Max Royal AOA

SOP of (work contract) Payment


Owner Activity

Take the measurement

Estate Manager Certify the measurement sheet

Flag out the quality issue

Checking of bills with reference to signed contract


document, as below -

Verify sample measurements along with Estate Manager

Check Qty, as certified by the Site Engineer

Check the respective items, for rates & specifications

Check quality issue for holding any qty.

Signed on abstract sheet.

Certification of extra item, if any.

Send the corrected bill to President/ Secretary

Check for Contractual compliance and random checking


of items ( rate & quantity) and sign.
President/ Secretary
Add delay analysis & change order with each bill

Check the documents and recomantaion

Treasurar/Accountent Make the Adhoc Payment

Make The Final Payment


Time Line

1-2 days

1 day

1 day

3 Days

6 Days