Professional Documents
Culture Documents
Supplementary Information
x NR/GN/TRK/3103/SU302
x NR/GN/TRK/3103/SU303
x NR/GN/TRK/3103/SU304
x NR/GN/TRK/3103/SU305
x NR/GN/TRK/3103/SU306
x NR/GN/TRK/3103/SU307
If you have any questions, or need assistance, please contact IHS Support
Information accessed via the links above is the property of the Copyright holder
Issue record
Issue Date Comments
1 First issue
Reference documentation
NR/L2/EDT/002, Computer Aided Design Drawing Specification
NR/L2/MTC/088, Arrangements for maintenance of new and changed assets.
NR/L2/TRK/001/C01, Inspection and maintenance of permanent way – Geometry
and gauge clearance.
NR/L2/TRK/2102, Design and Construction of Track.
NR/L2/TRK/3100, Telecommunications Maintenance Testing & Failure Investigation.
Surveying for Engineers. Uren, J. and Price, W.F. 5th edition 2010. ISBN
9780230221574
GPS Guidelines for the use of GPS in Surveying and mapping. Published by RICS
Books 2010.
RICS Guidance Note, Network RTK Best Practice Guide and Guidelines for the use
of Network RTK GPS in Land surveys. Newcastle University in association with the
Survey Association, Ordnance Survey, Leica Geosystems, Trimble and RICS.
Virtually Real: Terrestrial laser scanning: RICS Geomatics client guide series
Disclaimer
In issuing this document for its stated purpose, Network Rail makes no warranties,
express or implied, that compliance with all or any documents it issues is sufficient
on its own to ensure safe systems of work or operation. Users are reminded of their
own duties under health and safety legislation.
Supply
Copies of documents are available electronically, within Network Rail’s organisation.
Hard copies of this document may be available to Network Rail people on request to
the relevant controlled publication distributor. Other organisations may obtain copies
of this document from IHS. Tel: 01344 328039.
Page 2 of 69
--`,,,`,`,```,``,,,,``,,,`
Contents
1 Purpose 5
2 Scope 5
3 Definitions 5
4 Surveying and GRIP 6
5 General 7
6 GNSS surveys 7
7 Aerial techniques 23
8 Selective and non-selectable mapping techniques 34
9 Terrestrial laser scanning 35
Appendix A Track monitoring 44
Appendix B Survey and setting out for slab track 54
Figure 1 – Dual frequency GNSS receiver 8
Figure 2 – OSBM 12
Figure 3 – Examples of Engineer’s levels 13
Figure 4 – Example of digital level and bar-coded staff with conventional “E”staff 14
Figure 5 – Conventional levelling staff and view through the instrument 14
Figure 6 – Variations on cross-hairs as seen through an instrument 14
Figure 7 – Site Example with three TBMs and two level set up locations 16
Figure 8 – “Rise and fall” example 19
Figure 9 – Two-peg test 21
Figure 10 – Leica Rugby 200 and sensor 22
Figure 11 – Rotary wing aircraft 25
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 3 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Page 4 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
1 Purpose
This Guidance Note standard has been written to enable a general understanding of
the techniques that may be used to collect survey data for Topographic surveys
requiring a positional accuracy of better than r 100mm. It provides detailed project
processes for track monitoring and surveying for slab tracking as Appendices.
Such surveys are not an automatic requirement for all projects.
It specifically excludes ground investigation, geotechnical, building condition,
dilapidation surveys and surveys associated with Network Rail owned and operated
measurement trains.
It is intended to be used in conjunction with the suite of Network Rail Topographic
surveying standards. Parts of NR/L2/TRK/3100, Topographic, engineering, land and
measured building surveying – Surveying and general specify information to enable
a specification for survey data collection to be developed for the disciplines of Track
(specified in NR/L3/TRK/3101), Civils (specified in NR/L2/TRK/3102, in
development), OLE, Signalling and Commercial Property (all with standards to be
developed).
This Guidance Note provides guidance and recommendations on the GRIP stages
that the various techniques are best suited for.
2 Scope
This Guidance Note provides guidance on surveying activity for which a co-ordinated
engineering, land, topographic or measured building survey is required.
The concept of a survey risk register is covered in NR/L2/TRK/3100.
NOTE 1 It is important to consider the accuracy of the survey required and also the commercial and
technical risks involved with a survey.
NOTE 2 As an example consider a track renewal site where a decision has to be made as to which
technique is appropriate. This very much depends on the type of route. In general terms, a decision
has to be made between the options of a Hallade survey (NR/L3/TRK/3101 Section 5.11) or Total
Station (electronic theodolite and EDM) detail survey (NR/L3/TRK/3101 Section 5.8). All planned
works in the area need to be considered (track and other disciplines). Where adjacent tracks
(alongside or close by on the same track) are to be renewed a topographic survey would be
advantageous. When other works such as level crossing renewals, platform reconstructions, or
certain types of drainage work, are required, then a topographic survey has distinct advantages.
When new and innovative techniques not covered by this standard are developed
and are appropriate for use, these techniques can be presented to the Network Rail
Senior Survey Engineer for consideration and approval.
3 Definitions
For the purposes of this standard, the terms and definitions in NR/L2/TRK/3100
apply.
Page 5 of 69
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Construction testing
and commissioning
Output definition
Option selection
Project closeout
Detailed design
Pre-feasibility
Single Option
development
Hand back
Survey
Survey project
strategy* 9
Aerial
photography 9 9
LiDAR 9 9
Terrestrial Laser
Scanning 9 9 9 9
Ground land and
topographic 9 9 9 9 9
survey
Geographic
Information 9 9
Systems
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
NOTE *As defined in NR/L2/TRK/3100 Section 5.1
Table 1 – Surveying and GRIP
The needs at the earlier stages of the GRIP process (3 and 4) and the accuracies
required are better suited to remote sensing techniques such as aerial photography
and LiDAR. Other aerial mounted sensors may also be used to provide data such as
infra-red imagery (vegetation management, heat loss uses).
Accuracies needed for more detail at GRIP stages 3, 4 and 5 are more suited to
terrestrial laser scanning or ground topographic survey.
NOTE Terrestrial laser scanning cannot be used for survey of rails for alignment design or platform
edges unless special targets are used as shown in NR/L3/TRK/3101 Figure 12.
Page 6 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
5 General
A phase often used in surveying is to work from the “whole to the part”. In practice
this means that surveys are conducted in two parts: control survey and detail survey.
The control survey is a framework of ground markers that are surveyed to high
accuracy to find their location on the survey grid.
During the detail survey, instruments are established over the ground markers and
the features that we want to record are measured. The detail survey is carried out to
a lower accuracy than the control survey and adjusted to fit the survey control
framework. The detail survey also has a role in detecting gross errors in the survey
control.
