Professional Documents
Culture Documents
https://www.emerald.com/insight/0969-9988.htm
a case of India
R.V.K. Vigneshwar and S. Shanmugapriya 963
Department of Civil Engineering, Coimbatore Institute of Technology,
Coimbatore, India Received 7 June 2022
Revised 11 August 2022
Accepted 5 September 2022
Abstract
Purpose – Proper prediction of productivity can enable the enhanced estimation, realistic scheduling, and
accurate cost forecasting of construction processes. Due to the existence of different labor sources (unionized
and non-unionized), the prediction of productivity is still a significant problem in India. Moreover, the
construction procurement processes and on-site performance are the predominant elements that can result in
improved project outcomes. Thereby, the consideration of labor constraints and site conditions will play an
important role in productivity improvement.
Design/methodology/approach – This study investigates the factors affecting construction site
productivity. A total of 28 factors are grouped under 7 categories as follows: labor constraints, safety and
quality procurements, material and equipment (ME), site management, project working condition, delay
controls, construction methods and techniques, and external factors. Furthermore, by involving these factors,
the questionnaire survey was conducted among Indian construction practitioners. As a result, 204 responses
were received and the data were analyzed using a reliability test, relative importance index (RII), and analysis of
variance (ANOVA).
Findings – The result of this study highlighted the importance of strategic construction management activities
in terms of effective planning of ME, planning and realistic scheduling of construction activities, proper
communication, information sharing, etc. Thus, this study provides a clear insight to the Indian construction
practitioners in determining the effect of these site factors on the successful execution of their projects.
Originality/value – In this paper, the problem of construction productivity in India and its causes are
explained effectively. This study examines the preference of labor contract, labor source, and most importantly,
the factors affecting site productivity. Moreover, the other lagging issues regarding the management of
construction activities are also described in detail.
Keywords Construction productivity, Site productivity, Estimation and scheduling, Project execution,
Site conditions
Paper type Research paper
1. Introduction
Previous decades had reminded us that low productivity is a persistent and serious issue in
the construction industry (Gupta et al., 2018). The knowledge of productivity is a critical
component of construction management, and it is applied in the construction process such as
planning and scheduling, estimation, accounting, and cost control (Proverbs et al., 1998).
Some researchers stated that manufacturing industries had higher productivity rates than
the construction industry (Hasan et al., 2018). It is due to the fact that the productivity in the
manufacturing sector is seemed to be monotonous, but in the construction industry, there are
numerous factors that create fluctuations in achieving the desired results.
The authors wish to express their gratitude to the numerous respondents of this study, for their
generous collaboration and contributions. Engineering, Construction and
Informed consent: Informed consent was obtained from all individual participants included in the Architectural Management
Vol. 30 No. 2, 2023
study. pp. 963-985
Ethical statement: Authors state that the research was conducted according to ethical standards. © Emerald Publishing Limited
0969-9988
Conflict of interest: The authors declare that they have no conflict of interest. DOI 10.1108/ECAM-06-2022-0529
ECAM In India, the construction industry is the second-largest economic activity after
30,2 agriculture, employing approximately 33–40 million people (National Skill Development
Corporation, 2015; Dhal, 2020; Hasan and Jha, 2013; Dixit et al., 2018). Due to its larger size, the
construction industry greatly affects the nation’s gross domestic product (GDP) and causes
some fluctuations in local economics (Choi et al., 2013). In this competitive industry, reducing
the project cost and delivering the project on time are considered to be the most important and
critical factors (Palikhe et al., 2019; Hasan and Jha, 2016). Moreover, construction is a labor-
964 intensive industry (El-Gohary and Aziz, 2014) and it involves various people with different
levels of responsibilities (Wambeke et al., 2011). Thereby, the prediction or estimation of
construction tasks/activity highly relies on the laborers/workforce. Furthermore, Dhal (2020)
explained the precarious faces of laborers and the labor stand that exists in India. For the
better execution of the project with the available labor sources (unionized and non-unionized),
the proper prediction of the outturn (the productivity) is considered to be the preamble factor
for both pre-construction and execution phases. Therefore, the initial research questions are:
what are the factors that affect Indian construction productivity? How do these factors
influence the construction process? How do the preference and perceptions vary based on the
construction practitioners? Thereby, the first objective of this research is to identify and
analyze the factors affecting the site productivity based on the Indian scenario. Second, to
measure the impact and severity of the factors that affects site productivity (SP). Third, to
investigate and understand the various perceptional differences among the construction
practitioners.
Table 1. (continued )
Main factors ID Sub factors Source reference
Construction
site
Construction methods CMT1 The selection of construction Alinaitwe et al. (2007), Enshassi productivity
andtechniques [CMT] methods and practices has an et al. (2007), Durdyev and Mbachu
impact on site productivity (2011), El-Gohary and Aziz (2014),
Hwang et al. (2017), Gurcanli et al.
(2021)
CMT2 Utilizing advanced techniques and Durdyev and Mbachu (2011), 969
technology can enhance site Demirkesen and Ozorhon (2017), El-
productivity Gohary et al. (2017), Hwang et al.
(2017), Durdyev et al. (2018)
CMT3 The efficiency of the labor varies Alinaitwe et al. (2007), Jarkas (2010,
depending upon the buildability 2016), Durdyev and Mbachu (2011),
factor El-Gohary et al. (2017), Durdyev
et al. (2018)
External factors [EF] EF1 Government regulation affects site Maloney (1983), Enshassi et al.
efficiency (2007), Yates (2014)
EF2 Client interruption affects the site Durdyev and Mbachu (2011), Hasan
activities and Jha (2016), Durdyev et al. (2018)
EF3 The cultural and political influence Alinaitwe et al. (2007), Enshassi
affects the site execution process et al. (2007), Wang et al. (2010),
Hasan and Jha (2016) Table 1.
these workers and predict their performance for a specific task. This informal method of
employment (labor stand) results in employment variability, and it appears difficult to
estimate the project outcomes as well. For instance, the prediction of their outturn, level of
skill, training for the specific activity, safety, and quality are still remaining uncertain. By
employing these laborers, the industry is unable to predict and estimate construction activity
with precision. Consequently, this causes a lag in the project’s scheduling activities and it
often results in project delay and cost overrun.
Fourth, based on the reports of the planning commission of India’s 12th five-year plan, the
construction industry in India is found to contribute approximately 8% to the total GDP
(Dixit et al., 2017b). Similarly, the construction sector is the key driver of socio-economic
development in India. Moreover, it is expected to grow at an annual average rate of 6.6%
between 2019 and 2028 (Kar and Jha, 2020). Thereby, for the future development of the
industry and the employment of millions of laborers, construction productivity is still a major
area for improvement. Furthermore, productivity addresses the issue of resource efficiency in
the production of goods and services. Therefore, productivity growth is strongly correlated
with economic growth (Tran and Tookey, 2011).
