Professional Documents
Culture Documents
(Final Report) : Indonesia Pesawaran PV Power Plant Systems (10MW) Feasibility Study
(Final Report) : Indonesia Pesawaran PV Power Plant Systems (10MW) Feasibility Study
Indonesia Pesawaran PV
Power Plant Systems
Indon (10MW) Feasibility Study
esia
This Report
Pesa
is the final
waran
report of the
New and
PV [Final Report]
Powe
Renewable
r July. 6, 2017
Energy
Plant
Overseas
Syste
Supporting
ms(1
Program,
0MW Supervised by Dadam Micro Inc.
funded by
)
the Ministry
Feasi Participated by Gaia Energy Inc.
of Trade,
bility 위탁기관 ○○○○
Industry &
Study ○○○○
Energy.
MOTI
E
Ministry of Trade, Industry and
Energy
Document for Submission
Energy Center
Participated by :
Iksoo, Jun
Cheol Min, Han
Baek Heung, Seong
Jae Young, Lee
Dong Won, Lee
Se Hwan, Oh
Gyeong Mee, Lee
Cheol Hyun, Lee
Byeong Un, Jeong
Dong Soo, Kim
Seung Il, Park
Byeong Soo, Park
Chang Yong, Jeong
Dong Min, Lee
Jeong Gyu, Ha
Chang Hee, Song
ABSTRACT
Project Name Indonesia Pesawaran PV Power Plant Systems (10MW) Feasibility Study
1. Business Goal
Ÿ The pre-feasibility study determines the economic, technical and
environmental feasibility of large scale solar precinct at Negri Katon Villeage
in Pesawaran Regency, Lampung Province, Indonesia.
Ÿ The capacity of PV energy to be generated by this project is 10MW that will
be sold to to the Indonesian government operated power company (PT. PLN)
through PPA contract.
Ÿ For the purpose of this study a solar precint is defined as the co-location of
solar plants into a precinct to facilitate sharing of infrastructure, particularly
access to the electricity network.
❍ For the purpose of this study a solar precint is defined as the co-location of solar
plants into a precinct to facilitate sharing of infrastructure, particularly access to
the electricity network.
❍ The goal of this project is to build a 10MW solar power plant in the Pesawaran
Regency in Lampung Province, Indonesia and sell the generated power to the
Indonesian government owned power company (PT. PLN) in the form of PPA for
20 years and then sell it to the commercial market.
❍ This project is well aligned with Indonesia’s effort for the promotion of renewable
energy, solving power supply problems, and reducing GHG emissions.
❍ Once this project is completed, we will be able to get more business opportunities
for additional projects (grid-type or ESS-based standalone type systems) in
surrounding areas using the engineering knowledge and know-hows acquired
through this project.
❍ This study:
- Informs the Pesawarn Regency how best to develop a large-scale solar plant in
Negri Katon Villeage area
- Determins the feasibility of solar precinct
❍ Highlights the key measures, risks, and issues for the Pesawaran Goverment in
development and implementaion of solar power precinct.
❍ Business Structure
- 1 -
<Fig 1> Business Structure
❍ The SPC is a joint venture between the Dadam Consortium in Korea and the local
government company (BUMD - Badan Usaha Milik Daerah) mainly owned by the
Pesawaran Regency, Lampung Province, Indonesia. The stakes are 45% for the
Dadam consortium and 55% for the BUMD.
❍ Roles of SPC
- Dadam Consortium:
Ÿ SPC 45% fund raising
Ÿ EPC company selection
Ÿ PPA contract negotiation
Ÿ Export-Import Bank of Korea, Interbank TC loan based PF
Ÿ Power Plant Management
Ÿ Local staff training and technology transfer
- BUMD :
Ÿ Purchase contract with the landowers of the plant site 140,000m2
Ÿ Level 2 Environment Impact Assessment
Ÿ Licenses for solar power plant business
Ÿ PPA unit price negotiation and contract with the Ministry of Energy and
Mineral Resources (ESDM) and the government owned Power Company (PT.
- 2 -
PLN)
Ÿ Operation after the plant is built
3. Business Method
❍ BOT (Build-Operate-Transfer) based PPP (Public-Private-Partnership)
- Project feasibility study, Licensing, PPA contract, PF, and EPC company selection
- Power plant construction by EPC company
- O&M by SPC
❍ Location
- S 5°18‘06.56’‘ E 105°06’02.73‘’
- Negerikatun, Negeri Katon, Kabupaten Pesawaran, Lampung 35353 Indonesia
5. Sales Plan
❍ Electiry Generation (NASA solar radiation data) : 17,155 MWh/year (4.7hr/day)
- The solar energy at Negri Katon Village (-5.258897, 105.176788) in Pesawaran
Regency, which is a candidate for the PV power plant, was observed at
4.7kWh/m2/day (Global Solar Atlas).
- 3 -
<Fig 3> Solat irradiance map for the PV plant site
1) In 2017, Indonesia ESDM announced the Ministry Decree No 12/2017 on amendment of FIT for renewable
energy.
- 4 -
6. Estimated total construction cost
❍ Total amount : $15M USD
(unit: USD)
Items Amount
1) Design & Engineering 500,000
2) Fixed investment cost
PV Modules 6,400,000
Power Inverters 800,000
Main Junction Box 240,000
Incoming Panel 800,000
Monitoring System 560,000
Structure Manufacturing 1,600,000
Electric Works 1,600,000
Land 1,400,000
Sub-total 13,400,000
3) Development expenses 100,000
4) Initial working capital 100,000
5) Reserve money 900,000
Total 15,000,000
<Fig 4> Estimated EPC cost
❍ Funding Plan
7. Economic Feasibility
❍ To review the economic feasibility of investment in this project, both NPV2)
method and IRR3) method is applied and sensitivity analysis is also performed.
- 5 -
❍ The economic feasibility study using the NPV method and the IRR method was
based on the information received from the Indonesian Persawaran Government in
advance and the contents of various laws and regulations related to renewable
energy in Indonesia.
❍ The forecast period for explicit development is set at 30 years. The 20 years from
June 2018 until the end of June 2038 is the PPA contract period with the
Indonesian government, and the 10 years thereafter from July 2038 to June 2048 is
thecommercial production period.
❍ It is generally assumed that the actual operating period of the solar power plant
can last for 30 years or more and that the long-term demand for renewable energy
in Indonesia will steadily increase.
❍ It is assumed that systematic O&M by the SPC results in 0.5% efficiency decrease
over the previous year.
❍ Basic prerequisites for reviewing the economic feasibility of the investment in this
project:
No 항 목 조 건
1 PPA Unit Price $0.0735(USD)/kWh
2 Annual Power Production Amount 17,155MWh/y
3 WACC4) 5.098%
4 Cost of equity in NPV 10.49%
5 Menimum return of investment in IRR 10.49%
6 Funding Plan Equity (20%) + Debt (80%)
7 PF method Interbank TC Load by KEXIM
8 Debt Finance Interest Rate 5%
10 Land Purchase $1.4M(USD) / 140,000m2
Ÿ Investment Period: 7/1/2018~
6/30/2048
Ÿ No cash flow after the investment
11 Other Investment Prerequisites period
Ÿ During the investment period, the
initial project structure will be
maintained, and no new projects
will take place.
<Table 2> Basic conditions for economical feasibility study
2) NPV(Net Present Value): NPV is one of the measures of business value (feasibility). If it is smaller than 0, it
has no feasibility (value). If it is larger than 0, it is a feasibility.
3) IRR(Internal Rate of Return): IRR is the interest rate that discounts the cash flow of a business during a
business period to the present value, so that the combined value is equal to the investment expenditure.
4) WACC : Weighted Average Cost of Capital
- 6 -
❍ With the agreed procedures and assumptions provided for the economic feasibility
of the investment plan, the NPV is USD 364,875 and the IRR is 12.51%.
<Table 3> Result of economic feasibility using NPV and IRR methods.
❍ Future Plan
- 7 -
Chapter 2. Project Plan
1. Project Outline
1.1. Objectives and Background
n Objectives
❍ The goal of this project is to build a 10MW solar power plant in the Pesawaran
Regency in Lampung Province, Indonesia and sell the generated power to the
Indonesian government owned power company (PT. PLN) in the form of PPA for
20 years and then sell it to the commercial market.
❍ This project is well aligned with Indonesia’s effort for the promotion of renewable
energy, solving power supply problems, and reducing GHG emissions.
❍ Once this project is completed, we will be able to get more business opportunities
for additional projects (grid-type or ESS-based standalone type systems) in
surrounding areas using the engineering knowledge and know-hows acquired
through this project.
n Background
❍ Indonesia is located around the equator and its average daily solar radiation is
about 4.8kWh/m2. Thus the country is favorable for the photovoltaic power
generation. About 22MW solar photovoltaic power stations are only installed
currently in Indonesia, and most of them are photovoltaic power generating stations
for family use or small-sized ones. Photovoltaic power generation has not been
universalized yet.
❍ Solar photovoltaic energy has been used for energy supply to the provinces. It has
competitive price in the area like Pesawaran Regency, Lampung which is thinly
populated. MoEMR (Ministry of Energy and Mineral Resources) and PLN
(Perusahaan Listrik Negara) implemented PV program (solar photovoltaic energy
program) to about 1,000 islands, where electricity, water and sewerage had not
- 8 -
been supplied yet, with the aim of building up to 245MW facilities.
❍ SGI-Mitabu entered into a partnership with the local government in the southern
Sumatera and announced PV project (photovoltaic power) to build an 100-hectare
site (mount grounded) in Tanjung Api-Api, southern Sumatera in 2014. Currently
in Feb. 2015, fund-raising is in progress, for the same project.
❍ Dadam Micro entered into LOI with government officials of Pesawarn Regency,
Lampung Province, Indonesia at Pangyo Inno Valley, Korea on Apr. 7, 2017 to
proceed with the 10MW solar photovoltaic power station in Pesawaran Regency.
❍ As a result, entered into LOI on construction and operation required for 10MW
photovoltaic power generation in Pesawaran Regency, Lampung province.
<Fig 6> LOI agreement between Dadam Micro and Farsawaran officials (2017.4.7.)
- 9 -
<Fig 7> LOI letter signed
n Technology applied
❍ Size of the site : 140,000㎡
❍ Applicable technology
- The technology related to the PV power generation and grid connection system
used in this project has many commercialized solutions all over the world, and in
particular has many cases installed/operated in the Southeast Asia including the
equatorial region.
- 10 -
❍ Main Equipment List
335W Solar
PV Module
1 Module 40,000
polycrystalline
Inverter 500kW
2 5
(Grid connected) 350kW
PV DC
3 12 Channel 6
Connection board
Electrical panel
4 (Incoming panel 10,000kW 1
switchboard)
Fixed, hot
6 Construction Work 1
galvanized
- 11 -
n Ordering agency
❍ Introduction
Class JV 공공 민간 기타
- Estimated customer PT. INKO Usaha Patungan Surya is a SPC (Special Purpose
Company) for the purpose of the business for renewable energy, LED, and
tourism business in Pesawaran Regency.
- The SPC, the prospective client, is a joint venture between Dadam Consortium of
Korea and government owned local company PT. Laba Jaya Utama (BUMD). The
Dadam consortium has 45% stake, PT.Jaya Laba Jaya Utama has 55%.
- In the case of power generation projects under 10MW, MoEMR Regulation No.
3/2015 restricts the foreign share to be less than 49%.
- The contractor cooperates with the Persawaran Public Private Cooperation Support
Department (KPBU - Kerjasama Pemerintah dan Badan Usaha) responsible for
the economic development of the Persawaran regency.
- This business structure naturally helps the SPC negotiate the PPA unit price with
PT. PLN smoothly through the KPBU.
- The SPC selects the best performing EPC company within the budget through
bidding process based upon the recommendations from Investors and project
devlopers after this feasibility study is completed
- 12 -
be easier for the SPCE to take part in bids for public development projects in
Persawaran Regency and get successful project award.
- The majority shareholder of SPC (BUMD) maintains a friendly relationship with
government officials who manage various PPP (Private Public Partnership)
projects through the Public Private Partnership Department (KPBU) and has the
ability to carry out business in a way favorable to foreign operators.
- The orgamizatino structure for this project was confirmed after the meeting with
Mr. Usman Rohim Rasim (Pesawaran Gov. Official, KPBU department director),
Mr. Adhytia Hidayat Ronald (Local government official for infrastructure
planning), Mr. Abimanyu (ESDM central government official). The meeting held
on Jan. 19, 2018 during the 2nd visit to Pesawaran Regency.
- 13 -
<Fig 9> Meeting minutes for business structure and schedule (2018.1.19)
- 14 -
- The Dadam consortium in the SPC consists of Dadam Micro Co., Ltd., Gaia
Energy Co. and Destin Power Co., Ltd who is a strategic investmentor.
- Dadam Consortium:
Ÿ SPC 45% fund raising
Ÿ EPC company selection
Ÿ PPA contract negotiation
Ÿ Export-Import Bank of Korea, Interbank TC loan based PF
Ÿ Power Plant Management
Ÿ Local staff training and technology transfer
- BUMD :
Ÿ Purchase contract with the landowers of the plant site 140,000m2
Ÿ Level 2 Environment Impact Assessment
Ÿ Licenses for solar power plant business
Ÿ PPA unit price negotiation and contract with the Ministry of Energy and
Mineral Resources (ESDM) and the government owned Power Company (PT.
PLN)
Ÿ Operation after the plant is built
- 15 -
Ÿ Business structure and economic feasibility according to laws and regulations
of Indonesia.
2.2. Schedule
❍ Current Status
❍ Detailed schedule
- 16 -
<Fig 12> Detailed schedule
3. Expected Effect
3.1. Export Aspects
❍ This is the first project in the Lampung Province and if this project is successful,
similar projects are likely to be carried out.
