You are on page 1of 10

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/334206843

Sensitivity analysis of the contractor's financial effects achieved on a single


building site

Article  in  Scientific Review Engineering and Environmental Sciences · July 2019


DOI: 10.22630/PNIKS.2019.28.2.17

CITATIONS READS

4 1,125

2 authors:

Hubert Anysz Wojciech Rogala


Warsaw University of Technology Warsaw University of Technology
83 PUBLICATIONS   457 CITATIONS    7 PUBLICATIONS   13 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Operational Research in Engineering Sciences: Theory and Applications View project

Delays of Completion Dates in Construction Sector View project

All content following this page was uploaded by Hubert Anysz on 03 July 2019.

The user has requested enhancement of the downloaded file.


Scientific Review – Engineering and Environmental Sciences (2019), 28 (2), 183–191
Sci. Rev. Eng. Env. Sci. (2019), 28 (2)
Przegląd Naukowy – Inżynieria i Kształtowanie Środowiska (2019), 28 (2), 183–191
Prz. Nauk. Inż. Kszt. Środ. (2019), 28 (2)
http://iks.pn.sggw.pl
DOI 10.22630/PNIKS.2019.28.2.17

Hubert ANYSZ, Wojciech ROGALA


Faculty of Civil Engineering, Warsaw University of Technology

Sensitivity analysis of the contractor’s financial effects


achieved on a single building site

Key words: sensitivity analysis, financial ef- direct and indirect costs are the base for
fects, construction site, NPV, cash flow, terms modelling cash flow and profitability of
of payment, profit the project. Following variables are as-
sumed: discount rate, terms of payments
in the contracts signed by a general con-
Introduction tractor with a client and suppliers and the
level of retention money kept by a client
The contractor’s decision about till the completion stage of the project.
placing a bid in a tender procedure and The sensitivity analysis is prepared in or-
further construction project execution der to find how the aforementioned vari-
is usually based on predicted financial ables influence profitability, NPV and the
and economic effects of the decision required level of a contractor’s liquidity.
and on the certainty of their occurrence. This kind of analysis is one of the ba-
Sales and costs are estimated in advance, sis allowing for evaluation of the risk of
as well as, incomes and expenditures. possibly wrong decision, i.e. accepting
Based on that net present value (NPV) the project for execution but leading to
and the required level of liquidity which losing the contractor’s liquidity and fur-
is necessary to complete the project in ther to financial loss.
the assumed period are calculated. The
paper presents the influence of selected
parameters arising from the contract be- The model
tween the client and the general contrac-
tor, from the subcontracts, from the con- As every construction project is
tracts with suppliers and employees – on unique, the time schedule and monthly
the financial result of a single construc- costs of erecting it are unique too. There-
tion project. The time schedule of erect- fore, for the purpose of the paper, the ex-
ing multi-story apartment building, the

Sensitivity analysis of the contractor’s financial effects... 183


emplary project is analysed. Described higher than the cost in a given month.
in BCO 4 (2018) 14-story building with Then, inspired by Mangiero and Kraten
an underground parking is chosen (de- (2017) and Zawistowski and Kulejewski
sign labelled 1122-404 there). Based (2018), the spreadsheet for NPV calcula-
on BCO 4 (2018) the time schedule is tion (ACCA Textbooks, 1998; Estrada,
prepared. The total cost of construction 2011) could be prepared on settlement
works stated in the catalogue BCO 4 dates described in the table.
(2018) is 44.7 million PLN. As the cata- Sensitivity analysis is made includ-
logue provides information about the ing assumptions:
cost of the different type of works, based – half of the retention money is paid
on that and the prepared time schedule, back together with the last payment
it is possible to calculate the costs spent for work executed,
in each of 18 months. The cumulative – the second half is paid back after
cost spent over time by the contractor is 3 years warranty period,
shown in Figure 1. – there are no schedule delays,

FIGURE 1. The cumulative cost of the project spent over the time by a general contractor