Fifth, so far, the papers published in India regarding productivity had missed taking into
consideration of the factors such as safety and quality, usage of construction methods and
techniques, preference of labor contract, and labor source. Moreover, there were only a few
papers on the ‘‘framework to improve on-site construction productivity” and there is a
significant research and development gap in construction productivity in India (Dixit et al., 2019).
Thereby, in combination (third, fourth, and fifth), this study focuses on the factors affecting site
productivity, the consideration of labor source, and the analysis of practitioners’ perceptions.
Mostly, the developed countries are focusing on the advancement of technologies to
overcome the problem of productivity. The context of this study indicates the current
situation of the Indian construction industry, laborers’ employment, and their contribution to
India’s GDP. Thereby, focusing on the enhancement of industrial development from the
current level will make a more meaningful insight than following the same as of developed
countries.
ECAM 4. Methodology
30,2 From the literature review and the context of this study, the factors are selected and they are
grouped as shown in Table 1. To analyze the factors affecting site productivity, this study
adopted a questionnaire survey as the research method. Therefore, the questionnaire was
designed in consultation with the experts and it comprises two sections. The first part of the
questionnaire consists of general information about the respondent and the second part
consists of the factors affecting site productivity. A simple random sampling procedure was
970 followed to collect the data from different construction practitioners. Nearly 502 Indian
construction practitioners were contacted through mail, phone, social media (i.e. Linkedin),
and in person to evaluate the selected factors of site productivity. Thereby, with the ninety-
five percent confidence level and five percent margin of error, the targeted sample size was
found to be 218. During the pilot study, the weightage for many factors seems to be nearly
equal while using the five-point Likert scale. So, the scale was expanded and the respondents
were asked to fill the questionnaire with the seven-point Likert scale (strongly disagree–1;
disagree–2; moderately disagree–3; neither disagree nor agree–4; moderately agree–5; agree–
6; strongly agree–7). As a result, a total of 204 responses were received from the practitioners
and their detailed demographics were shown in Table 2. The acquired data were analyzed
using the reliability test (Cronbach’s alpha method), relative importance index (RII), and
analysis of variance (ANOVA). Thereby, the following section discusses the test results and
findings derived from the analysis.
The RII method was used to analyze the data using the equation suggested by
Shanmugapriya and Subramanian (2013) and Vigneshwar et al. (2022). Where W denotes
972 the weight assigned by respondents to each factor (ranging from 1 to 7 in this case), A denotes
the highest weight (i.e. 7 in this case), and N denotes the total number of respondents (i.e. 204
in this study). The results of the analysis were ranked and it is shown in Table 4.
Based on the designation of the respondent, the variation towards the factors of site
productivity was analyzed as shown in Table 4. The overall top factors that affect site
productivity are found to be effective planning of material and equipment, adequate planning
and realistic scheduling of activities, proper communication and information sharing,
maintenance of materials and equipment condition, and enhanced supervision. Furthermore,
to demonstrate the importance of the selected factors in the Indian construction industry, the
severity graph was developed.
Abdul Kadir et al. (2005) explained the severity index as the product of the importance
index and frequency index. By following this method, the overall RII values of this study are
considered as the importance index and the total number of highest weightage (7 ) given to
each factor was considered as the frequency index. Using these values, the severity graph
was drawn as shown in Figure 1. Moreover, the severity graph clearly shows the respondents’
acceptance rate and the criticality of the selected site productivity factors. Of the overall
respondents (204), the maximum respondents (125) had given the highest weightage to the
factor SM3 and that attributes to the need for proper planning and scheduling of site
activities. As shown in Figure 1, a minimum of 27% and a maximum of 61% of practitioners
have assigned the highest weight to the factors of site productivity. For instance, the lowest
frequency is 55 (as shown in the severity graph) and it accounted for 27% in total. Furthermore,
to determine the perception variation of respondents, the one-way ANOVA test was
performed. Specifically, Duncan Multiple Range Test (DMRT) was performed.
LC 0.884
SQP 0.875
ME 0.879
SM 0.862
PWC 0.876
DC 0.871
CMT 0.874
Table 3. EF 0.891
Reliability test Overall 0.889
Owner Contractor Consultant Architect Project manager Engineer Supervisor Academician Overall response
ID RII R RII R RII R RII R RII R RII R RII R RII R RII R Fr
LC1 0.954 2 0.822 20 0.895 12 0.667 27 0.896 10 0.854 14 0.643 28 0.937 9 0.872 14 103
LC2 0.904 13 0.84 16 0.918 6 0.81 15 0.953 1* 0.851 16 0.768 16 0.881 15 0.873 13 100
LC3 0.871 19 0.84 16 0.88 13 0.81 15 0.886 11 0.836 23 0.822 5 0.85 20 0.851 16 79
LC4 0.884 15 0.804 25 0.85 21 0.572 28 0.858 16 0.859 13 0.733 23 0.929 12 0.85 17 85
SQP1 0.874 16 0.786 26 0.82 24 0.874 8 0.867 14 0.839 20 0.75 20 0.874 17 0.846 20 82
SQP2 0.804 27 0.768 28 0.813 25 0.794 18 0.743 26 0.837 21 0.75 20 0.858 19 0.815 26 73
SQP3 0.944 7 0.822 20 0.918 6 0.937 1* 0.924 4 0.907 3 0.911 1* 0.953 5 0.919 3 117
SQP4 0.934 10 0.786 26 0.873 17 0.905 4 0.905 9 0.881 11 0.786 14 0.937 9 0.892 10 99
ME1 0.957 1* 0.858 14 0.94 2 0.905 4 0.934 2 0.905 4 0.84 3 0.999 1* 0.926 1* 124