❍ As similar projects are expected to use the techniques applied for this project,
additional exports are expected to occur.
- 17 -
(unit: USD)
Ratio
Items Amount Suppliers
(%)
1) Design & Engineering 500,000 3.3 EPC company
2) Fixed investment cost
Hyundai Heavy Industries,
PV Modules 6,400,000 42.7 Shinsung Solar Energy, Hanwha
Solar
KACO, DIK, Dasstech,
Power Inverters 800,000 5.3
YASKAWA
Main Junction Box 240,000 1.6 KACO, DIK, KDT, YASKAWA
Gwangsan Electricity, KD
Incoming Panel 800,000 5.3
Power
Monitoring System 560,000 3.7 KDT
Indonesian local company
Structure Manufacturing 1,600,000 10.7
contracted by SPC
Electric Works 1,600,000 10.7 Indonesian local enterprise
contracted by SPC
Land 1,400,000 9.3
Sub-total 13,400,000 89.3
3) Development expenses 100,000 0.7 SPC
4) Initial working capital 100,000 0.7 SPC
5) Reserve money 900,000 6.0 SPC
Total 15,000,000 100.0
- 18 -
Korea, the project is expected to help recover the sluggish economy of Korean
solar power plant related manufacturers.
- 19 -
Chapter 3. Overview of Indonesia
1. Overview
1.1. Basic Information
Central
North and
Middle
Continent Asia Americ Europe Oceania CIS South Africa
East
a Americ
a
Official name of
(Korean)인도네시아공화국 (English)Republic of Indonesia
country
Capital Jakarta
Form of
Presidential system, Republican government
governm ent
Islam:87%
9300B dollar(‘16) Christian: 6%
GDP (17th worldwide)
Religion Catholic: 3%
Hindu: 2%
❍ Indonesia is the world's largest archipelago with 17,508 islands, and it has the
largest size of Southeast Asia with a land area of 181.15 million km².
- 20 -
❍ Indonesia is the fourth most populated country in the world, with a total population
of 2263.02 million in 2017 (4th in the world)
❍ More than half of the Indonesian population lives in the Java-Bali area, and
economic activity is concentrated in the region. The remaining 50% of the
population live in Sumatra, Sulawesi, Kalimantan, Nusa Tenggara, Maluku, Papua and
about 6,000 islands.
❍ Indonesia's gross national income (GNI) per capita in 2015 is $ 3,440, and
Indonesia is considered a lower-middle income country under the World Bank
classification.’5)
5) The World Bank classifies countries with GNI per capita in the range of $ 1,026 to $ 4,035 as low and middle
income countries.
6) The poverty line stipulated by the Indonesian government is $ 21.20 per month, and the Indonesian government
classifies those who do not earn below this income as poor.
- 21 -
- Key agreements:
Ÿ Economic and technical cooperation agreement (1971)
Ÿ Forestry cooperation agreement (1987)
Ÿ Double tax avoidance agreement (1989)
Ÿ Investment promotion and protection agreement (1991)
Ÿ Cultural cooperation agreement (2000)
Ÿ Convention on extradition (2000)
❍ Korean companies in Indonesia
- Indonesia is Korea’s 7th exporting country and 7th importing country as of 2011,
and Korea is importing natural resources such as oil, natural gas, crude oil,
copper ore, etc from Indonesia.
- The trade scale with Indonesia is 22.9 billion dollar in 2010 and 20.8 billion
dollar in 2011.
- Current status of major investment enterprises in Indonesia (order of advance to
Indonesia, 5 million dollar or more)
Amount Mother
Corporation Invested compan
No. Company Year Type Biz Items (thousad y in
dollar) Korea
Manufactuin timber,
1 Corinth 1969 Production g afforestation, 550,000 -
non-forest land
Manufactuin
2 CJ Indonesia 1988 Production g articles of food 800,000 CJ
electric Samsun
Samsung Manufactuin g
3 Electronics
1991 Production
g
communication 68,000
Electro
equipment
nics
Manufactuin thread, cotton
4 Hanil Indonesia 1995 Production g yarn 5,000
Transportati marine
5 SMS Shipping 1993 Service
on transportation
50,000
Manufactuin monitor, audio,
6 LG EDI 1995 Production g etc 75,000 LG
Manufactuin
10 COSMOS India Ink 2000 Production
g
plastic, bags 80,000
sales of machine
11 Corinna 2001 Sales Service part 500,000
Daesan
12 KIRIN Miwon Food 2006 Production Distribution articles of food 100,000
g
❍ Since 2000, Korean companies have entered the Indonesian construction market in
- 22 -
an overall increasing trend. In particular, overall order volume has risen sharply in
2011.
- 23 -
(Source: Overseas Construction Comprehensive Information Service http://www.icake.or.kr/)
<Fig 15> Indonesian construction orders by Korean companies (2000-15) (Unit: US $ million)
- Especially, the growth of industrial facilities has been remarkable since 2011. In
particular, orders for power plant, refinery and chemical plant construction led to
this.
- Although the number of service(engineering) projects accounts for a large number
of successful cases, the proportion of orders received is low due to relatively low
unit prices.
❍ To accelerate such growth trends, the Indonesian government pushed ahead with
‘Master Plan 2011-2025 (MP3EI: The Master Plan on Acceleration and Expansion
of Indonesia Economic Development 2011-2025)’ for accelerating and expanding the
Indonesian economic development and achieved GDP 4-4.5 trillion dollar in 2025,
and made an ambitious blueprint “Make a new leap into the world’s 9th economic
power.”
- 24 -
❍ Indonesia also continues to maintain an important partnership with Korea in multiple
fields of economic cooperation including trade, investment, aid, and FTA.
❍ Indonesia is the biggest oil and gas producer in the Southeast Asia. It has a high
potential in developing resources with the reserve and production of mineral
resources including coal, tin, copper and nickel being in the world’s top rank. In oil,
Indonesia is ranked 22nd in terms of reserve, but both potential reserve and
confirmed reserve tend to be reduced. In natural gas, Indonesia ranks 10th in terms
of reserve, but the confirmed reserve tends to be increased, but the potential
reserve tends to be reduced. In abundance of coal, it is concentrated in both
southern Sumatera and eastern Kalimantan. Among mineral resources, tin is
distributed a lot in Sumatera, nickel in Kalimantan and Sulawesi, and copper in Irian
Jaya.
❍ To look at the production and export trends by sector, in energy sector, the
production and export of oil and natural gas tends to be reduced due to lack of
new oilfield development and investment, but in coal sector, its production tends to
be increased greatly. In mineral resources, tin and nickel rank the 2nd in terms of
production, and the production of copper ranks the fifth in the world. The
representative successful case in the field of Indonesian energy/mineral resources is
Samtan’s coal mine project in Paser, eastern Kalimantan. In 2000, the country’s
investment environment into resources improved greatly. Indonesia is planning to
invest more into productivity improvement and added value enhancement in
connection with large-size development project like master plan. Indonesia’s future
development of resources is likely to be concentrated in the development of energy
including gas and coal and rich mineral resources development. Especially influenced
by the New Mining Policy, the investment into the smelting facility for various
mineral resources is expected to increase greatly.
- 25 -
3.1.1. Indonesia economic recovery
❍ The International Monetary Fund (IMF) expects the global economy to recover
gradually, and the Indonesian economy is also expected to be positive. The
economy will grow by 5.1% in 2017 from 5.3% in 2018, up about 3.9% from 2018.
❍ Korea is the seventh largest export destination ($7 billion) in Indonesia and the
target country ($6.7 billion) for import
❍ No.3 in 2011 and 6th in exports for the next four years, then dropped to 7th in
2016
❍ Indonesia's exports to Korea in 2016 fell 8.4% YoY to USD7bn, while imports from
Indonesia to Korea declined 20.8% YoY to USD6.7bn in 2016
❍ From the past to the present, natural resources such as natural gas, crude oil and
coal are at the top of the list of imported goods from Indonesia to Korea.
- 26 -
3.2. Major issues and prospects
3.2.1. Accelerating privatization for infrastructure projects in Indonesia
❍ President Joko Widodo has organized Rp. 20.7 trillion (about $ 1.53 billion) budget
for the 2018 infrastructure projects. This will bring the infrastructure budget to
privatize public enterprises at a lower price than in 2017.
❍ Indonesia will host the 108th Asian Games in August 2018. To this end, Indonesia
is willing to construct facilities and related transportation infrastructure facilities for
the Asian Games.
❍ The Asian Games will be held in Jakarta and Palembang, as well as in various parts
of Indonesia including the Western Java Games, Ratu, Anchor, and Lead Sumatra
Rookbugging.
❍ Indonesia predicts that it will cost 10 trillion Rupiahs to build infrastructure for
Asian games and that the government budget will cover 5 trillion Rupiahs..
❍ After the announcement of the Asian Games as a host country, many companies
seeking investment opportunities in Indonesia are expected to increase their entry,
financial income and household consumption expenditure. Especially, GDP growth
and job creation are expected.
❍ From January 2018, Joko Widodo has presented a new pattern of village funding
throughout Indonesia.
- 27 -
❍ It aims at solving the infrastructure problems of each village and at the same time
creating jobs for the villagers.
❍ This project will be implemented with government support in over 100 districts.
The government expects the project to boost welfare, public purchasing power,
promote employment and raise funds.
❍ The Ministry of Labor decided to raise the minimum wage this year by 8.71% in
November last year. The minimum wage is calculated to combine the rate of
inflation (3.72%) and the gross domestic product growth rate (4.99%).
❍ Minimum wages in all provinces except Bengkulu and West Noosa Deong Gaara
province will increase by 8.71%.
❍ Jakarta has the highest weekly minimum wage of Rp.3,064,035. After that, Papua
province ranks second with 2.896550 Rupees, and then followed by northern
Sulawesi, Bangakaburi, Aza provinces.
❍ There are a lot of job seekers in Indonesia. Especially, Indonesian people are very
sensitive about the minimum wage because there are many people who do not go
to university and work. Therefore, Korean firms should keep an eye on the
Indonesian minimum wage regulations.
❍ According to a survey on a job information site in Hong Kong, there are about 30
million people in Indonesia who are 18 to 40 years old.
❍ ❍ Indonesia is the lowest among neighboring countries even after the minimum
wage increase. Still, Indonesia is attractive in terms of labor costs among ASEAN
countries.
❍ The Indonesian tax system has been improved in accordance with the Indonesian
social and economic conditions during the economic development plan
implementation process. The tax reform has been carried out in order to strengthen
the economic function of the tax through the revision of the main tax law
implemented since 1995. For example, Indonesia is expanding the scope of
withholding tax, strengthening taxation efforts for tax-exempt beneficiaries,
subdivision of taxation zones, encouraging the registration of personal tax numbers,
- 28 -
and pre-approval system (APA), and the introduction of a transfer pricing system.
❍ Indonesia's tax system is divided into three categories: national tax (personal
income tax, corporation income tax, value added tax, special consumption tax, stamp
tax, property tax, departure tax), local tax (reconstruction tax, automobile tax,
entertainment tax, etc.), and income tax.
❍ There is a Direction General Taxation (DGT) under the Treasury Department, and
the Internal Revenue Service (DGT) has subordinate local tax offices and regional
tax offices. All local taxpayer registration and filing procedures, processing of
taxation data, and taxpayer file management are handled by the local tax office
notification and management section. Based on the taxpayer's factual data and field
reports of the investigation department, (Or taxpayers) tax return through a regular
tax audit.
❍ Most of the taxpayers are managed by the local tax office in the province, but the
three tax offices in Jakarta manage foreign corporations, state enterprises, foreign
corporations and non-residents.
① Taxpayer responsible for foreign corporations: The taxpayers who have invested
foreign capital under the Foreign Investment Law
③ Tax offices for foreign corporations and non-residents: tax liability management
of foreign corporations and residents who have permanent business sites in
Indonesia
- 29 -
of the investment start, so that the investment error is not unilaterally attributed to
foreign investors.
❍ Indonesia does not allow the establishment of branch offices or branches where
foreign corporations can directly conduct commercial activities. Only permits the
opening of a representative to conduct market research, public relations and liaison
offices.
❍ On the other hand, foreign corporations are all kinds of companies and organizations
that do not have a domestic address, and income from real estate (including the
attached rights) located in Indonesia is equivalent to the amount of product obtained
from the property development, Corporate tax imposed on profit.
❍ Since 2010, corporate tax rate is 25% single tax rate. However, a 20% tax rate is
applied to listed corporations whose IPO is 40% or more of the vested stocks.
❍ Small businesses less than Rp 50 billion (KRW 6 billion in annual sales) apply
12.5% from taxable income of the target business year to Rp 4.8 billion (KRW 600
million).
4.2.2. Withholding
❍ The amount of withholding tax paid by the residents of Indonesia is deducted from
the amount of tax paid upon payment of the relevant income tax return. The
withholding tax paid by non-residents in Indonesia is subject to taxation on income.
❍ A person with a withholding tax shall pay the amount of tax collected from the
income earner by the 10th day of the following month, and if the refund occurs,
submit the withholding tax payment document instead of paying the withholding tax
amount by the 20th.
- 30 -
to withholding tax, the withholding tax rate may be reduced or exempted according
to the tax treaty between Indonesia and the relevant country.
❍ If the person subject to withholding tax has no tax registration number (Nomor
Pokok Wajib Pajak, NPWP), an additional 100% of the basic tax rate is imposed. In
addition, if the goods are exempted from import duty and VAT exemption,
temporarily imported for re-export purposes, and are subject to re-import, they
may not be subject to withholding from the beginning.
