Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
1. Executive Summary
I. Objectives of this report - SAIF
The various objectives of this report could be noted as below,
1. Evaluate the project management processes used by the Sponsor's company and compare
them to the PMBOK standards, identifying any areas of non-compliance or potential
improvement.
2. Provide recommendations for how the Sponsor's company can improve their project
management processes to better align with PMBOK standards, including specific actions or
best practices to implement.
3. Assess the effectiveness of the risk management strategies used by the Sponsor's company
and make recommendations for how they can be strengthened or improved to reduce project
risk and enhance project success.
4. Analyze the budget management practices of the Sponsor's company and recommend ways to
improve cost control and budget performance, including best practices for estimating,
budgeting, and tracking project costs.
5. Evaluate the overall project outcomes and deliverables achieved by the Sponsor's company,
assessing the extent to which they met project goals and objectives, and identifying any areas
for improvement in project planning, execution, or monitoring and control.
6. Provide a comprehensive report on the project management practices and outcomes of the
Sponsor's company, including an overview of project scope, timeline, budget, risks, and
stakeholder engagement, as well as a summary of key successes and challenges faced during
the project lifecycle.
Page 1
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
V. Key Recommendations
• The need for a repository of lessons learned to reduce email exchanges and interruptions in
project execution.
• Gaps in the Collect Requirements process may not be relevant in a construction setting, while
gaps in the Define Scope process may be due to the responsibility of the design team.
• The importance of asking contractors and suppliers about their lead time for delivering tasks
and materials, to update the project schedule accordingly and mitigate delays.
• The need for a comprehensive risk analysis during planning of cost management, regular review
and update of cost estimates, and use of earned value management techniques to monitor
project progress and performance.
• The potential benefits of implementing a Project Management Information System (PMIS) to
improve project documentation, communication, and collaboration.
• The importance of creating a list of industry-specific risks based on strategic frameworks, such
as PESTLE or TECOP, and regularly updating the prompt lists.
• The potential benefits of using data analysis and data representation tools and techniques in
stakeholder management.
Page 2
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
APPROVAL: To approve your final report, your sponsor must email your professor directly (with
a copy to BOTH student team members) with the following information:
o Written confirmation that they have reviewed and approved BOTH part of your Final Audit
Report
o A copy of the one-page feedback they provided to you for your Final Report
o A copy of the Final Audit Report document which they reviewed and approved.
Page 3
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
3. Audit Results
1.1 Project Integration Management
Sponsor`s Practice
• For the Develop Project Charter, none was done because the authorization is given by the VP of Construction.
• For the Develop Project Management Plan, our sponsor has reviewed the plans and specifications and drafted a preliminary
schedule which he sent to the appropriate stakeholders for comments. He made adjustments based on stakeholders’
comments and released a final copy of the schedule.
• For the Direct and Manage Project Work, our sponsor encouraged the site managers to create a 3-week look ahead
schedule that is being updated weekly and based on the overall project schedule. Also, he only needs approval from the VP
of Construction on changes that involve cost. He also distributes daily superintendent reports and monthly project schedule
to the stakeholders.
• For the Manage Project Work, our sponsor has to send the project plans and schedule to the VP of Construction for
comments because lessons learned in their previous projects are never documented. There are situations where the VP of
Construction will suddenly bring out something in the middle of the execution that will hamper the work. So, our sponsor
will let him know early of the execution details so the VP of Construction can give his comments ahead.
• For the Monitor and Control Project Work, our sponsor tracked the overall progress by conducting weekly project and site
manager meetings, releasing daily project reports, and weekly updating of the 3-week look ahead schedule.
• For the Perform Integrated Change Control, our sponsor required the approval of the VP of Construction for the change
requests. Change requests are generated from internal stakeholders.
• For the Close Project or Phase, our sponsor finalized the activities based on approved plans and specifications.
Findings
Process Areas of Compliance Gaps Quantitative
(ALL evaluation criteria met) (Evaluation criteria unmet) Result
1. Develop Project Expert judgment, Data gathering, Interpersonal
None 0%
Charter and team skills, Meetings
2. Develop Project Expert judgment, Data gathering, Interpersonal
None 100%
Management Plan and team skills, Meetings
3. Direct and Manage Expert judgment, Meetings, Project
None 100%
Project Work management information system
4. Manage Project Expert judgment, Knowledge management, Information
75%
Knowledge Interpersonal and team skills management
5. Monitor and
Control Project Expert judgment, Decision making, Meetings Data analysis 75%
Work
6. Perform Integrated Expert judgment, Change control tools,
Data analysis 80%
Change Control Decision making, Meetings
7. Close Project or
Expert judgment, Meetings Data analysis 66.67%
Phase
Recommendations
We recommended creating a repository of lessons learned from previous projects so it can be easily accessible as
a reference for future projects which will lessen email exchanges and sudden interruption in project execution.