ME2 0.934 10 0.875 11 0.948 1* 0.921 3 0.924 4 0.904 6 0.804 7 0.953 5 0.916 4 121
ME3 0.947 5 0.947 1* 0.903 9 0.858 9 0.924 4 0.883 9 0.786 14 0.953 5 0.905 7 116
SM1 0.854 25 0.822 20 0.858 19 0.762 22 0.82 20 0.827 25 0.768 16 0.842 23 0.831 23 78
SM2 0.947 5 0.929 3 0.925 4 0.858 9 0.867 14 0.904 6 0.804 7 0.977 2 0.914 5 118
SM3 0.951 3 0.929 3 0.918 6 0.937 1* 0.924 4 0.915 1* 0.804 7 0.945 8 0.923 2 125
SM4 0.941 8 0.947 1* 0.88 13 0.826 13 0.877 13 0.878 12 0.768 16 0.866 18 0.886 12 102
SM5 0.871 19 0.911 5 0.88 13 0.842 12 0.848 17 0.829 24 0.804 7 0.85 20 0.849 18 86
PWC1 0.851 26 0.84 16 0.85 21 0.794 18 0.772 24 0.849 17 0.804 7 0.889 14 0.843 21 84
PWC2 0.858 24 0.822 20 0.843 23 0.683 26 0.724 27 0.82 26 0.822 5 0.881 15 0.823 24 75
PWC3 0.901 14 0.893 9 0.903 9 0.889 6 0.915 8 0.915 1* 0.804 7 0.977 2 0.91 6 117
DC1 0.874 16 0.84 16 0.925 4 0.794 18 0.848 17 0.841 19 0.715 24 0.826 25 0.848 19 90
DC2 0.868 21 0.875 11 0.933 3 0.826 13 0.82 20 0.853 15 0.768 16 0.85 20 0.857 15 87
DC3 0.951 3 0.911 5 0.88 13 0.778 21 0.934 2 0.883 9 0.84 3 0.977 2 0.904 8 116
CMT1 0.917 12 0.893 9 0.873 17 0.889 6 0.886 11 0.905 4 0.875 2 0.937 9 0.904 8 102
CMT2 0.941 8 0.875 11 0.903 9 0.858 9 0.829 19 0.887 8 0.804 7 0.897 13 0.891 11 105
CMT3 0.874 16 0.911 5 0.858 19 0.81 15 0.781 22 0.837 21 0.679 27 0.834 24 0.838 22 77
EF1 0.791 28 0.822 20 0.76 27 0.715 25 0.686 28 0.752 28 0.715 24 0.699 28 0.751 28 55
EF2 0.861 22 0.911 5 0.797 26 0.747 23 0.781 22 0.795 27 0.715 24 0.818 26 0.809 27 72
EF3 0.861 22 0.858 14 0.737 28 0.747 23 0.762 25 0.847 18 0.75 20 0.818 26 0.823 24 80
Note(s): ID5 Indicators, R 5 Rank, Fr 5 Frequency of highest weightage (7) given to each factor, * indicates the top ranking factors
site
973
productivity
Construction
productivity
ECAM EF3 130
LC1
LC2
30,2 EF2 LC3
120
EF1 LC4
110
103 100
CMT3 100 SQP1
80.9 82.3 87.2
90
974 CMT2 72 80 87.3 85.1 85 SQP2
105 83.8 75.1 80
79 85 84.6
70
CMT1 55 82 81.5 117 SQP3
102 89.1 77 60
50 73
90.4 91.9
DC3 116 90.4 40 89.2 99 SQP4
85.7 92.6
87
DC2 84.8 91.6 124 ME1
90 75 78
91 84 90.5
121
DC1 82.3 84.9 ME2
83.1
84.3
117 116
86
PWC3 ME3
91.4
88.6 92.3
PWC2 118 SM1
102
PWC1 125 SM2
Figure. 1. SM5 SM3
Severity graph Frequency of Highest Weightage
SM4
Overall RII (%)
contract preferred, preferred workweek, and preference of labor source). From the test results,
the respondents’ designation, work experience, organization turnover, and preference of
workweek had shown a significant difference and are shown in Tables 5–8 respectively.
The null hypothesis is rejected if the p-value is less than 0.01, which indicates that there is a
highly significant difference between the groups. From Table 5, it is clear that there is a
difference in opinion with the factors of LC as the subset variations denote (i.e. a, b, c, and d). In
that, the academician, engineers, project managers, and consultants do have the constant
opinion (subset variation b), and the architects, supervisors, and contractors, are having
completely different opinions (subset variation a, c and d respectively). Similarly, the null
hypothesis is rejected if the p-value is less than 0.05 and it indicates there is a significant
difference in opinion with the factors of ME. From Table 5, it can be specified that the owners
and project managers are concerning the factors of LC and ME for better site execution with the
high mean values. From Table 6, based on the p-value it is found that there is a highly significant
difference among the respondents’ experience with the factors of LC, ME, SM, and DC.
Comparatively, this table (VI) suggests that the acceptance of the site productivity factors by the
experienced practitioners (above 20 years) is high when compared to the other respondents.
From Table 7, it is found that the large size organization (above 250 crores) had accepted
the importance of site management with a high mean value (33.1481). This result is in line
with the findings of Gurmu and Ongkowijoyo (2020) as the organization size increases, the
priority for management activities also increases. The results of Table 8 highlighted that the
respondents preferring the standard workweek had accepted the importance of safety and
quality procurements with a high mean value (24.56). From this, it can be concluded that:
following the standard workweek can assist in the safety and quality procurements of the
project execution.
Architect Supervisor Contractor Academician Engineer Consultant Project manager Owner F P
975
productivity
Construction
factors of site
respondent and the
designations of the
Table 5.
between the
Result of ANOVA test
productivity
ECAM 1–3 years 4–10 years 11–20 years Above 20 years F P
30,2
LC M 23.18 24.67 24.083 25.55 4.175 0.007**
S.D (3.569)a (3.3241)ab (3.215)ab (3.112)b
SQP M 23.84 24.49 24.08 25.04 1.032 0.38
S.D 3.106 3.780 3.063 3.124
ME M 18.59 19.20 19.91 20.36 5.195 0.002**
976 S.D (2.498)a (2.265)ab (1.530)bc (1.048)c
SM M 30 31.322 29.875 33 4.78 0.003**
S.D (3.992)a (4.087)ab (3.026)a (2.225)b
PWC M 17.76 18.14 17.92 18.13 0.249 0.862
S.D 2.796 3.008 2.320 3.719
DC M 17.41 18.81 18.79 19.18 4.402 0.005**
S.D (3.207)a (2.706)ab (1.8410)ab (3.064)b
CMT M 17.96 18.78 18.54 18.68 1.636 0.182
Table 6. S.D 2.626 2.393 2.126 1.961
Result of ANOVA test
EF M 16.34 17.13 15.29 17.77 2.529 0.058
between the
experiences of the S.D 3.414 3.282 4.418 3.663
respondent and the Note(s): 1. M-Mean, S.D- Standard deviation. 2. a, ab, b, bc, and c shows the differences in opinion (subset
factors of site variation)
productivity 3. ** denotes significance at a 1% level
6. Discussion
As previously outlined, construction productivity is the ratio of output to input. In that, the
most common input is the labor force. The labor cost of the project was estimated at around
20–50% of the total project cost by Kazaz and Ulubeyli (2004), 30–50% of the total project cost
by Hanna et al. (2005), Liu et al. (2011), Karim et al. (2013), El-Gohary and Aziz (2014), Gupta
et al. (2018) and 30–60% of the total project cost by El-Gohary et al. (2017) and Palikhe et al.
