You are on page 1of 1

REALISASI MATERIAL WTP 5 M3 PT.

BULUNGAN HIJAU PERKASA ( KHL )

No. URAIAN Qty. Sat. STATUS DATE KETERANGAN


A A.1 KEBUTUHAN MATERIAL TANGKI CLARIFIER
1 Tube Shelter / Lamela 2 ea Received 14/12/2015 lengkap
2 Dosing Pump Prominent 3 unit Received 13/02/2016 lengkap
Type : CNPB 0215 PP, Kapasitas : 16 Lt/Jam, Pressure : 1.5 Bar,
Power : 100-230 Volt; 50/60 Hz ; 11 W
3 Agitator 3 unit Received 13/02/2016 lengkap
4 Tandon 300 liter 3 ea PO 27/11/2015
5 Panel Control (WLC) System Raw Water Pump, Dosing Pump & Filter Pump 1 unit PO
Complete With CabLe System With PLN Standard
6 Pipa 3" PVC 3 btg Received 13/02/2016 lengkap
7 Pipa 2' AW 5 btg Received 11/1/2016 lengkap
8 Pipa 1 1/2" AW 15 btg Received 11/1/2016 lengkap
9 Pipa 1/2" AW 5 btg Received 13/02/2016 lengkap
10 Ball Valve 3" PVC 8 ea Received 13/02/2016 terima 3 ea kurang 5 ea
11 Ball Valve 1 1/2" PVC 10 ea PO
12 Ball Valve 1/2" PVC 6 ea Received 13/02/2016 terima 4 ea kurang 2 ea
13 Water mur 1 1/2" PVC 12 ea Received 13/02/2016 lengkap
14 Flange 3" PVC 10 ea Received 13/02/2016 stok gudang
15 Flange 1 1/2" PVC 4 ea PO
16 Elbow 3" PVC 10 ea Received 13/02/2016 lengkap
17 Elbow 2" PVC 10 ea Received 13/02/2016 lengkap
18 Elbow 1 1/2" PVC 20 ea Received 13/02/2016 lengkap
19 Tee 3" PVC 7 ea Received 13/02/2016 stok gudang
20 Tee 2" PVC 5 ea Received 13/02/2016 stok gudang
21 Tee 1 1/2" PVC 6 ea Received 13/02/2016 stok gudang
22 Tee reducer 1 1/2" - 1/2" PVC 4 ea Received 13/02/2016 lengkap
23 Reducer 3" - 1 1/2" PVC 2 ea PO
24 Reducer 2" - 1 1/2" PVC 6 ea PO 11/1/2016
25 Reducer 1 1/2" - 1/2" PVC 3 ea Received 13/02/2016 lengkap
26 Sock Lurus 1 1/2" PVC 5 ea Received 13/02/2016 lengkap
27 Sock Drat Luar 2" PVC 5 ea Received 13/02/2016 stok gudang
28 Sock Drat Luar 1 1/2" PVC 15 ea PO
29 Sock Drat Dalam 2" PVC 10 ea Received 13/02/2016 kurang 6 ea
30 Sock Drat Dalam 1/2" PVC 6 ea PO
31 Foot Valve 1 1/2" 2 ea PO 11/1/2016
32 Check Valve 1 1/2" 5 ea PO
33 Lem PVC 6 klg Received 13/02/2016 lengkap
34 Pelampung Radar 2 ea PO
35 Selang Benang 1/4" / dosing 1 roll Received 13/02/2016 stok gudang
36 Selang Benang 1/2" 10 mtr PO
37 Selang Spiral Konduit 20mm 1 roll Received 13/02/2016 stok gudang
38 Kabel 3 x 2.5mm 4 roll Received 13/02/2016 stok gudang
39 Kabel 3 x 0.75mm 2 roll PO 11/1/2016
40 Pipa Konduit 30 btg Received 13/02/2016 lengkap
41 Elbow Konduit 2 lsn PO
42 Sock Konduit 2 lsn Received 13/02/2016 lengkap
43 Isolasi Rubber 3M 1 ea PO
44 Isolasi Kabel 2 ea PO
45 Stick WLC 12 btg Received 13/02/2016 stok gudang
46 Sambungan Stick WLC 6 ea Received 13/02/2016 stok gudang
47 Electroda Holder WLC 3 ea Received 13/02/2016 lengkap
48 Dorados 4 ea PO
49 Clamp Pipa Konduit 20mm 5 bks PO 11/1/2016
50 Kabel Ties 300mm 5 bks PO
51 Clamp Kabel 10mm 3 bks PO 11/1/2016
52 Clamp Kabel 8mm 3 bks PO 11/1/2016
53 Dyna Bolt 12mm 20 ea Received 13/02/2016 lengkap
54 Dyna Bolt 10mm 20 ea PO 11/1/2016
55 Baut Flange set M16 x 80mm + 2 wp 56 ea Received 13/02/2016 lengkap ex. Buma adaro
56 Packing Rubber 2m x 1m x 0.4mm 1 lbr Received 13/02/2016 stok gudang
57 Isolatif 3 lsn Received 13/02/2016 lengkap
58 Kain Majun 3 kg Received 13/02/2016 stok gudang
59 Lem Besi 20 bks PO
60 Plug 3/4" 6 ea Received 13/02/2016 lengkap
61 Flange 1 1/2" 4 ea PO 11/1/2016
62 Baut M16 x 100 + nut & washer 20 ea PO
63 Kabel Tray 10 x 5 Cm (tanpa tutup) 5 btg PO
64 Kabel Tray 5 x 5 Cm (tanpa tutup) 3 btg PO
65 Besi Siku 30x30 3 btg PO
66 Cat Hample Biru 5kg 1 klg PO 11/1/2016
67 Thinner A Super Merah Putih 5 ltr 1 klg PO
68 Kuas 2" 3 ea Received 13/02/2016 lengkap
69 U-bolt pipa 1 1/2" 20 ea Received 13/02/2016 lengkap
70 Klam pipa PVC 1 1/2" 20 ea PO
71 Klam pipa PVC 2" 10 ea PO
72 Fitting lampu 1 ea PO
73 Lampu 15 watt tornado 1 ea PO
74 Breaker 4A 1 ea PO