Secondary Road, J.J. Linao Road (KO137 +056- KO137+872, KO143+150-KO143+330, KO146+000-KO146+604, KO
148+842-KO150+000, KO155+112- KO156+000) Bataan 2nd District
Location: Bataan 2nd District
Contractor: Orani Builders Supply
Date Started: February 18, 2018
Contract Completion Date: December 8, 2018
Contract Cost: 91,597,369.97
Implementing Office: DPWH Bataan 2nd District Engineering Office
Source of Fund: GAA FY 2018
Introduction
It has been raining in Bataan, specifically in all of the kilometer stations within the project scope, since June 1, 2018
up to date (September 15, 2018; 107 days) non-stop. It is not advisable to do excavation works because many times there
is zero visibility. Now, we have come up a catch-up plan as requested.
Strategy:
2 sections per 144 meter or 482.4 square meter road construction for PCCP
Start excavation for drainage (regardless of weather, extra safety personnel needed if bad weather occurs)
Construction of drainage (Diversion of water is required)
Start trimming of trees, for single arm posts to be installed.
Start of installation of wheelguards.
Have Sunday as workday
Timeline LEGEND
Start date 18-Feb-18 Title Abbr From to
End date 8-Dec-18 Beginning: B 1 10
Calendar days 286 Days Middle: M 11 21
Remaining Calendar Days 153 Days End: E 21 30 or 31
Days Delayed because of rains 99 Days
Holidays and sundays 14 Days
Proposed Moved End Date 31-Mar-19
Total Days to finish 167 Days
Present Date 17-Sep-18