(2019). The details provided in the context of this study explain the labor issues that are
happening in India. With this, the prediction of productivity is still a significant problem that
8 h 3 6 days 8 h 3 7 days 9 h 3 5 days 9 h 3 6 days F P
Construction
site
LC M 24.06 23.90 24.06 23.74 0.085 0.968 productivity
S.D 3.352 4.306 2.979 3.570
SQP M 24.56 24.49 24.42 22.62 3.163 0.026*
S.D (3.362)a (3.187)a (3.065)a (3.393)b
ME M 19.13 19.22 19.16 18.91 0.123 0.946
S.D 2.328 2.318 2.225 2.340 977
SM M 30.48 31.59 30.78 29.97 1.209 0.308
S.D 4.221 3.398 3.840 3.571
PWC M 17.57 18.44 18.32 17.56 1.317 0.27
S.D 3.209 2.766 2.559 2.743
DC M 18.06 18.46 18.34 17.82 0.366 0.777
S.D 3.131 3.507 2.387 2.886
CMT M 18.25 18.37 18.68 18.02 0.532 0.661 Table 8.
Result of ANOVA test
S.D 2.493 2.681 2.198 2.480
between the
EF M 16.69 17.07 16.56 15.88 0.715 0.544 respondent preferences
S.D 3.337 3.517 3.812 3.851 of the workweek and
Note(s): 1. M-Mean, S.D- Standard deviation. 2. a, and b shows the differences in opinion (subset variation) the factors of site
3. ** denotes significance at a 1% level productivity
restricts the growth of the Indian construction industry. Moreover, construction productivity
influences the direct cost of the project (Tsehayae and Fayek, 2014) and it can directly affect a
certain percentage of the nation’s GDP. Thus, the contribution of labor cost and productivity
to a project provides an understanding that: labor influences productivity, and productivity
influences the project cost. Thereby, the parameters of labor (preference of labor contract and
labor source) and the factors affecting the site productivity (the working conditions of the labor
at the site) are considered in this study.
Construction projects are complex undertakings that necessitate the collaboration of
several parties in the fields of finance, engineering, procurement, construction, and law
(Georgy et al., 2005). Thereby, the responses from all the construction practitioners were
obtained and their demographics were shown in Table 2. Moreover, from Table 2, the
preference for unionized and non-unionized labor sources seemed to be almost equal. In this
regard, the majority of studies had not addressed the difference between the contractor’s
profit percentages when using unionized and non-unionized workers. According to
Diekmann and Peppler (1984), contractors can save approximately 6–7 percent by
employing non-unionized laborers. Thereby, the existence of nonunionized labor sources is
advantageous for contractors, but it raises numerous questions about the quality and safety
of the work.
From the results of Table 4, the top factors that affect site productivity are effective
planning of materials and equipment, adequate planning and realistic scheduling of
activities, proper communication and information sharing, maintenance of materials and
equipment condition, and enhanced supervision. These results are in line with the findings of
Dixit et al. (2018), emphasizing the planning, scheduling, and availability of material as the
top factors influencing the SP in India. In addition to the results, the finding of Durdyev and
Ismail (2016) in Malaysia and Durdyev and Mbachu (2011) in New Zealand highlighted the
level of skill, the experience of the workforce, and rework as the most crucial factors affecting
the SP. Apart from the overall ranking (Table 4), the individual ranking based on the
designation of the respondent had shown some different results. The project managers
ranked labor skills as the first and the payment delays to the workers as the second
influencing factor in the site execution. The supervisor’s opinion showed that the site
ECAM efficiency is based on regular communication and proper information sharing and it is also
30,2 based on the selection of construction methods and practices. Moreover, the owners accepted
that the experience and knowledge of labor influence the site efficiency. These results
suggested that there are opinion differences based on the hierarchy of the designations that
exist in the construction industry. Especially, the supervisor had considered the factors with
the practical difficulties that they are facing at the site.
Furthermore, Figure 1 explains the acceptance of respondents towards the selected factors
978 of site productivity. The severity graph highlighted the importance of pre-construction
activities, especially planning and realistic scheduling of site activities (SM3) and proper
planning of ME at sites (ME1). Thereby, the planning of activities should completely rely on
feasible execution and there should be a better understanding among the teams of planning
and execution. From Tables 1 and 5–8, the variation in perception is observed among the
factors of labor constraint, material and equipment, site management, and delay controls. As
all these factors represent the capability of management in planning, scheduling, resource
controls, etc, there occurs a constant opinion difference based on the respondents’
designation, experience, and organization turnover. Moreover, the construction schedule
can reduce 15% or more of the total project cost (Thomas, 2015). As a result, the majority of
experienced practitioners, large organizations, and project managers realize the significance
of selected factors. Thereby, the consideration of the site factors can facilitate the proper
scheduling of construction activities and the achievement of better results.
In the era of digitalization, construction productivity can be increased through the
adoption of advanced digital tools and methodologies (Rodrigues et al., 2022). Further,
increasing investments in technology and organizational innovation will result in a paradigm
shift from “working harder and longer” to “working smarter” (Choi et al., 2013) However, more
research is required to establish the connection between productivity and modern concepts of
performance optimization (Naoum, 2016). Thereby, the selected factors will facilitate a
detailed understanding of the site productivity and future research can focus on developing
these factors as a tool for optimizing the project performance.
8. Conclusion
The proper planning of activities, labor, material, and equipment will path for the better
execution of the projects. Apart from the project’s size, the consideration of site activities and
labor parameters are playing a significant role in India. Therefore, this study focuses on
identifying and analyzing the factors affecting site productivity. The questionnaire survey
was conducted, and a total of 204 responses were obtained. The top qualitative factors
affecting site productivity are found to be effective material and equipment planning,
planning and realistic scheduling, communication and information sharing, material and
equipment maintenance, and proper supervision. The analysis of different perspectives of
construction practitioners revealed that there are significant differences in opinion among the
factors of labor constraint, material and equipment, site management, and delay controls.
Overall, the result of the data analysis suggested the importance of project management
activities that are essential during the project execution phase. As discussed in the context of
this study, the focus of this study is limited to the variables that influence site productivity
and labor parameters. In addition, the implication of this study highlights the possible
solution in line with the context of this study. However, there is more scope for research
identifying the most influencing factors of management in the Indian construction sector.
Thus, future studies will address these issues and will provide more accurate predictions
regarding the suggested different levels of productivity. Rather than the context of this study,
the Indian construction industry had accomplished more successful projects and standing
unique in the field of construction development (i.e. structural, geotechnical, infrastructural,
etc). As a sector, there are still many opportunities to improve in labor utilization,
management of projects, etc. Thereby, this study is the initial attempt to cover this area in
India. Further research will explain the operations and procedures for the total sector
development even more precisely.
