steel columns will be based on single pedestals of 0.3 m height.
A small channel on the surface of the foundation slab will be arranged around the building to
prevent decomposition of the salt ground by drainage of rain water from the siding of building.
The structure will be founded on a reinforced concrete foundation slab, which will be built on
the soil preparation of the plant site. The foundation slab will be made of reinforced concrete
and accommodate anchor bolts and embedded parts.
The concrete is made of sulphate-resisting cement. Because of high and severe corrosion,
foundation slab is made with a high strength of concrete, for example 45 N/mm², and an ele-
vated concrete cover.
The production plant will be provided with heating to guarantee an inside temperature of more
than 5 °C.
7.8.4 Infrastructure
For drainage, the road is sloped to one side. The drainage will be done into the site preparation
structure across the road.
A sewage pipe system will be built from points where waste water accumulates to the sewage
plant. In case of impossibility of underground pipelines, a gravity drainage system cannot be
used. The waste water has to be pumped to the sewage plant. All pipelines will be provided
with heating and insulation.
7.8.5 Facilities
On the plant site in Bolivia, the measured maximum between 2010 and 2012 is 1,135.3 mm,
that is approx. the double capacity as in Unterbreizbach.
For calculation of rainwater retention, the German values will be doubled. For an industrial site
usually an annuality of 5 years is used. Since statistical extreme values are missing in this case,
the values of an annuality of 100 years are used.
Due to the limited place closed to the process building the north-eastern and the south-eastern
retention basin will be equipped with pumps.
The dikes of retention basins will be built with the same material like building ground prepara-
tion of the plant site. The sealing will be done with a PVC-membrane. For drainage of rainwater
to the basins prefabricated concrete channels will be arranged.
The tailing pile will be located approx. 500 m in the east of the plant site. The ground of the
tailing pile will have the preparation as the plant site. The disposal will be filled up there to a
height of approx. 30 m. For drainage of the brine, the leak from the filled-up mass, a dike of
compacted salt with a height of approx. 2 m, will be arranged around the filled-up mass. The
distance between dike and the base point of filled-up mass should be approx. 20 m. The brine
will be collected in that interspace and evaporate there.
8 Project Execution
Below mentioned is a description of an execution procedure proposal, applicable for the exe-
cution structure of this project. However the execution procedure is outside battery limits of
ERCOSPLAN´s scope and is in full responsibility of GNRE-COMIBOL.
8.1 Objectives
The main objectives of the proposed project execution plan are to complete the project:
• Within (or below) the budget
• On (or ahead of) schedule
• While meeting the quality requirements and constructing the plant in the most efficient
manner
• While ensuring that health, safety, environmental and social obligations are adhered to.
8.2 Criteria
The project execution philosophy adopted also complies with the following criteria:
• Maximization of the sourcing of the equipment and materials from Bolivian or South
American Sources
• Execution by an general contractor team owned by GNRE-COMIBOL with the capacity
to manage and execute the full scope of work to be performed
• Training of residents local to the project site such that they can be productively em-
ployed during the construction phase
• Establishment of a construction-driven schedule.
The GNRE-COMIBOL project manager will be responsible for mobilizing a dedicated team of
senior engineers and technicians with the relevant experience to execute the project. He or she
will be responsible for implementing the necessary tools and systems to perform the work in
accordance with the methodology defined in this section of the report.
Soon after the initial mobilization, a project kick-off meeting will be held to introduce the team
members, confirm the project scope and present the project quality, cost and schedule objec-
tives. The respective responsibilities of the GNRE-COMIBOL project execution team will be
presented as well as the communication interface methods. The purpose of the kick-off meet-
ing is also for the participants to be made aware of their roles in the overall organization and of
the expectations placed on them.
The project procedure manual is prepared at the beginning of the detailed engineering and is
maintained and updated regularly, simultaneously with the project quality plan.
Project meetings will be held by the GNRE-COMIBOL project execution team on a regular ba-
sis to review the status of the project and to make decisions related to corrective actions. The
meetings scheduled on a regular basis shall be as shown in Table 15.
Meeting Chaired by
Monthly overall project review with owner Project manager
Weekly engineering and procurement progress Project manager
Monthly cost review Controls manager
Weekly construction progress review Construction manager
Weekly punch list reviews Engineering department manager
8.3.4 Communications
Successful project execution involves close and open communications among all parties and
all team members.
• The project management personnel must communicate the scope, technical require-
ments, schedule, estimate, project objectives and contractual terms to the team
• An integral part of project communications is defined precisely in the project procedure
manual
• Project web-sites are used to facilitate communications, electronic transfer of data and
e-mail
• To further facilitate communications, the project team will be located in a task-force ar-
ea. This creates an environment conducive to easy communications.
GNRE-COMIBOL’s project execution team’s ability to execute its mandate from the GNRE-
COMIBOL board in an efficient, timely and cost-effective method is dependent on the availabil-
ity and accuracy of information provided by its team and others. It is therefore proposed that
the management of all information flow, normally represented in documents, should be its re-
sponsibility and should be coordinated through a computer-assisted project management sys-
tem.
8.3.5 Reporting
GNRE-COMIBOL’s project execution team must work closely with GNRE-COMIBOL project
management and therefore will provide regular reports, updates and forecasts on the project
progress. Typical reports will include:
• Man-hour expenditure against budget
• Progress against plan
• Change order control
• Areas of concern.
Engineering data sheets, documents, drawings and other ongoing work will be submitted to
GNRE-COMIBOL project management or review and, where required, for approval. Items of
concern and plans of action will be discussed on a regular basis.
The dedicated project team will be located in GNRE-COMIBOL’s project execution team’s of-
fice.
The team of engineers and/or designers should be available on site to address questions from
contractors during the construction phase of the project. They shall represent each of the major
engineering disciplines and shall report to the resident construction manager.
The realization of the project follows the project implementation schedule shown in Appendix
G6.
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
The complete engineering scope will be defined in terms of deliverables and activities. Pro-
gress templates will be set up to standardize progress measurement. Once the man-hour
budget is approved, it will be frozen and any subsequent change will be through properly ap-
proved change notices. Progress reporting will be based on an earned value method.
A control budget will be prepared for the costs associated with the scope of work. Actual and
forecast-to-complete cost will be recorded to allow status reporting and cost trending. The pro-
ject budget forecast will be revised monthly to reflect proposed and approved changes.
