Left Tunnel Blasting Plan Unit B
Left Tunnel Blasting Plan Unit B
(Poly Changda)
According to the construction progress of the site, our company plans to carry
out the blasting work of Dhedre Inlet Right Tunnel on 24 December, 2022.
Please find this table as a blasting information and we will be there in Bunker
around ( 2 Am to 4 Am ) to take the blasting materials and planned to do
blasting around 5 Am.
Blasting
S.N. Specification Unit Quantity Returned
Materials
φ32×200mE
1 φ32×200mm KG 300
mulsion
ms1(≤25ms
2 piece 30
)
3 ms3(50ms) piece 40