Professional Documents
Culture Documents
WEEk1 DQ DFFDF FD
WEEk1 DQ DFFDF FD
Qty
Weight Wt.Qty Wt. Quantity
Subtask Units completed
Fabricate
∑( ∗
Install
366 ∗ 0.4
Inspect
+ 185 ∗ 0.5
Total
+ 42 ∗ 0.1)
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
Quiz
1. For reinforcement activity based on the given details answer the following questions
using Level of Effort (LOE) approach for output measurement
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
Daily
Productivity Calculations:
Weekly-
Periodic
Requirement: Total Qty- 250000 Kg. ; Work Days – 60 days
Cumulative
A B C D = B/C
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
DAILY PRODUCTIVITY & PRODUCTION
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
CUMULATIVE PRODUCTIVITY & PRODUCTION PRODUCTION KG
1
3
5
7
9
11
13
15
17
19
21
23
25
27
29
31
33
35
37
39
41
43
45
47
49
51
53
55
57
59
DAYS
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
Performance Factor (PF) =
•
•
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
PRODUCTION & PRODUCTIVITY PERFORMANCE FACTOR
DAYS
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
PRODUCTION & PRODUCTIVITY PERFORMANCE FACTOR - WEEKLY
FACTOR
PERFORMANCE
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
FACTOR
PERFORMANCE
Days (Week)
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
PRODUCTION & PRODUCTIVITY PERFORMANCE FACTOR - CUMULATIVE DAILY
FACTOR
PERFORMANCE
DAYS
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
������ � �
% �
A. % Complete =
� � ( )
� ( )
= = . ( %)
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
Eg. Reinforcement � ��� � �
% �
∑
∑
( )
( )
2.96%)
( )
( . )
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
Daily
Weekly-
Periodic
Requirement: Total Qty- 250000 Kg. ; Work Days – 60 days (10 weeks)
Cumulative
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
Daily
Weekly-
Periodic
Cumulative
Based on –
Running Avg. Weekly &
Performance Factor Benchmark
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)
Few…Factors Influencing Productivity – Multitude of Factors…
Inadequate Long- Errors and
Multitude of Design
Term and Short- Omissions in Plans Design Complexity Over Crowding
Change Orders Completeness
Term Planning and Specifications
Attitude &
Unavailability of Crew size and Equipment Project Size &
Festive Seasons motivation of the
Skilled Labour Composition Breakdowns Organization
Workforce
Delayed Decision Impractical QA/QC Uncontrolled Time of Day/Day of Client/Consultant Overtime and/or
Making Tolerances Breaks Week Practices Fatigue/Stress
Introduction to Lean Construction: Module 1 – Lean Basics – Session 04 – Productivity Measurement System (PMS)