ECAM 8.1 Limitations and future work
30,2 As previously discussed, productivity can be measured in terms of project site execution,
management capabilities, and industrial efficiencies. By measuring site productivity, it enables the
management in determining the output of project sites, and by measuring the management
productivity it enables the efficiency of different organizations (small, micro, and macro) in
completing a project. Consequently, the sum of the multiple organization efficiency contributes to
the nation’s GDP. Thereby, the initial measure should be appropriate and the factors to be
980 considered are outlined in this study. Future research can concentrate on developing a theoretical
framework model for the context of site productivity and the factors that affect management and
industrial efficiencies. Some references considered in this study may look old but to give the proper
credentials to the original statements they have been used.
References
Abdul Kadir, M.R., Lee, W.P., Jaafar, M.S., Sapuan, S.M. and Ali, A.A.A. (2005), “Factors affecting
construction labour productivity for Malaysian residential projects”, Structural Survey, Vol. 23
No. 1, pp. 42-54, doi: 10.1108/02630800510586907.
Agrawal, A. and Halder, S. (2020), “Identifying factors affecting construction labour productivity in
India and measures to improve productivity”, Asian Journal of Civil Engineering, Vol. 21 No. 4,
pp. 569-579, doi: 10.1007/s42107-019-00212-3.
Ahmad, F., Banerjee, R., Raza, Z. and Dixit, R.B. (2017), “Swot analysis of arbitration awards in Indian
construction contracts”, International Journal of Civil Engineering and Technology, Vol. 8 No. 3,
pp. 64-73.
Ahmadian Fard Fini, A., Akbarnezhad, A., Rashidi, T.H. and Waller, S.T. (2017), “Job assignment
based on brain demands and human resource strategies”, Journal of Construction Engineering
and Management, Vol. 143 No. 5, 04016123, doi: 10.1061/(ASCE)CO.1943-7862.0001273.
Alinaitwe, H.M., Mwakali, J.A. and Hansson, B. (2007), “Factors affecting the productivity of building
craftsmen - studies of Uganda”, Journal of Civil Engineering and Management, Vol. 13 No. 3,
pp. 169-176, doi: 10.1080/13923730.2007.9636434.
Cho, E. and Kim, S. (2015), “Cronbach’s coefficient alpha”, Organizational Research Methods, Vol. 18
No. 2, pp. 207-230, doi: 10.1177/1094428114555994.
Choi, K., Haque, M., Lee, H.W., Cho, Y.K. and Kwak, Y.H. (2013), “Macroeconomic labour productivity
and its impact on firm’s profitability”, Journal of the Operational Research Society, Vol. 64 No. 8,
pp. 1258-1268, doi: 10.1057/jors.2012.157.
CPWD (2019), Government of India, central public works department analysis of rates for Delhi,
Vol. 1, available at: https://cpwd.gov.in/Publication/CivilDAR_2019_Vol_1.pdf
Dai, J., Goodrum, P.M. and Maloney, W.F. (2007), “Analysis of craft workers’ and foremen’s
perceptions of the factors affecting construction labour productivity”, Construction
Management and Economics, Vol. 25 No. 11, pp. 1139-1152, doi: 10.1080/01446190701598681.
Dai, J., Goodrum, P.M. and Maloney, W.F. (2009a), “Construction craft workers’ perceptions of the
factors affecting their productivity”, Journal of Construction Engineering and Management,
Vol. 135 No. 3, pp. 217-226, doi: 10.1061/(ASCE)0733-9364(2009)135:5(397).
Dai, J., Goodrum, P.M., Maloney, W.F. and Srinivasan, C. (2009b), “Latent structures of the factors
affecting construction labor productivity”, Journal of Construction Engineering and
Management, Vol. 135 No. 5, pp. 397-406, doi: 10.1061/(ASCE)0733-9364(2009)135:5(397).
Demirkesen, S. and Ozorhon, B. (2017), “Measuring project management performance: case
of construction industry”, EMJ - Engineering Management Journal, Vol. 29 No. 4,
pp. 258-277, doi: 10.1080/10429247.2017.1380579.
Dhal, M. (2020), “Labor stand: face of precarious migrant construction workers in India”, Journal of
Construction Engineering and Management, Vol. 146 No. 6, 04020048, doi: 10.1061/(ASCE)CO.
1943-7862.0001761.
Diekmann, J.E. and Peppler, S.E. (1984), “Union and open shop labor cost differences”, Journal of Construction
Construction Engineering and Management, Vol. 110 No. 1, pp. 87-99, doi: 10.1061/(ASCE)0733-
9364(1984)110:1(87). site
Dissanayake, M., Fayek, A.R., Russell, A.D. and Pedrycz, W. (2005), “A hybrid neural network for
productivity
predicting construction labour productivity”, Proceedings of the 2005 ASCE International
Conference on Computing in Civil Engineering, pp. 819-830, doi: 10.1061/40794(179)78.
Dixit, S. (2018), “Analysing enabling factors affecting the on-site productivity in Indian construction
industry”, Periodica Polytechnica Architecture, Vol. 49 No. 2, pp. 185-193, doi: 10.3311/ppar.12710. 981
Dixit, S., Mandal, S.N., Sawhney, A. and Singh, S. (2017a), “Relationship between skill development
and productivity in construction sector: a literature review”, International Journal of Civil
Engineering and Technology, Vol. 8 No. 8, pp. 649-665.
Dixit, S., Pandey, A.K., Mandal, S.N. and Bansal, S. (2017b), “A study of enabling factors affecting
construction productivity: Indian scnerio”, International Journal of Civil Engineering and
Technology, Vol. 8 No. 6, pp. 741-758.
Dixit, S., Mandal, S.N., Thanikal, J.V. and Saurabh, K. (2018), “Critical analysis of factors affecting the
on-site productivity in Indian construction industry”, Creative Construction Conference 2018 -
Proceedings, July, pp. 38-45, doi: 10.3311/CCC2018-006.
Dixit, S., Mandal, S.N., Thanikal, J.V. and Saurabh, K. (2019), “Evolution of studies in construction
productivity: a systematic literature review (2006–2017)”, Ain Shams Engineering Journal,
Vol. 10 No. 3, pp. 555-564, doi: 10.1016/j.asej.2018.10.010.
Doloi, H. (2008), “Application of AHP in improving construction productivity from a management
perspective”, Construction Management and Economics, Vol. 26 No. 8, pp. 841-854, doi: 10.1080/
01446190802244789.
Durdyev, S. and Ismail, S. (2016), “On-site construction productivity in Malaysian infrastructure
projects”, Structural Survey, Vol. 34 Nos 4-5, pp. 446-462, doi: 10.1108/SS-12-2015-0058.
