You are on page 1of 29

Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

SEQUENCE OF OPERATION
FOR
BUILDING MANAGEMENT SYSTEM (BMS)

MEP HSE QA/QC MEP/ CIVIL Const.


Coordinator Manager Manager Coordinator Manager

Reviewed Reviewed Reviewed Approved


Originated by Date Date Date Date Date
by By by by

Sequence of Operation Building Management System (BMS) Rev. 00


Page 1 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

EQUIPMENT SEQUENCE OF OPERATION


1 - AIR HANDLING UNIT – (AHU) WITH VAV

General
Units are direct air type and consists with variable speed supply. They are controlled and
monitored by BMS, fan flow status is monitored by BMS through differential air pressure switch,
fan trip status and Auto (HOA) status through the starter panel/MCC. BMS can operate the unit if
MCC or starter is in Auto mode only hence “Not in Auto mode” alarm is generated in BMS
workstation.

• Chilled water-cooling coil with PICV modulating valve is controlled by BMS according to
the cooling demand.
• BMS regulates heating output of thyristor as per the heating demand, Temperature /
Humidity control
• Filter sections are monitored by BMS through air differential pressure switch across each
filter, i.e., Pre- filters & Bag in return air stream.
• Temperature and Humidity combine sensors are mounted in return air duct and
temperature sensor in supply air duct to monitor temperature and humidity
• Chilled water temperature entering the cooling coil is monitored.
• Fire alarm signal is connected to this AHU starter panel to switch off the fan in case of
fire. Main fire alarm panel is interfaced to BMS and status is update on the DDC though
network.
• Smoke Detector which is fixed in Return air duct (connected to Fire Alarm System), in
case monitors smoke then it will generate an Alarm and fire panel will “STOP” this AHU
immediately as per Fire Cause and Effect Matrix. It will Re-start only after Fire panel is
Resetted OR Alarm is cleared.
Start-up sequence:

The fan enable normally operates as determined by the time schedule or by the operator.
1. When the System Command is ON the following sequence starts:
2. The supply Air Fan is Commanded to start
3. The supply Air VFD is Commanded to start and ramp up gradually, and the fan speed
will be modulated to maintain the static pressure.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 2 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

4. The two-way modulating valve controls the chilled water flow through the coil to
maintain the Return air temperature set point.

The supply fan will be ON if the following conditions are satisfied:


1. The System Command is ‘ON’.
2. HOA switch is in ‘AUTO’.
3. There is no Fire Alarm Signal.
4. Trip Status is ‘NORMAL’.

Shutdown sequence:

The AHU will shut down in case of the following:


1. When the System Command is ‘OFF’ based on the time schedule or by the operator.
2. If there is no flow detected by the Differential Pressure Switch across the Supply Fan.
3. If a Trip Alarm is generated for the Supply Fan.
4. The HOA switch is off.

The AHU will be shut down in the following sequence:


1. The supply fan will stop.
2. The supply air and return air dampers will close.
3. The cooling coil valve will be closed when the supply fan is OFF.

Temperature control:
The AHU return air is maintained at 220C DB (Set point has to be confirmed by Client).
When the supply fan status is “ON” and the Return air temperature is below the set point (i.e., 220C
DB), the cooling valve is modulated towards close position.
When the supply fan status is “ON” and the return air temperature is above the set point, the
cooling valve is modulated towards open position to maintain the return air temperature at the set
point. Cooling valve is controlled using proportional plus integral control loop.
The cooling valve command is interlocked with the supply fan status. When the supply fan status is
off, the cooling valve is driven to closed position (0%open).

Heater control:
Heaters have stages; each stage will be commanded to start depending on the heating
requirement and to regulate the sensed space humidity i.e., if the Return air temperature is below
the Set Point OR the Return air humidity is at or above 65% the heater will get activated.
The heater command will be interlocked with fan run status i.e., heater will be turned “ON” only if
the Fan run status is proven “ON”.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 3 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

VFD Speed control:


The supply fan VFD of AHU will be modulated based on the Differential pressure transmitter
installed at the 2/3rd of the duct riser. Whenever the VAV’s which are installed on the serving zones
are modulated towards opening based on the requirement the differential pressure will reduce and
goes below the setpoint (received from the TAB team) due to which the VFD will be ramped up
and when the VAV’s are modulated towards closing the differential pressure in the duct will
increase going above the setpoint then the VFD will be modulated to ramp down the speed.

Fail to start indication:


Supply Fan ‘Fail to Start’ alarm is raised when there is command sent to start the fan, and there is
no supply fan run status for more than 2 minutes.

Failure during normal operation indication:


An alarm advisory is raised at the BMS workstation when the supply fan fault is ON with complete
equipment tag.

Alarm indication:
An alarm advisory is raised when the air temperature is outside of the set limit. Alarms are raised
immediately when the supply fan trip alarm is detected.

Fire mode:
In case of Fire, an alarm advisory will be raised at the BMS workstation and the Fire Alarm System
will trigger through its control module to turn OFF the AHU and cooling valve will be modulated
towards closed position.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 4 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

VARIABLE AIR VOLUME (VAV)

A- GENERAL
The VAV boxes will be controlling the air flow supplied to the serving area and will be controlled
based on the Zone temperature installed in the serving space.

