Ref: LIMAK-ZKB(JV)/E-35-III/081220/01

Dated: 08th December, 2020

Mr. LEE Youn Eoo


Team Leader/The Engineer (E-35)
M/s DOHWA Engineering Co. Ltd
National Highway Authority Complex, Burhan

Subject: Contractual Interim Admissibles Financial Charges against Delayed


Payments under Contract Sub-Clauses GCC 14.7 and GCC 14.8
Project: CONSTRUCTION OF HASSANABDAL – HAVELIAN SECTION OF E-35,
ICB-E-35-III : SARAI SALEH TO SIMLAILA (KM 39+611 TO KM 58+711)
Ref: i) This office Letter No. LIMAK-ZKB/E-35-III/311019/01 Dated 31st October, 2019.
ii) This office Letter No. LIMAK-ZKB/E-35-III/240519/01 Dated 24th May, 2019.
iii) This office Letter No. LIMAK-ZKB/E-35-III/031218/03 Dated 3rd December, 2018.
iv) This office Letter No. LIMAK-ZKB/E-35-III/031218/02 Dated 3rd December, 2018.
v) This office Letter No. LIMAK-ZKB/E-35-III/230718/01 Dated 23rd July, 2018.
vi) This office Letter No. LIMAK-ZKB/E-35-III/301117/01 Dated 30th November, 2017.
vii) This office Letter No. LIMAK-ZKB/E-35-III/290917/01 Dated 29th September, 2017.
viii) This office Letter No. LIMAK-ZKB/E-35-III/070617/01 Dated 7th June, 2017.

Dear Sir,
We, M/s LIMAK-ZKB(JV), as the Contractor, are contractually entitled to be
paid the eligible Financial Charges against the ‘Delayed Payments’ in conformance
with the in-built provisions of the sub-clauses GCC 14.7 and 14.8 of the Contract. In
this context, attached please find herewith an upto-date amount of PKR 37,982,856/-
(Pak rupees thirty-seven million nine hundred Eighty-Two Thousand Eight hundred &
Fifty-Six only) as the Contract-specific admissible charges entitled and worked out
against delayed payments and are payable to the Contractor as such.

2. With regard to the foregoings, the worthy Engineer, under the Contract
dictates, may please review and forward our contractual ‘ADMISSIBLES’ to the
Employer for the requisite processing and an early release of payment on this account
please.
Regards,

Engr. Manzoor Ahmed Qureshi


General Manager/PM,
M/s LIMAK JV ZKB C.C:-
 General Manager (E-35) NHA, Burhan
Enclosure (for addressee only): (Page 01 ~ 63)  Project Director (E-35, Package-III), NHA, Burhan
- Contractual Interim Admissibles + copies of Sub-Clauses  Resident Engineer, (E-35), Pkg-III, DOHWA
GCC 14.7 & 14.8 + copies of Engineer’s captioned IPCs &  Managing Director, M/s Limak-ZKB(JV)
EPCs Certifications alongwith their Pass Orders from NHA  Vice President(Contracts), ZKB – H/O