Durdyev, S. and Mbachu, J. (2011), “On-site labour productivity of New Zealand construction industry:
key constraints and improvement measures”, Australasian Journal of Construction Economics
and Building, Vol. 11 No. 3, pp. 18-33, doi: 10.5130/ajceb.v11i3.2120.
Durdyev, S., Ismail, S. and Kandymov, N. (2018), “Structural equation model of the factors affecting
construction labor productivity”, Journal of Construction Engineering and Management,
Vol. 144 No. 4, 04018007, doi: 10.1061/(ASCE)CO.1943-7862.0001452.
Eastman, C.M. and Sacks, R. (2008), “Relative productivity in the AEC industries in the United States
for on-site and off-site activities”, Journal of Construction Engineering and Management,
Vol. 134 No. 7, pp. 517-526, doi: 10.1061/(asce)0733-9364(2008)134:7(517).
El-Gohary, K.M. and Aziz, R.F. (2014), “Factors influencing construction labor productivity in Egypt”,
Journal of Management in Engineering, Vol. 30 No. 1, pp. 1-9, doi: 10.1061/(ASCE)ME.1943-5479.
0000168.
El-Gohary, K.M., Aziz, R.F. and Abdel-Khalek, H.A. (2017), “Engineering approach using ANN to
improve and predict construction labor productivity under different influences”, Journal of
Construction Engineering and Management, Vol. 143 No. 8, pp. 1-10, doi: 10.1061/(ASCE)CO.
1943-7862.0001340.
Enshassi, A., Mohamed, S., Mustafa, Z.A. and Mayer, P.E. (2007), “Factors affecting labour
productivity in building projects in the Gaza strip”, Journal of Civil Engineering and
Management, Vol. 13 No. 4, pp. 245-254, doi: 10.1080/13923730.2007.9636444.
Florez, L. and Cortissoz, J.C. (2017), “Using workers compatibility to predict labor productivity
through cluster Analysis”, Procedia Engineering, Vol. 196 June, pp. 359-365, doi: 10.1016/j.
proeng.2017.07.211.
Georgy, M.E., Chang, L.-M. and Zhang, L. (2005), “Prediction of engineering performance: a
neurofuzzy approach”, Journal of Construction Engineering and Management, Vol. 131 No. 5,
pp. 548-557, doi: 10.1061/(asce)0733-9364(2005)131:5(548).
ECAM Ghobakhloo, M., Zulkifli, N.B. and Aziz, F.A. (2010), “The interactive model of user information
technology acceptance and satisfaction in small and medium-sized enterprises”, European
30,2 Journal of Economics, Finance and Administrative Sciences, Vol. 19, pp. 7-27.
Ghoddousi, P. and Hosseini, M.R. (2012), “A survey of the factors affecting the productivity of
construction projects in Iran”, Technological and Economic Development of Economy, Vol. 18
No. 1, pp. 99-116, doi: 10.3846/20294913.2012.661203.
Ghodrati, N., Wing Yiu, T., Wilkinson, S. and Shahbazpour, M. (2018), “Role of management strategies
982 in improving labor productivity in general construction projects in New Zealand: managerial
perspective”, Journal of Management in Engineering, Vol. 34 No. 6, 04018035, doi: 10.1061/
(ASCE)ME.1943-5479.0000641.
Golchin Rad, K. and Kim, S.Y. (2018), “Factors affecting construction labor productivity: Iran case
study”, Iranian Journal of Science and Technology, Transactions of Civil Engineering, Vol. 42
No. 2, pp. 165-180, doi: 10.1007/s40996-018-0095-2.
Goodrum, P.M., Haas, C.T., Caldas, C., Zhai, D., Yeiser, J. and Homm, D. (2011), “Model to predict the
impact of a technology on construction productivity”, Journal of Construction Engineering and
Management, Vol. 137 No. 9, pp. 678-688, doi: 10.1061/(asce)co.1943-7862.0000328.
Gunduz, M., Birgonul, M.T. and Ozdemir, M. (2017), “Fuzzy structural equation model to assess
construction site safety performance”, Journal of Construction Engineering and Management,
Vol. 143 No. 4, 04016112, doi: 10.1061/(asce)co.1943-7862.0001259.
Gupta, M., Hasan, A., Jain, A.K. and Jha, K.N. (2018), “Site amenities and workers’ welfare factors affecting
workforce productivity in Indian construction projects”, Journal of Construction Engineering and
Management, Vol. 144 No. 11, 04018101, doi: 10.1061/(ASCE)CO.1943-7862.0001566.
Gurcanli, G.E., Bilir Mahcicek, S., Serpel, E. and Attia, S. (2021), “Factors affecting productivity of
technical personnel in Turkish construction industry: a field study”, Arabian Journal for Science
and Engineering, Vol. 46 No. 11, pp. 11339-11353, doi: 10.1007/s13369-021-05789-z.
Gurmu, A.T. and Aibinu, A.A. (2017), “Construction equipment management practices for improving labor
productivity in multistory building construction projects”, Journal of Construction Engineering and
Management, Vol. 143 No. 10, 04017081, doi: 10.1061/(ASCE)CO.1943-7862.0001384.
Gurmu, A.T. and Ongkowijoyo, C.S. (2020), “Predicting construction labor productivity based on
implementation levels of human resource management practices”, Journal of Construction
Engineering and Management, Vol. 146 No. 3, 04019115, doi: 10.1061/(ASCE)CO.1943-7862.
0001775.
Hanafi, M.H., Ghani Khalid, A., Razak, A.A. and Abdullah, S. (2010), “Main factors influencing labour
productivity of the installation of on-site prefabricated components”, International Journal of
Academic Research, Vol. 2 No. 6, pp. 139-146.
Hanna, A.S., Taylor, C.S. and Sullivan, K.T. (2005), “Impact of extended overtime on construction labor
productivity”, Journal of Construction Engineering and Management, Vol. 131 No. 6,
pp. 734-739, doi: 10.1061/(asce)0733-9364(2005)131:6(734).
Hasan, A. and Jha, K.N. (2013), “Safety incentive and penalty provisions in Indian construction
projects and their impact on safety performance”, International Journal of Injury Control and
Safety Promotion, Vol. 20 No. 1, pp. 3-12, doi: 10.1080/17457300.2011.648676.
Hasan, A. and Jha, K.N. (2016), “Acceptance of the incentive/disincentive contracting strategy in
developing construction markets: empirical study from India”, Journal of Construction Engineering
and Management, Vol. 142 No. 2, 04015064, doi: 10.1061/(ASCE)CO.1943-7862.0001048.
Hasan, A., Elmualim, A., Rameezdeen, R., Baroudi, B. and Marshall, A. (2018), “An exploratory study
on the impact of mobile ICT on productivity in construction projects”, Built Environment
Project and Asset Management, Vol. 8 No. 3, pp. 320-332, doi: 10.1108/BEPAM-10-2017-0080.