B- SEQUENCE OF OPERATION

VAV will be interlocked with System Enable.

Once enabled, the temperature control loop shall be enabled.

The air flow rate through the VAV terminal unit shall be modulated via a Proportional plus Integral
control loop, to maintain a constant space temperature of 22°C.

The air flow rate shall be controlled by modulating the damper. The output signal from the velocity
sensor/volume controller shall compensate for variations in system pressure by resetting the position
of the damper through the VAV controller to maintain the required air flow rate. A control algorithm
in the controller shall prevent the air flow rate from exceeding a pre-set range. The upper limit of the
range shall be the V max, the lower limit V min which will be provided the TAB team.

Once there is a demand for heating, the air volume controller shall be set to a fixed volume and the
heater shall be enabled.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 5 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

2 - AIR HANDLING UNIT – (AHU) WITHOUT VAV

General
Units are direct air type and consists with variable speed supply. They are controlled and
monitored by BMS, fan flow status is monitored by BMS through differential air pressure switch,
fan trip status and Auto (HOA) status through the starter panel/MCC. BMS can operate the unit if
MCC or starter is in Auto mode only hence “Not in Auto mode” alarm is generated in BMS
workstation.

• Chilled water-cooling coil with PICV modulating valve is controlled by BMS according to
the cooling demand.
• BMS regulates heating output of thyristor as per the heating demand, Temperature /
Humidity control
• Filter sections are monitored by BMS through air differential pressure switch across each
filter, i.e., Pre- filters & Bag in return air stream.
• Temperature and Humidity combine sensors are mounted in return air duct and
temperature sensor in supply air duct to monitor temperature and humidity
• Chilled water temperature entering the cooling coil is monitored.
• Fire alarm signal is connected to this AHU starter panel to switch off the fan in case of
fire. Main fire alarm panel is interfaced to BMS and status is update on the DDC though
network.
• Smoke Detector which is fixed in Return air duct (connected to Fire Alarm System), in
case monitors smoke then it will generate an Alarm and fire panel will “STOP” this AHU
immediately as per Fire Cause and Effect Matrix. It will Re-start only after Fire panel is
Resetted OR Alarm is cleared.
Start-up sequence:

The fan enable normally operates as determined by the time schedule or by the operator.
1. When the System Command is ON the following sequence starts:
2. The supply Air Fan is Commanded to start
3. The supply Air VFD is Commanded to start and ramp up gradually, depending upon
Supply air temperature set point.
4. The two-way modulating valve controls the chilled water flow through the coil to
maintain the Return air temperature set point.

The supply fan will be ON if the following conditions are satisfied:


1. The System Command is ‘ON’.
2. HOA switch is in ‘AUTO’.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 6 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

3. There is no Fire Alarm Signal.


4. Trip Status is ‘NORMAL’.

Shutdown sequence:

The AHU will shut down in case of the following:


1. When the System Command is ‘OFF’ based on the time schedule or by the operator.
2. If there is no flow detected by the Differential Pressure Switch across the Supply Fan.
3. If a Trip Alarm is generated for the Supply Fan.
4. The HOA switch is off.

The AHU will be shut down in the following sequence:


1. The supply fan will stop.
2. The supply air and return air dampers will close.
3. The cooling coil valve will be closed when the supply fan is OFF.

Temperature control:
The AHU return air is maintained at 220C DB (Set point has to be confirmed by Client).
When the supply fan status is “ON” and the Return air temperature is below the set point (i.e., 220C
DB), the cooling valve is modulated towards close position.
When the supply fan status is “ON” and the return air temperature is above the set point, the
cooling valve is modulated towards open position to maintain the return air temperature at the set
point. Cooling valve is controlled using proportional plus integral control loop.
The cooling valve command is interlocked with the supply fan status. When the supply fan status is
off, the cooling valve is driven to closed position (0%open).

Heater control:
Heaters have stages; each stage will be commanded to start depending on the heating
requirement and to regulate the sensed space humidity i.e., if the Return air temperature is below
the Set Point OR the Return air humidity is at or above 65% the heater will get activated.
The heater command will be interlocked with fan run status i.e., heater will be turned “ON” only if
the Fan run status is proven “ON”.

VFD Speed control:


The supply fan VFD of AHU will be modulated based on the Supply Air temperature setpoint.
Whenever the Supply air temperature goes above the setpoint (190C - adjustable) due to which the
VFD will be ramped up and when the Supply air temperature goes below the setpoint (190C -
adjustable) then the VFD will be modulated to ramp down the speed towards minimum setting and
will continue to run on minimum speed until the Return air temperature rises above the setpoint
again.

VFD is controlled using proportional plus integral control loop.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 7 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

VFD command is interlocked with the supply fan status. When the supply fan status is off, the VFD
is driven to 0% speed.

Fail to start indication:


Supply Fan ‘Fail to Start’ alarm is raised when there is command sent to start the fan, and there is
no supply fan run status for more than 2 minutes.

Failure during normal operation indication:


An alarm advisory is raised at the BMS workstation when the supply fan fault is ON with complete
equipment tag.