4.2.3. VAT
❍ The obligation to pay VAT on value added resulting from the provision of goods
subject to taxation and the provision of services. As in Korea, VAT is imposed at
all stages where goods and services subject to taxation are transferred by adopting
the Multi Stage Levy.
❍ Companies with an annual turnover of less than Rp.600 million (KRW70 million) are
exempt from VAT reporting obligations.
❍ The basic tax rate is 10%, but exceptional tax rate (5%) can be applied if it is
prescribed otherwise in the related tax law. 0% zero rate applies for exports of
short products, exports of intangible goods, and exports of services.
- 31 -
❍ The tax rate adopts the 4-step progressive tax system as shown below.
❍ In accordance with Regulation No.1 / 2007, if the conditions listed below are met,
investment in government-designated 22 high-tech industrial sectors made to the
Java and Bali regions (3-year income tax exempt) or elsewhere (5-year income
tax exemption), employees are exempted from income tax for up to 8 years.
① If you employ more than 2,000 employees, you will be exempted from income
tax for an additional year
② If the Indonesian SME owns more than 20% stake in the investment in
Indonesia, the income tax is exempted for one additional year.
③ If the investment amount (excluding land and buildings) is over $ 200 million,
the income tax is exempted for one additional year.
❍ Exemption from service fees generally applies only if the foreign resident receiving
income does not have a permanent establishment in Indonesia.
❍ If you do not submit the form specified by the Tax Office or the form specified by
the tax treaty partner country, you will not be eligible for tax and you will
withhold at 20% tax rate.
❍ Korea and Indonesia signed the double taxation agreement '88. 11.10 (concluded),
'89. 5. 3 (enacted)
❍ Withholding tax rate: 15% for dividend, 10% for interest, 15% for royalties
- 32 -
❍ A foreign corporation with a permanent establishment in Indonesia is obliged to pay
corporation tax on Indonesian domestic source income from business income from
the Indonesian workplace and from real estate rental and sale (real estate income)
in Indonesia.
❍ According to Article 5 of the Indonesian tax treaty, the Indonesian tax authorities
will determine whether a fixed business establishment
❍ Based on the Force of Attraction of Indonesia, the Indonesian tax authority will
only transfer the income to a fixed workplace if it proves that the income received
by the foreign corporation is received regardless of the permanent establishment in
Indonesia. If you can not prove that you are not taxable, there is a possibility of
taxation in Indonesia irrespective of the economic realities of income received from
foreign corporations.
❍ Land and building taxes are land and building taxes that are levied on acquired land
and buildings. Land and building taxes are calculated by using the real estate tax
value (NJKP) of the taxable object to obtain the tax base, and then apply the tax
rate of 0.5%.
❍ The value of the real estate tax is applied to the value of the application price of
Rp.1 billion (KRW 120 million) or less on the value of real estate taxation (NJOP)
announced by the Internal Revenue Service (DGT) on behalf of the Indonesian
Ministry of Finance Multiplied by 20%, multiplied by 40% for assets subject to
applied value over Rp.1 billion.
- 33 -
temporary uncertainty factors (tax amnesty system, election of governor of Jakarta,
and anxiety caused by Trump), and Indonesia's GDP growth forecast for 2017 will
change from 5.2% to 5.3%. So the investment situation in Indonesia is continuously
improving.
❍ Moody's, Fitch and S&P recently upgraded Indonesia's national credit rating to
investment grade thanks to careful macro / fiscal policy management in Indonesia.
- 34 -
<Fig 19> Indonesian Rupee to rise to normal level
❍ IPP investments are classified according to the type of related purchase contracts,
especially PPA.
❍ ❍ Third generation IPP projects are classified into 1) PPP projects, 2) FTP II
projects, and 3) IPP projects under the regular program of PLN. The risk allocation
has become clearer and more advantageous to investors. This project will be
implemented as a PPP project.
❍ PPP project
- A new Presidential Decree No.38 / 2015 on PPP was issued on March 20, 2015 to
address some of the problems that arise under the existing PPP scheme.
- These regulations cover a wide range of areas such as oil and gas infrastructure
(eg refineries), urban infrastructure, industrial complexes and infrastructure (eg
healthcare).
- State owned enterprises (SoE) and local government owned enterprises (RoE) can
serve as Government Contracting Agencies (GCA)
- The government must complete the procurement of land prior to the bidding of the
PPP project.
- Project developers are encouraged to develop project through arbitrary bidding by
providing relative compensation to the developers.
- It provides government support in the form of money contribution in connection with
the construction cost through the business performance guarantee letter, and
- 35 -
provides separate tax incentives.
- It provide a government guarantee to define the financial burden of the GCA.
❍ When: 2017.11.14
- 36 -
- Bonded area (KB)
- Free Trade Zone (KPB)
- Special Economic Zone (KEK)
- Industrial Complex (KI)
- PPP project (Public Private Partnership)
- 37 -
investment (excluding mining and banking industry), processing of license related
to establishment of corporation, investment information service, investment
monitoring
- As of October 2014, Indonesia has 34 provinces and municipalities. Local
governments have local investors, but foreign investors only provide investment
information for each region.
- From 2015, BKPM is issuing a power supply business license. As part of the
'one-stop' service, BKPM also handles services related to the establishment and
licensing procedures and permits for foreigners to work. The BKPM also has an
Investor Relations Unit for handling inquiries and providing information from
existing investors and potential investors.
Corporate tax
Pioneer Industries Ÿ 14.8.15 Establishment / corporation
exemption for 5 to 10
(Leading Industry) If it approved by the corporation (debate
years from the
falls under the reduction over the enforcement of the regulation
commencement of
requirement by the Ministry of Finance)
commercial production.
- Base metal New or Corporate Ÿ • At least one trillion Indonesian
Additional 50%
- Refinery increased Tax dollars (approx. US $ 90 million)
corporate tax
- Oil-gas originated investment Reduction Ÿ A company that has deposited at least
exemption for two
organic chemistry 10% of its planned investment in a
years after term
- Renewable Energy bank in Indonesia
- Decided by BKPM
- Machinery industry Ÿ Not withdrawing of the deposit before
on behalf of the
and communication realizing the investment plan.
Ministry of Finance.
<Table 8> Corporate tax exemption system for inducing specific industrial investment
- 38 -
Chapter 4. Energy Market Analysis
1. Global Energy Market
1.1. Global Energy
❍ According to the International Energy Agency (IEA), the World Energy Sector in
2040 predicts that oil, gas, nuclear, and low-carbon energy sources will be almost
uniformly weighted, Despite the ongoing trend, it is expected that fossil fuels will
continue to be a main energy source in 2040 and is expected to increase by 57%
than in 2012.
❍ Capacity of power generation facilities will be 10,716GW in 2040, with 42% of new
and renewable energy including hydro power, 25% of gas and coal, 6% of nuclear
power and 2% of oil prediction. In 2040, the generation amount is 40,104 TWh, so
that the share of coal and oil in power generation will decrease, nuclear power will
remain stagnant, while the proportion of gas and renewable energy will increase
❍ From 2014 to 2040, the total investment in the electric power industry is
estimated at USD 20.8 trillion, of which the non-OECD countries will account for
63.4%. Renewable energy investments are expected to be USD 12 trillion, 61% of
which will be invested by renewable energy sources. Wind power, hydro power and
photovoltaic power generation will be the largest investment sources. Global power
- 39 -
generation costs will increase by 81% from US $ 1.6 trillion in 2012 to USD 2.9
trillion in 2040, which is likely to be fueled by fuel costs and carbon price hikes.
The US and Europe are expected to increase carbon-cost burdens due to the
expansion of capital-intensive renewable energy sources, and China's dependence
on fossil fuels.
❍ ❍ The growth of CO2 emissions in the power generation sector will be more
moderate than in the past, but emissions will increase from 17.2 billion tons in
2012 to 17.5% in 2040 to 15.4 billion tons and 71% of the emissions will come
from coal-fired power generation.
❍ ❍ OECD countries will reduce their carbon dioxide emissions to 67%, but
non-OCED countries will increase their carbon dioxide emissions by 44%. It should
be noted that China's implementation of post-carbon policy was not implemented as
planned and the possibility of global carbon dioxide emission increases
❍ ❍ The world power industry has the largest growth in Asia, and the Middle East,
Central and South America and Africa are small but expected to grow rapidly. Asia
is expanding its power generation facilities in line with the high economic growth
rate. Considering the possibility of entering the electric power industry by country,
it is expected that Southeast Asia (Indonesia, Malaysia, Vietnam, Philippines) are
attractive.
❍ Since 2000, photovoltaic power generation has achieved a CAGR of 40% under the
systematic support of FIT.
❍ However, the Spanish market shrank in 2008 (the Spanish solar PV market shrank
quickly due to a decline in support and a sharp fall in oil prices amid the
government's policy support), German FIT cutbacks, and unstable financial markets
after the Lehman crisis, the global PV market entered the second downturn.
❍ Since then, the solar PV market has entered a second phase of growth due to
falling product prices and expanded support for solar power generation in Germany
and Italy. However, due to the fiscal cutbacks in post-2012 European countries,
further FIT cuts and China PV production capacity expansion entered the second
recession due to oversupply.
- 40 -
(Source: The Korea Export-Import Bank, Institute for Overseas Economy, 2015.09)
❍ Due to this, the market has declined and stagnated, leading to a first structural
adjustment due to oversupply until 2013, and some supply and demand conditions
improved thanks to large-scale installations of emerging economies such as China
and Japan in 2013-14.
❍ In the solar industry, the initial high-cost structure has been remarkably improved
due to economies of scale, cost reduction due to intensified competition, process
improvement and conversion efficiency enhancement.
❍ According to the data of the Korea Economic Research Institute (the global solar
market trend and major financial support model, 2015.09), the cost of power
generation is expected to decline to the level of grid parity for solar power
generation in 2016.
- 41 -
(Source: Source: EPIA, Shinhan Financial Investment Research Center, 2015.06)
❍ The center of the global solar market is moving to non-Europe centered on the
United States, China and Japan centering on policy support from the US, such as
the ITC system in the US and the FIT system in Japan.
❍ However, since 2012, structural restructuring has been achieved due to structural
oversupply, and companies that have survived the restructuring have entered a
competition to improve costs and efficiency.
❍ In this situation, it will be possible to reduce the policy support of the ITC, FIT,
etc., which are the driving force of the solar PV market growth, and it will take
more time than expected to reach the grid parity. There is a possibility that growth
potential will slow down.
- 42 -
- The value added in the photovoltaic industry is 10% in the manufacturing sector,
10% in the construction sector, and 80% in the business development, finance
and operation.
- There are more and more companies entering the project development business in
order to overcome the low margin of solar cell and module, and the gap between
the companies that have economies of scale and the late buyers is getting bigger
❍ Market move
- In Europe, where the early solar photovoltaic industry has been leading, the
European market has entered a mature stage. Demand growth has slowed since
2013, and discussions on the 'new climate change regime' Of major demand
- 43 -
countries moving to the US, China and Japan
- Recently, demand is spreading to the Middle East and Southeast Asia, North
Africa and Central and South America, where actual solar energy generation
efficiency is high.
- The rapid growth and diffusion of this demand is due to the fact that the solar
power industry has achieved economies of scale and the cost of power generation
has been lowered.
❍ USA
- In the United States, due to the nature of the market with a relatively
well-developed financial system, it is easy to raise funds necessary for solar
power generation. Therefore, the installed capacity of solar power in 2010 is
steadily growing from 1.1GW to 7.0GW in 2014
- In terms of environment and energy independence, solar power generation is
receiving policy support as a substitute because it is closing coal power
generation with less resources in its own country.
- US photovoltaic installation demand maintains robust growth as ITC (investment
tax credits) system has reduced 30% of solar installation cost to tax benefit.
- However, the demand for photovoltaic installations will be directly affected by the
reduction of the ITC system, which led to the growth of US photovoltaic
installation demand, at the end of 2016 (30% → 10%).
- According to SEIA and other research institutes, the demand for photovoltaic
installations in the US in 2017 is expected to decline from 2016 to 6 ~ 7GW.
❍ China
- In China, demand for photovoltaic power generation has grown dramatically from
0.5GW in 2010 to 11.5GW in 2013, but in 2014, due to the lack of a stable
- 44 -
financial system and a lack of stable power supply network, the solar power
demand of 10.6GW Solar power plant was built, which is less than the initial
target 14GW.
- In 2015, the allocation of dispersed photovoltaic power generation facilities by
local governments in China was actively managed, and as a result, the installation
of new photovoltaic power generation facilities by the end of the third quarter of
2015 was 9.3GW.
- In China, solar PV companies install more than 16GW / year in 2015, considering
that the annual solar PV installation capacity is about half of that in the fourth
quarter.
❍ India
- The Indian solar market will continue to grow mainly in large power plants in
2016.
- India plans to increase the cumulative capacity of photovoltaic power generation
to 100GW by 2022 by raising its target (22GW).
- The government of India is making efforts to participate in foreign companies and
capital inflow of the photovoltaic industry after the announcement of the
enlargement policy of solar power.
- US dollar-based contracts to induce foreign investors who are reluctant to invest
for a long time due to concerns about foreign exchange losses. In fact, Japan,
Korea and other countries are announcing plans to invest in solar power and
overseas investment is expanding (Japan Softbank , Korea Hanhwa Quseel, Korea
OCI, etc.)
- The Indian market, which created the 1.8GW solar PV market in 2015, will be
increased to 3.5 ~ 4.0GW, more than double the 2016
- 45 -
- Large electric power companies are in the solar power development business, and
the household market is being activated by the introduction of the net-metering
system that can deal with the electricity that is left to use. It is expected to
reach 350MW this year.