This same idea of working from the “whole to the part” applies with surveying using
other methods such as the Omnicom 3D surveyor train mounted video system. In
this case, the video is the detail survey and the survey control comes from the GNSS
and inertial measurements that are used to determine the location of the train.
As the survey PGM network is often not required by the engineer for their work, its
purpose is often not understood. It should be considered to be like the foundations of
a bridge: if it is ignored, problems will follow.
Provision of a witness diagram (an example is given in NR/L2/TRL/3100 Appendix
C) should mean that the PGM can be found again and used for further work without
needing to re-observe the whole framework.
For example, additions might be required to an original survey, or a design based on
this survey might need to be marked out on the ground for construction. However,
extending a survey PGM network because a new adjacent area is now required
might cause errors when a small site is extended to cover a much larger area. The
only solution in this case is to re-compute the new network and adjust the original
survey to fit the new framework.
6 GNSS surveys
6.1 Introduction
This guidance details GNSS uses for high precision survey PGM control networks
but different types of GNSS techniques may be used for the collection of Asset
Information for input into a GIS.
Several different methodologies are in regular use but only the Static and Rapid
static concepts are explained.
For PGM control surveys, ETRF89 co-ordinates are required. These are then
capable of being converted into the project’s chosen survey grid.
A typical dual frequency GNSS receiver, capable of receiving signals from GPS,
Glonass or Galileo is shown as Figure 1.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 7 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
6.2 General
GNSS survey “Good practice” should be adhered to as detailed in the following
documents:
a) GPS Guidelines for the use of GPS in Surveying and mapping. Published by
RICS Books 2010.
b) RICS Guidance Note, Network RTK Best Practice Guide and Guidelines for
the use of Network RTK GPS in Land surveys.
c) Guidelines for the use of Network RTK GPS in Land surveys, Newcastle
University in association with the Survey Association (TSA), Ordnance
Survey, Leica Geosystems, Trimble and RICS.
d) Network RTK Best Practice Guide.
Page 8 of 69
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Secondary 1 to 2 km 1 in 50,000 r3 mm
(Second order) Pair >400 m (20 mm per km).
Tertiary 200 m 1/50 000 r3 mm
(Third order) (20 mm per km).
Table 2 – PGM hierarchy
In addition to plan position, the heights are also derived from GNSS that are two to
three times less accurate than that of plan co-ordinates. Height is as important and
typically has to be more accurate than plan. So, although the absolute accuracy of
GNSS heighting is high – each point may have a standard error of (say) 20 mm – the
relative accuracy between nearby points is low.
Additionally, when using heights from GNSS, we require heights as defined by a
spirit level (Spheroid) rather than heights above the mathematically defined surface,
Page 9 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
the geoid measured by GNSS. The differences between the spheroid and the geoid
are given as a geoid model, a “grid” of latitude and longitude.
In Britain, in simplified terms, GNSS heights are converted to heights about the
height datum (Newlyn) using the Ordnance Survey’s correction surface – OSGM02.
All control surveys in GNSS will be recorded in raw data and post-processed to
include reference stations and precise ephemeris downloads. Active Net GNSS
surveying where appropriate for detail surveying of Band 3 (r25 mm) or lower
accuracy features should include tie readings to control PGMs established by higher
accuracy GNSS techniques.
6.3 Methodology
Before commencing the observations, the contractor’s lead field surveyor for the
project should carry out a reconnaissance, accompanied by the Client’s Survey
Manager (CSM).
Almanacs will be investigated for satellite coverage for each field survey day, to
avoid periods of poor configuration. Any periods where GDOP is greater than a value
of 8 will be omitted from the processing.
For every set up, a booking sheet to record antenna heights at the start and at the
end of observations should be used.
To observe a PGM control network, three or more GNSS receivers will be used
simultaneously, occupying at least three PGMs at any one time, using baselines of
between 20 min and one hour depending on satellite coverage.
By holding one station fixed and moving the two other GNSS units on to the next two
stations, a traverse run will effectively be observed with GNSS static observations,
with each control point fixed relative to at least two others in the network. The
primary PGMs should be occupied at least twice, once tying in the primary points
only, the second run when including measurements to the Second order PGMs.
The survey contractor should provide a detailed methodology that will detail the
manner of moving receivers around the network to achieve accurate results –
synchronous shifting, leap-frogging, etc., for acceptance by the CSM prior to
commencement of the site work.
Although all heights will be deduced from GNSS observations, so that the relative
accuracies between PGMs are consistent, it is necessary to spirit level between
PGMs to obtain level values that may be utilised for engineering construction.
6.4 Computations
All GNSS survey data will be downloaded to office computers.
Survey data processing should be carried out using the manufacturer’s approved
processing software.
Prior to processing the control network, antenna heights should be checked twice,
once on import and once during set up of processing parameters. As much data as
possible collected for each PGM should be used in the processing to maximize the
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 10 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
reliability. Where bad data through poor satellite coverage was encountered, the
information should be removed from the adjustment. This is achieved by editing the
receiver timelines.
All processing should be carried out in the ETRF89 co-ordinates. Primary points
should also be linked to downloaded OS Active Rinex data, which gives a gross error
check of the network.
Baselines should be processed and checked, loop closures should be computed and
a network adjustment (using “least squares methods”) should be performed.
The maximum error ellipse at 95% should not exceed 15 mm throughout the primary
control network. This gives a measure of the accuracy of the work.
Co-ordinates should be output in the ETRF89 grid along with their precision values.
These ETRF89 values in Latitude and Longitude may now be converted into the
project survey grid.
Further discussion on the intricacies of GNSS computation are beyond the scope of
this document and reference should be made to GPS Guidelines for the use of GPS
in surveying and mapping.
6.5 Deliverables
The survey report should include:
a) an introduction;
b) a list of equipment including makes of hardware and software, versions of
firmware, etc.
c) a method statement describing the survey technique used including the
computations;
d) a network diagram (*.dgn format);
e) quality reports giving how many times the network has been adjusted to
derive the final results;
f) a GNSS network adjustment that provides the error ellipses for each point,
and the residuals of each baseline;
g) final listings of co-ordinates (also provide as Excel spreadsheet) in ETRF89
compared with any previous supplied ETRF89 values;
h) the control station witness diagrams for new PGMs using the form
NR/L2/TRK/3100/PGM witness diagram in *.pdf format.