It is assumed that all systems in the – there is no cost increase,


building are built by subcontractors but – income tax is omitted in the analy-
the rest of the works are executed by a sis: as it is influenced by overall
general contractor’s forces. Based on headquarter cost and other contracts
the catalogue BCO 4 (2018) and IRS 4 managed by the general contractor;
(2018), as well as on previous analysis income tax is lowered by the depreci-
(Anysz, 2017, 2018), it was possible to ation too (Act of 29 September 1994
divide costs of the scheduled tasks ex- on accounting; Biernacki, 2015),
ecuted by the general contractor’s forces – depreciation and financial cost are
into following parts: labour cost, machin- excluded (as they concern mainly
ery cost, cost of construction materials, the whole company, not the certain
overall cost of the construction site. As construction site),
the catalogue gives the average cost of the – the discounting rate for NPV calcula-
building, it is assumed that the monthly tion should be higher than 0.
sales of the general contractor are 15%

184 H. Anysz, W. Rogala


TABLE. Settlement date of analysed costs and incomes
Cost/Income type Settlement date Remarks
sensitivity analysis for K form –10 to
Construction materials (K) 15th day of the month
60
Construction works (L) end of the each month sensitivity analysis for L from 0 to 90
65.2% of labour cost as workers’ renu-
end of the each month
meration
Labour costs 34.8% of labour cost as social security
10th day of consecutive
(Act of 13 October 1998 on the social
month
insurance system)
Machinery cost end of the each month –
Overall construction site cost end of the each month –
end of the each consecutive
Subcontractors –
month
25th day of the consecutive Act of 11 March 2004 on tax on goods
Value-added tax
month and services
Sensitivity analysis from M = 0%, VAT
Retention money (M) construction works invoice
included

Then, net value (NVn) – i.e. daily cash id 360


1 i 1 (2)
flow could be calculated for each day n of
work execution (as a difference between
As the warranty period was assumed
inflow and outflow of cash), as well as
to be 3 years, the last part of the retention
the maximum demand for cash (Fig. 2).
money will is given back on the 1,665th
Calculating NPV requires the use of dis-
day from the start of the work.
counting rate on daily basis depreciation
and financial cost are excluded (as they 1,665
NV
concern mainly the whole company, not
the certain construction site).
NPV ¦ (1  i n)n (3)
n 1 d
The daily discount rate (id) is cal-
culated the discount rate for NPV cal- where:
culation should be higher than 0 (id). It n – number of days from the start of the
is calculated based on yearly discount construction work execution.
rate i and the equation (1) assuming
The maximum demand for cash
360 days in a year.
(maxCd) during 540 days of the construc-
1 1 (1) tion work execution can be found as
1 360
(1  i ) (1  id ) n
max Cd min ¦ NVn for 1 d n d 540
The same NPV of the same single m 1
value paid in 360 days (calculated on
daily and yearly basis) can be achieved (4)
only if The model built has 4 variables:
terms of payment for suppliers (K), terms

Sensitivity analysis of the contractor’s financial effects... 185


FIGURE 2. Maximum demand for cash (for K = 30 days, L = 45 days, M = 8%)

of payment from the client (L), the reten- delivered materials for 2 weeks will af-
tion money rate (M) and the discount rate fect the project NPV by approximately
(i). The sensitivity analysis can be made 11,000 PLN. Negotiating shorter term of
for NPV and maxCd. It is to emphasize payment for construction works is more
that none of the variables (K, L, M, i) af- important as every 2 weeks will increas-
fect the profit achieved on the construc- es the project NPV by approximately
tion site (calculated as a difference be- 45,000–50,000 PLN. Each 1% of the
tween sales and the cost). retention money rate affects the project
NPV by approximately 25,000 PLN.
Many contractors treat the part of reten-
Sensitivity analysis tion money paying back after guarantee
period as a loss and assume that suspend-
The maximum demand for cash de- ed money are not going to be returned
pends on three variables (K, L, M). It is when guaranty expires. This makes the
independent from the discount rate i. The negotiations on the payment suspension
net present values depend on all of the rate affecting, the project profitability
above. How sensitive they are is shown even more – equally as payments from
in the figures below, separately for each a client.
variable. The Excel simulation allows to The discount rate has the greatest
present the influence on the project NPV impact on NPV, nevertheless it does not
and cash demand, depending on the set- depend on contract terms negotiations,
tlement date of materials and construc- but on the market conditions. In short
tion works invoice, retention money on term contracts executed in countries with
the guarantee account and the discount a stable economy, it should not influence
rate. the project much (Fig. 3).
The analysed project is profitable The analysis shows, that the cash
independently on the contract terms. In demand is much more susceptible to the
each case NPV of the project is positive, impact of the negotiated contract terms.
even if the worst case scenario is con- Extended payment for materials by two
sidered. Negotiating settlement date of weeks can lower the cash demand by