Alarm indication:
An alarm advisory is raised when the air temperature is outside of the set limit. Alarms are raised
immediately when the supply fan trip alarm is detected.

Fire mode:
In case of Fire, an alarm advisory will be raised at the BMS workstation and the Fire Alarm System
will trigger through its control module to turn OFF the AHU and cooling valve will be modulated
towards closed position.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 8 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

3- FRESH AIR HANDLING UNIT – (FAHU)

General
Units are direct fresh air type with dedicated supply and exhaust air fan. They are controlled and
monitored by BMS, fan flow status is monitored by BMS through differential pressure switch, fan
trip status and Auto (HOA) status through the starter panel/MCC. BMS can operate the unit if MCC
or starter is in Auto mode only, if “Not in Auto mode” alarm is generated at BMS workstation.
Unit equipped with Heat Recovery Wheel for enhanced energy efficiency and performance. A
standby exhaust fan equipped with motorized damper will be available in case of failure of exhaust
air fan of the FAHU unit.
• Chilled water-cooling coil with PICV modulating valve is controlled by BMS according to
the cooling demand.
• BMS regulates heating output of thyristor as per the heating demand, Temperature /
Humidity control.
• Filter sections are monitored by BMS through air differential pressure switch across each
filter, i.e., Pre- filters & Bag in return air stream.
• Temperature and Humidity combine sensors are mounted in return air duct and
temperature sensor in supply air duct to monitor temperature and humidity.
• Chilled water temperature entering the cooling coil is monitored.
• Extract air temperature and Ambient air temperature is monitored by BMS.
• Extract air damper is controlled and monitored by BMS.
• Outside Air Damper is controlled and monitored by BMS.
• Temperature before and after energy recovery wheel is monitored by BMS.
• Fire alarm signal is connected to starter panel to switch off the fan in case of fire. Main
fire alarm panel is interfaced to BMS and status is update on the DDC though network
• Smoke Detector which is fixed in Return air duct (connected to Fire Alarm System), in
case monitors smoke then it will generate an Alarm and fire panel will “STOP” this AHU
immediately as per Fire Cause and Effect Matrix. It will Re-start only after Fire panel is
Resetted OR Alarm is cleared.

Start-up sequence:

The fan enable normally operates as determined by the time schedule or by the operator.
When the System Command is ON the following sequence starts:
1. Motorized dampers at the Supply, Return and Fresh Air duct will be commanded ON.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 9 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

2. Upon proof of opening of dampers, the Supply Air Fan & Extract Air Fan is Commanded
to start. Extract Air fan will be interlocked with Supply Fan i.e., Extract will be turned
“ON” only if Supply fan is in “ON” condition.
3. Heat Recovery wheel will be electrically interlocked with Extract fan i.e., the HRW will
be commanded ON along with Extract Air fan.
4. The two-way modulating valve controls the chilled water flow through the coil to
maintain the Supply air temperature set point.

The Supply fan will be ON if the following conditions are satisfied:


1. The System Command is ‘ON’.
2. HOA switch is in ‘AUTO’.
3. There is no Fire Alarm Signal.
4. Trip Status is ‘NORMAL’.

The Extract fan will be ON if the following conditions are satisfied:


1. The System Command is ‘ON’.
2. Supply Fan is “ON”
3. HOA switch is in ‘AUTO’.
4. There is no Fire Alarm Signal.
5. Trip Status is ‘NORMAL’.

Shutdown sequence:

The FAHU will shut down in case of the following:


1. When the System Command is commanded ‘OFF’ based on the time schedule or by
the operator.
2. If there is no flow detected by the Differential Pressure Switch across the Supply Fan.
3. If a Trip Alarm is generated for the Supply Fan.
4. The HOA switch is off.

The FAHU will be shut down in the following sequence:


1. The supply fan will stop.
2. Extract fan will stop.
3. The supply air, return air & Outside air dampers will close.
4. The cooling coil valve will be closed when the supply fan is OFF.

Temperature control:
The FAHU return air is maintained at 220C DB (Set point has to be confirmed by Client).
When the supply fan status is “ON” and the return air temperature is above the set point, the
cooling valve is modulated towards open position to maintain the return air temperature at the set
point. Cooling valve is controlled using proportional plus integral control loop.
When the Return air temperature is below the setpoint, the cooling valve will be modulated towards
minimum opening (provided by the HVAC team/consultant).

Sequence of Operation Building Management System (BMS) Rev. 00


Page 10 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

Once the Return air temperature setpoint is achieved the cooling valve will be locked on the
minimum opening setting and heater shall be activated in order to maintain the setpoint and to
provide continuous treated fresh air to the building.

The cooling valve command is interlocked with the supply fan status. When the supply fan status is
“OFF”, the cooling valve is driven closed position (0%open).

Heaters have stages; each stage will be commanded to start depending on the heating
requirement and to regulate the sensed space humidity i.e., if the Return air temperature is below
the Set Point OR the Return air humidity is at or above 65% the heater will get activated.
The heater command will be interlocked with fan run status i.e., heater will be turned “ON” only if
the Fan run status is proven “ON”.