6.6 Levelling
6.6.1 Introduction
The vertical is the direction which a plumb bob takes when it hangs freely, under the
effect of gravity. A horizontal surface is a surface at right angles to it. The height of a
point is defined as the distance up or down the vertical through a point associated
with a reference horizontal surface or datum.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`--- Page 11 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
The datum used is related to a point known as a “Bench mark” (BM). This may have
a simple local value or be related to the Ordnance Survey Newlyn datum (OSBM)
from which all heights in the UK are defined. Figure 2 shows a typical OSBM.
Figure 2 – OSBM
The network of OSBM have now been superseded by the use of GNSS levels
(see 6.7).
At its simplest, levelling is measuring between the ground and a horizontal plane
established by a spirit level or more, usually by a survey instrument known as a
level. In addition to the level, a tripod to place the level on and a measuring staff is
needed.
6.6.2 Instrumentation
Levels fall into several categories.
a) the Tilting or “Dumpy” level where before each reading a spirit level bubble
has to be adjusted (now generally superseded);
b) an automatic level (like an Optic in use for track levelling) that has a
suspended compensator to define the horizontal plain. The tolerances of the
compensator should be satisfied when the circular bubble on the automatic
level is centralised. The compensator is a free hanging prism within the
telescope, of both the automatic and digital levels which creates the
necessary refraction so that the line of sight of is horizontal. When used near
heavy machinery, the compensator can vibrate making readings impossible.
Most instruments available today fall into the latter category and are classed
as “Engineer’s levels”. There is also a variation on the Engineer’s level called
a “Digital level”. These instruments may be further split up depending on the
accuracy needs. Engineers’ levels are usually read to 1 mm with an accuracy
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`--- Page 12 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
of 1 to 2 mm. A more accurate and precise level is also available that may be
read to an accuracy of 0.1 mm and estimated to 0.001 mm;
c) laser levels where a plain is defined by a rotating laser and a sensor is used
on a measuring staff to provide a reading.
Conventional Engineer’s levels are used to sight directly upon an E-type levelling
staff and the readings are read off (as shown in Figure 5) by the observer which
allows direct measurement to the order of 10 mm with estimation to the order of
1 mm. Examples of the different types of levels are shown in Figure 3.
.
A digital level reads a bar-coded levelling staff (as shown in Figure 4). It is sighted
onto the staff and focussed then, with the press of a button, it observes the bar-code
in the field of view and calculates the observed measurement. This is stored in the
on-the instrument’s memory for download at a later time. If a value for the start BM is
known, a level may be computed on the instrument. This has the huge advantage of
removing booking error with the disadvantages of the extra costs associated with
buying a digital level and the reliance on batteries. Some digital levels do not
function correctly in low light levels or in darkness.
Figure 4 gives an example of a digital level and the associated bar-coded levelling
staff alongside a conventional “E” reading staff, that the operator has to read and
also estimate to get the mm value.
Figure 5 shows the view through the level telescope of a conventional levelling staff
and the reading estimated to 1mm.
Figure 6 shows a range of different cross-hair arrangements for different level
instruments.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`--- Page 13 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 14 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
In Figure 6, the two small “cross-hairs” are known as “Stadia hairs”, If readings of the
staff for each are taken, the lower subtracted from the higher and multiplied by 100,
the distance to the staff will be known to within 100 mm. It is a good way of
estimating distances.
Table 3 gives an indication of the accuracy that may be achieved using various
configurations of equipment.
Maximum sight
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Equipment Maximum misclosure
distance to staff
Geodetic level and invar 60 m 2 mm u ¥k
staves (stabilised)
Digital level with barcode 80 m 5 mm u ¥k
staves
Automatic optical level with 90 m 15 mm u ¥k
E-pattern staves
Key
k is the distance levelled in kilometres.
Table 3 –Accuracy of levelling equipment
Page 15 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Use the “rise and fall” method of computation when control levelling, as this shows
arithmetic errors. The “height of collimation” method should only be used when
taking many intermediate observations and particularly on building sites for setting
out.
The plane is called the height of collimation (HofC) and is defined by the height at
which the telescope of the levelling instrument is set up.
The rise and fall method has the advantage of being able to compute the differences
in height as you work and allows direct comparison with the second set of readings
when double levelling.
Figure 7 shows an example of a site with three TBMs and two locations where an
automatic level was set up. Table 4 shows what was written in the survey book.
Figure 7 – Site Example with three TBMs and two level set up locations
BS IS FS HofC RL Remarks
2.900 TBM1, Bolt at base of signal SN71
2.401 A
1.980 B
0.747 1.545 TBM2, Corner of LOC cabinet base
1.228 C
2.156 D
1.896 TBM3, Corner of access steps
Table 4 – Survey book example
Page 16 of 69
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
6.6.5 H of C method
The height of collimation for each set up is the horizontal plane that is viewed
through the telescope. This is shown in Figure 7 by the dotted line passing
horizontally through the levelling instrument’s telescope.
As in this example, we don’t know the height of any of the TBMs and we are only
interested in the relative heights throughout the site, we can assign an arbitrary
height of 10.000 metres to TBM1. As the staff reading between TBM1 and the height
of collimation is our backsight, adding the backsight value to TBM1’s reduced level
value will give us the height of collimation for this initial set up.
In this case, we obtain a value for height of collimation of 12.900 m. This height of
collimation will remain the same for this set up. For each of the intermediate sights,
we have measured the staff reading between the ground and the height of
collimation. Therefore, to calculate the reduced level of the ground, we subtract the
intermediate sight’s value from the height of collimation.
So, for point A of this survey, we should subtract 2.401 m from 12.900 m, giving a
reduced level for point A of 10.499 m. We can apply the same equation to calculate
the reduced level at point B.
We have taken a foresight at TBM2 from which we can calculate the reduced level at
this location in much the same way as we would treat an intermediate sight.
In setting up and levelling the levelling apparatus at another location, a new height of --`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
collimation will have been set and will need calculating. As we know the reduced
level of TBM2 (from using equation [3]) and we have taken a backsight to TBM2, we
can use equation [1] to calculate the new height of collimation. This new value is
then used to calculate reduced levels for the intermediate sights and for the next
TBM.
After performing these calculations, our survey book appears as shown in Table 5.
Table 5 shows calculated reduced levels for the example site shown in Figure 7.
Page 17 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
BS IS FS HofC RL Remarks
2.900 12.900 10.000 TBM1, bolt at base of signal SN71
2.401 10.499 A
1.980 10.920 B
0.747 1.545 12.102 11.355 TBM2, corner of LOC cabinet base
1.228 10.874 C
2.156 9.946 D
1.896 10.206 TBM3, corner of access steps
3.647 3.441 0.206 0.206 Check calculations
Table 5 – Calculated reduced levels for the example site
Checks on the calculations may be done by subtracting the sum of the Foresights
(FS) from the sum of the Backsights (BS) and comparing this value with difference in
Reduced level (RL) between start RL and final RL as shown in Table 5 in italics.
