Professional Documents
Culture Documents
6.4. Clause 25.0 – Works completion is deemed to be deleted and replaced with the following
clause:
The contractors’ attention is drawn to the fact that on this particular contract,
time is regarded as being of the essence and the contractual completion date is
non-negotiable and cannot be moved. Where the contractor is delayed due to
circumstances beyond his control, the contractor must immediately notify the
Principal Agent of the delay. The Principal Agent will assess the situation and will
instruct the contractor on the required course of action required to be taken so as
to mitigate the delay and to bring works back on program.
Clause 29.5 is deemed to be amended by the deletion of 40 working days and the
substitution of …. working days therefor.
Clause 29.7 is deemed to be amended by the deletion of 15 working days and the
substitution of ….. working days therefor.
6.6. Clause 31.9 – The words seven (7) calendar days are deemed to be deleted and the
following words “as per the contractor’s appointment letter” are substituted therefor.