❍ In Indonesia, which is likely to enter the power industry, power consumption has
been surging for the past five years due to the expansion of private sector
electricity demand along the economic growth.
❍ As a result, thermal power generation accounted for more than 80% of the total
power generation, and the price of coal-fired power generation increased by an
average of 9.5% over the past five years owing to the price increase of oil-fired
power plant due to rising oil prices. So the share of coal-fired power generation
will increase by 3.3% and the share of petroleum thermal power generation by
2.7%
❍ The share of renewable energy sources (TPES, total primary energy supply) in
Indonesia was 33.4% in 2012 (25.3% for biofuels and wastes, 7.6% for geothermal
energy sources, 0.5% for hydroelectric power) Renewable energy sources accounted
for 11.4% (6.5% of hydroelectricity, 4.8% of geothermal energy sources, 0.1% of
biofuels and wastes).
❍ Despite the high hydropower potential, Indonesia has not been able to build a
visible hydroelectric power station recently. As a result, the average annual growth
rate of power generation in the last five years is only 3.9%
❍ According to the national energy policy, it will develop new and renewable energy
sources such as geothermal, hydro, bio energy, and solar energy, and increase the
proportion to 16.9% in 2020 and 31.0% in 2050.
❍ The total amount of electricity generated in Indonesia in 2015 is 200.4 TWh, which
has grown at a CAGR of 8.1% over the past seven years.
- 46 -
(Source: Amendment to the Indonesian Power Development Project Plan (RUPTL 2016-2025))
❍ Indonesia's power generation has steadily increased since the 1990s in line with
population growth, economic growth, and electricity demand growth due to improved
electricity penetration.
❍ The Indonesian Power Corporation (PT PLN) is leading the Indonesian power
generation sector, with the Electricity Corporation accounting for 84% (36,897 MW
out of 44,000 MW) of the total power generation capacity in Indonesia. The
remaining 26% is owned by independent power producers (IPPs).
❍ Indonesia has been operating the Fast Track Program since 2006 (revised in 2009)
to address the power shortage problem, and plans to secure a total capacity of 42
GW by 2019 .
- This expansion program mainly supported by Indonesia PT PLN is composed of
FTP-1, FTP-2 (2009-2018) and FTP-3 (2015-2024), the content of which
was codified by PT PLN in the Electricity Power Supply Business Plan (RUPTL).
- FTP-1 is a coal-fired power plant with a capacity of 9,975 MW. FTP-2 is a
- 47 -
coal-fired thermal power plant with 4,000 MW of geothermal energy, 1,1735 MW
of coal, 280 MW of coal gas, ) The construction of the power plant is included.
- The FTP-3 plan is a separate plan for FTP-1 and 2, with the goal of capacity
expansion of 35 GW by 2019, 56% coal-fired power, 36% gas and the remaining
6% Will be built through the construction of other energy sources including hydro
and geothermal energy.
❍ Indonesian Power Corporation (PT PLN) plays a dominant role in the power
transmission sector in Indonesia.
❍ Since Indonesia Electric Power Corporation has the right to refuse to provide power
supply service, in case of IPP, electric power will be supplied only to the area
where the electric power corporation refused to supply electric power.
❍ The transmission system in Indonesia consists of 7 power grids and 600 individual
grids. Indonesia Electric Power Corporation had about 39,900 circuit-km power grid
(86,500 MVA capacity) as of 2013
❍ As part of the ASEAN Power Grid Project, Indonesia is planning to expand the
- 48 -
connection between Malaysia and the country, and is also planning to establish a
connection with Singapore for the first time ever.
(Source: PLN)
<Fig 28> Sumatra Island Power Supply and Demand Plan 2017-2019 (Source PLN)
❍ Indonesia has very rich renewable energy sources such as geothermal energy,
hydropower, and biomass, but currently uses only about 5% of renewable energy
potential.
- 49 -
<Table 11> Indonesian renewable energy potential and secured generation capacity, 2013
- 50 -
2.3. Policy
2.3.1. National Energy Policy
❍ The energy law of Indonesia (EL7, Energy Law No. 30, 2007), which was
established in 2007, is the basis of energy sector management, basic principles of
national energy mix, institutional structure of energy sector and government
Establishment of role-sharing structure among ministries
❍ The overall plan for the development of the Indonesian energy sector is the
National Energy Policy (NEP).
❍ The overall goal of the development of the Indonesian energy sector through the
National Energy Development Plan (NEP14), which was revised in 2014, is to
improve the domestic consumption7) of Indonesian energy resources used for
export. By reorganization of the national energy mix8) centered on domestic energy
sources, Indonesia will reduce national subsidies on fossil fuels and electricity to
reduce dependence on imported fuel. This will ensure energy security, and
Indonesia will promote the following policies to achieve its goals.
1) Reduced oil consumption
2) Development of coal and renewable energy sources, promotion of consumption
3) Optimization of gas consumption and production
4) Considering the introduction of nuclear power (as a last resort)
❍ Indonesia plans to maintain the share of renewable energy sources in the total
primary energy supply (TPES) by 23% in 2025, 25% in 2030 and 31% in 2050
through the National Energy Development Plan (NEP14)
❍ The NEP14 of Indonesia is composed of the National Energy General Plan (RUEN),
the National Electricity General Plan (RUKN) and the Electricity Power Plan Supply
7) Indonesia has announced plans to halt exports of coal and natural gas in the future, and eventually to finalize
the export through NEP14.
8) Indonesia will cut state subsidies on fossil fuels and electricity to reduce dependence on imported fuel.
- 51 -
Business Plan '), which will be developed as a detailed policy plan.
❍ In order to achieve the target ratio of new and renewable energy, utilization of new
and renewable energy is prioritized. Central and local governments provide the
following types of support: (1) tax benefits (such as investment tax credit), (2)
mitigation of licensing and non-licensing, (3) FiT for renewable energy, and (4)
(5) Additional subsidy for renewable energy. This support will depend on the
feasibility and economics of power infrastructure development. PR No. 4/2016
defines a variety of tax benefits related to the development of renewable energy.
❍ PR No. 4/2016 specifies that hydropower, geothermal and wind power plants and
their transmission facilities can be developed within the Natural Reserve Area
(Natural Reserve Area) according to the current regulations.
- 52 -
2.3.2. Climate Change Response Policy
❍ The Government of Indonesia did not specify specific plans for achieving the GHG
emission reduction targets in the country-specific mitigation plans. But focusing on
the National Action Plan for GHG Emissions Reduction (RAN-GRK), established in
2011 based on the NAMA (Nationally Appropriate Mitigation Action), the
Indonesian government is expected to make efforts to achieve the NDC goal.
❍ Indonesia supports FIT subsidy system (2009) to support all renewable energy
sources (solar, wind, biomass, biogas, geothermal, hydroelectric power plants, less
than 10 MW)
❍ Indonesia has long supported the difference between electric production and
transportation prices and consumer prices through electric subsidy schemes.
❍ The Indonesian government announced that it will abolish the power subsidy system
for large enterprises (industrial sector) in 2008 and plan9) to gradually reduce the
electricity subsidies to SMEs (industrial sector) and other consumers in 2014.
9) In 2014, the Indonesian government introduced the Automatic Tariff Adjustment Mechanism (ATAM). By 2018,
the government will abolish the electricity price subsidy for all types of power consumers except for extreme
households, and supply electricity to market prices. Announced plans
- 53 -
<Fig 31> Status of Indonesian Electricity Grant Support System, 2003-2012
2.3.4. Act on Electricity Fee and Bidding of New & Renewable Energy Business
(No. 12/2017)
❍ The new regulations are different for each type of resource such as solar, wind,
hydro, biomass, biogas, waste, and geothermal.
❍ The regulation stipulates that electricity generated from renewable energy should be
- 54 -
sold and supplied to PT PLN Persero, an Indonesian energy state company, and
specifies the guidelines for PLN to procure electricity from power plants using
renewable energy.
❍ The regulation limits the unit price of renewable energy. If the basic production
unit price (BPP, basic production unit price) exceeds the national average price, the
electric power charge is limited to 85% of the rate through the system applied to
all renewable energy power plants. There are no restrictions if the basic unit price
of the region does not exceed the national average unit price.
<Table 13> Indonesian Government Renewable Energy Electricity Production Rate Table (2017 year)
❍ Until now, coal-fired power generation has a large share in the energy market, and
thus the renewable energy production fee is expected to be in competition with the
electricity production cost of the coal-fired power plant. However, PLN continues
to limit the cost of producing coal power plants from $ 0.04 to $ 0.07 per kWh.
❍ Problem
- The new production standard price specification conflicts with other existing
regulations. It is said that the local BPP and the national BPP are determined
annually by the Ministry of Mineral Resources and Energy based on the proposals
of PLN, but the other regulations are to report PLN local governments BPP
quarterly to Mineral Resources and Energy Department.
- In addition, there are no codified provisions for whether to display the price in
- 55 -
rupiah or in dollars. The BPP announced by the government is in dollars, but the
BPP announced by PLN is marked as Rupiah.
- There is a controversy in the interpretation because the government does not
specify at what level the rate system should be used if the developer has to
decide whether or not it can meet the condition of performing the project with
less than 85% of the local production unit price.
- The government's price cap rule provides PLN with the possibility to impose
lower rates on energy developers than local production costs.
❍ In Indonesia, the private sector has begun to introduce private capital in the
electric power sector since 1992, when it has become difficult to respond to the
surge in electricity supply and demand in the late 1980s. At the end of 2013, 24
IPPs and 24 captive power plants (CPP) , And the electricity production ratio is
72% for PLN, 21% for IPP, and 4% for other small private power generation
companies.
❍ The PLN has tremendous power over Indonesia's power generation business and can
veto the power generation business. IPP can only develop in areas not included in
the power generation plan of PLN, The IPPs must enter into a Power Purchase
Agreement (PPA) with the PLN. Also, IPPs that want to sell electricity directly to
the end consumer need to build their own power grid.
- 56 -
<Fig 32> Indonesian power industry sales structure
❍ As a general principle, IPP private companies are able to sell electricity only
through competitive bidding. However, in the case of electricity generation (small
hydro, geothermal, biomass, wind, solar heat), surplus electricity, If you supply, you
- 57 -
can directly designate without going through bidding.
- 58 -
3.3. Electric Power System / Supply / Development
❍ Indonesia PLN is a power supplier and is in charge of the construction, operation
and maintenance of transmission and distribution facilities. PLN has been
continuously developing the power supply system of the government, taking into
consideration the need for effective response to the increase of power generation
capacity and power generation And the total length of the transmission plan
operated as of 2013 reaches 828,283 km (including high / medium voltage grid).
❍ The main transmission system is divided into the islands of Sumatra, Sulawesi, and
Karimantan islands in Java and Bali, and is divided into Southeast and
South-eastern parts of Sulawesi and Karimantan. have. As the transmission
network is constructed on each island, it is a constraint factor of efficient power
management and power import and export through the grid connection with
neighboring countries is not done.
❍ The power loss rate fell from 17% to 18% in the early 2000s due to the aging of
the transmission forecast, but dropped to about 10.7% as of 2013 due to
investment in the transmission and distribution sector. The voltage of the
transmission system is 500 kV, 275 kV, 150 kV and 70 kV.
- 59 -
transmission network construction project will be implemented in Sumatra and
Java-Bali grid, and Kalimantan and Sulawesi will strengthen power grid
connection system.
- The expansion of the distribution plan will focus on improvement of supply
voltage, minimization of losses, and maintenance of the old system.
- 60 -
- The investment required to develop power infrastructure by 2020 is
approximately USD 96,205 mil. (USD 9,621 mil. Average per year), USD 67,815
mil. In terms of electricity production, USD 14,928 mil. To the transmission
facility, USD 13,461 mil. Is required for power distribution facilities.
- Following the transmission, substation and distribution system, the biggest
investment is power plant development.
- 61 -
❍ However, in 2013, the Indonesian government hiked electricity rates by 15% in
order to meet the rising fuel prices and the need to reduce subsidies to reduce the
budget deficit.
❍ In addition, although the 2014 budget allocated 0.8% of Indonesian GDP, there is a
need to increase the electricity bill. In accordance with the ministerial order of the
Minister of Mineral Resources and Energy of Indonesia, Announced in April 2014
the Minister of Energy and Mineral Resources. According to the announcement, the
regulations, signed by Minister of Mineral Energy, Jero Wacik, have been approved
by the Indonesian Parliamentary Mineral Energy Commission (Komsi VII DPR) for
industrial electricity tariff hikes (including adjustments) The main contents of No. 9
of 2014 are as follows.
Ÿ Electricity billing will be conducted for four classification codes that no longer
receive government subsidies as of October 1, 2013.
Ÿ Rupiah, exchange rate, inflation, and crude oil prices are factors that affect
electricity supply, and are not artificially controllable by the government.
- 62 -
Ÿ In accordance with the announcement of the Ministerial Decree, the existing
relevant provisions (the Ministerial Ordinance on Mineral Energy, No. 30,
2012) are no longer valid and have been abolished.
❍ The I-3 group refers to SMEs that use an intermediate voltage of 200 kWA or
more, and the I-4 group refers to a large company using high-voltage power of
30,000 kWA or more.
❍ Electricity prices for each customer in Indonesia are set differently depending on
the usage group. Electricity charges for each group announced by PLN in June 2015
are shown in the figure below. The most expensive electricity bill is IDR
1,661.01Rp, which is a high of USD 0.13 USD. The Indonesian government is
trying to eliminate electricity subsidies in the future and to raise electricity rates
by more than 10% in 2015.