The complete list of deliverables and activities that constitute the scope of engineering work will
be defined, with a budget assigned to each deliverable and activity. These deliverables and
activities will be grouped into manageable segments called internal work packages (IWPs) that
can be accomplished by a discipline responsible for the work on a definite schedule. The IWPs
will relate to the lower levels of the project WBS, thus allowing proper integration of the scope,
schedule and estimate.
Internal change notices (ICNs) will be recorded and the man-hours distributed over the deliver-
ables involved in the change. The ICN man-hours will become part of the revised budget only
when approved by the project manager.
Standard earned value reports and curves will be provided for engineering progress.
A GNRE-COMIBOL project planner will develop the implementation schedule showing detailed
activities and important project milestones. Based on the approved schedule, the planner will
provide engineering with the target dates for the issue of each IWP. Engineering will prepare
the detailed schedule for each deliverable and staffing assignment, which will be integrated by
the planner into the project schedule. A permanent baseline schedule will be maintained.
Input to purchase packages and construction contracts will be defined and target dates will be
established for issue of the technical documents required to compete packages so that the
responsible parties may issue the information to vendors and suppliers. Engineering delivera-
bles that are necessary for completing a package will be linked to such packages to ensure
timely completion.
The GNRE-COMIBOL project planner will hold regular meetings with engineering and pro-
curement groups to review the schedule. The project monthly progress report will show the
current versus planned status for all phases of work and will highlight the critical areas.
Progress measurement templates will be assigned to each deliverable so that progress can be
measured in a standardized manner and with minimum subjectivity.
As work progresses, earned man-hours will be calculated according to the template stage
reached during the reporting period. The planner will validate the physical progress information
to ensure correct progress reporting.
At the end of each reporting period, the GNRE-COMIBOL package engineer will enter forecast-
to-complete man-hours for each deliverable and activity. Spent man-hours will be collected
from the timesheet system and entered at the IWP or discipline level to calculate productivity.
Any productivity issues will be analyzed and corrective action taken.
The forecast-to-complete man-hours from the engineer will be incorporated into the planning
update cycle. Based on the forecast-to-complete man-hours, manpower forecasting and level-
ing will be done on a regular basis to ensure the most efficient use of resources. Any revisions
to manpower profiles and forecast dates will be reviewed and confirmed with engineering.
Engineering will be responsible for early identification of scope changes and their man-hours
and schedule impact. Potential scope changes will be recorded in the system with the estimat-
ed man-hours. All potential changes will be analyzed and either approved or rejected. This in-
formation will be integrated into the forecast-for-man-hours, staffing profiles and project sched-
ule.
Tight cost control will be required throughout the life of the project, quickly identifying devia-
tions so that corrective action can be taken.
Control Budget
The control budget for the project will be established and set as a baseline. Subsequently, all
cost monitoring will be carried out based on this baseline cost.
Cost Monitoring
Cost monitoring will be a continuous process in which cost trends will be recorded and moni-
tored. A monthly project cost control report will be issued showing original budget, scope
changes and transfers, forecast-to-complete, incurred, and period and overall variances.
The cost controller will interface with planning and engineering for monitoring and trending to
ensure that potential cost impacts are identified and mitigated well in advance.
Controlling the changes is critical to maintaining the project under its predicted cost and
schedule. Engineering changes will require approval from the GNRE project management,
where applicable, before they are initiated. Departure from approved standards or design crite-
ria will also require approval. Both these elements are important factors in controlling the
growth of the budgeted amounts.
GNRE’s project execution team will be required to submit change notices for the GNRE’s pro-
ject management whenever the project scope or schedule affects the performance of the ser-
vices. Change notices will be reviewed and discussed at regular intervals during the project life.
The project budget forecast will be revised monthly to reflect proposed and approved changes.
The construction management function co-ordinates, directs and supervises the work of on-site
contractors. The construction manager will also ensure that constructability and access as-
pects are taken into account in the layouts and designs and that adequate temporary facilities
and lay down areas are designed. Part of these activities has been accomplished in coordina-
tion with the selection of the different main construction contractor.
Key points in the coordination of construction activities will include:
• Provision of a well-drained and prepared site
• Clearly defined channels of communication between construction and design personnel
• Comprehensive planning of the sequencing of construction
• Control of the flow of materials
• Co-ordination of shop fabrication activities and site activities
• Comprehensive planning of all temporary construction facilities including accommoda-
tion.
During the design phase of the project, regular reviews of the engineering will be done to en-
sure that appropriate construction input is achieved. Typical features that will be examined dur-
ing the reviews are:
• Construction path and sequence
• Prefabrication and pre-assembly opportunities
• Rigging studies for heavy lifts
• Access for heavy equipment
• Safety considerations
• Scope and preparation of construction contract packages
• Practicality of design with respect to construction.
The strategy document, which is the base for the authority approval procedure, addresses is-
sues including:
• Approach to the work
• Resource loading
• Health, Safety & environmental plan
• Waste management
• Medical evacuation
• Heavy lift transport.
Certain elements in the strategy report will be revised during the process of preparing imple-
mentation.
Temporary living accommodation will be provided for workers and supervisory and manage-
ment personnel involved in the project construction and commissioning.
The camp size is based on preliminary estimations of expatriate construction manpower, and
will be adjusted with the different main construction contractor’s recommendations to adapt to
the construction schedule and workforce. Local manpower will find accommodation in local
community villages.
Temporary office buildings will be provided at the construction site for the different main con-
struction contractor’s personnel.
8.6.2 Safety
All construction work on the site will be carried out in accordance with a health and safety pro-
gram established by the GNRE’s project execution team. This program will also meet the re-
quirements of Belarusian regulations and applicable international industry standards.
The safety program will aim at providing the highest levels of safety for the construction work-
ers, all site personnel and visitors. The program and activities will monitor closely the actions of
the contractors and provide supplementary services in order to achieve an exemplary safe site.
The commitment will extend to close liaison and co-operation with the GNRE’s operating plant
personnel during the commissioning phase.
The GNRE´s construction manager will have overall responsibility for the execution of work on
site. Site engineers and inspectors will ensure technical compliance to design and standards,
and any deviations will be brought to the construction manager's attention for remedial action.
The construction manager will be responsible for monitoring all activities affecting the quality of
the physical construction work within the project, whether the work is performed by construc-
tion contractors or vendors. The field quality assurance program will be directed towards mini-
mizing potential quality problems rather than reporting after the fact.
The site quality program will be audited in accordance with the project quality assurance plan
developed by GNRE’s project execution team’s quality assurance manager.
