Home work 1
P 5 ft 10 ft 20 ft
1 Jam 3987.5 psi 3991.3 psi 3991.4 psi
10 Jam 3980.9 psi 3994.6 psi 3988.8 psi
15 jam 3979.8 psi 3983.7 psi 3987.7 psi
1 jam (5 ft)
948∅�� �2
� �
�=
�. �
948(0.15)(1.25)(75 × 10−6)(5)2
�=
50. (1)
� = 6.6 × 10−3
10 jam (5 ft) 2
948∅�� �
� �
�=
�. �
948(0.15)(1.25)(75 × 10−6)(5)2
�=
50. (10)
� = 6.6 × 10−4
15 jam (5 ft) 2
948∅�� �
� �
�=
�. �
948(0.15)(1.25)(75 × 10−6)(5)2
�=
50. (15)
� = 4.4 × 10−4
P 5 ft 10 ft 20 ft
1 Jam 3987.5 psi 3991.3 psi 3991.4 psi
10 Jam 3980.9 psi 3994.6 psi 3988.8 psi
15 jam 3979.8 psi 3983.7 psi 3987.7 psi