Page 4
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
Findings
Process Areas of Compliance Gaps Quantitative
(ALL evaluation criteria met) (evaluation criteria unmet) Result
1. Plan Scope
Expert judgment, Data Analysis, Meetings None 100%
Management
2. Collect Expert judgment, Data Gathering, Data Analysis, Data Representation, Context
62.5%
Requirements Decision Making, Interpersonal and Team Skills Diagram, Prototypes
Expert judgment, Data Analysis, Decision Expert judgment, Data Analysis,
3. Define Scope Making, Interpersonal and Team Skills, Product Decision Making, Interpersonal and 0%
Analysis Team Skills, Product Analysis
4. Create WBS Expert judgment, Decomposition None 100%
5. Validate Scope Inspection, Decision Making None 100%
6. Control Scope Data Analysis None 100%
Recommendations
We have no further recommendation because the sponsor has an effective and regular communication and
collaboration between project team members. We see the gaps in Collect Requirements process to be not
relevant in a construction setting, and the gaps in Define Scope is understandable because it’s under the
responsibility of the design team.
Page 5
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
Findings
Process Areas of Compliance Gaps Quantitative
(ALL evaluation criteria met) (evaluation criteria unmet) Result
1. Plan Schedule
Expert judgment, Meetings Data analysis 66.67%
Management
Expert judgment, Decomposition, Rolling wave planning,
2. Define Activities None 100%
Meetings
Precedence diagramming method, Dependency
3. Sequence
determination and integration, Leads and lags, Project None 100%
Activities
management information system
Parametric estimating,
4. Estimate Activity Expert judgment, Analogous estimating, Decision making, Three-point estimating,
50%
Durations Meetings Bottom-up estimating,
Data analysis
Schedule Network Analysis, Critical Path Method, Data analysis, Schedule
5. Develop
Resource optimization, Leads and Lags, Project Compression, Agile 62.50%
Schedule
management information system release planning
Data analysis, Critical path method, Project management
6. Control
information system, Resource optimization, Leads and Schedule compression 83.33%
Schedule
lags
Recommendations
We recommend asking the contractors and suppliers about their updated and true lead time for delivering tasks and
materials in consideration of the risks that they could face in executing the job/orders so the project schedule will be
updated accordingly in advance instead of mitigating delays when the schedule is already tight.
Page 6
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
Findings
Areas of Compliance Gaps Quantitative
Process
(ALL evaluation criteria met) (evaluation criteria unmet) Result
1. Plan Cost
Expert judgment, Data analysis, Meetings none 100%
Management
Analogous estimating,
Parametric estimating,
Expert judgment, Analogous estimating, Parametric
Bottom-up estimating,
estimating, Bottom-up estimating, Three-point
2. Estimate Costs Three-point estimating, 25%
estimating, Data analysis, Project management
Data analysis, Project
information system, Decision making
management information
system
Expert judgment, Cost aggregation, Data analysis, Cost aggregation,
3. Determine
Historical information review, Funding limit Historical information 66.67%
Budget
reconciliation, Financing review,
To-complete
Expert judgment, Data analysis, To-complete
performance index,
4. Control Costs performance index, Project management 50%
Project management
information system
information system
Recommendations
We recommend that the sponsor must consider conducting a comprehensive risk analysis during the planning of cost
management to identify potential risks and contingencies that may impact project costs. They should regularly review and
update their cost estimates throughout the project life cycle to account for any changes in scope or unforeseen expenses.
It is also recommended to use earned value management (EVM) techniques to monitor the project's progress and
performance.
Page 7
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
● For the manage quality process, the sponsor mentioned that the quality checks were regularly conducted by the site team
and also by the project management team for the work done. The sponsor also conducted audits and physical checks to
confirm on a regular basis.
● For the control quality process, the sponsor conducted a weekly walk through of the reports and checklist made by the
consultant. Daily report was created by the site supervisor which were reported to the project manager. The sponsor also
mentioned that weekly site visits were conducted to confirm the reports and resolve any issues with onsite teams.
Findings
Process Areas of Compliance Gaps Quantitative
(ALL evaluation criteria met) (Evaluation criteria unmet) Result
Expert judgment, Data gathering, Data analysis,
1. Plan Quality Decision making, Data representation, Test and none 100%
Management inspection planning, Meetings
Recommendations
We have no recommendation for the Project Quality Management as all the processes follows the tools and
techniques within the PMBOK standard.