The contractors will submit their construction schedule to meet the master schedule. GNRE’s
project execution team’s planners will review and recommend approval of the contractors’
schedules.
Weekly reviews and measurements of contractors’ progress will be performed. Problem areas
will be identified and corrective measures will be proposed to maintain the productivity and
meet the required schedules.
The activities of the construction contractors will be monitored through weekly meetings to en-
sure strict observance of the laws and regulations governing the construction industry in the
Republic of Belarus and of the site labor relation policy, as defined for all contracts.
The responsibility for labor relations will rest with the different main contractor and other site
contractors.
8.6.7 Security
GNRE, in conjunction with the different main contractor, will establish a complete security pro-
gram to ensure protection of the physical assets during the construction phase. It will include
elements such as the site security policy, emergency telephone numbers, emergency re-
sponse plan, site patrols, communications, visitor’s procedures, and the main gates access
control system.
GNRE’s project execution team’s site materials controller will have overall responsibility for
construction materials management. The electronic project management system will be used
to plan and manage the construction materials receipts, distribution and inventory control.
A waste management plan will be established in each construction contract. The plans will ad-
dress, as a minimum:
• Construction waste such as scrap metal and non-hazardous liquid waste
• Non-putrescent waste from the construction camp such as cans and bottles
• Putrescent waste from the temporary camp and temporary office facilities such as waste
foodstuffs
• Sanitary waste.
All construction contractors will be required to comply with the waste management plan.
Unless the waste is of a hazardous material, the nominated contractors will be responsible for
removal of any waste to an area allocated by the GNRE.
Any material, waste or otherwise, must have proper authorization before removal from site.
Particular procedures will be adopted relating to the handling of hazardous waste.
8.6.10 Pre-Commissioning
The pre-commissioning manager will co-ordinate, direct and supervise the work of a group of
engineers, technicians and inspectors engaged in the inspection, testing and commissioning
of equipment and systems and in the supervision of contractors’ personnel assigned to com-
missioning and performance testing activities.
The pre-commissioning manager will ensure liaison with operations personnel for the prepara-
tion of checklists showing responsibilities of GNRE, the technology supply contractors, GNRE’s
project execution team, vendors and construction contractors for pre-operational testing, cold
commissioning, hot commissioning and performance testing, and he or she will schedule these
activities.
Preparatory work will consist of detailed pre-commissioning plans and schedules, assembling
of pre-commissioning manuals and vendors' manuals. Close coordination with GNRE’s com-
missioning team and GNRE’s project execution team’s construction management team will be
maintained throughout the preparatory and execution phases.
Pre-commissioning supervisors and their groups will have direct responsibility for carrying out
pre-commissioning work in their respective sectors. Sector engineers from the design office will
be assigned to these groups to reinforce the knowledge of process and equipment.
Pre-commissioning includes all pre-operational verifications and testing required to make the
plant ready for start-up and commissioning. The work includes the initial run-in of all permanent
equipment and services, including fire detection and prevention systems, testing of controls,
instrumentation and system run-in performances, the verification of alignment, first lubrications
and the installation of temporary facilities required as well as correction of minor omissions and
defects.
The commissioning and start-up of an equipment facility and/or system will be the responsibil-
ity of the GNRE’s commissioning manager. During that period, the activities of GNRE’s project
execution team may cover:
• Technical assistance
• Contract administration
• Planning and scheduling
• Project controls
• Procurement and expediting services
• Vendor and/or contractor interface
• Correction of deficiencies.
The plan for the commissioning of this project calls for a two-phase commissioning program.
The commissioning of each area follows mechanical completion and hand-over from the con-
tractor to GNRE’s team. The surface facilities commissioning is normally split in two main seg-
ments, termed cold and hot commissioning. The following are the main activities in each of
these tasks:
Cold commissioning
• Loop checks
• Verification with vendor representatives
• Wet commissioning (filling up with water and transfer for process equipment only).
Hot commissioning
• Bring up to operating condition
• Hot water batch (fill up with hot water and transfer for process equipment only)
• Brine transfer, for process equipment only.
All of the process utilities, i.e. LPG, electrical power, cooling and process water must be con-
firmed to be available prior to any commissioning activity initiation.
It is to be noted that all of the equipment supplied will have gone through the shop pre-testing
before being shipped to the site for installation. This should minimize the potential extensions
to the duration of commissioning.
The commissioning and testing programs will require that certain analysis of intermediate and
final product will be required. The construction of the laboratory and its equipment, located in
the administration building, will therefore be required to have been completed and the equip-
ment tested and calibrated prior to the start of any commissioning programs.
This section covers the requirements needed to run the operations at the processing plant
along with all associated operations. The following figures based on the experiences of ERCO-
SPLAN in their over 60th years of experience in potash plant operations and are only recom-
mendations for the operation procedure of GNRE.
8.7.1 General
Based on this analysis the personnel requirements have been estimated in the following ac-
cording to following system:
• Management level personnel;
• Processing personnel for plant operations;
• Maintenance personnel for all operations;
• Administration personnel;
• Laboratory and QA/QC personnel;
• Load and unload personnel;
• Utilities personnel;
• Waste management personnel;
• Service personnel.
The personnel or staffing requirements for the different parts of the operation is discussed in
the following sections. The personnel have been classified in different groups with different
salary levels based on required skill sets, management requirements, and expatriate/non ex-
patriate categories. It is expected that the expatriates will manage and train local personnel.
(1) Management
The management level includes the upper management for different sections of the operation,
who are responsible for supervising their respective sections. The management level is not
assigned to shift systems; therefore all jobs are calculated as number of jobs.
Processing personnel includes the staff requirements for the processing plant, as well as for
loading and unloading facilities at the plant. The estimate presented here is based on experi-
ence from operations on similar projects. The fundamental assumption with this estimate is
that. The processing personnel as listed in Table 18 are mostly assigned within a 3 shift-
system.
During start-up and acceleration of the plant, increased personnel may be required. At that
time, start-up staff from different suppliers and installation companies will be engaged.
Number Number
Field of application Level Total demand
of jobs of shifts
Chief Project Engineer Production Upper 1 3 4
Project Engineer Deloading Middle 1 3 4
Project Engineer Raw Salt Storage Middle 1 3 4
Project Engineer Potash Circuit Middle 2 3 9
Plant Op - Potash Circuit 1 Lower 2 3 9
Plant Op - Potash Circuit 2 Lower 2 3 9
Plant Op - Potash Circuit 3 Lower 2 3 9
Plant Op- Residue Management Lower 3 3 13
Helper Lower 5 3 22
Σ 84
The maintenance personnel are assigned within a 3-shift-system; the estimated personnel
numbers are given in Table 19.