Hwang, B.-G., Zhu, L. and Ming, J.T.T. (2017), “Factors affecting productivity in green building
construction projects: the case of Singapore”, Journal of Management in Engineering, Vol. 33
No. 3, 04016052, doi: 10.1061/(ASCE)ME.1943-5479.0000499.
ILO (2015), “Good practices and challenges in promoting decent work in construction and Construction
infrastructure projects”, available at: http://www.ilo.org/wcmsp5/groups/public/—ed_
dialogue/—sector/documents/publication/wcms_416378.pdf site
Jang, H., Kim, K., Kim, J. and Kim, J. (2011), “Labour productivity model for reinforced concrete
productivity
construction projects”, Construction Innovation, Vol. 11 No. 1, pp. 92-113, doi: 10.1108/
14714171111104655.
Jarkas, A.M. (2010), “Buildability factors influencing formwork labour productivity of isolated
foundations”, Journal of Engineering, Design and Technology, Vol. 8 No. 3, pp. 274-295, doi: 10. 983
1108/17260531011086162.
Jarkas, A.M. (2016), “Effect of buildability on labor productivity: a practical quantification approach”,
Journal of Construction Engineering and Management, Vol. 142 No. 2, 06015002, doi: 10.1061/
(asce)co.1943-7862.0001062.
Kar, S. and Jha, K.N. (2020), “Examining the effect of material management issues on the schedule and
cost performance of construction projects based on a structural equation model: survey of
Indian experiences”, Journal of Construction Engineering and Management, Vol. 146 No. 9,
05020011, doi: 10.1061/(asce)co.1943-7862.0001906.
Karim, N.A., Hassan, S., Yunus, J. and Hashim, M. (2013), “Factors influence labour productivity and
the impacts on construction industry”, Caspian Journal of Applied Sciences Research, Vol. 2
August, pp. 349-354.
Karthik, D. and Kameswara Rao, C.B. (2019), “Identifying the significant factors affecting the masonry
labour productivity in building construction projects in India”, International Journal of
Construction Management, Vol. 0 No. 0, pp. 1-9, doi: 10.1080/15623599.2019.1631978.
Kazaz, A.Y. and Ulubeyli, S. (2004), “A different approach to construction labour in Turkey:
comparative productivity analysis”, Building and Environment, Vol. 39 No. 1, pp. 93-100, doi: 10.
1016/j.buildenv.2003.08.004.
Kazaz, A., Ulubeyli, S., Acikara, T. and Er, B. (2016), “Factors affecting labor productivity:
perspectives of craft workers”, Procedia Engineering, Vol. 164 June, pp. 28-34, doi: 10.1016/j.
proeng.2016.11.588.
Kermanshachi, S., Rouhanizadeh, B. and Govan, P. (2022), “Developing management policies and analyzing
impact of change orders on labor productivity in construction projects”, Journal of Engineering,
Design and Technology, Vol. 20 No. 5, pp. 1257-1279, doi: 10.1108/JEDT-10-2020-0428.
Kisi, K.P., Mani, N., Rojas, E.M. and Foster, E.T. (2017), “Optimal productivity in labor-intensive
construction operations: pilot study”, Journal of Construction Engineering and Management,
Vol. 143 No. 3, 04016107, doi: 10.1061/(asce)co.1943-7862.0001257.
Li, H., Li, X., Luo, X. and Siebert, J. (2017), “Investigation of the causality patterns of non-helmet use
behavior of construction workers”, Automation in Construction, Vol. 80, pp. 95-103, doi: 10.1016/
j.autcon.2017.02.006.
Liu, M., Ballard, G. and Ibbs, W. (2011), “Work flow variation and labor productivity: case study”,
Journal of Management in Engineering, Vol. 27 No. 4, pp. 236-242, doi: 10.1061/(asce)me.1943-
5479.0000056.
Loganathan, S. and Kalidindi, S. (2015), “Masonry labor construction productivity variation : an
Indian case”, Proceedings of the First Indian Lean Construction Conference, Vol. 1 February,
pp. 175-185, available at: https://www.researchgate.net/publication/272744373_MASONRY_
LABOR_CONSTRUCTION_PRODUCTIVITY_VARIATION_AN_INDIAN_CASE_STUDY?
enrichId5rgreq-ff97826fc8477c93b5a92fa20a16ee3d-XXX&enrichSource5Y292ZXJQYW
dlOzI3Mjc0NDM3MztBUzoyMDA0NTkxMTQ1NTMzNDVAMTQyNDgwNDU4NTUy
Maloney, W.F. (1983), “Productivity improvement: the influence of labor”, Journal of Construction Engineering
and Management, Vol. 109 No. 3, pp. 321-334, doi: 10.1061/(ASCE)0733-9364(1983)109:3(321).
Misra, B.S. (2020), “Determinants of total factor productivity in Indian states”, Indian Growth and
Development Review, Vol. 13 No. 1, pp. 259-282, doi: 10.1108/IGDR-01-2019-0008.
ECAM Naoum, S.G. (2016), “Factors influencing labor productivity on construction sites: a state-of-the-art
literature review and a survey”, International Journal of Productivity and Performance
30,2 Management, Vol. 65 No. 3, pp. 401-421, doi: 10.1108/IJPPM-03-2015-0045.
Nasirian, A., Arashpour, M. and Abbasi, B. (2019), “Critical literature review of labor multiskilling in
construction”, Journal of Construction Engineering and Management, Vol. 145 No. 1, 04018113,
doi: 10.1061/(asce)co.1943-7862.0001577.
National Skill Development Corporation (2015), Human Resource and Skill requirements in the
984 Building Estate and Real Estate sector (2013-17), (2017-22), New Delhi.
Nyoni, T. and Bonga, W.G. (2016), “An empirical investigation of factors affecting construction sector
labour productivity in Zimbabwe”, International Journal of Business and Management Invention
ISSN, Vol. 5 No. 8, pp. 68-79, available at: www.ijbmi.org68%7C
Palikhe, S., Kim, S. and Kim, J.J. (2019), “Critical success factors and dynamic modeling of construction
labour productivity”, International Journal of Civil Engineering, Vol. 17 No. 3, pp. 427-442, doi:
10.1007/s40999-018-0282-3.
Park, H.S., Thomas, S.R. and Tucker, R.L. (2005), “Benchmarking of construction productivity”,
Journal of Construction Engineering and Management, Vol. 131 No. 7, pp. 772-778, doi: 10.1061/
(asce)0733-9364(2005)131:7(772).
Patil, S.K., Gupta, A.K., Desai, D.B. and Sajane, A.S. (2013), “Causes of delay in INDIAN transportation
infrastructure projects”, International Journal of Research in Engineering and Technology,
Vol. 02 No. 11, pp. 71-80, doi: 10.15623/ijret.2013.0211013.