It is not possible to work out the misclosure error in this case as the true heights of
the TBMs are not known. However, by repeating the observations (flybacks or
double levelling) a misclosure may be obtained. In a situation where the benchmarks
had known heights the misclosure could be calculated from comparing actual and
calculate reduced levels.
The backsight and foresight values read on the flybacks and calculated heights of
collimation and reduced levels are shown in Table 6.
BS FS HofC RL Remarks
1.865 12.071 10.206 TBM3
1.627 0.716 12.982 11.355 TBM2
2.984 9.998 TBM1
Table 6 – Readings taken during a fly back run and the calculations
where
n is the number of set ups.
As this site involved two set ups, the allowable misclosure is ±4mm so the survey is
acceptable. Due to the misclosure, an adjustment should be made to the reduced
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 18 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
In Figure 8, the intermediate sighting is subtracted from the backsight and the
resultant rise is written in the rise column on the same line as the observation.
In the next line, the intermediate sight is subtracted from the foresight to arrive at a
fall of 2.111. It is written in the fall column on the same line as the observation.
To derive the reduced level, the TBM value of 35.688 has first the rise of 1.424
added to it to arrive at 37.112 and then the fall of 2.111 taken from that value to get
35.001.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`--- Page 19 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
The advantage of the “rise and fall” method is that checks are easily obtained of the
calculation by summing all the rises and all the falls and taking one from the other.
This value should then equal the final reduced level taken away from the start
reduced level. This is also shown in Table 5.
important that the operator on the staff check that when putting up an extra section
of the staff that the staff goes up fully and locks into position.
If the staff is not vertical, the observer will not be able to take an accurate reading
from it. In this case, rocking the staff to and fro or using a specially designed spirit
level bubble is necessary.
The level of some surfaces will change depending upon weather conditions. For
example, a tarmac surface will expand in heat and muddy ground, when wet, can
encourage the tripod feet to sink into it. This effect can be minimised by treading the
tripod legs well into the surface and leaving a minimum of time between setting up
the apparatus and taking readings.
Errors in recording readings can be avoided by sticking to a rigorous double
checking procedure. Using a digital level will remove this common source of error.
Although errors in TBMs or change points (CP) are given by the misclosure of the
levelling, intermediate sights are not checked. If they are observed using a digital
level, the chances of an error are small.
Page 20 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
levelling instrument is set up at this point. Pacing out these distances is accurate
enough.
The levelling staff is placed at each location and the readings are recorded. The
reading at B is S1 and the reading at A is S2.
The level is set up at a new point, D, that is L/10 (metres) away from point B, as
shown in Figure 9. The levelling staff is placed at points A and B and the readings
recorded. This time, the reading at B is S3 and the reading at A is S4.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Figure 9 – Two-peg test
Using the values for S1, S2, S3 and S4, the collimation error, e, can be calculated
using equation [5]
Collimation error e = (S1 – S2) – (S3 – S4) per L metres equation [5]
Page 21 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Page 22 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
7 Aerial techniques
7.1 General
Aerial techniques are all known as remote sensing and do not require direct access
to the track side.
7.2 Costs
The cost “per line kilometre” varies depending on location, corridor width,
specification and length of corridor. Mobilisation costs for both aerial survey and
ground survey are “diluted” by longer route corridors, i.e. “economy of scale”.
Budget costs comparison for a “standard aerial survey” including aerial data
acquisition, ground control, digital terrain models, orthophoto production and 1:500
mapping the following guideline rates apply (at 2010 prices):
a) Helicopter LiDAR survey: £800 per line kilometre;
b) Helicopter aerial photography: £1000 per line kilometre;
c) Fixed wing aerial photography: £600 per line kilometre.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 23 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Page 24 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
7.4.2 Process
The locations and the extent of each site to be digitally mapped should be clearly
defined on appropriate existing OS mapping.
Page 25 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Page 26 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
All GNSS photocontrol points should be measured where they are located on the
photography and a bundle block adjustment undertaken to derive final co-ordinates
to set up individual stereo models.
Reconnaissance and design of horizontal and vertical control including connections
to project survey grid, identification of locations of permanent ground markers and
photocontrol should be carried out by the contractor.
The proposed design of the horizontal and vertical control nets and pattern of
photocontrol, methodology, instrumentation, and methods of adjustment should be
submitted to the Client’s Survey Manager for acceptance.
7.4.6 Deliverables
The following should be delivered:
a) a copy of the flight plan for acceptance;
b) one digital copy of each photograph index plot based on Ordnance Survey
maps at 1:25,000 scale or similar;
c) the index plot, including
1) the relative positions of all accepted exposures,
2) the date and scale of photography,
3) the camera type, focal lengths and serial number,
d) a technical report as specified in NR/L2/TRK/3100, 10.4.
e) scaled photomosaics, should be prepared at 1:2500 scale using the full extent
of effective exposures, covering the route where these are required. The
photomosaics should be compiled in A1 size sheets (in digital format) which
should, where possible, contain more than one strip of photography in each
sheet. Strips may be joined by cut lines. A title block as specified in
NR/L2/EDT/002 should be included in each sheet.
Page 27 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
provide large scale site plans at 1:500 scale (or 1:200 as agreed with the Client’s
Survey manager) and a Digital Terrain Model (DTM).
The standards of accuracy and content specified below should be achieved where
the ground and other features are visible stereoscopically on the aerial photography.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`--- Page 28 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 29 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
j) Where the ground surface is not visible on the photographs in these locations
because of vegetation, overhanging structures, vehicles or other obstructions,
alternative locations should be heightened nearby.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 30 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
The LiDAR data or point cloud data and associated imagery may then be used for
mapping and digital terrain model production. A DTM is produced by modelling the
laser points classified as ground.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`--- Page 31 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Mapping accuracy
Ground
Mapping Flying Swathe Point sample Plan accuracy Vertical
scale height width density distance – x,y accuracy – z
m m pts/m mm mm mm
1:200 100 70 80 20 r40 r30
1:500 200 145 50 40 r70 r40
Table 11 – Rotary wing LiDAR accuracies
7.10 Deliverables
The following should be delivered:
a) all rails, plain line and switches and crossings, switch tips, crossing noses,
knuckles of diamonds, last through timber bearer. shown by the running edge
where visible on the LIDAR survey.
b) limits of wing rails and check rails in switches and crossings;
c) limits of continuous check rails in plain line, guard rails on bridges, viaducts,
etc.
d) railway stations, platforms, buildings, bridges, tunnel portals, level crossings,
cess lines, signal posts and gantries and other permanent structures;
e) small railway features such as line side drainage, catch pits, signals, third rail,
OLE wire, signs, point and signal operating rods or wires, cable troughs and
Page 32 of 69
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
All co-ordinate schedules and location diagrams should be quoted to three decimal
places of a metre.
