Professional Documents
Culture Documents
Contents
2. Power house
The powerhouse must have adequate space for the above equipments
and this necessitates close coordination between the electrical,
mechanical and civil engineers during design.
The power house location and size is determined by site conditions and
project layout.
ii. Semi-out door: this powerhouse has a fully enclosed generator room.
The main hoisting and transfer equipment is located on the roof of the
plant & equipment is handled through hatches located in the roof.
iii. Outdoor: a generator room is not provided with this type of power
house structure. Generators are enclosed in a weather proof.
– horizontal mounting.
Suitable turbines:
Two types of layout s are generally used namely with
horizontal Francis turbines:
The width of the working bay is generally equal to about one unit bay, if
the unit is planned to be major overhauled in the power house.
The width of the unit bay is so determined that the clearance between
the two units or between the unit and the wall, should be sufficient for
the erection and disassembly of the unit, generally, about 2m.
Contd..
For the side unit, its unit bay should have an additional
width (about 1m per Units).
Capacity of unit in Height to crane rail from generator floor in meter of operating head in m
1000 KVA 25 50 100 150 200
Machine hall
Length: the length of the machine hall depends on the number of
units and the size of machine.
Service crane: The crane should be designed for such a capacity that it can lift the
heaviest component in the power house.
Normally, the heaviest part is the rotor and the stator.
Cable and bus bar: These are placed in the cable ducts made in the floor of the
generator in the bus bar galleries (cable galleries).
High voltage cables should be carried separately.
Switch Yard: This is the yard with step up transformers. This should be located near
the power house. In most cases switch yards are kept out side the power house.
Thanks
For
Your
Attention!
Power house