Name of Project: Asset Preservation Program Rehabilitation/Reconstruction/Upgrading of Damaged Paved Roads-

Secondary Road, J.J. Linao Road (KO137 +056- KO137+872, KO143+150-KO143+330, KO146+000-KO146+604, KO
148+842-KO150+000, KO155+112- KO156+000) Bataan 2nd District
Location: Bataan 2nd District
Contractor: Orani Builders Supply
Date Started: February 18, 2018
Contract Completion Date: December 8, 2018
Contract Cost: 91,597,369.97
Implementing Office: DPWH Bataan 2nd District Engineering Office
Source of Fund: GAA FY 2018
Introduction

It has been raining in Bataan, specifically in all of the kilometer stations within the project scope, since June 1, 2018
up to date (September 15, 2018; 107 days) non-stop. It is not advisable to do excavation works because many times there
is zero visibility. Now, we have come up a catch-up plan as requested.

Strategy:

 2 sections per 144 meter or 482.4 square meter road construction for PCCP
 Start excavation for drainage (regardless of weather, extra safety personnel needed if bad weather occurs)
 Construction of drainage (Diversion of water is required)
 Start trimming of trees, for single arm posts to be installed.
 Start of installation of wheelguards.
 Have Sunday as workday
Timeline LEGEND
Start date 18-Feb-18 Title Abbr From to
End date 8-Dec-18 Beginning: B 1 10
Calendar days 286 Days Middle: M 11 21
Remaining Calendar Days 153 Days End: E 21 30 or 31
Days Delayed because of rains 99 Days
Holidays and sundays 14 Days
Proposed Moved End Date 31-Mar-19
Total Days to finish 167 Days
Present Date 17-Sep-18

Sept Oct Nov Dec Jan Feb Mar


Remaining Quantity Start Finish M E B M E B M E B M E B M E B M E B M E
Title Quantity Unit Duration July 16,2018
FACILITIES OF THE ENGINEER
Provision of Field Office for the Engineer (Rental Basis) 8.87 mos. 195 16-Sep 30-Mar-19
OTHER GENERAL REQUIREMENTS
Project Billboard/Signboard (DPWH) 0.00 each 0
Project Billboard/Signboard (COA) 0.00 each 0
Occupational Safety and Heallth Program 8.87 mos. 195 16-Sep 30-Mar-19
Traffic Management 8.87 mos. 195 16-Sep 30-Mar-19
Mobilization/Demobilization 0.50 l.s. 30-Mar-19
EARTHWORKS
Individual Removal of Trees 30.00 each 14 16-Sep 30-Sep
Removal of Structures and Obstruction 1.00 l.s. 14 16-Sep 30-Sep
Removal of Actual Structures/Obstruction (.23 thk. ACP) 23,599.78 sq.m. 180 16-Sep 15-Mar
Surplus Common Excavation 16,234.82 cu.m. 180 16-Sep 15-Mar
Structure Excavation 890.00 cu.m. 45 16-Sep 31-Oct
Subgrade Preparation 29,460.78 sq.m. 180 16-Sep 15-Mar
SUBBASE AND BASE COURSE
Aggregate Subbase Course 5,743.82 cu.m. 180 16-Sep 15-Mar
Aggregate Base Course 5,743.82 cu.m. 180 16-Sep 15-Mar
SURFACE COURSES
Portland Cement Concrete Pavement, 230 mm thk. 1,644.00 sq.m. 29 1-Nov 30-Nov-18
Portland Cement Concrete Pavement, 280 mm thk. 28,525.30 sq.m. 195 16-Sep 30-Mar-19
DRAINAGE AND SLOPE PROTECTION STRUCTURES
Paint 718.00 sq.m. 51 10-Oct 30-Nov
Pipe Culverts, 910 mm dia 20.00 m. 51 10-Oct 30-Nov
Rubble Concrete 646.00 cu.m. 51 10-Oct 30-Nov
MISCELLANEOUS STRUCTURES
Trees 1,500.00 each 14 16-Sep 30-Sep
Refflectorized Thermoplastic Pavement Marking White 427.00 sq.m. 29 1-Mar-19 30-Mar-19
Refflectorized Thermoplastic Pavement Marking Yellow 390.00 sq.m. 29 1-Mar-19 30-Mar-19
Reflectorized Thermoplastic Rumble Strips 147.00 sq.m. 29 1-Mar-19 30-Mar-19
Chevron Signs ( 450 x 600 mm) 42.00 each 11 20-Mar 31-Mar
Single Arm Post, with Street Light 12.00 each 11 20-Mar 31-Mar