- 63 -
<Table 15> Electricity bill for each group in Indonesia (June 2015, source: PLN)
- 64 -
3.5. Electric Power Supply Plan in Indonesia
❍ The Indonesian electric power supply plan is largely divided into a national power
plan established by the central government, a power supply plan established by the
PLN, and a regional power plan established by the local government.
Establis
DIVISION Unit Contents
hment
Ÿ Power demand and supply, investment and
National Central
financing, renewable energy use
Power Plan governm 10 year
Ÿ Expansion of new renewable energy ratio from
(RUKN) ent
current 4.9% to 17% by 2020
Power 10 year Ÿ Supply planning, demand forecasting, power
Power
construc (yearly generation, production and fueling and indexing
Supply Plan
tion readjust Ÿ Target of securing additional power of 57.3GW by
(RUPTL)
(PLN) ment) 2021
Ÿ Establishment based on RUKN
Regional Local Ÿ Strengthen the role of local governments in
Power Plan governm - determining permits and power tariffs
(RUKD) ent Ÿ Strengthen private-sector investment opportunities
in the power supply sector
<Table 16> Electric power supply plan in Indonesia
❍ In spite of the fact that the capacity of power generation facilities has been
expanded to include coal-fired power generation for the last five years, the share
of thermal power generation decreased from 82.1% to 78% due to the development
of new and renewable energy sources such as geothermal and hydroelectric power.
❍ By 2019, the PLN is planning to develop 10.2GW and 25.3GW through IPP, and the
power development capacity of IPP is 2.5 times that of PLN, which shows that the
- 65 -
Indonesian government's finances have deteriorated.
- 66 -
4. PV Market in Indonesia
4.1. Solar Power
❍ Indonesia has an average solar radiation of 4.8 kWh / m2 per day, which is
favorable for solar power generation. Although solar radiation varies across the
islands of Indonesia, international standards are considered favorable for solar
energy development and are considered a viable energy source for off-grid islands
and remote people
- 67 -
4.2. Photovoltaic Power Generation Status
❍ Currently installed capacity is about 80 MW, mostly off-grid solar home systems
or small-scale off-grid systems (mostly hybrid systems10) combined with
small-scale diesel plants)
❍ According to LAKIP KESDM 2015, the currently installed solar power plant is
about 85.2 MW, slightly higher than the planned 76.9 MW. This is due to the
construction of a 5 MW solar power plant in Kupang, East Nusa Tenggara.
- 68 -
❍ For this reason, solar power development will be conducted mainly in remote areas,
with the power generation ratio being low (less than 60%) in the eastern part of
Indonesia. In addition, solar energy is suitable as renewable energy that does not
increase the power generation cost compared with current power system
❍ In July 2013, DGNREEC released details of the bid for a total of 140 MW of
ongrid solar power plants in Indonesia's remote area (approximately 80). This is
due to the fact that in 2013, the MoEMR Regulation No. 17/2013 and DGNREEC
Regulation No.979.K / 29 / DJE / 2013. It is also known as the PV IPP structure
and is priced at USD 0.25 for a bidding project of 140 MWp. USD 0.30 / kWh FiT
applies (depending on domestic goods and service use)
❍ The Gorontalo power plant commenced operations in February 2016 and is operated
through PT Brantas Energy, a subsidiary of PT Brantas Abipraya (Persero). Sumba
Power Station is built by Conergy, PT Buana Surya Energi Persada and PT Indo
Utama Solutions
❍ MoEMR is the MoEMR Regulation No. MoMR Regulation No.19 / 2016 to replace
the 17/2013, which is expected to lead to more solar PV projects. It will also
support the 5,000 MW target announced in early 2016
- 69 -
Chapter 5. Field Analysis
1. Climatic Conditions
❍ Indonesia, which is adjacent to the equator, has an average daily radiation of 4.8
kWh / ㎡, which is a favorable climate for photovoltaic power generation. There is
no big difference by region, but there is a lot of solar radiation in the eastern part
where there is less pollution damage or air pollution.
❍ Local solar radiation and climate are not affected by typhoons, less influenced by
wind,
❍ Local climate is affected by the rainy season, so Sumatera Island and Surabaya
Island areas except Jakarta are suitable for solar irradiation.
❍ Among the two candadate sites in the Pesawaran area, Negri Katon Village was
selected because land slope is gentle and is located close to the power connection
- 70 -
point.
- Location of the site : (S 5°18‘06.56’‘, E 105°06’02.73‘’)
- Negerikatun, Negeri Katon, Kabupaten Pesawaran, Lampung 35353 Indonesia
<Fig 42> Location of Final Solar Power Plant: Negeri Katon Village
❍ Two candidate areas in Pesawaran area were received from the local government
KPBU (government and business cooperation) department.
- 71 -
- Candidate Site #1 Lumbi Rejo Village
Ÿ Jalan PT Gramer, Lumbi Rejo, Negeri Katon, Kabupaten Pesawaran, Lampung
35353 Indonesia
Ÿ S 5°18‘14.1336’‘ E 105°04’16.5576‘’
Ÿ It is decided that this area is not suitable because it is composed of reverse
slope terrain (southward) and it will cause excessive civil engineering cost
since it is about 2km away from power connection point (3 phase pole)
<Fig 44> Survey of the site #1 and its power connection point
- 72 -
<Fig 46> Power linkage site survey
❍ Equipment Installation
- Measurement equipment is installed near the final candidate site to collect
measurements and data such as rainfall, temperature, solar irradiation for 4
months.
- Measuring device was installed for loss prevention and easy management by the
help of local Pesawaran official, measuring instrument on the local village
headman’s roof of house, and Data loger in the village headman’s livingroom of
house (Unnamed Road, Negerikatun, Negeri Katon, Kabupaten Pesawaran,
Lampung 35353 Indonesia) (S 5°18‘06.56’‘, E 105°06’02.73‘’)
- 73 -
<Fig 47> Installation of measuring equipment in the final destination Negeri Katon village
- 74 -
❍ Measurement data collection and equipment dissemble (March 19, 2018)
- Conducted actual local data analysisFrom January 17, 2018 to March 21, 2018
Collected measured solar radiation, temperature, and rainfall data for about 2.5
months
- Disassemble measurement equipment
<Fig 48> Data confirmation and measurement equipment dissemble (March 19, 2018)
❍ In order to proceed with the project, domestic products such as solar modules,
inverters and electric appliances are used in domestic Hyundai and Hyosung
products, and solar photovoltaic structures are being built in the production
infrastructure.
❍ Local climate is affected by the rainy season, so Sumatera and Surabaya Island
areas except Jakarta are suitable for solar irradiation.
- 75 -
<Fig 49> PT. EST INT meeting and field survey (Nov. 2017)
❍ Held a meeting at the site to see if any local manufacturer can make the
structure(s)
- Evaluated the local engineer’s technical skills
- The number of local manufacturing workers was 15. Among which, there were
three electric engineers, four structure machine engineers, and the rest were
installation engineers.
- Their work experience was three years or more.
- PT EST was largely specialized in manufacturing, installing, and selling
refrigerator structures and electric devices.
- The area for the factory was 600 pyeong or so and judged to be appropriate for
manufacturing structures.
- 76 -
<Fig 50> Visits and Survey of Local Photovoltaic Manufacturers (March, 2018)
- 77 -
Chapter 6. Technical Analysis
1. General Design Criteria for Photovoltaic Systems
❍ PV power plant design plan
- Photovoltaic system design plan should choose a place without shade as a
principle of southward installation
- It is general to design with an inclination angle of about 25 ~ 35 degrees
considering installation condition and local terrain characteristics.
- It is important to determine the installation capacity relative to the area to be
installed, and it should be designed so as to minimize the generation of shadows
due to the generation of shadows when many modules are installed.
❍ Design Considerations
- Solar power generation system design is a complex design that needs to consider
civil engineering, structure, electricity,
- It is necessary to maximize the efficiency and business efficiency by further
reviewing the regulations by the local government before the design, availability
of grid linkage, confirmation of the occurrence of shading and various RISK items.
Process Consideration
Civil Design Cadastral map, installation area, cross section, etc.
Structure Design Array structure, wind pressure load, fixed load, etc.
Serial, parallel calculation, trunk line, connection board,
Electrical Desing
inverter etc.
Construction Design Electric room, etc.
<Table 19> Process-specific considerations
- The support of the solar power generation facility should be safe structure
- 78 -
against structural load and other vibration and shock including self weight, load
load, snow load, wind load etc.
- The connection between the support and the module-support is to be fastened
with a bolt. The cutting and welding parts (plated products only) must be
galvanized or coated with epoxy-zinc paint at least twice.
- Module support material
Ÿ Mild zinc or molten zinc - Aluminum - Magnesium alloy plated sections
Ÿ Stainless steel (STS)
Ÿ Aluminum alloy
- Use a module dedicated line or TFR-CV (one core, 1C) wire for wiring from the
module to the inverter. If the wires are installed or installed on the ground, take
extra measures to prevent damage to the sheath. You must take it.
- Each serial group of modules shall be composed of modules with the same
short-circuit current. When two or more solar cell series connected to one
inverter (MPPT, one multi-string, So that the output voltage and the output
current of the inverter circuit are equal to each other.
❍ Determine the inclination angle, incidence angle, and separation distance for the
array of PV modules
<Fig 51> Identify the latitude and longitude <Fig 52> Determining the separation
of the installation site distance between modules
- 79 -
Load Type Consideration
Wind pressure It is the most important load, calculated by the wind force coefficient,
load the design speed pressure and the flow area.
The weight of the main body of the base unit and the weight of the
Fixed load load such as the solar cell module to be loaded on the base unit and the
weight of the excretion material necessary for the array construction.
Earthquake Generally, it is smaller than the wind pressure load, but it is necessary
to be careful when it is used for the stand and the disaster prevention
load such as the street lamp etc.
(a) Vertical solar cell connection (b) Horizontal solar cell connection
<Fig 53> Shading loss of solar cell
- 80 -
according to the irradiation / temperature condition, the inverter needs MPPT
control to achieve maximum output and efficiency under all conditions.
❍ Analysis method
- The analytical method is on a monthly or weekly basis. The changes in rainfall
were analyzed depending on surrounding temperature and rainfall.
❍ Result
- Collected solar irradiation data according to temperature and precipitation for 4
months from November 15, 2017 to March 21, 2018, which is the rainy season
in Indonesia (October to March).
- 81 -
<Fig 55> Irradiance data for 5 months in Pesawaran area
- 82 -
Mean Mean rainfall Mean solar Mean solar
Month temperature irradiance radiation hour
(℃) (㎜) (w/㎡) (hr)
Nov. 2017 27.19 0.13 171 4.0
Dec. 2017 26.67 0.32 171 4.1
Jan. 2018 26.48 0.21 169 4.1
Feb. 2018 26.22 0.34 167 4.0
Mar. 2018 26.01 0.43 172 4.2
Total Average 26.48 0.29 170 4.1
<Table 21> Analysis of solar radiation data at installed area
❍ Monthly climatic data from Nov. 16, 2017 to Nov. 30, 2017 (15 days)
- The picture below represents the data on temperature and rainfall on a monthly
or weekly basis from Nov. 16, 2017 to Nov. 30, 2017 for one month.
- In analyzing ambient temperature, it was proven that the temperature was 35.1 ℃
max., 23.1 ℃ min., and 27.19 ℃ on average.
- For the rainfall, it was found that it ranged from 0.2 ㎜ min. to 11.2 ㎜ max.
- In analyzing the solar radiation, it was found that the radiation was 970 W/㎡
max. and 171 W/㎡ on average, and the solar radiation hour was 4.0 hr.
<Fig 56> Climatic conditions of the Pasawaran solar installation area (Nov. 2017)
❍ Monthly climatic data from Dec. 1, 2017 to Dec. 31, 2017 (one month)
- The picture below represents the data on solar radiation depending on
temperature and rainfall on a monthly or weekly basis from Dec. 1, 2017 to
- 83 -
Dec. 31, 2017 for one month.
- In analyzing ambient temperature, it was proven that the temperature was 35.1
℃ max., 22.3 ℃ min., and 26.67 ℃ on average.
- For the rainfall, it was found that it rained from 0.2 ㎜ min. to 25.4 ㎜ max.
- In analyzing the solar radiation, it was found that the radiation was 983 W/㎡
max. and 171 W/㎡ on average and the solar radiation hour was 4.11 hr.
<Fig 57> Climatic conditions of the Pasawaran solar installation area (Dec. 2017)
❍ Monthly climatic data from Jan. 1, 2018 to Jan. 31, 2018 (one month)
- The picture below represents the data on solar radiation depending on
temperature and rainfall on a monthly or weekly basis from Jan. 1, 2018 to Jan.
31, 2018 for one month.
- In analyzing the ambient temperature, it was proven that the temperature was
35.9 ℃ max., 21.6 ℃ min., and 26.48 ℃ on average.
- For the rainfall, it was found that it rained from 0.2 ㎜ min. to 30.4 ㎜ max.
- In analyzing the solar radiation, it was found that the radiation was 924 W/㎡
max. and 169 W/㎡ on average and the solar radiation hour was 4.05 hr.
- 84 -
<Fig 58> Climatic conditions of the Pasawaran solar installation area (Jan. 2018)
❍ Monthly climatic data from Feb. 1, 2018 to Feb. 28, 2018 (one month)
- The picture below represents the data on solar radiation depending on
temperature and rainfall from Feb. 1, 2018 to Feb. 28, 2018 for one month.
- In analyzing the ambient temperature, it was proven that the temperature was
33.5 ℃ max, 22.2 ℃ min., and 26.22 ℃ on average.
- For the rainfall, it was found that it rained from 0.2 ㎜ min. to 41.2 ㎜ max.
- In analyzing the solar radiation, it was found that the radiation was 1,022 W/㎡
max. and 167 W/㎡ on average and the solar radiation hour was 4.01 hr.