Σ 43
The administration personnel are not assigned within shift systems; therefore all jobs are only
calculated for single shifts. The staffing tiers conform to middle and lower level as shown in
Table 20.
The QC & Lab personnel are assigned within a 3-shift-system as continuous control of brines
and crystal crops are required during operation. The staffing tiers conform to the upper and
middle levels as shown in 0.
The utilities personnel are assigned with a 3-shift-system. The staff for utilities will conform to
the middle and lower level and are detailed in Table 22.
The Services personnel are partly assigned within a 3-shift-system and are responsible for
health, safety and security, running the workers camp, and providing cleaning services at the
plant administration building. These staff conforms to the middle and lower level as detailed in
Table 23.
Group of
Plant Maintenance Group of
Maintenance
General Foremann Technicians
Engineers
Superintendent
Process Plant Trainer Group of Trainer
Group of
Chief Loading Technicians
Assistant Manager
Chief Engineering
Group of Engineers
LCR Superintendent
The LCR superintendent fulfils the role of resourcing the operations with both expatriate staff
and local personnel, as required. This person is responsible for all hiring, benefits administra-
tion, labor relations, community relations, company social activities, receptions and parties,
events, donations to eligible recipients, site medical care, site security, site publications (news-
letter) and off-site training courses. Furthermore, managing community relations is his respon-
sibility.
Administration Superintendent
The administration superintendent plays a key role particularly in assuring that the operation
runs smoothly. Salaries and bills are paid, as well as accounts receivables are handled on a
timely basis. Parts and materials are on hand as needed.
Product handling and shipping is coordinated with quality control and off-shore
sales/marketing, responsible for financial reporting, banking, accounting, payroll, accounts
payable, accounts receivable, lands management, insurance coverage, auditing, building care
and cleaning, road maintenance, purchasing, warehousing, records storage, IT site services,
phone services, lease vehicles administration, infrastructure administration, dealing with cus-
tomer complaints, trash management and tenant relations.
HSEC Manager
The HSEC manager is responsible for safety, health, and environment relations for GNRE at all
sites and locations where GNRE operates, under the direction of the general manager. Emer-
gency response and fire-fighting services come under this person’s area of responsibility
Safety training is coordinated across the entire project site by this person. Recognition of indi-
vidual safety performance by employees is given at annual safety achievement banquets. Safe-
ty and environmental audits are conducted and evaluated in conjunction with third party audi-
tors. The HSE coordinator attends all senior management meetings involving department
heads and meets with community leaders. They also will undertake part of all public relations
activities.
(9) Maintenance
The production site is designed so that equipment maintenance is mainly performed within the
plant in order to be self-sufficient due to the remote nature of the site and reliability of local con-
tractors and suppliers.
For this reason, the plant’s central maintenance workshops shall be equipped with:
• Vehicle maintenance shops
• Machine shop
• Plate work shop
• Welding shop
• Paint shop
• Carpenter shop
• Hydraulic and pneumatic workshop
• Electrical workshop
• Instrumentation and control workshop.
For field maintenance work on mechanical, piping, electrical and instrumentation equipment
and systems, sufficient manpower and organization structure is provided. Allowances are also
made for planned plant shut down maintenance work, and overhauls of major pieces of
equipment that would require the participation of the equipment manufacturers either on site,
or at their own repair shop facilities.
The paint shop is equipped for regular painting of miscellaneous equipment as well as small
vehicles. The booth consists of:
• Paint booth
• Ventilation and filtration system
• Paint storage and preparation area.
No sand-blast facilities are provided. The surface preparation is performed using portable tools
such as hand grinders, rotating brushes, sanders, etc.
This workshop is equipped with a test bench for testing and verification of hydraulic equipment
such as cylinders, hydraulic pumps, valves, distributors, etc.
A similar test bench is supplied for the testing and verification of pneumatic equipment.
This workshop is also equipped with hose clamp machine for fabricating hose fitting re-
placements.
This workshop has all tools and equipment required for maintenance and testing of electrical
equipment, instrumentation systems, control valves calibration and repair as well as testing of
DCS/PLC hardware.
Maintenance and testing instruments shall include megohmeters, electronic multimeters with
clamp-on attachments, recorders, memory oscilloscopes, vibration meters, digital tachometers
and thermometers as well as:
• Tool box sets
• Electric hoist for lifting control and safety valves, and other heavy instruments such as
mass flow meters
• Calibration rig for control valve
• Calibration rig for safety relief valve
• Pneumatic calibrator
• Water and mercury columns
• Dead weight tester; resistance temperature detector (RTD) calibrator; oil bath complete
with electric heater and test gauges
• Calibrator for moisture transmitters
• Hand held calibrators for smart hart instruments
• DCS/PLC equipment test lab (consisting of lamps and push-buttons panel, control sys-
tem test rack, operator interface station, signal generators and receivers, etc.)
• Clamp meters and digital multi-meters
• Fibre optic cables test kit.
Maintenance crews are will carry out routine maintenance of all mechanical, piping, electrical
and instrumentation equipment and installations. A dedicated team will cover day shifts, while
night shifts are covered by a skeleton multidiscipline crew.
Planning and manpower provisions are to be made for handling the increased maintenance
workload during the planned general plant shut downs and major equipment overhauls. A por-
tion of the shut-down work is performed by outside contractors for major equipment such as
the power generators, fluid bed dryers and selected items. The planned major overhauls would
require participation of the equipment manufacturers’ personnel on site. For selected cases the
components would be sent to the manufacturers’ shop for the required repairs and recondition-
ing.
Overall scope of operator training shall be based around tasks within the plant, to keep the
operation at a steady rate of production; the scope of the training for each individual depends
on the respective job assignment in the plant and is selected from the following:
• Outline of plant
• Orientation and look-at training for plant management
• Orientation for production department
• Orientation for the production control department (laboratory)
• Orientation for the maintenance department (mechanical, instrumentation and comput-
er specialist)
• Orientation on product application tests.
After pre-designing of equipment, ERCOSPLAN sent inquiries for necessary equipment for pot-
ash processing to possible suppliers. Thereon equipment suppliers sent quotations to ERCO-
SPLAN.
ERCOSPLAN had to decide independently for one supplier for each equipment, to be consid-
ered in the detail engineering documents due to that GNRE-COMIBOL was not in the position
to make a decision because of Bolivian regulations.