186 H. Anysz, W. Rogala


FIGURE 3. The NPV on the discount rate dependence

1.5 million PLN. The two weeks delay by successful negotiations, but in each
in payment for construction works can of the cases analysed it is positive. The
increase the maximum cash demand by most important factor, which influenc-
3.6 million PLN. Retention money as a es the project success, is cash demand.
guarantee of precise performance does The settlement invoice date for materi-
not affect cash demand so vitally as well als and construction works can influence
as the discount rate does (Fig. 4). the project success, as cash demand can

FIGURE 4. The influence of the retention money rate on cash demand and NPV values

Certainly, raising the retention mon- differ from 1.6 million up to 14.2 mil-
ey rate increases cash demand (what is lion PLN. This may cause, despite that
invisible in Fig. 4) but this influence can project NPV is attractive, that the contrac-
be almost neglected. The applied scale of tor with low financial liquidity is unable
the vertical axis allows for showing the to complete the project successfully. The
level of cash demand while its increase is two variables influencing cash demand
invisible. The scale is kept for Figures 3– the most are: terms of payments from a
–6 for easier comparison of the influence client and terms of payment to suppli-
of different variables. The analysis made ers (Figs. 5, 6). Their influences are the
above proves that NPV of the project opposite. Making extended settlements
analysed is stable. It can be improved with suppliers, improve the liquidity of

Sensitivity analysis of the contractor’s financial effects... 187


FIGURE 5. The influence of terms of payments to suppliers on cash demand and NPV values

FIGURE 6. The influence of terms of payments from a client on cash demand and NPV values

the general contractor. When the general terms, which allows maintaining the fi-
contractor is paid later, the demand for nancial liquidity of the contractor. Mak-
cash rises. Their joint influence can be ing the horizontal section of the chart
shown as a surface chart (Fig. 7). Maxi- shown in Figure 7 at 7.5 million PLN
mum cash demand is shown on the verti- – Figure 8 can be drawn. The extreme,
cal axis. but still acceptable contract terms for the
Such an approach can help the con- contractor, who is able to invest up to
tractor to analyse, whether he is able to 7.5 million PLN, are shown in Figure 8.
finish the project with success, depend- Each contract terms below the particular
ing on his financial condition. It can also line can be accepted. This figure shows
give the contractor an answer, to what that if 30 days payment time for mate-
extent they can take part in negotiations. rials and construction works are agreed,
This approach also allows evaluating the the payment delay of over 2 weeks is to
material distributor offer. In many cases, cause the loss of contractor’s financial
it can turn out, that e.g. choosing the more liquidity. In such case, despite the high
expensive distributor, but offering better NPV, the contractor will not be able to
payment terms can lower the risk of the complete the project. It turns the profit-
project. As much more depends on cash able project into a very risky one.
demand, the point is to find the contract

188 H. Anysz, W. Rogala


FIGURE 7. Maximum cash demand depending on settlement dates of construction works and invoices
for construction materials (for i = 2%, M = 5%)

FIGURE 8. Acceptable contract terms (the area below the line) where 7.5 million PLN is not exceeded
(for different retention money rates and i = 2%)

