Avaasa One Project Quality Plan
Avaasa One Project Quality Plan
PROJECT NAME
PROJECT QUALITY PLAN KAKINADA, ANDHRA PRADESH
CLIENT AVAASA REALTORS, HYDERABAD
EPC CONTRACTOR CR TRUE BUILD INFRASTRUCTURE LLP
2. PURPOSE
The Quality Management System (QMS) is established to ensure the product quality is achieved
through control of processes. For each department and activities, the standard operating
procedures. Work Instruction, Work procedures have been framed and followed strictly. For supply
of every major material / machinery, prior inspection has to be done and the inspection report to be
submitted to the Management and Client
This Project Quality Plan is prepared and formulated as Management Summary of Quality related
activities required to meet the terms of contract. This plan sets out the Management practices,
describes the quality Management System and its relationship with Corporate Quality System.
Quality Plan: A document specifying which procedures and associated resources shall
be applied by whom and when to a specific project, product, process or
contract
Procedure: Specified way to carry out an activity or a process
Relevant procedures established which clearly specifies the criteria and methods for effective
operation, control, necessary resources and information to support the operation and
monitoring of the process involved.
Quality Policy
Method Statement
HSE Plan
Risk Assessment
Drawings
After reviewing the document, status of approval shall be mentioned in the document submittal
by the approving authority. Status shall be the following;
Superseded copies are destroyed in all sections except QA master copy to prevent the
unintended usage.
Beyond the retention period, the documents shall be disposed at the discretion of the
management either by shredding or by suitable means.
All the records within the company are maintained in either hard copies or soft copies.
6
6.1 Quality Objectives
Frequency of Format of
S.No. Objectives Desirable Measures
Measurement Record
Percentage of rejection Monthly
1 Zero Monthly
during material inspection Report
7. REPORTS
Reports are meant for sharing of information to the right person. The following reports shall be
prepared in the project and depends upon the stage of project.
A. Daily Progress Report
When the Construction work is initiated, the daily excavation, concrete, Brick Work and other
activities are quantified and reported to management.
B. Monthly Progress Report
Monthly Progress Report will be prepared by the Planning Engineer in consultation with Project
Manager and will be reported to the Management and Client. The Monthly Progress Report
consists the following:
Product
o As per BOQ materials used for project. Block, tiles, doorframes. Details etc.
Finance
o Project Budget
Project Progress
o Activities completed during month, Activities planned for next month
QA & QC Manual – R0 P a g e 10 |
7.4 Work Environment
Site Management shall determine, provide and maintain the work environment necessary to
execute the project.
Work environment shall include temperature, heat, humidity, light, airflow, hygiene and noise.
7.5 Calibration
To provide confidence in the validity of measurement results, measuring equipment shall be
calibrated or verified at specified intervals against measurement standards traceable to
international or national measurement standards.
Calibration status of the Measuring equipment shall be identified with suitable identification
stickers.
Measuring equipment shall be safeguarded from adjustments, damage and deterioration that
would invalidate the calibration status and subsequent measurement results.
7.6 Communication
The Project Manager is the authorized person for correspondences, periodical reporting,
commercial matters and attending progress review meetings regarding all contractual
obligations to meet the Client requirements. In the absence of Project Manager, the
representative authorized by the Project Manager shall co-ordinate with Client.
HR and Admin in-charge shall co-ordinate for statutory and regulatory requirements. The mode
of communication can be Telephone, Email, Courier and in person.
8. ENGINEERING
Based on the input received, CR True Build Rebar detailing team prepare and forward Rebar shop
drawings (Bar Bending Schedule) and Form work scheme drawings to the Client/consultants for their
review and approval.
The approved Bar Bending Schedule and Formwork scheme drawings shall be stamped as “GOOD
FOR COSTRUCTION” and then forwarded to the civil construction team to proceed Reinforcement
and Formwork.
The Client approved revised drawings shall be stamped and issued to the concerned. The
superseded drawings shall be withdrawn from the user department and shall be disposed
appropriately
If there are any major changes in the drawings, the Design Manager shall issue a hold note to the
project site and stop.
Any change in the input resulting to a variation in the design and detailing output shall be considered
as Design change. Impact due to the changes will be intimated to the Client through Project
Manager.
The Client approved revised drawings shall be stamped and issued to the concerned. The
superseded drawings shall be withdrawn from the user department and shall be disposed
appropriately.