Page 8
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
Findings
Process Areas of Compliance Gaps Quantitative
(ALL evaluation criteria met) (Evaluation criteria unmet) Result
1. Plan Resource Expert judgment, Data representation,
None 100%
Management Organizational theory, Meetings
Expert judgment, Bottom-up estimating, Expert judgment,
2. Estimate Analogous estimating, Parametric Bottom-up estimating, Analogous
Activity estimating, Data analysis, Project estimating, Parametric estimating, 14.29%
Resources management information system, Data analysis, Project management
Meetings information system,
Decision making, Interpersonal and
3. Acquire Decision making, Interpersonal and team
team skills, Pre-assignment, Virtual 0%
Resources skills, Pre-assignment, Virtual teams
teams
Colocation, Virtual teams, Communication Colocation, Virtual teams,
technology, Interpersonal and team skills, Communication technology,
4. Develop Team Recognition and rewards, Training, Interpersonal and team skills, 12.5%
Individual and team assessments, Recognition and rewards, Training,
Meetings Individual and team assessments
Interpersonal and team skills,
Interpersonal and team skills, Project
5. Manage Team Project management information 0%
management information system
system
Data analysis, Problem solving,
Data analysis, Problem solving,
6. Control Interpersonal and team skills,
Interpersonal and team skills, Project 0%
Resources Project management information
management information system
system
Recommendations
Since the activity performed on site was outsourced to contractors, all the scope of maintaining resource management
were taken care of by the sub-contractors. Sponsor conducted regular meetings with the contractor to make sure the
schedule is on time, hence there are no further recommendations.
Page 9
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
Recommendations
We recommend that the project management team consider implementing a PMIS. A PMIS can provide a
centralized platform for project documentation, communication, and collaboration, which can help ensure that
project information is accurate, complete, and readily available. PMIS can help improve project management
processes, increase transparency, and reduce the risk of errors and omissions.
Page 10
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
1.8 Project Risk Management
Sponsor`s Practice
• For the Plan Risk management process, the sponsor goes though risks are mainly during the tender phase of the project, where the scope of
work is defined. Metrus Construction Ltd. ensures that the scope of work is well-defined to minimize the chances of cost/budget creep. In
addition.
• For the Identify Risk management, the Sponsor/Project Manager reads all the available project documents to put the project scope together
properly. The risks are assessed based on the scope of work defined during the tender phase. Metrus Construction Ltd. relies on their project
manager’s expertise and experience to identify potential risks based on the project scope and requirements.
• For the Perform Qualitative Risk Analysis process, the identified risks are assessed and prioritized based on the probability of occurring and
potential impact. The major risks considered were Cost creep which is due to poor scope definition and schedule creep which would be a
result of poor communication with subtrades as to when they are need onsite or if the subtrades don’t present themselves on the scheduled
date and time.
• For the Quantitative risk analysis process, since the project was a tenant driven project the scope of the project was clearly laid out in the
in the lease agreement. The sponsor analysed the potential risks and the extent of impact due to those risks. The impact was gauged on the
basis the impact on cost and or impact on schedule for the defined scope.
• For the Plan risk responses process, the sponsor used a collaborative approach to identify and address potential challenges and uncertainties
in the project. They held meetings with the site team to identify any buildability issues which are any design features or any obstruction
during the actual construction process. that could impact the project. Then, sponsor coordinated meetings with the design team to discuss
potential solutions to these issues. In some cases, sponsor suggested solutions to the design team, which were to be implemented upon
design team’s approval.
• For the Implement Risk responses process, the sponsor collaborated with the subject matter experts (SMEs) on the identified risks and used
a written directions and plans from the SMEs to guide the subcontractors on how to proceed with the project in a way that addressed the
identified risks, challenges and uncertainties. There were plans laid out to mitigate risks and those plans included graphical representations,
such as diagrams or blueprints, that helped to visually communicate the necessary steps to the subcontractors. The sponsor's involved clear
communication and guidance to ensure that the project is completed successfully and in accordance with the project plan.
• For the Monitor Risks Process, the sponsor would have discussions with the staff of Metrus and SMEs on how they would implement the
mitigation strategies to the identified potential risks and developed risk mitigation plan. This plan was then reviewed and vetted, and the
agreed-upon actions were communicated to the subtrades involved in the project. By keeping the lines of communication open and involving
all stakeholders, the sponsor was able to effectively monitor risks and implement mitigation strategies to minimize their impact on the
project.