VFD Speed control:


The supply fan VFD of AHU will be modulated based on the Supply Air temperature setpoint.
Whenever the Supply air temperature goes above the setpoint (190C - adjustable) due to which the
VFD will be ramped up and when the Supply air temperature goes below the setpoint (190C -
adjustable) then the VFD will be modulated to ramp down the speed towards minimum setting and
will continue to run on minimum speed until the Return air temperature rises above the setpoint
again.

Exhaust fan VFD will be slave to the Supply fan VFD i.e., it will follow the same frequency (speed)
as that of Supply fan.

VFD is controlled using proportional plus integral control loop.


VFD command is interlocked with the supply fan status. When the supply fan status is off, the VFD
is driven to 0% speed.

Heat Recovery Wheel


Heat recovery wheel will be electrically interlocked with the Supply / Exhaust Fan command i.e., it
will turn ON when the Supply / Exhaust Fan is turned ON.

Standby Exhaust Fan

In case of failure of exhaust air fan of the FAHU unit, the standby exhaust unit will be activated,
which will first open the associated motorized damper and upon proof of open status of the
damper, the exhaust fan will be started. Once the main exhaust fan is back to normal condition, the
standby exhaust fan will stop and the main exhaust fan will start to run.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 11 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

Fail to start indication:


Supply Fan ‘Fail to Start’ alarm is raised when there is command sent to start the fan, and there is
no supply fan run status for more than 2 minutes.

Failure during normal operation indication:


An alarm advisory is raised at the BMS workstation when the supply fan fault is ON with complete
equipment tag.

Alarm indication:
An alarm advisory is raised when the air temperature is outside of the set limit. Alarms are raised
immediately when the supply fan trip alarm is detected.
Fire mode:
In case of Fire, an alarm advisory will be raised at the BMS workstation and the Fire Alarm System
will trigger through its control module to turn OFF the Supply and Extract fans of FAHU and cooling
valve will be modulated towards closed position.

Run hours:
The supply fan status is totalized to display the total run hours (RUN-HRS) of the equipment.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 12 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

4- BASEMENT SMOKE EXTRACT SYSTEM

A- SYSTEM DESCRIPTION

Basement Smoke extract system consist of below listed equipment which will operate based on
CO level, time scheduling and in Fire mode.

Each Basement floor have dedicated set of Smoke Extract, Car Park Jet / Induction fans & Fresh
Air fan as mentioned in the below table and will be operated accordingly.

BASEMENT-1 QTY BASEMENT-2 QTY


EQUIPMENT NAME
NOS. NOS.

SMOKE EXTRACT FANS 4 4

CAR PARK JET / INDUCTION FANS 8 8

FRESH AIR FANS 4 4

B- SEQUENCE OF OPERATION

SCHEDULED CONTROLLING

All the Fans will be interlocked with System Enable, HAND-OFF-AUTO and Trip Status. Whenever
all the Fans are in Auto mode, Trip Status is Normal, System enable point is enabled and as per
Scheduling the Fans will run after every 2 hours (adjustable) at low speed i.e., Jet Fans will run at
Low speed and Smoke Extract / Fresh air fans will run at minimum speed 30Hz (adjustable).

CONTROLLING BASED ON CO LEVEL

Since the controlling of complete system need to be done based on CO level in each parking floor,
hence average of all the CO sensors in each parking floor will be the reference for controlling the
fans operation.

Considering all the interlock (mentioned in the scheduled operation) are satisfied and based on
average reading of 4 nos. of CO sensors in one zone (tower) on one floor the system will operate
in following sequence:

1. When the average reading of 4 nos. of CO sensors in one zone (tower) on one floor is
above the setpoint i.e., 25ppm (adjustable) then the Smoke extract fans and Fresh Air fan
serving that particular floor will start to run on minimum speed i.e., 30Hz (adjustable) and
Jet fan will start running on Low speed.
2. The VFD’s on Smoke extract fans and Fresh air fans will be modulated through
proportional and integral (PI) control loop

Sequence of Operation Building Management System (BMS) Rev. 00


Page 13 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

3. After a certain duration of Smoke extract, Fresh Air and Jet fan running, if the average CO
reading is still above setpoint i.e., 25ppm (adjustable), and continues to increase and
reaches 30ppm or more then the PI control loop will modulate the VFD’s of Smoke extract
and Fresh Air fans and ramp up to the speed of 40Hz and Jet Fans will continue to run on
Low speed.
4. Once the average of 4 nos. of CO level is controlled and is below the allowed setpoint i.e.,
20ppm, the Smoke Extract Fans and Fresh Air fans will modulate towards minimum speed
ultimately stopping the Fans and in conjunction to it Jet Fans will also stop running.
5. In this complete operation the Jet Fan will run on Low speed and will run in high speed in
case of Fire only.

FIRE MODE

In case of fire, all above mentioned controlling scheme will be overridden and the system will run at
full/maximum speed. The override action will be done by providing a trigger from Fire Alarm
system control module to the override contactor of each MCC panel. There will be no control from
BMS in case of Fire.

C- ALARM INDICATIONS

An alarm advisory is raised when any of the following event occurs.