9. PURCHASING
QA & QC Manual – R0 P a g e 11 |
8
9
9.1 Material and Supplier Approval
Material approved by the Client shall be used in the project. Any alternative material required
due to any specific reason shall again submit for approval.
Material approval submittal shall be submitted to the Client/consultants along with details of
materials with source and sample manufacturer test certificates for review and approval.
Purchased materials and components shall meet the contract requirements.
9.2 Supplier Evaluation
The supplier performance assessment shall be conducted as per the Supplier performance
assessment guideline to ensure the supplier is able to continue meeting the project
requirements.
Supplier performance assessment shall be conducted minimum once in six months by the
procurement department together with the project personal.
If the supplier fails in the assessment, then the supplier is black listed and new supplier will be
identified, if required.
QA & QC Manual – R0 P a g e 12 |
Reinforcement bars shall be stacked at certain height above the ground level to avoid contact
with earth / soil to prevent rust formation / corrosion and distortion.
C. Structural steel
Structural steel raw materials / fabricated items shall be stacked at certain height above the
ground level to avoid contact with earth / soil to prevent rust formation / corrosion and
distortion.
D. Cement
Cement shall be stored in a place, which is dry, leak proof, and as moisture proof as possible.
Cement bags shall be stacked above the floor on wooden planks in such a way, so that it is about
150 to 200 mm above the floor.
Cement bags shall be stacked close to each other to reduce circulation of air. The height of stack
should not be more than 10 bags to prevent the possibility of lumping under pressure.
Cement bags shall be stacked in such a manner to facilitate their removal and use in the order in
which they are received.
Label showing date of receipt of cement on each stack of cement bags shall be ensured to know
the age of cement.
When it is required to store cement for a long period of time or during the monsoon, the stack
shall be completely enclosed by a water proofing membrane such as polyethylene.
E. Admixtures
Liquid admixtures can be stored in barrels or bulk tankers. Powdered admixtures can be placed
in special storage bins and some are available in premeasured plastic bags.
Dispenser tanks at concrete plants should be properly labelled for specific admixtures to avoid
contamination and avoid dosing the wrong admixture. Most liquid chemical admixtures should
not be allowed to freeze; therefore, they should be stored in heated environments. Consult
admixture manufacturer for proper storage temperatures. Powdered admixtures are usually less
sensitive to temperature restrictions, but may be sensitive to moisture.
F. Curing Compound
Curing compound is supplied in containers. The containers shall be closed and do not exposed to
direct sunlight. The containers shall be stored under normal warehouse conditions or as per the
manufacturer recommendation.
G. Repair Material
It shall be kept in a dry environment, in its original, unopened packing. If stored in conditions of
high humidity and / or temperature, the shelf life will be reduced.
QA & QC Manual – R0 P a g e 13 |
Mix designs shall be established as per the requirements mentioned in IS 10262:2009
specification.
The Ready Mix Concrete (RMC) shall be inspected and tested at the project site as per the
requirements and acceptance criteria mentioned in IS 1199:1959 and project technical
specification provided by the Client/consultants.
B. Temperature maintain of concrete as per specification
All RCC concrete should be maintain the temperature of 30degree +/- 2drgree.
C. Allowable Tolerances
Concrete work around elevator shafts, including slabs, beams columns and walls shall not fall
more than 13 mm away from theoretical locations, except where jump-form tolerances apply.
D. Variations from Plumb
Lines and surfaces of columns, walls, corners and the like:
o 6mm per 3m
Exposed column, control joint grooves and other conspicuous lines shall correspond at all
locations and shall not exceed
o 6mm per 6m
E. Level Alignment
Elevation of top of slab (both slab-on-ground and suspended slabs prior to shoring removal),
20mm measured from planned elevation.
Elevation of top of slab, measured at columns and walls at time of turnover of floors for tenant
fit-out, maximum differential slope between adjacent columns and walls of distance / 500 with a
maximum deviation from the average elevation of a full floor of 30mm.
Elevation of formed surfaces before removal of shores, 20mm.
Lintels, sills, parapets, horizontal grooves and other lines exposed to view, 13mm.
F. Alignment of Stairs
o Difference in height between adjacent risers, 3 mm
Unless otherwise noted, formed surfaces may slope with respect to the specified plane at a rate
not to exceed 6 mm in 3m.
For lintels, sills, parapets, horizontal grooves and other lines and surfaces exposed to view, 6mm
in 6m.