<Fig 59> Climatic conditions of the Pasawaran solar installation area (Feb. 2018)
- 85 -
❍ Monthly climatic data from Mar. 1, 2018 to Mar. 31, 2018 (one month)
- The picture below represents the data on solar radiation depending on
temperature and rainfall on a monthly basis from Mar. 1, 2018 to Mar. 21, 2018
for one month.
- In analyzing the ambient temperature, it was proven that the temperature was
35.0 ℃ max., 22.3 ℃ min., and 26.01 ℃ on average.
- For the rainfall, it was found that it rained from 0.2 ㎜ min. to 35 ㎜ max.
- In analyzing the solar radiation, it was found that the radiation was 1026 W/㎡
max. and 172 W/㎡ on average and the solar radiation hour was 4.21 hr.
<Fig 60> Climatic conditions of the Pasawaran solar installation area (Mar. 2018)
❍ Module spec
- Maker: Hyundai Heavy Industries Green Energy
- Nominal output (Pmpp): 335 W(Multi)
- Solar Cell Type: Muti 72 cells
- Array configuration: 16 sets serial, 186 sets parallel
- Array output: 9,986 kW(50 ℃)
❍ Inverter spec
- 86 -
- Maker: HYOSUNG
- Nominal output (Pmpp): 1,000 kWac· Q’ty: 10 sets
- Q’ty: 10 sets
❍ The loss rate is assumed on the premise that earth radiation loss is 3.3%, PV
modular connection, temperature, & wire connection loss 9.3%, inverter loss 2.3%
and entire loss rate 14.9%.
- 87 -
<Fig 62> PVSYST loss rate of the grid-connected system
- 88 -
<Fig 63> PVSYST power generation analysis of grid-connected power generation system
- 89 -
3.2. Analysis of power generation using local climatic data
❍ Conditions
- Data accumulated locally for 4 months (2017.11.15~2018.03.19)
- Solar radiation (radiation of the sun compared to the area = kWh/m2/day)
appears to be 4.1kWh on average. Despite the rainy season, the data is good.
- Solar radiation for dry season : 5.9kWh
- Entire solar radiation on average = 5.1kWh/m2/day (simulation analysis – good)
❍ PV module spec
- Maker: Hyundai Heavy Industries Green Energy
- Nominal output (Pmpp): 335 W(Mono)
- Solar Cell Type: Muti 72 cells
- Open Circuit Voltage(Voc) : 46.5 V
- Short Circuit Current (Isc) : 9.4A
- Voltage at Max. : 38.2V
- Current at Max. Power (Impp) : 8.8A
- Module Efficiency (%) : 17.1%
- Temp. Coefficients of Pmax : -0.42% / °C
- 90 -
<Fig 64> PV module spec
- 91 -
❍ Inverter spec
- Maker: HYOSUNG
- Rated Output Power : 1,000 kW
- Max Input Voltage: 1,000 Vdc
- MPP Range : 600 Vdc ∼ 850 Vdc
- Rated Input Voltage : 1,000 Vdc
- Max Input Current : 1,667 A
- Rated Output Voltage : AC 380 Vac(+10/-12%)
- Rated Output Current : 1,520 A
- Output Frequency : 60 Hz
- Max Efficiency: 98.1%
- 92 -
<Fig 66> 10MW photovoltaic system diagram
- 93 -
- Gross generation: 9,969.6 kWP
- Module specification: 335 WP, 72 cells, Multi
- Module installation q’ty: 29,760 ea
- Module Size: 1960 W × 998 L × 40 t
- Inverter specification: grid-connected, 10ea, 1000 kWP
- Array q’ty : 1,860 ea(18 serial, 1,060 parallel)
- Module angle of inclination: 10°, detergency considered (sun angle: 5° in summer
season, - 5° in winter season)
- 94 -
<Fig 69> 10MW PV transmission and distribution facility skeleton diagram #2
- 95 -
Ÿ L shape steel: SS400, hot dip galvanize, L-50 ㎜ × 50 ㎜ × 5 ㎜
Ÿ Basic Base Plate: SS400, hot dip galvanize
Ÿ Structure connecting support: SS400, hot dip galvanize
Ÿ Anchor: SS400, hot dip galvanize
Ÿ Bolt and nut : SS400, hot dip galvanize
❍ Structure Layout and 3D Modeling for each zone for 10MW PV system
- Modular angle of inclination: -20° ~ 20°
Ÿ It is good to install the modular angle of inclination according to the latitude
- 96 -
(latitude of this site is 5°), but the modular angle of inclination ranges from –
20° to 20° as the solar altitude moves from south ↔ north (from summer to
winter) at the PV stations. Thus it was designed to obtain the max.
generating efficiency by season by adjusting the angle by 5°. (angle of altitude
in summer 65° southward, angle of altitude in winter 73° northward at PV
stations in Indonesia)
- 97 -
0° 5° 10°
0° 5° 10°
- 98 -
Chapter 7. Environment Impact Assessment
1. Overview
❍ This EIA reprt is to provide foundation to sell the electricity produced at 10MW
solar photovoltaic power station, Pesawaran Regency, Indonesia to PT. PLN for
supply to Lampung Province.
2. Background
2.1. Geographic Environment
- 99 -
❍ Indonesia has an advantage for photovoltaic power generation at the average daily
solar radiation of about 4.8kWh/m2 as it is located around the equator.
- 100 -
3. Environment Impact Assessment Tasks
3.1. Progress
<Fig 74> Solar power plant scheduled for evaluation of environmental impact MAP
- 101 -
3.2. PV Plant Site(Geography)
- 102 -
3.3. Climate Characteristics: Precipitation, Atmospheric Pressure,
Wind speed & Duration of Sunshine
- The month with the highest rainfall was January, 456mm recorded, and the month
with the lowest precipitation was recorded at 52.9mm in June.
- The most frequent month was January to February, 20 days to rain, and the
lowest rain frequency to June was 6 days.
❍ The flora and fauna distribution around the solar power plant development
project areas was researched.
❍ It is judged that there will be no ecosystem damage resulted from the
- 103 -
<Table 24> Pesawaran Regency Atmospheric Pressure, Wind Speed & Duration of Sunshine
❍ Fauna distribution :
Ÿ Butterfly (Appias libythea)
Ÿ Sooty-headed bulbul bird (Pycnonotus aurigaster)
Ÿ Prenjak bird (Prinia familiaris)
Ÿ Ground pigeon (Coturnix coturnix)
Ÿ Snake (Oxyuranus microlepidotus)
Ÿ Dederuk bird (Spteptopelia bitorquata)
Ÿ Zebra dove (Geopelia striata)
❍ Data of Flood and Storm Disaster in Pesawaran Regency in 2013-2017. Given this
data, solar photovoltaic plans are all safe from blood and storm disaster.
- 104 -
Disaster Report 2016 Disaster Report 2017
<Table 25> Pesawaran Regency Disaster Report(2013 ~ 2017)
❍ Using the hand drill method two soil samples used for soil analysis were collected
research the constituents of soil, Analysis of whether soil bearing capacity can
support solar modules
- 105 -
❍ Sampling Position
(a) 1st soil sampling area (b) 2nd soil sampling area
<Fig 76> Soil sampling area map of PV plant site
❍ The soil support capacity of the preliminary area of the power plant was estimated
to be 164.70 tons at the maximum load of 2 x 2m2 in the soil of 3m depth.
Confirm there are no problems.
- 106 -
1st Sample 2nd Sample
<Fig 78> Soil sample component structure
- According to the classification of the soils, the primary soil samples consisted of
7.17% of gravel, 20.56% of sand and 72.27% of silt.
- The second soil sample consisted of 8.31% of gravel, 19.11% of sand and 72.58%
of silt.
❍ Water Content
- 107 -
❍ Gravity of Soil
❍ Sieve Analysis
- 108 -
❍ Atterberg Limit
- 109 -
with the Andonian water quality standards.
❍ The development of a solar power plant in a specific area will have a social impact
on the society around the solar power plant, except for the outlying areas where
the locals do not live much.
❍ An example of the positive impact of a solar power plant is the acceptance of the
community on the existence of a solar power plant that can create jobs and the
community can participate directly or indirectly in plant operation as a construction
or worker.
❍ While the negative impact of community rejection on the presence of solar power
plants.
❍ For example, conflicts between communities and the management of solar power
plants and conflicts between communities divided into pros and cons of the
presence of solar power plants are negatively affected.
❍ Therefore, to minimize these negative effects, the planned solar power plant
development in Tresno Maju village of Negri Katon Sub District of Pesawaran
Regency needs to involve surrounding communities at the planning stage.
❍ Involving the surrounding communities in the planning phase can prevent negative
- 110 -
<Table 27> Analysis of the composition of drinking water in Negri Katon solar power plant
area
problems in advance.
❍ The type of social impact that usually occurs at the pre-construction stage is the
employment creation for the community in Tresno Maju Village. Therefore, the
power plant construction management team should engage with local communities,
relevant organizations and stakeholders to discuss on the issues that may become
conflicts together.
- 111 -
<Table 28> Matrix for Social Impact Analysis
- 112 -
Chapter 8. Economic Feasibility
1. Key Points
❍ The economic analysis data provided hereafter is the result of Samduk Accounting
Corporation as a service provider who was contracted to carry out economic
feasibility of 10MW solar power plant project in Pesawaran Regency in Lampung
Provice, Indonesia.
❍ The economic feasibility study using the NPV method and the IRR method was
based on the information received from the Indonesian Persawaran Government in
advance and the contents of various laws and regulations related to renewable
energy in Indonesia.
NPV IRR
❍ The economic analysis used the financial plan and other data from the investment
plan and investment period (from June 30, 2018 to June 30, 2048) proposed by the
11) NPV(Net Present Value): NPV is one of the measures of business value (feasibility). If it is smaller than 0, it
has no feasibility (value). If it is larger than 0, it is a feasibility.
12) IRR(Internal Rate of Return): IRR is the interest rate that discounts the cash flow of a business during a
business period to the present value, so that the combined value is equal to the investment expenditure.
- 113 -
company without verification or additional confirmation, and did not carry out due
diligence on assets and liabilities.
❍ With the agreed procedures and assumptions provided for the economic feasibility
of the investment plan, the NPV is USD 364,875 and the IRR is 12.51%..
2. Prerequisites
❍ Basic prerequisites for reviewing the economic feasibility of the investment in this
project:
No 항 목 조 건
1 PPA Unit Price $0.0735(USD)/kWh
2 Annual Power Production Amount 17,155MWh/y
3 WACC13) 5.098%
4 Cost of equity in NPV 10.49%
❍ We will have a PPA contract with the government owned power company PT. PLN
(Perusahaan Listrik Negara) through series of PPA unit price negotiation with the
- 114 -
Ministry of Energy and Mineral Resources (ESDM) and PT. PLN.
❍ If the base production unit price (BPP: Biaya Pokok Penyediaan) in the region
exceeds the national average price, the electricity sales price produced by solar
power resource is limited to 85% of the base production price in the region.
❍ Since the BPP in Lampung Province is $0.0777(USD) which exceeds the national
average BPP which is $0.0739(USD), we will negotiate with PT. PLN and ESDM
during the bidding to set the BPP to $0.0735 that will ensure 100% compensation
for this project.
14) In 2017, Indonesia ESDM announced the Ministry Decree No 12/2017 on amendment of FIT for renewable
energy.
- 115 -
Page 6 BPP for Lampung $0.0777(USD) Page 8: National Average BPP $0.0739(USD)
<Fig 84> Indonesia Ministry of Energy and Mineral Resources on Renewable Energy
Resources(No 12/2017) (No 1401/2017)
❍ According to the latest regulation (No. 12/2017) of the Minister of Energy and
Mineral Resources of Indonesia concerning the use of renewable energy resources
for power supply, the cost of renewable energy production is limited.
- The new regulation on the price of power standard for renewable energy
resources was announced in Jakarta on January 30, 2017, and the new regulations
defines that different production unit prices are used based on the types of
resources such as solar, wind, hydro, biomass, and biogas.
- The regulation stipulates that electricity generated from renewable energy should
be sold and supplied to PT PLN Persero, an Indonesian energy state company,
and specifies guidelines for PLN to procure electricity from power plants using
renewable energy.
- If the base production price (BPP) in the region exceeds the national average
price, the electricity rate is limited to 85% of the rate through the system
applied to all renewable energy power plants. There are no restrictions if the
local BPP does not exceed the national average unit price.
- The government authorities of Indonesia are highly likely to grow the electric
power generation market using renewable energy sources and expect to lower the
- 116 -
electricity production cost using renewable energy sources.
page #1 Production Unit Price Act (No 12/2017) page #8 NRE Unit Price Regulation (85%)
<Fig 85> Ministry of Energy Mineral Resources Restricted Specification of Renewable Energy
Production Unit Price(No 12/2017)
<Table 31> Interpretation of the Ministry of Energy and Mineral Resources Act (No 12/2017)
(Filed by KOTRA 2017)
- 117 -
3.2. Annual Power Generation
<Fig 86> Solar irradiance of PV plant candidate site (Global Solar Atlas)
❍ Actual Data
- Based on actual data acquired using the measuring devices installed at the
- 118 -
cadidate site for 4 months, average solar radiation was calculated at 5.15 kWh/m2
/day, but not used as data for economic feasibility analysis.