1. Fan “HAND-OFF-AUTO” switch is in Auto mode and Fan DPS is not active after initial
waiting period (60 sec) of Fan command, then a “No Air flow” alarm shall be initiated at
BMS workstation.
2. Fan is Tripped.
3. Average of 4 nos. of CO level is above the allowed CO level setpoint.

5- DUCTED INLINE EXHAUST FAN

A- GENERAL
The fan operation is generally a continuous operation.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 14 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

B- SEQUENCE OF OPERATION
NORMAL MODE
The exhaust air fan is twin motor fan it will be set from the BMS duty and standby. The fan shall start
and stop either locally at the MCC via the “HAND-OFF-AUTO” switch, for testing purposes, or
remotely from the BMS when the “HAND-OFF-AUTO” switch is on the AUTO Position.

When Enable command is generated from the BMS Station according to the time schedule
configured the motorized damper will be commanded to Open and upon proof of open status the
Fan will be commanded to turn “ON”.

FIRE MODE
In case of fire, above mentioned controlling scheme will be overridden and the system will run at
maximum speed. The override action will be done by providing a trigger from Fire Alarm system
control module to the MCC panel. There will be no control from BMS in case of Fire.

C- ALARM INDICATION
Alarm will be raised at the BMS workstation for the following event:
- Fan HOA switch is in Hand position
- Fan is tripped.
- When No Flow is detected by the DPS across the Fan after 30 sec. (adjustable) of “ON”
command to the Fan.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 15 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

6- KITCHEN EXHAUST FAN (KEF)

A- GENERAL
The fan operation is generally a continuous operation.

B- SEQUENCE OF OPERATION
NORMAL MODE
The fan shall start and stop either locally at the Auto Changeover panel via the “HAND-OFF-AUTO”
switch, for testing purposes, or remotely from the BMS when the “HAND-OFF-AUTO” switch is on
the AUTO Position.

When Enable command is generated from the BMS Station according to the time schedule
configured the motorized damper will be commanded to Open and upon proof of open status the
Fan will be commanded to turn “ON”.

FIRE MODE
In case of fire, above mentioned controlling scheme will be overridden and the system will be
controlled by Fire Alarm system. The override action will be done by providing a trigger from Fire
Alarm system control module to the Auto Changeover panel. There will be no control from BMS in
case of Fire.

C- ALARM INDICATION
Alarm will be raised at the BMS workstation for the following event:
- Fan HOA switch is in Hand position
- Fan is tripped.
- When No Flow is detected by the DPS across the Fan after 30 sec. (adjustable) of “ON”
command to the Fan.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 16 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

7- STAIRCASE PRESSURIZATION FAN (SPF)

A- GENERAL
These Fans will run for Pressurizing the stairwell in case of fire only.

B- SEQUENCE OF OPERATION

Staircase pressurization fans and its respective MVCD’s will operate only in case of fire; hence the
ON/OFF control will be done by Fire Alarm System through a trigger from control module to the
Starter control panel and dampers will be controlled through an interlock in the Starter control panel
itself.

Upon confirmation of Air flow status and Dampers opening status monitored by BMS and based on
the pressure sensor which will be monitoring the pressure in the stairwell, the VFD speed command
will be modulated by BMS to maintain a pressure of 45 to 55Pa (adjustable) in the stair well.

The VFD’s will be modulated through proportional and integral (PI) control loop.

If the pressure in the stairwell exceeds 55Pa then PI control loop will modulate the VFD’s of
Pressurization Fans to ramp down the speed and if the pressure falls below 45Pa then VFD’s will
be modulated to ramp up the speed.

Once the fire signal is reset, the VFD will be modulated towards 0Hz gradually and starter control
panel will turn OFF the fans and will close the dampers as well.

C-ALARM INDICATIONS

Alarm will be raised at the BMS work station for the following events:

- Air flow status


- MVCD’s open status

Sequence of Operation Building Management System (BMS) Rev. 00


Page 17 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

8- LIFT PRESSURIZATION FAN (LPF)

A- GENERAL
These Fans will run for Pressurizing the lift well in case of fire only.

B- SEQUENCE OF OPERATION

Lift pressurization fans and its respective MVCD’s will operate only in case of fire; hence the ON/OFF
control will be done by Fire Alarm System through a trigger from control module to the Starter control
panel and dampers will be controlled through an interlock in the Starter control panel itself.

Upon confirmation of Air flow status and Dampers opening status monitored by BMS and based on
the pressure sensor which will be monitoring the pressure in the Lift well, the VFD speed command
will be modulated by BMS to maintain a pressure of 25 to 40Pa (adjustable) in the stair well.

The VFD’s will be modulated through proportional and integral (PI) control loop.

If the pressure in the lift well exceeds 40Pa then PI control loop will modulate the VFD’s of
Pressurization Fans to ramp down the speed and if the pressure falls below 25Pa then VFD’s will
be modulated to ramp up the speed.

Once the fire signal is reset, the VFD will be modulated towards 0Hz gradually and starter control
panel will turn OFF the fans and will close the dampers as well.