ERCOSPLAN’s reasons for consideration of equipment suppliers in the detail engineering
were:
• Technical and technological
• References in potash industry
• Economical
• Quality of delivered quotation documents.
Table 24 below shows all mechanical equipment quotations. Considered mechanical equip-
ment in ERCOSPLAN’s detail engineering documents is marked with a cross in column “Con-
sider in Detail Engineering”.
Remark:
Delivered quotations by various equipment suppliers often had been similar resp. were evalu-
ated as comparable. Hence, the date of delivery of quotation influenced the consideration in
the detail engineering documents.
All machinery, material and equipment which are isbl of the scope of ERCOSPLAN have been
chosen according to the widespread experience of the authors in potash processing opera-
tions worldwide. Prices have been selected from blue chip companies with high experience
supplying equipment, section and bulk material for the potash industry.
Remark: All equipment, buildings, devices which are osbl (especially water sewage, furniture,
laboratory equipment, equipment for offices, administration building, laboratory, canteen,
warehouse, workshop, fire station, hospital and vehicles e.g. fire truck ambulance, trucks,
cranes, buses, loaders, cars) are not considered in the calculation.
CAPEX of the equipment were estimated on the base of the equipment specified in the equip-
ment list for the whole processing plant isbl of ERCOSPLAN scope (details see Appendix G1).
CAPEX for pipes and valves at plant site were estimated with an accuracy possible at the pre-
sent state of the project and includes all pipes and valves which are planned according to the
scope of ERCOSPLAN (details see Appendix G2 and Appendix G3).
All materials, devices and equipment for the power supply, instrumentation, automation and
communication systems were estimated on the specifications and bills of quantity of the ER-
COSPLAN scope (details see Appendix G4).
CAPEX for infrastructure and buildings at plant site were estimated with an accuracy possible
at the present state of the project and includes all infrastructure and buildings planned accord-
ing to the scope of ERCOSPLAN (details see Appendix G5).
For calculations of the indirect CAPEX costs ERCOSPLAN used the following percentages
• EPCM
It has been established as a 15 % of Direct Capital Expenditures.
• Owner costs
They are estimated as a 1 % of direct capital costs.
• Provisory facilities
They are estimated as a 2 % of direct capital costs.
• Start up and commissioning
They are estimated as a 1 % of direct capital costs.
• Insurance
Estimated as 1 % of direct capital costs.
• Contingencies:
Reserve to contingencies is estimated as a 5 % of direct and indirect capital costs.
Table 25 Cost Overview of Direct and Indirect Capital Expenditures of Processing Plant
8.9.4 Crystallizate
According to the process calculation the hourly demand for crystallizate from evaporation
ponds is approx. 540 t/h respectively approx. 280 m³/h (without design safety factor of 20 %).
According to the process calculation the hourly demand for process water is approx. 270 m³/h
(without design safety factor of 20 %).
Liquefied petroleum gas is majorly necessary for process building heating. Heating itself is
necessary to keep process building frost-free. The liquefied petroleum gas consumption for
heating purposes is estimated with approx. 75,000 Nm³/a.
Furthermore liquefied petroleum gas is used for heating up process water in reagent dosing
plant. The amount, necessary for heating up the process water to approx. 80 °C is estimated
with approx. 20 Nm³/h.
Drying section consumes liquefied petroleum gas, too. Especially heating media is needed for
generating hot air for drying. The liquefied petroleum gas consumption for drying purposes is
estimated with approx. 400 – 500 kg/h during usual operation.
For consumption of process chemicals for flotation and thickeners please see chapter 6.4.
Furthermore chemicals for anticaking treatment of product after drying / cooling are necessary.
The consumption of chemicals for anticaking is as follows:
Potassium ferrocyanide K4[Fe(CN)6] 11.05 kg/h resp. 83 t/y
Sodium carbonate Na2CO3 4.76 kg/h resp. 36 t/y
Fuel for combustion engines like trucks, cars and front end loaders is not considered in ER-
COSPLAN’s scope of works.
The processes of construction and operation of the Project involve a number of risks inherent
to the activities both for the environment and for human life and health.
This chapter describes the risks associated with such activities and the preventive measures
that are necessary to perform that plan will be part of risk prevention at work and environmental
risks.
At all times, making reference to the Laws and Regulations in Force in the Plurinational State of
Bolivia regarding Health and Safety at Work and Environmental Laws type. These laws are
listed at the end of the chapter.
Before the start of the work, there will be a Health and Safety Study by the contractor to be ap-
proved by the Labor Authority and the Work Center Opening, Book of Outsourcing and Inci-
dent Book.
In this study the following should be considered:
• Appointment of safety and health during the performance of work, commissioning and
operation of the plant as well as the appointment of a preventive action by workgroup or
turn.
• Employee participation system in safety and health.
• Informing workers on each of the activities they are undertaking and acquired risk in-
formation in their job.
• Training in occupational safety and first aid courses.
• List of equipment of individual and collective protection to use as a play activity and
profession
• Risks associated with each of the activities to be performed during commissioning con-
struction and operation of the plant.
• Risks associated with each of the professions required in the construction, commission-
ing and operation of the plant.
• Preventive measures according to the activities to be developed.
• Preventive measures by occupation.
• List of necessary auxiliary equipment in all phases of the project, and associated risks,
preventive measures.
• And finally, along with the Health and Safety Plan must be accompanied by an Emer-
gency Plan indicating emergency exits, evacuation in case of accident, contact num-
bers in case of accident, maps with evacuation routes to hospitals and centers closest
Health and performance standards based on type of accident. In section 5.2. Emergen-
cy Plan shows the basic guidelines of the content.
8.10.2 Risks
• All workers on the project will have mandatory training on health and safety and envi-
ronment.
• It is necessary to evaluate all activities known reviews, and continuous monitoring of the
same.
• It must visually inspect the equipment and tools used at the beginning and end of each
work shift, reporting to superior any type of anomaly detected.
• When performing maintenance work, ensure that interlocking system is working.
• To prevent the risk of road accidents within the project area or area of work, draw up a
plan that includes transit zones of both vehicles and pedestrians, considering speed re-
strictions, demarcations and traffic signals.
• Workers who drive during the execution of the work and during operation of the plant
should be in possession of a valid driver's license appropriate to each vehicle.
• The weight of the trucks loaded with equipment or materials shall not exceed the maxi-
mum allowed according to routes/bridges they are using.
The unexpected natural phenomenon of high magnitude earthquakes can always involve risks
to those working in the Project.