- Actual data-based solar radiation is estimated to be 9.8% more than NASA solar
radiation data
- Vision Pro2 model of weather forecasting instrument by USA David Digital
- Actual data based irradiation time for the period (2017.11.15~2018.3.20): 4.1h
- Average sunlight time per day for 4 monts of measurement:: 5.9h
- Average annual irradiation time through simulation: 5.15h
- 119 -
n Risk free rate of return(Rf) = 2.161%
- Average annual return of 5-year government bonds(as of March 30, 2018)
- 120 -
3.4. Capital cost in NPV method
n Concept
❍ The net present value method (NPV) is a method of examining the economic
feasibility of an investment based on the company's future cash flow. It is a typical
analytical method, which is one of the most commonly used analytical techniques.
❍ The NPV Act reflects the future profitability of the company to be evaluated. It
can identify the future flow of profits, and can reflect the corporate environment at
the time of evaluation.
❍ Considering the temporal factors, we value the current cash flow more than the
future cash flow. The capital cost used as the discount rate is the minimum rate of
return for the investment. It is also a guideline to determine the capital structure
of future business by presenting the criteria for the future.
❍ In the end, it is theoretically the most reasonable evaluation method to evaluate the
intrinsic value of a company when considering the purpose of the business and the
purpose of investing in the business.
❍ NPV method is reflected in the investment decision based on the result calculated
by subtracting the investment amount from the present value of the investment. If
the NPV is larger than 0, the investment plan will be adopted. The same applies to
whether NPV is greater than zero.
- 121 -
Sales revenue
- Cost of sales, SG & A expenses
= Operating profit
+ Interest income
- Interest expense
= Pre-tax profit
- Income tax expense on pretax profit
+ Cost without cash outflow such as depreciation cost
❍ The value of the enterprise (the value of the equity capital and the value of the
other capital) is evaluated on the basis of the surplus cash flow of the capital
investor and is calculated by discounting the surplus cash flow of the capital
investor at an appropriate discount rate.
❍ The appropriate discount rate is the 'Weighted Average Cost of Capital' (WACC),
which reflects the required rate of return of shareholders and creditors, which is
the capital donor. This economic evaluation is based on the principle of applying the
cash flow for calculating the value of equity capital, since ultimately the value of
equity capital calculated should exceed the amount of equity capital procurement.
- 122 -
Ke=Rf + β ╫ {E(Rm) Rf)} + α
Rf : Risk-free rate of return
β : The relative risk of the investment relative to the overall market
portfolio (systemic risk)
E(Rm) Rf : Market risk premium(Systematic risk premium)
α : Specific Premium
- 123 -
interest rate from the KOSPI index average annual return of 11.26% from 1980
to March 31, 2018.
- The result of the cost of equity (discount rate) calculated by applying the above
factors to the CAPM model
❍ The IRR (Internal Revenue Law) is a method of determining the economic value of
an investment by applying the cash value of the time value of the money and the
cash flow in the same way as the NPV method. Therefore, the minimum ROI of the
IRR method is 10.49%.
❍ In this case, we compare the calculated IRR with the minimum rate of return
(Hurdle rate) that determines whether to invest or not. If the IRR exceeds the
minimum ROI, we believe the investment is economical.
❍ PF funding for this project will be made using the overseas business re-lending
program supported by Export-Import Bank of Korea (KEXIM).
- 124 -
<Fig 1> Overseas business finance loan structure
❍ There are three types of products in the first-tier financing. We will use the funds
for overseas business activation (Interbank TC Loan) for this project.
- 125 -
❍ As of May 31, 2018, the Korea Export-Import Bank of Korea has signed a credit
line of USD 200 million with the Export-Import Bank of Indonesia, so it is not
difficult to raise funds for this project.
❍ The cost of other capital will ultimately be taken into account for the net cash flow
- 126 -
for the economic evaluation of the investment. Therefore, it is necessary to make
assumptions about the borrowing condition. In order to invest in this project, we
plan to use the ex-bank financing of the Export-Import Bank (5-year grace period
15-year installment repayment). As a condition of lending to the Export-Import
Bank, the interest rate is usually determined by taking into account the amount of
risk added (the export-import bank's funding rate + the borrowing institution or
the risk of the project). Considering these requirements, the cost of other capital
for this project is 5%.
- 127 -
❍ The Indonesian Export-Import Bank confirmed that the discount rate for the bank
interest rate was 2% ~ 3%.
❍ The following statement is from Mr. Usman, the head of PPP program in the
Pesawaran Regency, which contains the price of the land and the total purchase
price.
<Fig 89> Mr. Opinion on land purchase by Usman (President of PPP @ Pesawaran)
- 128 -
- This assumes an estimated period of time considering the actual operating period
of the solar power plant, since the actual operating period of the solar power
plant can last for more than 30 years and the demand for long-term renewable
energy in Indonesia is expected to steadily increase.
4. Economic Analysis
4.1. Investment Plan
4.1.1. Investment Breakdown
❍ For the normal operation of the project, investment in tangible assets such as
building basic plant facilities and acquisition of land use rights should be
concurrently carried out. Total investment by each investor is as follows.
(unit: USD)
- 129 -
(*1) In the case of Power Inverters requiring reinvestment during the total estimated
period of 30 years, it is assumed that the same amount will be reinvested in June of
2026, June of 2034 and June of 2042, respectively, by applying the useful life of 8
years.
(*3) Assume that land is purchased in bulk. Assuming that the purchased land will
be transferred to the amount of 4,540,757 won, which is the end of the estimated
period, which is 4% increase per year. In this case, the total transfer of the PV
plant value can be shown, but it is assumed that the value is already reflected in the
land transfer price for conservative estimation.
(unit: USD)
구분 금 액
Land Cost ($/square meter) 10
square meter 140,000
Land Cost($) 1,400,000
<Table 37> Land cost
(unit: USD)
Item Equipment Price Depreciation method Life span
PV Modules 6,400,000 Straight-line method 20y
Power Inverters 800,000 Straight-line method 8y
- 130 -
Main Junction Box 240,000 Straight-line method 20y
Incoming Panel 800,000 Straight-line method 20y
Monitoring System 560,000 Straight-line method 20y
Structure Manufacturing 1,600,000 Straight-line method 20y
Electric Works 1,600,000 Straight-line method 20y
투자 전 프로젝트 개발비용 500,000 Straight-line method 20y
합 계 12,500,000
(*) Most equipment is assumed to be capable of continuous operation for 30 years through continuous maintenance management.
- 131 -
Power Inverters 100,000 100,000 100,000 100,000 100,000 100,000 100,000
Main Junction Box - - - - - - -
Incoming Penel - - - - - - -
Monitoring System - - - - - - -
Structure Manufacturing - - - - - - -
Electric Works - - - - - - -
Design & Engineering - - - - - - -
Sub-total 100,000 100,000 100,000 100,000 100,000 100,000 100,000
Financial Year 2046.12 2047.12 2048.06
PJT Year 28.5 29.5 30
PV Modules - - -
Power Inverters 100,000 100,000 50,000
Main Junction Box - - -
Incoming Penel - - -
Monitoring System - - -
Structure Manufacturing - - -
Electric Works - - -
Design & Engineering - - -
Sub-total 100,000 100,000 50,000
- 132 -
Financial Year 2018.12 2019.12 2020.12 2021.12 2022.12 2023.12 2024.12
PJT Year 0.5 1.5 2.5 3.5 4.5 5.5 6.5
Price(USD) 0.0735 0.0735 0.0735 0.0735 0.0735 0.0735 0.0735
Quantity(Kw) 8,577,500 17,069,225 16,983,450 16,897,675 16,811,900 16,726,125 16,640,350
Revenue(USD) 630,446 1,254,588 1,248,284 1,241,979 1,235,675 1,229,370 1,223,066
Financial Year 2025.12 2026.12 2027.12 2028.12 2029.12 2030.12 2031.12
PJT Year 7.5 8.5 9.5 10.5 11.5 12.5 13.5
Price(USD) 0.0735 0.0735 0.0735 0.0735 0.0735 0.0735 0.0735
Quantity(Kw) 16,554,575 16,468,800 16,383,025 16,297,250 16,211,475 16,125,700 16,039,925
Revenue(USD) 1,216,761 1,210,457 1,204,152 1,197,848 1,191,543 1,185,239 1,178,934
Financial Year 2032.12 2033.12 2034.12 2035.12 2036.12 2037.06 2038.06
PJT Year 14.5 15.5 16.5 17.5 18.5 19.5 20
Price(USD) 0.0735 0.0735 0.0735 0.0735 0.0735 0.0735 0.0838
Quantity(Kw) 15,954,150 15,868,375 15,782,600 15,696,825 15,611,050 15,525,275 7,719,750
Revenue(USD) 1,172,630 1,166,326 1,160,021 1,153,717 1,147,412 1,141,108 647,189
Financial Year 2039.06 2040.06 2041.06 2042.06 2043.06 2044.06 2045.06
PJT Year 21.5 22.5 23.5 24.5 25.5 26.5 27.5
Price(USD) 0.0942 0.0942 0.0942 0.0942 0.0942 0.0942 0.0942
Quantity(Kw) 15,353,725 15,267,950 15,182,175 15,096,400 15,010,625 14,924,850 14,839,075
Revenue(USD) 1,445,873 1,437,796 1,429,718 1,421,641 1,413,563 1,405,486 1,397,408
Financial Year 2046.06 2047.06 2048.06
PJT Year 28.5 29.5 30
Price(USD) 0.0942 0.0942 0.0942
Quantity(Kw) 14,753,300 14,667,525 7,270,900
Revenue(USD) 1,389,331 1,381,253 684,707
❍ Estimation of production
- Since July 2018 when the production is started, the annual production is
estimated as follows, assuming a 0.5% decrease in power generation efficiency
compared to the previous year.
- Based on the NASA data, the amount of solar radiation in the region is assumed
to be 4.7 hours.
- Assuming that the efficiency decrease by 0.5% compared to the previous year
will continue due to systematic management
(unit: USD)
Financial Year 2018.12 2019.12 2020.12 2021.12 2022.12 2023.12 2024.12
Pjt Year 0.5 1.5 2.5 3.5 4.5 5.5 6.5
Capacity kW 10,000 10,000 10,000 10,000 10,000 10,000 10,000
Irradiance(h) 4.70 4.70 4.70 4.70 4.70 4.70 4.70
Op. days(day) 182.5 365 365 365 365 365 365
Efficiency(%) 100.00% 99.50% 99.00% 98.50% 98.00% 97.50% 97.00%
Yield(Kwh) 8,577,500 17,069,225 16,983,450 16,897,675 16,811,900 16,726,125 16,640,350
Financial Year 2025.12 2026.12 2027.12 2028.12 2029.12 2030.12 2031.12
Pjt Year 7.5 8.5 9.5 10.5 11.5 12.5 13.5
Capacity kW 10,000 10,000 10,000 10,000 10,000 10,000 10,000
- 133 -
Irradiance(h) 4.70 4.70 4.70 4.70 4.70 4.70 4.70
Op. days(day) 365 365 365 365 365 365 365
Efficiency(%) 96.50% 96.00% 95.50% 95.00% 94.50% 94.00% 93.50%
Yield(Kwh) 16,554,575 16,468,800 16,383,025 16,297,250 16,211,475 16,125,700 16,039,925
Financial Year 2032.12 2033.12 2034.12 2035.12 2036.12 2037.12 2038.12
Pjt Year 14.5 15.5 16.5 17.5 18.5 19.5 20.5
Capacity kW 10,000 10,000 10,000 10,000 10,000 10,000 10,000
Irradiance(h) 4.70 4.70 4.70 4.70 4.70 4.70 4.70
Op. days(day) 365 365 365 365 365 365 182.5
Efficiency(%) 93.00% 92.50% 92.00% 91.50% 91.00% 90.50% 90.00%
Yield(Kwh) 15,954,150 15,868,375 15,782,600 15,696,825 15,611,050 15,525,275 7,719,750
Financial Year 2039.06 2040.06 2041.06 2042.06 2043.06 2044.06 2045.06
Pjt Year 21.5 22.5 23.5 24.5 25.5 26.5 27.5
Capacity kW 10,000 10,000 10,000 10,000 10,000 10,000 10,000
Irradiance(h) 4.70 4.70 4.70 4.70 4.70 4.70 4.70
Op. days(day) 365 365 365 365 365 365 365
Efficiency(%) 89.50% 89.00% 88.50% 88.00% 87.50% 87.00% 86.50%
Yield(Kwh) 15,353,725 15,267,950 15,182,175 15,096,400 15,010,625 14,924,850 14,839,075
Financial Year 2046.12 2047.12 2048.06
Pjt Year 28.5 29.5 30
Capacity kW 10,000 10,000 10,000
Irradiance(h) 4.70 4.70 4.70
Op. days(day) 365 365 182
Efficiency(%) 86.00% 85.50% 85.00%
Yield(Kwh) 14,753,300 14,667,525 7,270,900
n Operation expense
❍ Aggregate of operating expense
(unit: USD)
Irradiance(h) 2018.12 2019.12 2020.12 2021.12 2022.12 2023.12 2024.12
Op. days(day) 0.5 1.5 2.5 3.5 4.5 5.5 6.5
Efficiency(%) 15,000 31,500 33,075 34,729 36,465 38,288 40,203
Yield(Kwh) 30,000 61,800 63,654 65,564 67,531 69,557 71,644
Insurance 1,500 3,090 3,183 3,278 3,376 3,477 3,581
Depreciation 342,500 685,000 685,000 685,000 685,000 685,000 685,000
Total 389,000 781,390 784,912 788,571 792,372 796,322 800,428
Financial Year 2025.12 2026.12 2027.12 2028.12 2029.12 2030.12 2031.12
PJT Year 7.5 8.5 9.5 10.5 11.5 12.5 13.5
A&M 42,213 44,324 46,540 48,867 51,310 53,876 56,569
O&M 73,793 76,007 78,287 80,636 83,055 85,547 88,113
Insurance 3,688 3,799 3,913 4,030 4,151 4,276 4,404
Depreciation 685,000 685,000 685,000 685,000 685,000 685,000 685,000
Total 804,694 809,130 813,740 818,533 823,516 828,699 834,086
Financial Year 2032.12 2033.12 2034.12 2035.12 2036.12 2037.12 2038.12
PJT Year 14.5 15.5 16.5 17.5 18.5 19.5 20.5
A&M 59,398 62,368 65,486 68,761 72,199 75,809 79,599
O&M 90,756 93,479 96,283 99,171 102,146 105,210 108,366
Insurance 4,536 4,672 4,812 4,956 5,105 5,258 5,416
Depreciation 685,000 685,000 685,000 685,000 685,000 685,000 392,500
Total 839,690 845,519 851,581 857,888 864,450 871,277 585,881
- 134 -
Financial Year 2039.12 2040.12 2041.12 2042.12 2043.12 2044.12 2045.12
PJT Year 21.5 22.5 23.5 24.5 25.5 26.5 27.5
A&M 83,579 87,758 92,146 96,753 101,591 106,670 112,004
O&M 111,617 114,966 118,415 121,967 125,626 129,395 133,277
Insurance 5,578 5,745 5,917 6,095 6,278 6,466 6,660
Depreciation 100,000 100,000 100,000 100,000 100,000 100,000 100,000
Total 300,774 308,469 316,478 324,815 333,495 342,531 351,941
Financial Year 2046.12 2047.12 2048.06
PJT Year 28.5 29.5 30.0
A&M 117,604 123,484 64,829
O&M 137,275 141,393 72,818
Insurance 6,860 7,066 3,639
Depreciation 100,000 100,000 50,000
Total 361,739 371,943 191,286
- 135 -
Increase rate 5% 5% 5% 5% 5% 5% 5%
A&G(Yearly) 83,579 87,758 92,146 96,753 101,591 106,670 112,004
Month 12 12 12 12 12 12 12
A&G Estimation 83,579 87,758 92,146 96,753 101,591 106,670 112,004
Financial Year 2046.12 2047.12 2048.06
PJT Year 28.5 29.5 30.0
Investment 15,000,000 15,000,000 15,000,000
Ratio 0.20% 0.20% 0.20%
A&G 30,000 30,000 30,000
Increase rate 5% 5% 5%
A&G(Yearly) 117,604 123,484 129,658
Month 12 12 6
A&G Estimation 117,604 123,484 64,829
❍ O&M Expenses
- O & M Expenses is the cost associated with plant operation by a company who
is specialized in solar power plant maintenance.