Proverbs, D.G., Holt, G.D. and Olomolaiye, P.O. (1998), “A method for estimating labour requirements
and costs for international construction projects at inception”, Building and Environment,
Vol. 34 No. 1, pp. 43-48, doi: 10.1016/S0360-1323(97)00064-4.
Rani, H.A., Farouk, A.M., Anandh, K.S., Almutairi, S. and Rahman, R.A. (2022), “Impact of COVID-19
on construction projects: the case of India”, Buildings, Vol. 12 No. 6, p. 762, doi: 10.3390/
buildings12060762.
Rivas, R.A., Borcherding, J.D., Gonzalez, V. and Alarcon, L.F. (2011), “Analysis of factors influencing
productivity using craftsmen questionnaires: case study in a Chilean construction company”,
Journal of Construction Engineering and Management, Vol. 137 No. 4, pp. 312-320, doi: 10.1061/
(asce)co.1943-7862.0000274.
Rodrigues, F., Alves, A.D. and Matos, R. (2022), “Construction management supported by BIM and a
business intelligence tool”, Energies, Vol. 15 No. 9, p. 3412, doi: 10.3390/en15093412.
Shan, Y., Zhai, D., Goodrum, P.M., Haas, C.T. and Caldas, C.H. (2016), “Statistical analysis of the
effectiveness of management programs in improving construction labor productivity on large
industrial projects”, Journal of Management in Engineering, Vol. 32 No. 1, 04015018, doi: 10.
1061/(asce)me.1943-5479.0000375.
Shan, Y., Imran, H., Lewis, P. and Zhai, D. (2017), “Investigating the latent factors of quality of
work-life affecting construction craft worker job satisfaction”, Journal of Construction
Engineering and Management, Vol. 143 No. 5, pp. 1-10, doi: 10.1061/(ASCE)CO.1943-7862.
0001281.
Shanmugapriya, S. and Subramanian, K. (2013), “Investigation of significant factors influencing time
and cost overruns in Indian construction projects”, International Journal of Emerging
Technology and Advanced Engineering, Vol. 3 No. 10, pp. 734-740.
Shehata, M.E. and El-Gohary, K.M. (2011), “Towards improving construction labor productivity and
projects’ performance”, Alexandria Engineering Journal, Vol. 50 No. 4, pp. 321-330, doi: 10.1016/
j.aej.2012.02.001.
Siriwardana, C.S.A. and Ruwanpura, J.Y. (2012), “A conceptual model to develop a worker
performance measurement tool to improve construction productivity”, Construction Research
Congress 2012: Construction Challenges in a Flat World, Proceedings of the 2012 Construction
Research Congress, 2009, pp. 179-188, doi: 10.1061/9780784412329.019.
Somanathan, E., Somanathan, R., Sudarshan, A. and Tewari, M. (2021), “The impact of temperature on Construction
productivity and labor supply: evidence from Indian manufacturing”, Journal of Political
Economy, Vol. 129 No. 6, pp. 1797-1827, doi: 10.1086/713733. site
Thomas, H.R. (2015), “Benchmarking construction labor productivity”, Practice Periodical on Structural
productivity
Design and Construction, Vol. 20 No. 4, pp. 1-10, doi: 10.1061/(ASCE)SC.1943-5576.0000141.
Thomas, A.V. and Sudhakumar, J. (2013), “Critical analysis of the key factors affecting construction
labour productivity -an Indian perspective”, International Journal of Construction Management,
Vol. 13 No. 4, pp. 103-125, doi: 10.1080/15623599.2013.10878231. 985
Thomas, H.R., Sanders, S.R. and Bilal, S. (1992), “Comparison of labor productivity”, Journal of Construction
Engineering and Management, Vol. 118 No. 4, pp. 635-650, doi: 10.1061/(ASCE)0733-9364(1992)
118:4(635).
Tran, V. and Tookey, J. (2011), “Labour productivity in the New Zealand construction industry: a
thorough investigation”, Australasian Journal of Construction Economics and Building, Vol. 11
No. 1, pp. 41-60, doi: 10.5130/ajceb.v11i1.1841.
Tsehayae, A.A. and Fayek, A.R. (2014), “Data-driven approaches to discovering knowledge gaps
related to factors affecting construction labor productivity”, Construction Research Congress
2014, Vol. 2008, pp. 837-846, doi: 10.1061/9780784413517.086.
Vereen, S.C., Rasdorf, W. and Hummer, J.E. (2016), “Development and comparative analysis of
construction industry labor productivity metrics”, Journal of Construction Engineering and
Management, Vol. 142 No. 7, pp. 1-9, doi: 10.1061/(ASCE)CO.1943-7862.0001112.
Vigneshwar, R.V.K., Shanmugapriya, S. and Sindhu Vaardini, U. (2022), “Analyzing the driving factors of
BIM adoption based on the perception of the practitioners in Indian construction projects”, Iranian
Journal of Science and Technology, Transactions of Civil Engineering, pp. 2637-2648. doi: 10.1007/
s40996-022-00834-9.
Vogl, B. and Abdel-Wahab, M. (2015), “Measuring the construction industry’s productivity performance:
critique of international productivity comparisons at industry level”, Journal of Construction
Engineering and Management, Vol. 141 No. 4, pp. 1-10, doi: 10.1061/(ASCE)CO.1943-7862.0000944.
Wambeke, B.W., Hsiang, S.M. and Liu, M. (2011), “Causes of variation in construction project task
starting times and duration”, Journal of Construction Engineering and Management, Vol. 137
No. 9, pp. 663-677, doi: 10.1061/(asce)co.1943-7862.0000342.
Wang, Q., El-Gafy, M. and Zha, J. (2010), “Bi-level framework for measuring performance to improve
productivity of construction enterprises”, Construction Research Congress 2010: Innovation for
Reshaping Construction Practice - Proceedings of the 2010 Construction Research Congress,
Vol. 35 No. 8, pp. 970-979, doi: 10.1061/41109(373)97.
Yates, J.K. (2014), “Productivity Improvement for Construction and Engineering”, American Society of Civil
Engineers, 1801 Alexander Bell Drive, Reston, Virginia, 20191-4382. doi: 10.1061/9780784413463.
Zhan, W. and Pan, W. (2020), “Formulating systemic construction productivity enhancement
strategies”, Journal of Construction Engineering and Management, Vol. 146 No. 8, 05020008,
doi: 10.1061/(asce)co.1943-7862.0001886.
Corresponding author
R.V.K. Vigneshwar can be contacted at: vigneshwar.2902@gmail.com
For instructions on how to order reprints of this article, please visit our website:
www.emeraldgrouppublishing.com/licensing/reprints.htm
Or contact us for further details: permissions@emeraldinsight.com