The cash demand are the same for re- payment delay, the contractor should not
tention money – 5 and 10% in described accept this project or should secure the
case. Analysis of the influence of pay- additional financial resources.
ment delays on basis of Figure 8 can con-
tribute as well to finish project on time,
as this delays of payments are the third Conclusions
reason of construction delays (Leśniak, Within up-to-date construction mar-
2012; Anysz & Zbiciak, 2013). ket conditions, contractors can accept
Taking into account, that total indebt- only secure contracts that guarantee the
edness of construction companies is over profit on a desirable level. However, the
4,700 million PLN (Coface, 2018) and prospect of the profit may be only illuso-
small and medium construction compa- ry one. Despite the high profit, contactors
nies suffer from 4 months delay in pay- can easily go bankrupt if they do not cal-
ments (Kochalska, Bałdys-Rembowski, culate the cash flow and do not analyse
Rogowski & Kaźmierczak, 2018), if the financial liquidity within particular
there is any risk of construction works contract terms.

Sensitivity analysis of the contractor’s financial effects... 189


The presented sensitivity analysis References
shows how the payment conditions influ-
ence the project NPV and cash demand. ACCA Textbooks (1999). Managerial Finance.
London: AT Foulks Lynch.
Cash demand strongly depends on the
Anysz, H. (2017). The profit as in-company evalu-
terms of the invoice payment. The influ- ation of the construction site effectiveness.
ence for NPV is lower, nevertheless, in MATEC Web of Conferences, 117, 00009.
case of less profitable contracts, it can be DOI 10.1051/matecconf/201711700009
important enough to make the proposed Anysz, H. (2018). Założenia systemu rozliczeń
set of analysis before accepting the con- TKW + M (techniczny koszt wytworzenia
plus marża [Assumptions of the TMC + M
tract. What was surprising, the influ- settlement system (total manufacturing cost +
ence on the project NPV of the retention margin)]. Przegląd Budowlany, 89(1), 48-53.
money rate is similar to the terms of the Anysz, H. & Zbiciak, A. (2013). Przyczyny po-
invoice payment. Despite NPV stability, wstawania opóźnień w realizacji kontraktów
in this particular project, negotiations of budowlanych: analiza wstępnych wyników
badania ankietowego [The reasons of delays
terms of payment (with the client and the in building contracts execution: the prelimi-
suppliers) can influence a lot the finan- nary analysis of the survey]. Autobusy: tech-
cial liquidity of the contractor. nika, eksploatacja, systemy transportowe,
The reason for the most of construc- 14(3), 963-972.
tion companies bankruptcy is the loss of BCO 4 (2018). Biuletyn cen obiektów budowla-
nych BCO. Część I – obiekty kubaturowe. IV
financial liquidity. The reasons for the kwartał 2018 r. [Cost of erecting building ob-
lack of cash for running a business are jects BCO. Part I – volume building objects.
delays in payments and overestimation 4Q 2018]. Sekocenbud, 69(1839).
of investment opportunities. In both cas- Biernacki, K. (2015). Paradoks podatkowy w me-
es, analysis, as presented in this paper, todzie NPV [Tax paradox in NPV method].
Zeszyty Naukowe Uniwersytetu Szczecińskie-
can protect the contractor from taking
go. Finanse, Rynki Finansowe, Ubezpiecze-
a wrong decision leading to the loss of nia, 74, Vol. 1. Rynek kapitałowy, wycena
financial liquidity. Simulating the cash przedsiębiorstw, inwestycje, 389-396. DOI
flows and analysis of particular contract 0.18276/frfu.2015.74/1-33
terms influence on NPV and cash de- Coface (2018). Badanie płatności w Polsce
mand, can contribute not only to produc- 2018: Opóźnienia płatnicze wzrosły pomimo
solidnego wzrostu gospodarczego. Notat-
tive negotiations but also to analysis how ka prasowa [Payment survey in Poland:
possible delays in payments can influ- Payment delays increased despite solid
ence financial stability of the company. economic growth. Press release]. Retrieved
The presented analysis proves that from: http://www.coface.pl/Aktualnosci-i-
accepting the profitable contract is only media/Biuro-prasowe/Badanie-platnosci-w-
Polsce-2018-Opoznienia-platnicze-wzrosly-
a part of the project success. By nego- pomimo-solidnego-wzrostu-gospodarczego
tiating the contract terms, contactor can [accessed: 07.04.2019].
substantially lower the cash demand and Estrada, J. (2011). The essential financial toolkit.
the risk of insolvency. The above can London: Palgrave Macmillan.
contribute as to easier surviving on the IRS 4 (2018). Informacja o stawkach robocizny
kosztorysowej oraz cenach pracy sprzętu
market as to earning a good reputation of budowlanego IRS. IV kwartał 2018 r. [In-
a reliable company. formation on labour cost estimate rates and