Findings
Areas of Compliance Gaps Quantitative
Process
(ALL evaluation criteria met) (Evaluation criteria unmet) Result
Plan Risk Management Expert judgment, Data analysis, Stakeholder analysis Meetings None 100%
Expert judgment, Data gathering, Data analysis, Interpersonal and
Identify Risk Prompt list 83.33%
team skills, Prompt lists, Meetings
Perform Qualitative Expert judgment, Data gathering, Data analysis, Interpersonal and
Risk Categorization 85.71%
Risk Analysis team skills, Risk categorization, Data representation, Meetings
Perform Quantitative Expert judgment, Data gathering, Interpersonal and team skills, Representation of
80%
risk Analysis Representations of uncertainty, Data analysis uncertainty
Expert judgment, Data gathering, Interpersonal and team skills,
Plan Strategies for threats, Strategies for opportunities, Contingent
None 100%
Risk Responses response strategies, Strategies for overall project risk, Data analysis,
Decision making
Implement Expert judgment, Interpersonal and team skills, Project management Project Management
66.67%
Risk Responses information system Information system
Monitor Risks Data analysis, Audits, Meetings None 100%
Page 11
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
1.9 Project Procurement Management
Sponsor`s Practice
• For the Plan Procurement Management process, the Sponsor’s approach is to document decisions related to procuring items
or services for the project through "Tendering-Contract Letting." This process involves sending out a request for quotation
(RFQ) to potential contractors and selecting the most suitable vendor or contractor through a bidding process. They have pre-
approved a list of vendors and or contractors who have met their specific requirements and standards for working on their
projects.
• For the Conduct Procurement process, The Metrus Construction Limited performs a tender analysis to ensure that all bidders
have bid on the same item. And once they receive the proposals submitted by different vendors and evaluate them against
predefined criteria, they identify the most suitable vendor for the project. After the tender analysis, Metrus Construction Ltd
performs a negotiation with the lower trades to agree on a price. This negotiation involves discussing the terms and conditions
of the contract and resolving any issues or concerns that arise during the negotiation process. Finally, after the negotiation,
Metrus Construction Ltd. let’s or awards the contract to the selected vendor.
• For the Control Procurement process, the Sponsor ensures effective communication with suppliers and vendors throughout
the project to keep them updated with site schedule and any changes that may affect their availability. Following this the
sponsor schedules vendors and suppliers in advance to ensure that they are available when needed on-site. The Company uses
a payment clause that holds a certain percentage of the payment until the project is completed to ensure that the agreed-
upon terms of the contract are met.
Findings
Process Areas of Compliance Gaps Quantitative
(ALL evaluation criteria met) (Evaluation criteria unmet) Result
Plan Procurement Expert judgment, Data gathering, Data analysis, Source
None 100%
Management selection analysis, Meetings
Expert judgment, Advertising, Bidder conferences, Data
Conduct
analysis, Interpersonal and team skills, Control None 100%
Procurements
Procurements
Control Expert judgment, Claims administration, Data analysis,
None 100%
Procurements Inspection, Audits
Recommendations
We have no recommendation for the Project Procurement Management as all the processes follows the tools and
techniques within the PMBOK standard.
Page 12
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
Sponsor`s Practice
• For the Identify stakeholder process, the Sponsor is taking a structured approach to stakeholder management. They begin
by identifying the stakeholders involved in the project, including SMEs, subcontractors, tenants, and authorities having
jurisdiction.
• For the Plan Stakeholder Engagement Process, the sponsor uses a RACI chart analysis to develop strategies for involving
stakeholders in the project, which helps to ensure that they are engaged appropriately based on their role and responsibility.
• For the Manage Stakeholder Engagement process, the Sponsor communicates with stakeholders on a weekly basis, which
helps to keep them informed and engaged in the project. With the use of RACI charts and regular communication the Sponsor
is making an effort to involve stakeholders in decision-making and to address their concerns throughout the project.
• For the Manage Stakeholder Engagement process, the Sponsor employs strategies to ensure successful engagement and
collaboration with stakeholders, which includes ground rules, interpersonal and team skills. They also monitor and adjust
their approach to stakeholder management as necessary, and thus they are willing to be flexible and adapt to changing
circumstances.