Although the characteristics of the project (design engineering) and its site are not associated
with particular vulnerabilities to such events, it is considered that upon the occurrence of a cat-
astrophic natural phenomenon must operate the emergency and evacuation systems.
In the event that strong movements produce structural damages and power cut, will take into
account the following preventive measures:
• It will cut the power supply.
• It will establish and maintain demarcated the security area and free of any unnecessary
element.
• It will provide energy support in those critical systems to operational continuity.
• It will be a good signage of emergency exits.
The fire protection systems proposed for this project are based on good engineering practice
and the use of Bolivian standards.
As general measures Fire Prevention Plan must be:
• All employees shall be subject to the measures and obligations by the same.
• Facilities will be provided with information required to fight any attempts of fire or fire, as
established by current legislation in this area. In the case of treated inside sensitive are-
as of the building will be installed sprinklers and extinguishers, while outdoor facilities
provided hydrants will have complete coverage of all work area. These systems will be
monitored with main fire alarms and detection systems.
Page 256 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 601 Fax: +49 361 3810 605 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
• In surrounding areas, fuel storage shall be prohibited to light fires and/or items cause
sparks as well as to smoke.
• Training will be provided to workers of the project on all activities that may present a risk
of fire.
• It shall provide, maintain and regularly inspect the fire suppression systems.
• It will have defenses, guards or enclosures in areas where works of flame cutting, weld-
ing, sawing, cutting and roughing down, mechanical maintenance and other are done.
• It will achieve the regular maintenance of electrical facilities.
• It will connect to ground all the equipment that can generate sparks and store static
electricity.
With regard to the risks of fire or explosions by handling flammables and/or combustibles, con-
sider the following measures:
• The handling of the fuel elements will be made according to the procedures established
for this purpose.
• All trucks go into the site or in the plant with fuel, must be certified respective sealing
and hermeticism.
• The transport and storage of fuel shall be in compliance with the safety measures stipu-
lated by Normative and Law.
• At the point of discharge will display a sign "Danger fuel unloading, No Smoking," with
the existence of ABC type fire extinguishers, neutralizers and absorbent elements, such
as sand, pellets.
Hazardous solid industrial waste will be stored, handled and transported in compliance at all
times the current Bolivian law.
The main objectives are:
• Minimizing the amount of waste generated.
• Optimizing the use of resources through reuse or recycling.
• Authorized final disposal sites that ensure minimal environmental impact.
• The transportation of this waste will be performed by an authorized company for this
purpose, which must have its plan of risk prevention and accident control for transport
and management of the waste and it will be compatible with current legislation.
• Drivers of vehicles must be trained in the use and handling of transported substances
as well as first aid procedures and spill control.
• Transport vehicles will have systems of communication, first aid equipment, emergency
equipment (shovels, absorbers, fire extinguishers, personal protective equipment such
as gloves, goggles, helmet, etc..), as applicable. Besides trucks valves are designed to
be watertight and prevent any kind of leakage.
• Recognition and analysis of the route in which the trucks will move, as well as the alter-
native route in case of interruption or cuts on the normal route.
• During the handling waste will be taken the precautions to prevent inflammation and/or
reaction.
• It is necessary to train all staff who handle and store these hazardous substances.
• Updated maintenance of the list of all controlled products and their review at their re-
ception of packages containing such products (container, label, etc.).
• There will be a special area for the storage of hazardous substances, which will be
properly marked and equipped as required by the authorities.
• Drums of fuel and oil are arranged on wood pallets or other devices in order to facilitate
transport and to prevent moisture or corrosion themselves of by direct contact between
the drum and the soil.
• Tanks for the preparation and storage of reagents possess with containment.
• The fuel loading machinery and used equipment will be in a defined area.
• All facilities receiving, storage and use of these residues will have a fire protection sys-
tem.
For control of accidents and/or medical emergencies, the affected area will immediately notify
the hospital or nearest health center, through established communication systems.
An example is shown below.
SERVICES TELEPHONE
Fire -----------------
Ambulances -----------------
Police -----------------
It is also important to consider emergency brigades on site with appropriate equipment, vehi-
cles and trained personnel.
If the conditions of the victim or victims are not grave, the emergency brigade shall provide
appropriate first aid.
Once patient or patients are stable, it is necessary to transfer them to the nearest hospital to
complete the first aid.
The security brigade will be responsible for maintaining everyday signage, replacing if it is nec-
essary.
Traffic accidents can occur to both the work's own staff, and third parties who are affected by
them. The treatment of these accidents will be the same as for labor accidents.
In the case of an accident traffic performances are:
• Care for the injured.
• Communication with ambulances and first aid.
• Police will be notified of the number of accidents immediately, affected cars, location
and direction.
• Responsible Communication for prevention.
8.10.3.3 Performance Standards in the Case of Accidents Caused by Fire and / or Explo-
sion
In the event of fire and/or explosion, an accident management plan will be brought into action
which considers the following actions:
If there are larger fires, set up a perimeter of insulation and communicate the event to the
Emergency Coordinator.
The staff should be transferred to the previously defined security zone.
The areas of greatest risk of fire will be safeguarded, especially the fuel storage and hazardous
substances storage.
To fight fire with existing equipment, it is necessary to know in advance the location of the ele-
ments of fire attack. Usually the first attack should be carried out with extinguishers. If during
firefighting the fire escapes the control of the staff, this must be removed immediately from the
site, give the respective alarm and notify trained teams about the situation.
During implementation, commissioning and operation of the project, executing and managing
companies must have the implementation of an Environmental Management System, such as
Rules and Governing Law on Environmental Safety.
The Environmental Management System states the control and management of waste generat-
ed on site, environmental monitoring measures applied by a waste management plan, envi-
ronmental instructions, environmental monitoring programs and other procedures established
in quality manual company, drafted in accordance with the requirement of the standard.
• Promoter: COMIBOL
• Contractor: The contractor will be responsible for implementing protective and correc-
tive measures provided for in this plan, submitting periodic reports to the promoter. It
will therefore be necessary to appoint a Responsible Environmental Monitoring in
charge of developing the actions set out in this document and any other document of
good environmental practices reported by the Promoter and their own environmental
measures described in the Environmental Management System of the Promoter.
To do this, the various mechanisms that will be implemented to ensure the execution of the
works will respect the environment:
• Identification and quantification of environmental aspects and impacts
• Reduced pollution and the impact: On the water, atmospheric, acoustics and vibration
and soil.