C-ALARM INDICATIONS

Alarm will be raised at the BMS work station for the following events:

- Air flow status


- MVCD’s open status

Sequence of Operation Building Management System (BMS) Rev. 00


Page 18 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

9- FAN COIL UNIT (FCU) – FOR COMMON AREA

A- GENERAL
FCU (Fan Coil Unit) serving the common area is equipped with Fan and Cooling Coil with motorized
valve actuator. Zone temperature monitored and controlled by modulating cooling valve actuator.
FCU is controlled by dedicated thermostat which is connected to a controller and the same will be
communicating to the BMS workstation through an automation server.

B- SEQUENCE OF OPERATION:

FCU fan is turned “ON” once the command is given from the thermostat. The speed of the fan will
vary depending on the demand.

Filter sections are monitored by BMS through Air differential pressure switch across filter.

Cooling valve will be modulated to control the space temperature. When the space temperature is
above the set point, then cooling valve will be modulated towards open position. When the space
temperature is below the set point, the cooling valve is modulated towards close position and
accordingly Fan speed will be varied.

C-ALARM INDICATION

Alarm will be raised at the BMS workstation when following events are occurred:
- Filter status is blocked
- Space temperature is above OR below setpoint.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 19 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

10- PLATE TYPE HEAT EXCHANGER

A-GENERAL

Two sets of Plate type heat exchanger shall be installed in basement-2 ETS room of which primary
side will be connected to the district cooling plant (by others) and the secondary side will be
connected to the secondary pumps which will supply the required chilled water to the terminal units
in both the towers.

Each Heat exchanger will be equipped with Inlet/Outlet temperature on the secondary side,
Differential pressure transducer at the index circuit and PICV valve on the Bypass line.

B- BYPASS VALVE CONTROL

The PICV valve installed on the bypass line will operate based on inlet temperature on secondary
side of heat exchanger. If the inlet temperature is less than setpoint i.e., 14.5℃ (adjustable) then
PICV valve on the bypass will be modulated towards opening by the proportional and integral
control loop and will continue to open until the set temperature is more than 14.5℃.

If the inlet temperature at the secondary side increases more than setpoint i.e., 14.5℃ (adjustable)
then PICV will modulate towards closing and gradually it will be completely closed.

C- ALARM INDICATIONS

Alarm will be raised at the BMS workstation for the following events:

- Inlet Temperature of heat exchanger on secondary side is less than 9℃ (adjustable) OR


higher than 16.5℃ (adjustable).

D- INTERFACE WITH DISTRICT COOLING PLANT

Points which are available from the point list attached will be shared to the BBU PLC, through
BACnet/IP from the BMS.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 20 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

11- SECONDARY CHILLED WATER PUMPS

A-GENERAL
Secondary Chilled water system will consist of 3nos. of Variable speed pumps (2 Duty + 1 Standby
/ Assist) serving the chilled water to two towers i.e., Tower-A & Tower-B. The chilled water riser of
both the towers will be equipped with Differential Pressure Transmitter which will be installed at the
2/3rd length of each riser i.e., in Tower-A DPT shall be installed at Level-10 and in Tower-B DPT
shall be installed at Level-6.

B- SEQUENCE OF OPERATION
All the Pumps will be interlocked with System Enable, HAND-OFF-AUTO and Trip Status. When all
the pumps are in Auto mode, Trip Status is Normal, System enable point is enabled, pumps are
ready to start.

Pumps will operate in 2 duty and 1 Standby / Assist combination. Also, whenever any of the duty
pump fails to operate or is tripped then the standby pump will take over and will continue the
operation and an alarm will be raised at the BMS workstation.

Since we have two differential pressure sensors on both the risers, amongst the two sensors,
whichever is reading the least value will be considered as reference for modulating the speed of
the pumps and will be operated in following sequence.

1. In addition to the above-mentioned interlock, whenever the reading on any of the two
differential pressure sensors installed is less than the desired setpoint (to be provided by
the TAB team) then the VFD will start to modulate, ramping up the speed of the Duty pump-
1 gradually towards 100%. The VFD will be modulated by Proportional and Integral (PI)
control loop module.

2. When the chilled water valve on each AHU/FCU start to open due to increasing load, the
differential pressure sensor shall send a signal to the BMS, which in turn shall control the
VFD on the CHW pumps to maintain the set differential pressure in the line, thus increasing
the CHW flow in the circuit.

3. When the differential pressure setpoint is not achieved by ramping up the VFD speed of
Duty Pump-1 to maximum allowed speed (to be received from the pump manufacturer),
then after a certain time delay its speed shall be ramped down gradually to the minimum
speed (to be received from the pump manufacturer) and then the Duty pump-2 will be
introduced and both the pumps will further be ramped up in synchronization in order to
achieve the desired differential pressure setpoint.

4. Once the desired setpoint is achieved then both the pump’s speed shall start reducing
gradually until it reaches to minimum speed (to be received from the pump manufacturer)
eventually stopping one pump after defined time delay and the differential pressure shall be
maintained by one pump.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 21 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

5. In the event of minimum load in both the towers, only one pump will run at minimum speed
maintaining the chilled water circulation in the circuit and in the event of full load, the 2 duty
pumps shall operate and will be sequenced in such a way that each duty pump will be
rotated weekly and will be replaced by standby pumps.