Page 33 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
All data should be delivered in electronic format and hard copy when requested.
The final deliverable to Network Rail should be presented in a format specified in
NR/L2/EDT/002 as Microstation .dgn, MX GENIO files and Land XML v1.1 files.
Rails are to be provided as continuous strings. A project specific string labelling
convention should be made available from the Client’s Survey Manager.
Additional information may be provided in the form of:
a) orthophoto imagery;
b) 1/500 topographic mapping;
c) long- or cross-sections.
d) cross-sections from the DTM in .AVI movie format;
e) 3D airborne fly-throughs;
f) 3D oblique views of imagery draped over the final DTM in .jpg format.
The Project manager or Designated Project Engineer should define what additional
information is needed.
Page 34 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
9.2 Instrumentation
Two types of instrumentation are available:
a) “Time of flight” scanner. A “pulse” of laser energy is emitted from the scanner.
The time it takes for the “pulse” to travel from the scanner to the object and
back is measured, knowing the speed of the laser light, allows the distance to
be calculated. The key benefit is a longer scanning range.
b) Phased-based ranging system. A constant beam of laser energy is emitted
from the scanner and the phase shift of the returned laser light is measured
allowing the distance to be calculated.
The incoming scan dataset may be reviewed in “real-time” to so that the data is
being collected correctly.
Software provides a full set of geo-referencing, surveying, and CAD-integrated
engineering tools for creating accurate deliverables and managing large scan data
sets.
Figure 14 shows one of the Leica terrestrial laser scanners.
Page 35 of 69
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
9.4 Data collection
To locate the scans in a predetermined co-ordinate system, targeted points need to
be co-ordinated by conventional total station. As an alternative, when using certain
scanners, they may be set up and orientated over a PGM as would be done with a
total station, and the scans orientated to the grid system in that manner.
Data voids need to be minimised during the scanning process by the selection of
appropriate scanning positions and minimising temporary obstructions to the scanner
during operation (vehicles or pedestrians). Figure 15 shows a dark void or shadow in
a point cloud.
Page 36 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
where
Q is data quality
m is point density on the object in mm
Ȝ is the minimum feature size in mm.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Q = 1 – (10/5) = –1
This is an unacceptable fit.
Q = 1 – (2/5) = 0.60
Page 37 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
To keep data manipulation costs to a minimum, this data should be defined in the
project deliverables in terms of the following data types in Table 12. The costs
increase from Type 1 to 4, with Type 4 being probably approximately 20 times as
expensive as Type 1.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
e.g. the outline of the side of a cube. This
may be difficult to interpret simply for what
is needed, does give a good impression of
complexity.
Type 2 Surface to be constructed Joining lines in a series of blocks to define
surfaces, e.g. all the surfaces of a cube
given and linked to one another. This
should allow sections and simple floor
plans
Type 3 Surface plus As with Type 2. but with the addition of
main features such as doorways,
windows, main structural members. Types
2 and 3 could be combined.
9.6 Software
Software plays a critical role in handling the high-definition point clouds and aids in
the speedy extraction of engineering information. The data is stored in a database of
information. The scan data in its raw form are simply co-ordinates in a text file but
millions of points.
It is possible to use software such as Leica TruView and others such as PointTools,
to enable the point cloud data model to be viewed on-line. These are a simple add-
on to Microsoft Internet Explorer web browser. Scan data is stored on a server and
requires a good broadband link to use properly.
In Figure 16, all locations where individual point clouds have been created by setting
up the scanner for this area of survey are shown. By “clicking” the mouse over an
individual location, the image–point cloud at that location is displayed.
Page 38 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 39 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Page 40 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Page 41 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
9.7.4 Disadvantages
Laser scanners are not capable of detailing points that do not actually exist in space
such as the running edges of rails or the corner of the top of platform copers.
However, there are ways to interpolate these utilising special targets.
Page 42 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
The subject measured needs to be accessed ideally from all sides so that it can be
scanned fully.
Scanning should not be performed in adverse weather conditions where the quality
of data may be affected.
For example, scanning in heavy rain can lead to data voids due to rain drops or
erroneous data points due to the returns from the raindrops or refraction of the
measurement beam.
Huge amounts of data will need to be stored and managed. Consider that three
hours work during 17 scans collected 515 million points and created a database of
9.7 Gb in size.
The spacing of points is much closer than conventional surveying. Enough
computing power is needed to allow the manipulation of the data into a handleable
format. A good quality PC, with 2 GB RAM minimum and a dedicated graphics card
is required.
Skilled Data Modellers are needed to derive the greatest benefits from such data.
They will need to attend a training course lasting four days.
Scanner locations should be stable because the data is not collected
instantaneously. However, this does not prevent the use of scanners located on
hoists when weather conditions or local site conditions allow. Clearly accuracy needs
are important in deciding the most appropriate scanner locations.
A system for checking data collected by laser scanning needs to be developed. The
concept of Q numbers combined with scan metadata and registration residuals
should give a measure of if the dataset conforms to the specified accuracy
requirement.
This is a fast-developing technique. Proposals utilising these methods should be
reviewed in the light of the most recent developments.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 43 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Appendix A
Track monitoring
A.1 Introduction
Construction activities often occur adjacent to the operational railway and can cause
a risk of destabilisation of the track. The risk is principally to the track vertical
alignment, with a lower risk to horizontal alignment.
A.2 Responsibilities
The Project Manager should:
a) assess construction activities or site works: to identify any required mitigating
measures and/or a level of infrastructure monitoring. Monitoring levels are
described in A.4.6 and A.4.7.
b) be responsible for devising and agreeing the Asset Management Plan (AMP).
c) define the roles and responsibilities for monitoring, recording, interpreting and
reporting the data from the monitoring works;
d) agree the communication links between the site and the Maintenance
organisation and demonstrate that they work.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
A.3 Asset Management Plan (AMP)
A.3.1 General
An Asset Management Plan (AMP) should be produced by the Project Manager in
accordance with NR/L2/MTC/088.
A track monitoring plan should be included in the AMP.
The monitoring plan should:
a) include the names of individuals with post holder responsibilities for
implementing the AMP on site, management of external factors (see below
clause d) for types of external factors) and for the day-to-day management of
the data from the monitoring works;
b) include full details of the monitoring regime, such as reporting regularity, the
extent and duration of the monitoring;
c) define the competency of those monitoring the track;
d) define how the effects of external factors like pre-existing movement trends,
weather conditions likely to prevail during the site works (e.g. whether or not
hot weather patrolling is being undertaken) will be managed.