• Regeneration of spaces
• Environmental Monitoring Program.
In the following sections, the impacts and preventive measures will be studied.
Impacts can cause: increased water turbidity, as in the case of spills and arid lands, which ad-
versely affects the water.
Oils and fuel spills as well as wastewater discharges can cause outbreaks of infection, so they
should also pay special attention.
To avoid direct conditions in the waters, the following preventive measures apply during the
execution of work:
• Each of the containers and waste storage containers located on site will be periodically
emptied as often as necessary.
• The handling of materials will be done to avoid any spill, if it occurs, will proceed to col-
lect and deposit in the appropriate container.
• The stock of machinery and material storage areas will be located away from including
streams, ponds and wetlands in general. In such areas, place a layer of absorbent ma-
terial to control spills of fats, oils, fuels, etc. Also, it will build a perimeter ditch machin-
ery park to collect runoff and manage them properly.
• At the beginning of the execution of the works, the head inform all workers of a total ban
of uncontrolled dump of all work products.
• At the beginning of each working day each of the operators responsible for managing
the various machinery and equipment will review the equipment to do not leak oil or any
other fluid.
• Preferably to be used existing access for the passage of machinery and equipment
avoiding move outside the tracks.
Construction activity causes the emission of large amounts of dust, particles and combustion
gases, due to the operation of the engines of the various equipment, and displacements.
These gases are formed by soot, carbon monoxide, oxides of sulfur and nitrogen oxides.
All these substances are harmful pollutants to the health, hence their control necessary.
As general measures in the execution of the work, it will strictly use the necessary machinery,
making sure that this produces the less possible pollution, both atmospheric as acoustic, re-
gardless of the implementation of other measures, which are detailed below:
• It will monitor the maintenance of the machinery involved in the work is carried out in
suitable workshops and controlled technical inspections passed by machinery and ve-
hicles.
• That machinery that does not pass technical inspections will be checked by periodic
maintenance to ensure low air emissions, for which the Department of Administration
will request documentation of technical inspections performed, or otherwise performed
preventive maintenance on machinery that does not belong to the company.
The execution of construction work generates high noise levels, especially during phases of
earthmoving.
The impact of such noise depends on the nature of the emissions, distance and receptor sensi-
tivity, for this we can take the following general measures:
• Install mufflers on mobile equipment.
• Minimize the movement of machinery for the works, and so the vibrations will optimize
the location of park construction machinery and storage areas.
• Control noise emissions resulting from the activity, both in levels and timetables estab-
lished by the regulations, performing noisier operations in the central hours of the day.
The soil contamination will occur for potential spills agents contaminants: such as liquids and
oils. In order to overcome these spills shall proceed as is provided for in the Emergency Plan
Environmental.
To reduce the impact on the ground, the following measures will be implemented:
• Oil changes will be made machinery in the workshops.
• Cleaning of concrete casks outside the work place.
• As far as possible the existing routes to the machinery works have to be used, neces-
sary auxiliary roads have to be minimized.
After use, all areas affected during the construction phase should be restored to their original
condition.
Table 26 shows the required inspections including responsible persons and frequency of in-
spection for all environmental control points.
WORKS
Check that in the works hazardous substances MANAGER AND DAILY
that are being used have been identified SITE MANAGER
• Labour Law: Decree Law 16998 of 1979 "Occupational Safety, Health and Welfare".
• Environmental Law promulgated on April 27, 1992. Regulation of Law No. 1333 of the
Environment.
– General Rules of Environmental Management.
– Regulation in the Field of Water Pollution.
– Regulations for activities involving hazardous substances.
– Regulation of Solid Waste Management.
– Regulation on Prevention and Environmental Control.
Table 27 presents an overview of single steps of a potash production development, their spe-
cific activities and potential environmental impacts.
Table 27 Major Potential Environmental Effects that may occur during Potash Production
Environmental aspects that can be affected by production activities were grouped under ‘air,
‘water’, ’land’ and ‘social values’.
Air quality can be affected by emissions of
• Dust
• Exhaust particulates and exhaust gases such as carbon dioxide (CO2), carbon monox-
ide (CO), nitrogen oxides (NOX), and sulphur oxides (SOX)
• Volatile organic compounds (VOC's) from fuelling and workshop activities
• Greenhouse gases such as CO2 and methane are believed to contribute to global
warming.
Due to the use of high quality dedusting systems with an exhaust gas content of lower than
20 mg/m3 dust contamination cannot occur.
The used modern burning and incineration systems avoid a high content of carbon dioxide
(CO2), carbon monoxide (CO), nitrogen oxides (NOX), and sulphur oxides (SOX)
The production of volatile organic compounds (VOC's) from fuelling and workshop activities is
minimized
Large volumes of water are typically required by production and beneficiation activities. This
water consumption may lead to a fall in the level of the local water table, affecting the surround-
ing ecosystem and potentially resulting in competition with other users.
All of the requested water will be supplied by wells.
The land surface and sub-surface can be disturbed by activities such as
• Extraction of brine;
• Deposition of overburden;
• Disposal of beneficiation wastes.
These activities could result in wide range of potential impacts on the land, geological structure
and topsoil. Additionally, the production can affect the hydrological cycle, wildlife habitat and
biodiversity of the area. In some instances, sites of archaeological, cultural or other significance
may be affected.
All deposits of waste are safe due to special design of the storages.
Social goods and intangible values such as community lifestyles, land values and the quality of
the ecosystem in the vicinity of the plant site could be affected by factors such as
• Modification of the landscape;
• Noise and vibration from activities such as the operation of equipment;
• Changes in wildlife habitat.
The major potentially adverse environmental effects could occur during the different activities of
the production life cycle. Generally the activities of most significance are construction, extrac-
tion, beneficiation and waste disposal. Associated activities may have an impact but these tend
to be relatively less important. Rehabilitation and closure can have some impact, but these ac-
tivities are carried out with the objective of repairing any adverse effects that may have oc-
curred during production, to leave a safe and stable site. Rehabilitation is more effective when
conducted progressively throughout the life of the operation. Adopting a holistic approach to
planning and environmental management, that encompasses the entire life cycle, helps to pre-
vent or mitigate environment effects from the outset, while fostering stewardship of the ore re-
source and the layers under which it lies.
