Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program

PMPG 5503 Capstone Research Project

Status Report
Project Name: CAPSTONE PROJECT

Group Member Names: Anubhav Khatri (N01539425)


Jhon Alberto Polo Vasquez (N01535881)
Rohit Patidar (N01479014)

Group Number: 9

Submission Date: 02/10/2023

Projects Performance Possibilities: We Are Leading The Way


Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program

1. Project Information

Project Name: CAPSTONE PROJECT


Project Description:

The Capstone Project is a Project Management Postgraduate (PMPG) course created to give students
the chance to investigate project management practices at a business and contrast the real-world
application of project management techniques with the standards taught in the program.
The Capstone Project's objective is to prepare an audit report on a closed project that the Sponsor
completed utilizing the predictive methodology. In this project, we will evaluate the most effective
project management methods applied in the Sponsor's project and compare them to benchmarks from
the PMI’s Project Management Body of Knowledge (PMBOK) 6th edition guide. Our team will be
conducting interviews with our Sponsor to learn how our Sponsor handled their project utilizing
various processes, tools, and techniques, as well as to assess and compare it with the knowledge areas
and processes specified in the PMI’s Project Management Body of Knowledge (PMBOK) guide.

Date of Report: 02/10/2023 Project Sponsor: Nandita Saxena


Reporting Period: 01/11/2023 – 04/05/2023 Submitted By: Anubhav Khatri
Jhon Alberto Polo Vasquez
Rohit Patidar

2. Project Status*
Status Item Previous Current Details & Rationale

Projects Performance Possibilities: We Are Leading The Way


1
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program

Status Status
The project is moving along as planned and the team
is learning how to use project management
Overall Project Status N/A techniques from the sponsor.
Overall Project Status score is 97.25% (the aggregate
of Quality / Scope Status and Schedule Status).
The Capstone Project's quality and scope standards
were attempted to be met by all project deliverables
that were submitted. Nevertheless, the project
charter fell short. Positive responses have been
Quality / Scope Status N/A received from the PMO.
Quality / Scope Status score is 94.5% [the aggregate
of two project deliverables divided by the maximum
possible score indicated in the rubric, i.e., (13.55 +
14.8) / (15 +15) = 94.5%]

Each team member has successfully finished all


duties allocated to them on schedule. The deadline
for submitting each project deliverable has been
Schedule Status N/A met. Everything went according to schedule during
every meeting.
Therefore, Schedule Status score is 100%.

Performance Factors
*LEGEND
GREEN YELLOW RED
Overall ALL STATUS ITEMS ONE OR MORE STATUS ITEMS YELLOW - ONE OR MORE STATUS ITEMS
Project GREEN – Requires resolution by PM and Team. RED - Requires immediate
Status Progressing well Management needs to be aware and Sponsor or Senior Management
provide assistance attention and/or intervention
Quality/ Meets or exceeds Actual differs from planned deliverables. Not meeting expectations -
Scope broad expectations Reliability/ robustness of deliverables in requires intervention and/or
Status in all areas question (e.g. scope creep, etc.) change control, etc.
Schedule On schedule Delays or risk of delay Late - will not complete in time to
Status meet business goals.

3. Milestones / major accomplishment details this reporting period.


Major Milestone / Key Activities
Planned date Actual date Status & Supporting Details
(scheduled and/or achieved)
1. Sponsor Confirmation Email 01/10/2023 01/05/2023 Closed

Projects Performance Possibilities: We Are Leading The Way


2
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program

This milestone covers all


significant achievements
related to the sponsor search,
Sent such as team formation, kick-
off team meetings, sponsor
search, and kick-off meetings
with sponsors.
Closed
This milestone covers all
significant steps in developing
the project charter, which
2. Project Charter submitted 01/21/2023 01/21/2023 formally recognizes the
Capstone Project's existence
and permits the team to utilize
organizational resources to
execute the project.
Closed
This milestone covers all
significant steps in developing
the audit plan, which includes
3. Audit Plan submitted 01/26/2023 01/26/2023 the interview questions for the
sponsor and outlines the
quantitative strategy used by
the team to evaluate the
interview results.
Closed
This milestone covers all
significant achievements made
4. Status Report #1 submitted 02/10/2023 02/10/2023 throughout the specified time
that were connected to the
controlling and monitoring
stage of the capstone project.