190 H. Anysz, W. Rogala


prices of construction equipment IRS. 4Q Summary
2018]. Sekocenbud, 60(1830).
Kochalska, H., Bałdys-Rembowski, R., Rogow- Sensitivity analysis of the contrac-
ski, W. & Kaźmierczak, D. (2018). Sytuacja tor’s financial effects achieved on a single
finansowa przedsiębiorstw budowlanych.
building site. Based on catalogues, the time
Niestabilna kondycja branży na szczycie
schedule of erecting multi-storey building
koniunktury – Ogólnopolski Raport BIG
InfoMonitor o zadłużeniu firm z sektora
has been prepared. Real current conditions
budowlanego. Wydanie drugie [Financial and the average cost of the building allows
position of construction enterprises. The for creating the model where four variables
unstable condition of the industry at the peak influence NPV and maximum cash demand of
of the economic growth. National Report of a contractor erecting the building. The simu-
InfoMonitor Economic Information Bureau lation made in the spreadsheet is the base for
on the debt of construction companies. Se- calculating and presenting the sensitivity
cond edition]. Warszawa: BIK Group. analysis of each variable separately, as well
Leśniak, A. (2012). Przyczyny opóźnień budo- as, for creating the surface chart where the
wy w opiniach wykonawców [Causes of joint influence of terms of payments affects
construction delays from the viewpoint of the maximum demand for cash. The way of
contractors]. Technical Transactions. Civil using of this chart has been described aim-
Engineering, 109(1-B), 57-68. ing at the protection of the contractor from
Mangiero, G.A. & Kraten, M. (2017). NPV Sensi- losing financial liquidity while the profitable
tivity Analysis: A Dynamic Excel Approach. project is executed.
American Journal of Business Education,
10(3), 113-126. Authors’ address:
Ustawa z dnia 11 marca 2004 r. o podatku od to- Wojciech Rogala
warów i usług. Dz.U. 2004 Nr 54, poz. 535 [Act (https://orcid.org/0000-0001-7798-1191)
of 11 March 2004 on tax on goods and services. Hubert Anysz
Journal of Laws 2004 No 54, item 535]. (https://orcid.org/0000-0002-3804-5859)
Ustawa z dnia 13 października 1998 r. o syste- Politechnika Warszawska
mie ubezpieczeń społecznych. Dz.U. 1998 Wydział Inżynierii Lądowej
Nr 137, poz. 887 [Act of 13 October 1998 on al. Armii Ludowej 16, 00-636 Warszawa
the social insurance system. Journal of Laws Poland
1998 No 137, item 887]. e-mail: w.rogala@il.pw.edu.pl
Ustawa z dnia 29 września 1994 r. o rachunko- h.anysz@il.pw.edu.pl
wości. Dz.U. 1994 Nr 121, poz. 591 [Act of
29 September 1994 on accounting. Journal of
Laws 1994 No 121, item 591].
Zawistowski, J. & Kulejewski, J. (2018). Influ-
ence of the contractor’s payment method on
the economic effectiveness of the construc-
tion project from the contractor’s point of
view. Open Engineering, 8, 562-570. DOI
10.1515/eng-2018-0055

Sensitivity analysis of the contractor’s financial effects... 191

View publication stats

You might also like