Findings
Process Areas of Compliance Gaps Quantitative
(ALL evaluation criteria met) (evaluation criteria unmet) Result
1. Identify Expert judgment, Data gathering, Data analysis, Data Data analysis, Data
60%
Stakeholders representation, Meetings representation
2. Plan Stakeholder Expert judgment, Data gathering, Data analysis, Decision Data analysis, Data
66.66%
Engagement making, Data representation, Meetings representation
3. Manage
Expert judgment, Communication skills, Interpersonal
Stakeholder None 100%
and team skills, Ground rules, Meetings
Engagement
4. Monitor Data analysis, Decision making, Data representation,
Data analysis, Data
Stakeholder Communication skills, Interpersonal and team skills, 66.66%
representation
Engagement Meetings
Recommendations
We recommend project management team should prioritize the use of data analysis and data representation tools and
techniques in stakeholder management. These tools can help identify, analyze, and represent stakeholder information in a
structured and meaningful way, leading to more effective stakeholder engagement and management.
Page 13
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
4. Appendix A
Audit Questions and Responses
Page 14
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
The major stakeholders are within the organization. I
managed the internal decision-makers so that they
don’t require changes at inappropriate times in a project
How did you document and manage the
Collect cycle, and this is done by furnishing them a copy of my
stakeholder needs and requirements to meet
Requirements email about every decision I make so if they have
objectives?
anything to add or change, do it now. In other cases, I
also set up a meeting about my project schedule so they
can put all their additional expectations if they have any.
How did you develop a detailed description of This was already developed by the internal stakeholders
Define Scope
the project and product? in conjunction with the design team.
How did you break down the project deliverables Through the creation of a weekly 3-week schedule
Create WBS and project work into smaller and more which is pulled-out from the WBS of the overall
manageable components? schedule.
No formal acceptance procedures since they are the
owners but we rely on the consultant review reports to
identify deficiencies along with the building municipal
How did you formalize the acceptance of the
Validate Scope authorities having jurisdiction and us, Metrus. Once the
completed project deliverables?
deficiencies are cleared and the consultants and the
building authorities sign off on grant occupancies, then
we also accept the deliverables as complete.
Through the weekly project and site manager meetings,
and 3-week look ahead schedule. Changes to the scope
How did you monitor the status of the project
baseline were managed by involving internal
Control Scope and product scope, and managing changes to the
stakeholders in all decision-making so that they don't
scope baseline?
apply changes at an inappropriate time through the
project lifecycle.
Page 15
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
advancing or delaying the start of an activity is done on
a regular basis by the site team because of trade
generated delays.
Page 16
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
g) Knowledge Area: Project Communications Management
Process Powerful Question Sponsor’s Response
Plan How did you identify the communication By first identifying Stakeholders and performing
Communications requirement of the project and what Stakeholder analysis and setting up RACI communication
Management methods did you use to address them? chart.
Can you describe the process of creating a
strategy for ensuring that the right I am in-charge for the communications, the strategy was
Manage
information is distributed to the centred around creation of RACI Chart which was used to
Communications
appropriate individuals involved in the dictate the communications protocol
project?
Project requirements were set by our company Metrus
How did you ensure the process of Construction Limited. And I had the knowledge of all the
Control information distribution met the requirements that were set and met by all the subtrades
Resources requirements of those involved in the or contractors and also these requirements were
project? communicated to each sub trades through their scope of
work.
Page 17
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
Page 18
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
Page 19
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
6. Appendix C
Quantitative Approach
Page 20
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
1. References -
Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) (6th ed.). Project Management Institute.
Page 21
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
2. RACI Chart (include all tasks executed in the completion of this Audit Report - ensure each task includes
an actual task and includes a verb that clearly describes the action) - DAVE
Team Members
Tasks
1.
2.
3.
4.
5.
6.
Legend: R=Responsible, A=Accountable, C=Consult, I=Inform
Page 22
Humber College, Faculty of Applied Sciences and Technology - Project Management Graduate Program
3. Rubric
1. Exec Summary The following areas are complete and professional, with no
spelling or grammatical errors and does not exceed one page:
Objectives of this report, Purpose of Sponsor Project, Audit
Approach Results, Key Findings, Key Recommendations. /3
3. Integration Audit
Results /2.5
9. Procurement Audit
Results /2.5
10. Appendix A: Audit Questions and correlating responses for each knowledge area
Questions & process presented in table format with consistent summarization.
Responses No spelling or grammatical errors. /2
11. Appendix B: Agendas, minutes and any other records from each meeting
Original Notes & provided. No spelling or grammatical errors.
Minutes /0.5
12. Appendix C: Three clear and complete formulas provided, logical and
Quantitative followed.
Approach /0.5
13. Reference Complete, accurate and properly formatted using APA style. /0.5
Page 23