4. Decisions this reporting period


 All future project deliverables will take into account the sponsor's and PMO's suggestions.
 The majority of the sponsor's recurring interviews will take place on Friday from 11 AM to 3
PM.

Projects Performance Possibilities: We Are Leading The Way


3
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program

 The agenda will be shared with the sponsor at least 24 hours before the meeting.
 The knowledge area summaries will be shared with the sponsor to facilitate the review of the
final audit report.
 Each project deliverable will have a new leader assigned to it as part of a leadership rotation.

5. Issue Management this reporting period


Status
Impact Decision
Issue Description Owner Resolution (open/
(H,M,L) Due Date
closed)
The team decided to
1. The locations and hours meet on Friday at 11
of our three team AM for the discussion
members' jobs vary. Anubhav of deliverables and
Finding a good time for work distribution.
Jhon H 04/05/2023 Open
team meetings and The final review and
assessing deliverables Rohit submission meetings
seems to be are held 5 hours prior
challenging. to deadline at any
cost.
2. Each team member has
their own ideas for
solving any problem
because they all come
The group resolved
from diverse
to achieve a
professional Anubhav resolution either by
backgrounds. Because
Jhon vote among team H 04/05/2023 Open
of the differences in our
Rohit members or by
points of view and ways
unanimous decision-
of thinking, the team
making.
occasionally finds it
challenging to accept
the comments from its
teammates.

6. Risk Management this reporting period


Assigned
Risk Description Action Required Due Date Status
Resources
If any technology issue Anubhav Connect to an alternative 04/05/2023 Open
(e.g., poor internet network/use an alternative

Projects Performance Possibilities: We Are Leading The Way


4
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program

connection, electricity
outage, laptop failure)
occurs before the
scheduled meeting or device to conduct the meeting
during the interview with as planned.
the Sponsor.
Jhon
Then the meeting will need Reschedule the meeting as
to be rescheduled which Rohit
soon as possible to minimize
will lead to a delay in the impact on the scheduled
submitting deliverables meeting series.
and, therefore, put
meeting the project
deadline at risk.
Inform PMO about the
occurred risk and discuss
further steps within the
If the Sponsor is unable to project framework.
participate in Capstone
Project due to unforeseen If the risk occurs at the
circumstances (e.g., heavy beginning of the project, the
workload, inflexible team should quickly find the
Anubhav replacement of their current
schedule, personal
matters). Jhon Sponsor. 04/05/2023 Open
Then the submission of Rohit
project deliverables may be If the risk occurs at the later
delayed, and Capstone stage of the project, the team
Project may not be can ask their current Sponsor
completed on time. to suggest another colleague
who has worked on the same
projects and falls under all
requirements defined by PMO.

7. Change Control
Decision
Change Request Description Submitter Reviewer Status
Due Date
1. N/A N/A N/A N/A N/A

Projects Performance Possibilities: We Are Leading The Way


5
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program

8. RACI Chart

Team Members
Tasks
Anubhav John Rohit

1. Conduct team meetings C A R


2. Review the assignment A R C
3. Assign tasks to team members R C A
4. Project Information C A R
5. Project Status A C R
6. Project Milestones R C A
7. Decisions Made R C A
8. Issue Management C R A
9. Risk Management A R C
10. Review Status Report C R A
11. Finalize Status Report R A C
12. Submit Status Report A C R

Legend: R=Responsible, A=Accountable, C=Consult, I=Inform