Page 268 of 273
ERCOSPLAN Ingenieurbüro Anlagentechnik GmbH
Arnstaedter Strasse 28, 99096 Erfurt, Germany
Phone: + 49 361 3810 601 Fax: +49 361 3810 605 e-mail: processing@ercosplan.com web: http://www.ercosplan.com
P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\Allgemein\Liefer\Auslieferung\14-03-14_Detail\Report\11-024_DE_FINAL_rev01_2014-03-14.docx
Final Engineering Design of a KCl Industrial Plant in Bolivia
EAT 11-024
Handling encompasses the transportation and stockpiling operations that occur between the
extraction of the potash crystallizate and their beneficiation to produce concentrated products.
Surface transportation methods may include road trucks and off-road haul trucks, conveyors
and slurry pipelines.
Dust may be generated from traffic on unsealed roadways. During loading and unloading op-
erations and at conveyor transport of salt, dust emissions are negligible as the material has to
be protected against moisture and precipitation. During the stacking of stockpiles and reclama-
tion operations dust emissions can occur.
Equipment emissions are reduced by the use of exhaust filters on critical area, regular equip-
ment maintenance programs.
Heavy vehicles and equipment use can generate significant noise, sometimes around the
clock, affecting the well-being of neighboring communities. The impact is reduced by the care-
ful location of roads, use of noise barriers or buffer zones, sequencing of transporting opera-
tions and restricting the operating hours of the equipment.
Beneficiation and concentration activities applied in the potash industry may comprise size
reduction separation, concentration using flotation processes and drying.
Beneficiation and concentration processes may adversely affect the environment by the
• Generation of wastes such as salt tailings and brines;
• Consumption and contamination of large volumes of fresh water during processing with
brines;
• Emission of dust from processing operations such as drying;
• Emission of exhaust particulates and gases during the generation of electrical power
and the drying of product.
Other potential impacts include noise and vibration produced by the equipment.
The following measures to minimize the environmental effects given
• Generation of wastes such as salt tailings and brines;
• Tailings and brines are stored during operation in safe and closed areas.
• Consumption and contamination of large volumes of fresh water during processing with
brines;
• Emission of dust from processing operations such as drying
• Each of the critical points were dust can come to the environment where equipped with
bag filters, which cleans the dusty air to a content of 20 mg/m3.
• Emission of exhaust particulates and gases during the generation of electrical power
and the drying of product.
• All emission data for exhaust gases of burning processes like generation of power
and exhaust air from drying are lower as requested by the Bolivian standards for
emission.
The large volumes of waste generated during beneficiation of potash may potentially cause
adverse environmental effects. Volumes and type of waste depend on the ore characteristics
(ore grade, constituent minerals, and contaminants), in addition to the specific beneficiation
process employed.
The beneficiation of potash produces wastes such as
• Tailings consisting largely of impure salt (NaCl) with smaller amounts of other minerals
such as anhydrite;
• Slimes consisting of insoluble fines such as clay and dolomite;
• Brines containing NaCl or MgCl2;
The beneficiation plant implements measures to contain and recover process spillages, in or-
der to minimize environmental effects and product loss.
All wastes like tailings and brines are stored during operation in safe and closed areas.
The beneficiation operation consumes large quantities of fresh water for processes such as
washing and flotation. The water will be sourced from nearby water well. Water management is
an important aspect of the operation and is usually integrated with waste disposal. Recircula-
tion or recovery of the waste process water/brine is effected.
Process waters/brines are used to transport waste as a slurry/solution to the disposal areas.
They should be recovered for reuse, minimizing the need for additional fresh water input.
Where fresh water sources are not available for beneficiation, salt water can be used for parts
of the processing process.
Water management is an important aspect of the operation and is usually integrated with waste
disposal. If possible, recirculation or recovery of the waste process water/brine is effected.
Contamination of surface may occur from the spillage of process water, brines, ore concen-
trates, wastes or chemical reagents during processing. A variety of methods to contain spills
will be used, such as drains, bunds around storage and processing tanks and dams for major
process spills. These allow spills to be recovered and returned to the process or be disposed
of safely.
During processing significant amounts of brine can be accumulated only due to malfunction or
incorrect operation.
Dry processing operations may generate significant quantities of dust during operations. This
can be controlled to some extent through the use of emission control equipment such as bag
houses and wet scrubbers.
Exhaust emissions from vehicle engines, electrical power generation and product dryers may
contain greenhouse gases such as CO2 and other gases such as NOX or SOX.
The use of improved fuel or energy consumption techniques and technologies reduces the
emission of greenhouse gases and other exhaust particulates and gases. Exhaust gases from
the power plant will be filtered with special filters for NOX, SOX and so on.
Beneficiation processes generate high levels of noise and vibration produced by pumps, centri-
fuges and stirring devices. A high share of these noises will be eliminated by the process build-
ing cover. Residual noise pollution can be reduced in many cases by enclosing the plant and
retaining suitable buffer zones around the plant site. Some of these measures also assist in
reducing the visual impact of the site. Noise from plant components will not exceed 75 dB at
boundary lines of plant.
The efficiency of resource recovery influences the environmental impact of other activities such
as extraction or waste disposal.
Product loss during beneficiation through the loss of crystallizate to waste streams, dust emis-
sions and process spillages results in both an economic loss as well as the need to extract and
process additional ore to meet demand. Spillage of concentrated product brine may occur dur-
ing beneficiation, prevention or recovery of these can assist maximizing the resource. Potash
minerals are found in association with a variety of other minerals that may have an economic
value if recovered and separated.
The beneficiation of potash typically produces large volumes of waste that may cause a variety
of adverse environmental effects if not managed and disposed of in a safe, stable and envi-
ronmentally sound manner.
Major environmental concerns are typically related to
• Land surface disturbance from the construction and operation of large waste disposal
impoundments such as dams, ponds and stacks;
• Safety and stability of the storage facility. Failure can result in extensive and widespread
off-site effects.
• Other impacts may include: wind-generated dust from tailings; adverse effects on wild-
life; and the visual disturbance resulting from large elevated dams or tailings stacks.
9.10.2 Tailings
Engineered surface containment methods such as stacks (or piles), dams and ponds can be
used to contain liquid and solid wastes. This involves an integrated system comprising engi-
neered impoundments, walls, containment dykes, liners, drains, ditches and capture wells.
These confine any adverse environmental effects of the waste to a limited area, while providing
a high degree of management control. Stacking may reduce the area of land disturbed.
PATH P:\2011\024_GNRE_KCl_Industrial_Plant_Bolivia\MTA\3_AP_Detail\Text\11-
024_DE_FINAL_rev01_2014-03-14.docx
REVISION 01
CHECKED BY Marcel Lindner