Page 44 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Before site works starts, a joint Dilapidation Survey should be carried out that include
the condition of the track (such as the presence of closed joints) and of the track
components. This should be recorded by the Project Manager or their representative
and the maintenance organisation’s Track Engineer. This should define any remedial
works arising.
A set of “baseline” monitoring readings should be taken up to a month prior to any
work commencing on site. Any existing monitoring data for the site should be
incorporated or referenced into this base data. The base readings should
demonstrate that the track complies with the ‘Maintenance limits’ for gauge (Table
1), geometry (Table 5a) and position defined in NR/L2/TRK/001/C01: Inspection and
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 45 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Where PGMs already exist, the Network Rail Project Manager or their representative
should obtain, from Network Rail Senior Survey Engineer, any existing survey PGM
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,
Page 46 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
values associated with the site. The survey should include PGMs that are located
outside the zone of influence. Any existing PGMs located within the zone of influence
should be reported to the Network Rail Senior Survey Engineer.
Where no existing PGMs occur, one new fixed monitoring pillar (NR/L2/TRK/3100,
Appendix B, B.7, Type 6) should be established in a place of safety, enabling forced
centring of the total station. It is necessary to confirm the position of the pillar for
each observation period from reference backsight targets outside the zone of
influence.
When levelling only is required, simpler Bench marks, such as any of Types 1 to 4
(NR/L2/TRK/3100, Appendix B), should be used.
All results should be recorded either directly on the instrument and downloaded to a
computer or booked in a level book and the results computed by standard height of
collimation or rise and fall methods.
Results should be presented on a spreadsheet.
Page 47 of 69
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
The Project Manager or their representative should review the survey and determine
the requirement for comparison with the track design installed at the site. This will
generally only be required for worksites where a length of six metres or more of track
might be disturbed.
Any additional monitoring of a particular infrastructure element should be agreed
between the Project Manager or their representative and the Maintainer’s
organisation representative on a site-specific basis.
Page 48 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
1) at three-hourly intervals during the works, and up to 13:00 on the first full
day of operation following return of the infrastructure to operational use at
the end of a possession, then every two days for 13 days from return to
operational traffic at the end of a possession; or
2) until any settlement has stabilised.
The monitoring should not be withdrawn, where settlement has occurred, without the
agreement of the maintainer.
The following parameters should be measured:
a) cant using a calibrated cross level;
b) six-foot;
c) cess rail and six-foot levels at three-metre intervals from the centre-line of the
works using a level (type as defined in A.4.4) and staff;
d) any other, as agreed with the maintainer;
e) track parameters for horizontal alignment will be taken at 10 m intervals from
the centre-line of the works;
f) any other, as agreed with the maintainer or triggered by earth movements
around structures such as OLE and signal gantries.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`--- Page 49 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Open Cut 50 mph TSR for one week and increase to normal
line speed when agreed with the Track Engineer.
Weekly monitoring until any deflections have
stabilised. The withdrawal of monitoring where
settlement has occurred will be with the agreement of
the maintainer.
Sheet Piling Standard
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Extending existing embankments Precautionary Monitoring, plus interrogation of NMT
trace information for the development of long
wavelength faults.
Extensions of culverts No action
In platforms and where other tight clearances apply, the tolerances, given in Table
A2, may have to be reduced in order to maintain satisfactory clearances.
Page 50 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
NR/L2/TRK/001/C01 (gauge (Table 1), geometry (Table 5a) and position) defines
requirements for intervention limits.
For some Project works, the limits for vertical displacements given might not be
wholly appropriate. Most anticipated settlements are expected to occur over a short
wavelength. In many locations, these can be less than the 20m versine chard length.
This could result in track deflections occurring that are greater than those in the table
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
going undetected.
In order to address this issue, the track should be measured in the vertical plain at
three-metre intervals, the intervention limits to be as given in Table A.3.
Page 51 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Where dynamic measurements are obtained from a Track recording vehicle (TRV),
the Maintenance organisation and the Project Manager should arrange for these
measurements to be merged with the data obtained from the site monitoring regime
to confirm the adequacy of the track or, conversely, to identify any remedial action
that is required and the timescale for such action.
If requested, the Maintainer should provide NMT data to the Project Manager for
three months from completion of works at a particular site.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
The results of infrastructure monitoring should be reviewed by the Project Manager
or their representative to determine what action, if any, is required. If remedial action
is required, the Project Manager or their representative should inform the Maintainer.
Page 52 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Prior to any works taking place on site, the contractor should mark the half chord
positions throughout the planned site, and take the six-foot and relative level
readings (known as “pre-readings”) to the adjacent track. A check should also be
carried out by the contractor, on the datum plate readings in the area affected by the
renewal and their values recorded. If the datum plate is located within the area of
land movement, this will have to be taken into consideration.
Following completion of the remedial works the contractor should measure the new
six-foot and relative levels (known as “post-readings”). The difference between the
pre- and post-readings is then added to the validated slews and lifts on a form to
give the new lifts and slews required to achieve the design if necessary. Once the
track has been installed within the tolerances these readings should become the “as-
built” readings.
The as-built six-foot and relative levels should be taken and compared to the
validated design values to so that the track has been installed to normal construction
tolerances specified in NR/L2/TRK/2102:
a) horizontally: r10 mm horizontally (at 100 to 125 mph); or r15 mm at speeds
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 53 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Appendix B
Survey and setting out for slab track
B.1 Introduction
Appendix B provides guidance on the survey requirement for surveys to set out slab
track within restricted clearance areas. This usually applies to tunnels but can apply
to any area where an increase in track fixity is required.
Processes are provided so that these works use processes that give consistent
results, which will eliminate delays and rework during installation.
This guidance applies to all projects and contracts related to slab track installations
within Network Rail.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Each location will pose different requirements, so this guidance allows for some
flexibility of approach.
Structures less than 200 m in length, that are intervisable end-to-end might not
require PGMs inside the structure as it should be possible to undertake all
measurements from the external PGMs.
Where it is necessary to link into an existing control grid, this should not be allowed
to disrupt the relative accuracy through the structure.
B.2 Equipment
Due to the need for high accuracy and precision, top end accuracy equipment should
be used. Table B1 gives details of suitable total stations, Table B2 provides target /
prism holder details and Figure 1 gives an example of the Leica professional series
of targets.
Page 54 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Table B4 gives examples of suitable precise levelling instruments that use Barcoded
staves. Table B5 provides details of instruments that may be used for measurements
to provide details for structure gauge calculations.