C- ALARM INDICATIONS

Alarm will be raised at the BMS workstation for the following events:

- Any pump is tripped.


- Standby pump is turned ON.
- Differential pressure is less than setpoint.
- HOA switch is in Hand position.
- In the event of no flow on the pump, when command is “ON”

12- PRESSURIZATION UNIT

Pressurization unit shall have its control panel connected to the BMS to indicate its operation. It will
monitor pump health, common fault alarm, pressure alarm and HOA status.

A Graphical representation of the plant will be produced to indicate the status and alarms.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 22 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

13- DOMESTIC WATER TRANSFER PUMPS

Transfer Pumps will be controlled by its own control panel and will be monitored only at the BMS for
Run and trip status of each pump through hardwired connection from DDC panel to Pump control
panel.

A Graphical representation of the plant will be produced to indicate the status and alarms.

14- IRRIGATION WATER PUMP SET

Irrigation Pumps will be controlled by its own control panel and will be monitored only at the BMS for
Run and trip status of each pump through hardwired connection from DDC panel to Pump control
panel.

A Graphical representation of the plant will be produced to indicate the status and alarms.

15- LIFTING/SUMP PUMP

Sump Pumps will be controlled by its own control panel and will be monitored only at the BMS for
Run and trip status of each pump and Sump Low-level & High-level alarm, through hardwired
connection from DDC panel to Pump control panel.

A Graphical representation of the plant will be produced to indicate the status and alarms.

16- FIRE PUMPS

Firefighting Pumps will run only in case and that too will be controlled by its own control panel and
will be monitored only at the BMS for Run and trip status of each pump through hardwired
connection from DDC panel to Pump control panel.

A Graphical representation of the plant will be produced to indicate the status and alarms.

17- BOOSTER PUMP

Booster Pumps will be controlled by its own control panel and will be monitored only at the BMS for
Run and trip status of each pump through hardwired connection from DDC panel to Pump control
panel.

A Graphical representation of the plant will be produced to indicate the status and alarms.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 23 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

18- DOMESTIC WATER CIRCULATION PUMP SET

Domestic Water Circulation Pumps will be controlled by its own control panel and will be monitored
only at the BMS for Run and trip status of each pump through hardwired connection from DDC
panel to Pump control panel.

A Graphical representation of the plant will be produced to indicate the status and alarms.

19- HOT WATER CIRCULATION PUMP SET

Hot Water Circulation Pumps will be controlled by its own control panel and will be monitored only
at the BMS for Run and trip status of each pump through hardwired connection from DDC panel to
Pump control panel.

A Graphical representation of the plant will be produced to indicate the status and alarms.

20- WATER TANKS

Water Level in tank shall be monitor through Level switch. A Hooter and Audio-visual unit shall be
connected through control panel. When Level switch indicated High level then control panel shall
trigger the Hooter NO/NC switch position from NO to NC, and Hooter and Audio alarm shall have
triggered. Once the Tank Level comes to normal state, the NC point shall toggle to NO position
and Hooter and Audio alarm shall settle to normal.

21- WATER SOFTENER

Water Softener will be controlled by its own control panel and will be monitored only at the BMS for
Hand/Auto, Run and trip status of the system and Level Status, through hardwired connection
from DDC panel to Water Softener control panel.

A Graphical representation of the plant will be produced to indicate the status and alarms.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 24 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

22- POOL WATER HEAT EXCHANGER

Primary and secondary side inlet and outlet of the heat exchanger will be equipped with the
immersion temperature sensor and a DPT will be installed at the index on the secondary side
which will be connected to a DDC through which it will be monitored at the BMS.

The PICV at the outlet of the heat exchanger will be open OR close based on temperature setpoint
of the heat exchanger outlet temperature and will serve as isolation for inlet of the pool.

A Graphical representation of the plant will be produced to indicate the status and alarms.

23- POOL FILTRATION PUMP

Pool Filtration Pump will be controlled by its own control panel and will be monitored only at the BMS
for Panel Live, Run and trip status of each pump through hardwired connection from DDC panel
to Pump control panel and pressure will be monitored at the header of the pump set through an in-
line pressure sensor which will be connected to the DDC.

Also, DPS will be installed across the filter to monitor the filter status which will be connected to
DDC.

A Graphical representation of the plant will be produced to indicate the status and alarms.

24- OIL INTERCEPTOR

Oil interceptor panel will provide volt free contact for the Tank level status and the Tank overflow
status which will be monitored at the BMS.

A Graphical representation of the system will be produced to indicate the status and alarms.

25- GARBAGE ROOM ODOR CONTROL UNIT

The GROC Fan Run, Trip status and VOC level through VOC sensor will be monitored by the BMS
and Necessary alarms will be initiated accordingly.

A Graphical representation of the system will be produced to indicate the status and alarms

26- GARBAGE ROOM DX REFRIGERANT UNIT

The Garbage room DX Unit will be monitored for Run Status, Trip Status and Room temperature
via a Room temperature sensor.