G. Building Lines
QA & QC Manual – R0 P a g e 14 |
Variations of the linear building lines from established position in plan and related positions of
columns, walls, beams and partitions:
o 6mm in 3m
o 9mm in 6m
o 25mm maximum.
Faces of formed slab edges turned down spandrels and parapets shall not deviate from
theoretical position or alignment by more than the distance in consideration divided by 500 or
by 13 mm, whichever is less.
Place post tension tendons and anchorages to the following horizontal and vertical tolerances
for the corresponding horizontal and vertical member dimensions:
o 200mm and less: plus, or minus 6mm
o Deviations in horizontal plane which may be necessary to avoid openings or inserts shall
have radius of curvature of not less than 6.4m
o Provide concrete cover not less than that required by the applicable fire rating.
o For dimensions of more than 300mm but not over 900 mm +13mm, -10mm
Footings and pile caps shall vary in plan dimension from theoretical by not more than - 13mm nor
more than +50mm. The Centre of gravity shall be within 2 percent of the theoretical footing
dimension but in no case shall deviate from theoretical by more than 50mm. Footings and pile caps
shall not be reduced in thickness by more than 5 percent of the specified thickness but, in no case,
shall the thickness be less than the theoretical by more than 75mm.
I. Reinforcement
Rebar shall be Fe 500D or Fe550D as per IS 1786, unless otherwise given in drawings. Reinforcement
shall be bent and fixed in accordance with procedure specified in IS 2502.
QA & QC Manual – R0 P a g e 15 |
Unless given, mechanical connections shall develop in tension and compression not less than 125
percent of the specified yield strength of the bar.
Deformed bars prepared for stud welding in accordance with AWS D1.1. Material shall conform to
AWS D1.1, chapter 7, Type C. Provide 12mm diameter, 915 mm long bars, unless otherwise given in
drawings.
Tolerance on Placing of Reinforcement
Unless otherwise specified, the reinforcement shall be placed within the following tolerances:
For effective depth 200mm or less ± 10 mm
For effective depth more than 200 mm ± 15 mm
Tolerance for Cover
Unless specified otherwise, actual concrete cover should not deviate from the required nominal
cover by + 10 mm. Physical, mechanical and chemical tests of rebar shall be carried out as per the
approved ITP.
J. Formwork
The formwork shall be designed and constructed so as to remain sufficiently rigid during placing and
compaction of concrete and shall be such as to prevent loss of slurry from the concrete. The
tolerances on the shapes, lines and dimensions shown in the drawing shall be within the limits given
below:
Deviation from specified dimensions of cross +12 mm
section of columns and beams -6 mm
Deviation from dimensions of footings
Dimensions in plan + 50 mm
-12 mm
0.02 times the width of the footing in the
Eccentricity direction of deviation but not more than 50 mm
Thickness + 0.05 times the specified thickness
These tolerances apply to concrete dimensions only and not to positioning of vertical reinforcing steel
or dowels.
Stripping Time
Forms shall not be released until the concrete has achieved strength of at least twice the stress to
which the concrete may be subjected at the time of removal of formwork. Unless otherwise given,
stripping time shall be as follows:
Minimum period before
Type of Formwork
striking formwork
Vertical formwork to columns, walls, beams 16-24 hours
Soffit formwork to slabs (Props to be refixed immediately
3 days
after removal of formwork)
Soffit formwork to beams (Props to be refixed immediately
7 days
after removal of formwork)
Props to slabs Spanning up to 4.5 m 7 days
QA & QC Manual – R0 P a g e 16 |
Props to beams and arches Spanning up to 6 m 14 days
QA & QC Manual – R0 P a g e 17 |
Extreme NCR - 2 days
Once NCR received, the root cause for occurrence of non- conformance shall be analyzed and
necessary correction and corrective action shall be taken to prevent the recurrence.
Non-conformity shall be dealt by one of the following ways:
Taking appropriate action to eliminate the detected nonconformity.
Authorizing its use, releasing for execution with permission from Client representative, if the
non-conformity does not affect its intended usage.
When non-conforming product is corrected, it shall be subject to re-verification to demonstrate
conformity to the requirements.
14.4 Management Review
Project site quality management system shall be reviewed by the Top Management monthly
once to ensure the compliance, adequacy and effectiveness and to identify opportunity for
improvement.
15. ATTACHMENTS
c) Method statements
QA & QC Manual – R0 P a g e 18 |