Page 55 of 69
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
B.3 Process
B.3.1 PGM hierarchy
The link into an existing PGM network should be arranged by Network Rail prior to
the issue of accepted values. This should be done before any detail survey work
commences.
Each end of the tunnel or structure should have baselines of sufficient length to
traverse between which are also in sympathy with each other in terms of co-ordinate
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
values. The creation of these points cannot be specific due to the diverse nature of
the areas involved.
Techniques for establishing these points may include use of GNSS and a long
baseline through the structure itself.
Page 56 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Once the baselines have been created, specific processes should apply. The
following definitions apply:
a) First order: external control already in existence at a given interval;
b) Second order: baselines at each end of the structure;
c) Third order: PGMs through the tunnel, including demountable tables or pillars;
d) Fourth Order: non-occupiable wall mounted Track Machine Guidance spigots
(TMGs). These might already be in existence.
e) Level datum point: ground or wall mounted markers used to provide height,
e.g. Building research establishment (BRE) levelling bolts.
Refer to NR/L2/TRK/3100, Appendix B for PGM types and for pillar construction.
Page 57 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
All traverses should have a computed accuracy of 1/70,000 or better. This will be an
error of less than 1.5 mm per 100 m in practice.
Fourth order points are not mandatory but might be useful on a busy site. These
would take the form of an expanding wall socket with a permanently installed TMG to
take a Leica circular prism. To provide values for these points, they should be
observed from at least three fixed control points (Third order tables) and then
computed using a least squares package.
Level values should be established from GNSS data and conversion to OS Newlyn
datum via OSGM02 from the Ordnance Survey website.
Level values created by GNSS do not have a very high relative accuracy, so use the
value for one PGM only, as a site datum and loop level from this to provide
consistent relative levels and the loop should be closed within itself.
Any errors should then adjust the existing level datum in the same way as the plan
values were done.
Through the structure, at intervals of 50 m to 70 m, BRE sockets should be fixed to
provide an independent height scheme (level datum points). This would also allow
the levelling of the demountable tables and the TMG position.
The height point of the TMG (using Leica GPH1P prism mount) is a point in space
58 mm from the wall end of the spigot along its shaft axis.
Levelling accuracies should be better than 1 mm per km.
At no point may Feno markers, wooden pegs or nails on sleepers be used as PGMs
because these are not permanent.
All data should be submitted in raw and computed format. It should include all
traverse computations and instrument set ups.
Free stationing should not be used unless there are sufficient points to resolve the
solution. A minimum of six targets plus one independent long check shot should be
used.
Page 58 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
• Method 1: The instrument is set up at one location along with a target either
side on the adjacent control points and checks are carried out as stated
above.
Measurements are taken to the track measuring device from 30 m beyond the
back PGM to 30 m beyond the forward PGM (only applies when PGMs are
spaced closer than 150 m apart) at an interval of at least five metres on
curves and 10 m on straights. Where there is any doubt, resort to five-metre
intervals. The instrument is then leapfrogged forward so the forward PGM
becomes the back PGM and the process is repeated which also provides an
overlap of points.
If using the Amberg GRP 3000 system, the overlap can be checked first. If
this is deemed acceptable, measurements may continue.
• Method 2: The instrument and targets are set up as in Method 1.
Measurements are taken to the track measuring device from 30 m beyond the
midpoint between PGMs, towards the back PGM, to 30 m beyond the
midpoint to the forward PGM at the interval specified above. The instrument is
then moved to the forward PGM and the process repeated. Checking overlap
points as before.
Individual target rail shoes should not be used.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`--- Page 59 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
Page 60 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
From these deliverables, all conversions into propriety surveying software can be
done.
Page 61 of 69
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
A distinction should be made between setting out ballasted zone (B.4.3.2), slab track
(B.4.3.3), and the transition zone (B.4.3.4).
B.4.3.3.1 General
The method of alignment measurement should follow the same practice as the
survey of the track where by the co-ordinate values of a point on the track have the
most sympathy with the PGM nearest to them.
The track should be supported by jacks at an interval of around two metres and there
should be enough jacks to allow at least two days lead on concrete pouring. The
jacks should have pointed ends so that lateral movement is unlikely when adjusting
for height. Lateral stability would also be improved by the use of adjustable bars
fixed to the adjacent rail.
A three measurement run approach should be used in order to eliminate sympathetic
movement, where adjusting one jack influences one already done.
Initially, the sleepers should be coarse lined using the Datum marks and a simple
offset and height difference. A run with the GRP TMD should then be undertaken,
measuring offsets to the datum marks, not co-ordinating points and the necessary
approximate adjustments to the position are made.
Page 62 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
A further series of survey runs with the GRP in “measure (no record)” mode co-
ordinating points (measure and compare but not recording) should follow that will
show the amount of change required on the horizontal and vertical props
(regulating).
While adjustment values are greater than 5 mm per prop, it is expected that there will
be effects on adjacent props when adjustments are made.
B.4.3.3.2.2
Where regulation is adjacent to a concreted zone or a regulated zone “manual
compensation” techniques as given in Section B.4.3.7 should be employed to assure
regulation is in sympathy with this section.
B.4.3.3.2.3
If during the regulation a new instrument location is required “dynamic
compensation” methods as given Section B 4.3.5 should be employed to assure
regulation from the new instrument location is in sympathy with the previous
instrument location.
B.4.3.3.2.4
The “Measure (no record)” function on GRP software should be used and the track
adjusted on the preliminary pass. Work should be undertaken in the same direction
for each pass.
Where possible, adjust the props to give 0 mm plan and height to design, but within
5 mm is tolerable.
Note that changes of greater than 5 mm at a prop location will affect the adjacent
props.
B.4.3.3.2.5
On the second pass, “Measure (no record)” should be used, and the track props
should be adjusted to 0 mm in plan and height. A final value within 2 mm is
acceptable.
Page 63 of 69
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
B.4.3.3.2.6
Utilising “Measure (no record)” a third and final pass is undertaken. The track props
should be adjusted to 0 mm in plan and height. Values outside of r1 mm should not
be accepted and if necessary measures to re-configure or replace the prop should
be taken if a read out to r1 mm cannot be achieved.
B.4.3.3.2.7
The final measurement record run should be taken at 2 metre round number centres.
Values at the design chainage locations identified in Table 5 - Existing and proposed
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
clearances and sixfoots should also be gathered and recorded on NR/GN/TRK/3100
Six-foot check against proposed form.
Measurements should extend 10 m into concreted zone and to the ends of the
regulated zone. Unregulated track should not be measured. The measurement file
should be named YYMMDDSS* on board the GRP and be indexed in a master log of
measurements for each track stating Road, start chainage and end chainage.