A hooter will be used for annunciating the alarm for temperature monitored by BMS.

A Graphical representation of the system will be produced to indicate the status and alarms

Sequence of Operation Building Management System (BMS) Rev. 00


Page 25 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

27- GARBAGE CHUTE PANEL

Garbage Chute will be controlled by its own control panel and will be monitored only at the BMS for
Panel Live, Run and trip status through hardwired connection from DDC panel to control panel.

A Graphical representation of the plant will be produced to indicate the status and alarms.

28- ELECTRIC WATER HEATER

The following points pertinent to the Electric water heater will be monitored by the BMS and
Necessary alarms will be initiated accordingly:
-INLET/OUTLET CHW Temperature shall be monitored through Immersion temperature sensor.
-EWH run/trip status shall be monitored through volt free contact in the unit respective panel.

A Graphical representation of the plant will be produced to indicate the status and alarms.

29- WATER LEAK DETECTION SYSTEM

The BMS shall monitor the following signals from water leak detection system through the
Voltage free contacts from WLD.
- Panel Live status
- Panel Alarm signal

30- FIRE ALARM SYSTEM

The BMS shall monitor the following signals from FAS through the Voltage free contacts.
-Common fault alarm.
-Alarm status.

In addition to above the Fire Alarm system will be monitored at the BMS via. BACnet/IP
protocol.

31- LIGHTING CONTROL SYSTEM

Lighting control system critical points will be monitored at BMS via. BACnet/IP protocol.

32- UPS

The BMS shall monitor the following signals from UPS through the Voltage free contacts.
-Common fault alarm.
-Battery fault.
-Bypass mode

Sequence of Operation Building Management System (BMS) Rev. 00


Page 26 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

-Data monitoring

33- CCU SERVER

The BMS shall monitor the following signals from CCU through the Voltage free contact.
-CCU ON/OFF Status.

34- LIFT

The BMS shall monitor the following signals from Lift unit through the Voltage free contacts.
-Lift Run Status.
-Common fault alarm.

35- CBS

The BMS shall monitor the following signals from CBS system through the Voltage free
contacts.
-Common fault alarm.
-Mains Fault.

36- GENERATOR

The BMS shall monitor the following signals from the Diesel Generator through the Voltage
Free contacts by Generator supplier.
-Generator Breaker on/off status.
-Generator common fault alarm.
-Generator battery charger trouble alarm.
-Generator fails to start.
-Generator fuel level alarm.

37- CAPACITOR BANK

The BMS shall monitor the following signals from CB system through the Voltage free
contacts.
-Common fault alarm.

38- ATS LV ROOM

The BMS shall monitor the following signals from the ATS LV Room through the Voltage

Sequence of Operation Building Management System (BMS) Rev. 00


Page 27 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

Free contacts by ATS supplier.


-Duty Selector switch Monitoring (HOA)
-Generator Breaker on/off status.
-Generator TV IP Status.
-Main Breaker ON/OFF status.
- Main Breaker TV IP Status.
-Battery charger status.

39- EMP

The BMS shall monitor the following signals from the EMP Panel through the Voltage
Free contacts.
-EMP panel on/off status.
-EMP panel trip Status.

40- SOFT-INTEGRATION

40.1- BTU METER SOFT-INTEGRATION (via. M-BUS)

BTU meter shall be mapped to the billing software through a converter from which the consumption
report for each meter can be monitored and bills can be generated for each tenant.

40.2- COLD WATER METER SOFT-INTEGRATION (via. M-BUS)

Cold water meter shall be mapped to the billing software through a converter from which the
consumption report for each meter can be monitored and bills can be generated for each tenant.

40.3- HOT WATER METER SOFT-INTEGRATION (via. M-BUS)

Cold water meter shall be mapped to the billing software through a converter from which the
consumption report for each meter can be monitored and bills can be generated for each tenant.

40.4- KWH METER SOFT-INTEGRATION (via. MODBUS RTU)

KWH meter shall be monitored at the BMS via. Modbus protocol. All the meters will be monitored
for different parameters which are received at the BMS server from each meter.

40.5- ZCV SOFT-INTEGRATION (via. BACNET/IP)

ZCV shall be monitored at the BMS via. Fire Alarm system to which it will be connected directly
through hardwired connection. Fire Alarm system shall share the data to BMS via. BACnet/IP
protocol.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 28 of 29
Dev Manager/ Client Rep: Lead Consultant Main Contractor MEP contractor: BMS Sub Contractor:

40.6- CCU SEVER (via. BACNET/IP)

CCU Server shall be monitored at the BMS server through BACnet/IP protocol. Critical parameters
of each CCU will be monitored at the BMS.

40.7- SECURITY SYSTEM (via. BACNET/IP)

Security System shall be monitored at the BMS server through BACnet/IP protocol. Critical
parameters of each CCU will be monitored at the BMS.

40.8- LIGHTING CONTROL SYSTEM (via. BACNET/IP)

Lighting control system shall be monitored at the BMS server through BACnet/IP protocol.Critical
parameters of each CCU will be monitored at the BMS.

Sequence of Operation Building Management System (BMS) Rev. 00


Page 29 of 29

You might also like