B.4.3.3.2.8
This report not only defines the comparison with Table 5 - Existing and proposed
clearances and sixfoots but also enables the rate of change parameters that affect
track quality to be considered. For example, a rate of change in alignment over a 5
or 10 m and for head of rail over a three-metre chord for twist to conform to Network
Rail construction tolerances as specified in NR/L2/TRK/2102 Appendix A Table A2.
Such information may be compiled on NR/GN/TRK/3100 Track Geometry Sign Off
sheet. A spreadsheet with an appropriate Macro that computes directly such
parameters is available from the TMD manufacturer. This sheet also allows for sign
off when acceptable tolerances have been achieved
B.4.3.3.2.9
Providing the tolerances are achieved then the process should proceed to the Check
survey. Otherwise remedial action may be taken where necessary and the process
repeated, returning to B.4.3.3.2.6.
B.4.3.3.2.10
The CST should now be called in for the checks and form NR/GN/TRK/3100 Six-foot
check against proposed form and NR/GN/TRK/3100 Track Geometry Sign Off sheet
should be passed to the Main Contractor, who in turn will collate other forms, the
check survey results and should present them to the NR representative for approval
to concrete.
Page 64 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
B.4.3.3.2.11
The CST should utilise the same location, references and technique for set up,
orientation and height transfer or free station and when possible should utilise the
Contractors total station.
B.4.3.3.2.12
The CST should measure same locations as Contractor either by:
a) using their own TMD calibrated and compared with the Contractor’s TMD; or
b) using the Contractors TMD, but should create their own measurement file on
board the GRP.
B.4.3.3.2.13
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
The CST should produce results to their own format and report to the Main
Contractor.
Figure B.4 illustrates the typical situation when an Amberg TMD is being used in
association with a Leica total station
Figure B.3 – Amberg TMD and total station
Table B6 gives the tolerances for each of the TMD runs to ensure that the track is
being progressively moved towards the design proposed position.
Page 65 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Key: d = 20 m, x = 10 m
Figure B.4 – Track adjustment at total station positions I and II with and
without DC
Page 66 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
e) Deduce uncompensated DC values, second position– first position values and
note on form NR/GN/TRK/3100 Dynamic Compensation (DC) Report Sheet.
B.4.3.8 Procedure
The procedure should be as follows.
a) Position the TMD at the fixed point on the track and enter GRP “Construction
Mode” and the position reporting will be evident.
b) Note real time reported values on form NR/GN/TRK/3100 Manual
compensation (MC) report sheet (Chainage, Left Rail, Right Rail, Axis).
c) Measure the track point (store it within the Construction Mode).
Page 67 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
d) Activate the GRP software “Manual compensation" button and enter the
chainage distance within which the differences should be smoothly reduced
so that the track axis is back on reported design position after the distance
indicated.
e) Note chainage distance on NR/GN/TRK/3100 Manual compensation (MC)
report sheet. Value in millimetres should be a function of absolute max value
on form NR/GN/TRK/3100 Manual compensation (MC) report sheet x10000.
i.e. Absolute maximum of –1.8, –1.2 and 0.9 is 1.8 mm at each two-metre
track adjustment location.
Once smoothness has been achieved and the alignment deviation is satisfied a
check should be made for clearance during the pre-pour adjustment phase and the
post-pour as-built phase.
A gauging run may be done using the GRP or other instruments and the data output
into a clear route format or an agreed static profile model.
Page 68 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
Ref: NR/GN/TRK/3103
Issue: 1
Date: 4 September 2010
Compliance date: N/A
The GRP software allows the presentation on site of a clearance from a static
theoretical profile canted with the as-found track position to the structure as surveyed
by the system Profiler.
Results should be recorded on form NR/GN/TRK/3100 Profile and six-foot check
against proposed design form.
Using these functions, a check should be made using a set of “developed” static 2D
values for Network Rail approved structural clearance and a report should be made
ahead of Construction (by applying design lifts and slues to the as-found values) in
order to check the correlation of the data with proposed from Table 5 - Existing and
proposed clearances and sixfoots.
The results of this pre-construction report should be used to prepare for acceptance
of the slues measured at the regulated track “pre-pour” stage.
An on-site means to evaluate all the data produced should be provided. This could
potentially save several hours of delay in the process.
Once the slab track has had the form work broken and the rail head cleaned of any
residue, the as built process should be repeated for both alignment and gauge with
the GRP. These records provide the “as built” and are required for hand back.
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Page 69 of 69
Copyright Network Rail
Provided by IHS under license with Network Rail Licensee=Colas Rail Limited/1121223091, User=jones, nigel
No reproduction or networking permitted without license from IHS Not for Resale, 02/28/2014 03:14:53 MST
13/07/2010
Version 1
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Senior Survey Engineer or team, or the Project Survey Systems
Building and Civils, Signalling, Control and Plant, OLE, and Engineer (CSM/Client’s Survey Manager), to define the most
Property. requiring a positional accuracy of better than r 100mm suitable survey techniques.
in position. It provides detailed project processes for track
monitoring and surveying for slab tracking as Appendices. It provides guidance and recommendations on the GRIP stages
It specifically excludes ground investigation, geotechnical, that the various techniques are best suited for.
building condition, dilapidation surveys and surveys associated This standard is also applicable to commercial remits in assisting
with Network Rail owned and operated measurement trains. in defining specifications.
What’s New/Changed:
This document updates that originally provided as the Survey and mapping guidance note that forms part of the DOORS suite of
Cross discipline engineering requirements (NR/EE/SPE/00065).
The appropriateness of various techniques for the GRIP process is also highlighted. This includes the creation of a Project Survey
strategy shall be created prior to the commencement of work as specified in NR/L2/TRK/3100.
The strategy identifies a Survey risk register, defines the Survey grid, PGM hierarchy and Project longitudinal design
chainage/metreage.
Detailed appendices are provided for Track stability monitoring and Surveying for the design and implementation of slab track.
Affected documents:
Reference Impact
NONE
Briefing requirements: Where Technical briefing (T) is required, the specific Post title is indicated. These posts have specific responsibilities
within this standard and receive briefing as part of the Implementation Programme. For Awareness briefing (A) the Post title is not mandatory.
Please see http://ccms2.hiav.networkrail.co.uk/webtop/drl/objectId/09013b5b80417471 for guidance.
*NOTE: Contractors are responsible for arranging and undertaking their own Technical and Awareness Briefings in accordance with their own processes and procedure
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---
Supplementary Information
Information accessed via the links above is the property of the Copyright holder
--`,,,`,`,```,``,,,,``,,,`,,,`,`-`-`,,`,,`,`,,`---