- This maintenance cost is estimated to be 0.5% of the investment cost for the
first year of the project and 3% annual increase rate.
(unit: USD)
Financial Year 2018.12 2019.12 2020.12 2021.12 2022.12 2023.12 2024.12
PJT Year 0.5 1.5 2.5 3.5 4.5 5.5 6.5
Invement 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000
O&M rate 0.40% 0.40% 0.40% 0.40% 0.40% 0.40% 0.40%
O&M cost 60,000 60,000 60,000 60,000 60,000 60,000 60,000
Change rate 3% 3% 3% 3% 3% 3%
O&M(yearly) 60,000 61,800 63,654 65,564 67,531 69,557 71,644
Month 6 12 12 12 12 12 12
O&M estimate 30,000 61,800 63,654 65,564 67,531 69,557 71,644
Financial Year 2025.12 2026.12 2027.12 2028.12 2029.12 2030.12 2031.12
PJT Year 7.5 8.5 9.5 10.5 11.5 12.5 13.5
Invement 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000
O&M rate 0.40% 0.40% 0.40% 0.40% 0.40% 0.40% 0.40%
O&M cost 60,000 60,000 60,000 60,000 60,000 60,000 60,000
Change rate 3% 3% 3% 3% 3% 3% 3%
O&M(yearly) 73,793 76,007 78,287 80,636 83,055 85,547 88,113
Month 12 12 12 12 12 12 12
O&M estimate 73,793 76,007 78,287 80,636 83,055 85,547 88,113
Financial Year 2032.12 2033.12 2034.12 2035.12 2036.12 2037.12 2038.12
PJT Year 14.5 15.5 16.5 17.5 18.5 19.5 20
Invement 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000
O&M rate 0.40% 0.40% 0.40% 0.40% 0.40% 0.40% 0.40%
O&M cost 60,000 60,000 60,000 60,000 60,000 60,000 60,000
Change rate 3% 3% 3% 3% 3% 3% 3%
O&M(yearly) 90,756 93,479 96,283 99,171 102,146 105,210 108,366
Month 12 12 12 12 12 12 12
O&M estimate 90,756 93,479 96,283 99,171 102,146 105,210 108,366
Financial Year 2039.12 2040.12 2041.12 2042.12 2043.12 2044.12 2045.12
PJT Year 21.5 22.5 23.5 24.5 25.5 26.5 27.5
Invement 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000
O&M rate 0.40% 0.40% 0.40% 0.40% 0.40% 0.40% 0.40%
- 136 -
O&M cost 60,000 60,000 60,000 60,000 60,000 60,000 60,000
Change rate 3% 3% 3% 3% 3% 3% 3%
O&M(yearly) 111,617 114,966 118,415 121,967 125,626 129,395 133,277
Month 12 12 12 12 12 12 12
O&M estimate 111,617 114,966 118,415 121,967 125,626 129,395 133,277
Financial Year 2046.12 2047.12 2048.06
PJT Year 28.5 29.5 30.0
Invement 15,000,000 15,000,000 15,000,000
O&M rate 0.40% 0.40% 0.40%
O&M cost 60,000 60,000 60,000
Change rate 3% 3% 3%
O&M(yearly) 137,275 141,393 145,635
Month 12 12 6
O&M estimate 137,275 141,393 72,818
❍ Insurance
- Insurance is the cost of insurance premiums for stable PV power plant.
- This maintenance cost is estimated to be 0.5% of the investment cost for the
first year of the project and 3% annual increase rate.
(unit: USD)
Financial Year 2018.12 2019.12 2020.12 2021.12 2022.12 2023.12 2024.12
PJT Year 0.5 1.5 2.5 3.5 4.5 5.5 6.5
Investment 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000
Insurance rate 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
Premium 3,000 3,000 3,000 3,000 3,000 3,000 3,000
Change rate 3% 3% 3% 3% 3% 3%
Insurance(year) 3,000 3,090 3,183 3,278 3,376 3,477 3,581
Month 6 12 12 12 12 12 12
Estimate 1,500 3,090 3,183 3,278 3,376 3,477 3,581
Financial Year 2025.12 2026.12 2027.12 2028.12 2029.12 2030.12 2031.12
PJT Year 7.5 8.5 9.5 10.5 11.5 12.5 13.5
Investment 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000
Insurance rate 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
Premium 3,000 3,000 3,000 3,000 3,000 3,000 3,000
Change rate 3% 3% 3% 3% 3% 3% 3%
Insurance(year) 3,688 3,799 3,913 4,030 4,151 4,276 4,404
Month 12 12 12 12 12 12 12
Estimate 3,688 3,799 3,913 4,030 4,151 4,276 4,404
Financial Year 2032.12 2033.12 2034.12 2035.12 2036.12 2037.12 2038.12
PJT Year 14.5 15.5 16.5 17.5 18.5 19.5 20
Investment 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000
Insurance rate 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
Premium 3,000 3,000 3,000 3,000 3,000 3,000 3,000
Change rate 3% 3% 3% 3% 3% 3% 3%
Insurance(year) 4,536 4,672 4,812 4,956 5,105 5,258 5,416
Month 12 12 12 12 12 12 12
Estimate 4,536 4,672 4,812 4,956 5,105 5,258 5,416
Financial Year 2039.12 2040.12 2041.12 2042.12 2043.12 2044.12 2045.12
PJT Year 21.5 22.5 23.5 24.5 25.5 26.5 27.5
Investment 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000 15,000,000
Insurance rate 0.02% 0.02% 0.02% 0.02% 0.02% 0.02% 0.02%
Premium 3,000 3,000 3,000 3,000 3,000 3,000 3,000
- 137 -
Change rate 3% 3% 3% 3% 3% 3% 3%
Insurance(year) 5,578 5,745 5,917 6,095 6,278 6,466 6,660
Month 12 12 12 12 12 12 12
Estimate 5,578 5,745 5,917 6,095 6,278 6,466 6,660
Financial Year 2046.12 2047.12 2048.12
PJT Year 28.5 29.5 30.0
Investment 15,000,000 15,000,000 15,000,000
Insurance rate 0.02% 0.02% 0.02%
Premium 3,000 3,000 3,000
Change rate 3% 3% 3%
Insurance(year) 6,860 7,066 7,278
Month 12 12 6
Estimate 6,860 7,066 3,639
Corporate tax 0 0 0 0 0 0 0
- 138 -
Interest expense (280,000) (240,000) (200,000) (160,000) (120,000) (80,000) (20,000)
Interest expense 0 0 0 0 0 0 0
Interest expense 0 0 0
- 139 -
Interest rate(**) 5% 5% 5% 5% 5% 5% 5%
Month 12 12 12 12 12 12 12
Interest expense 560,000 520,000 480,000 440,000 400,000 360,000 320,000
Financial Year 2032.12 2033.12 2034.12 2035.12 2036.12 2037.12 2038.06
PJT Year 14.5 15.5 16.5 17.5 18.5 19.5 20
Basic principal 5,600,000 4,800,000 4,000,000 3,200,000 2,400,000 1,600,000 800,000
Repayment(*) (800,000) (800,000) (800,000) (800,000) (800,000) (800,000) (800,000)
Final principal 4,800,000 4,000,000 3,200,000 2,400,000 1,600,000 800,000 0
Interest rate(**) 5% 5% 5% 5% 5% 5% 5%
Month 12 12 12 12 12 12 6
Interest expense 280,000 240,000 200,000 160,000 120,000 80,000 20,000
<Table 47> Annual Interest Cost
- 140 -
PJT Year 28.5 29.5 30
Pre-tax profit/loss 1,279,434 1,293,094 681,601
Carryover 0 0 0
Taxable income 1,279,434 1,293,094 681,601
Corporate tax rate 25% 25% 25%
Corporate tax 319,859 323,273 170,400
❍ Interest income
- Interest income reflects the increase in interest earned through deposits in
financial institutions. It is assumed that the deposit interest rate of 3% will be
maintained conservatively because the interest rate on Indonesian deposits is 4%.
- Assuming that the deposit balance, which is the basis for calculating interest
income, is the same as the average and ending balance.
(unit: USD)
- 141 -
Average balance 1,232,512 2,224,311 3,226,597 4,239,363 5,262,595 6,296,266 7,340,336
Interest rate 3.0% 3.0% 3.0% 3.0% 3.0% 3.0% 3.0%
Month 12 12 12 12 12 12 12
Interest income 36,975 66,729 96,798 127,181 157,878 188,888 220,210
Financial Year 2046.06 2047.06 2048.06
PJT Year 28.5 29.5 30
Basic principal 7,864,965 8,924,540 9,994,361
Final principal 8,924,540 9,994,361 15,096,319
Average balance 8,394,753 9,459,451 12,545,340
Interest rate 3.0% 3.0% 3.0%
Month 12 12 12
Interest income 251,843 283,784 188,180
❍ The year-on-year cash flow calculated considering current net income, depreciation
expense, investment spending, and borrowing fluctuation is as follows:
(unit: USD)
- 142 -
Debt 0 0 0 0 0 0 0
Debt repayment (800,000) (800,000) (800,000) (800,000) (800,000) (800,000) (800,000)
FCF (73,799) (47,413) (20,496) (19,008) (812,044) (646) 19,920
Financial Year 2037.12 2038.12 2039.12 2040.12 2041.12 2042.12 2043.12
PJT Year 19.5 20.5 21.5 22.5 23.5 24.5 25.5
NI 155,755 531,608 886,556 897,042 907,528 918,005 928,459
Depreciation cost 685,000 392,500 100,000 100,000 100,000 100,000 100,000
Investment 0 0 0 0 0 0 0
expenditure
Land sale 0 0 0 0 0 0 0
Debt 0 0 0 0 0 0 0
Debt repayment (800,000) (800,000) 0 0 0 0 0
FCF 40,755 124,108 986,556 997,042 1,007,528 1,018,005 1,028,459
Financial Year 2044.12 2045.12 2046.12 2047.12 2048.6 0 0
PJT Year 26.5 27.5 28.5 29.5 30 0 0
NI 938,882 949,258 959,575 969,821 511,201 0 0
Depreciation cost 100,000 100,000 100,000 100,000 50,000 0 0
Investment 0 0 0 0 0 0 0
expenditure
Land sale 0 0 0 0 4,540,757 0 0
Debt 0 0 0 0 0 0 0
Debt repayment 0 0 0 0 0 0 0
FCF 1,038,882 1,049,258 1,059,575 1,069,821 5,101,957 0 0
❍ Key assumptions
- Cash flow assumptions: Based on the yearly cash flow (FCF) estimates described
in the previous section.
- Discount rate: Capital cost 10.49% applied
- Total investment amount: USD 15,000,000
- Investment fund source: Equity capital USD 3,000,000 (20%) + Other capital
USD 12,000,000 (80%)
- Estimated duration:
Ÿ PPA production period (20years)(2018.7.1~2038.6.30)
Ÿ Commercial production period (10years)(2038.7.1~2048.6.30)
- Cash flow after investment period: Assuming no additional cash flow
- 143 -
❍ Economic Feasibility Review Conclusion
- In making this investment decision, NPV is USD 364,875, which is the total
investment amount of USD 3,000,000 or more of total investment amount, which
means that if the capital cost is 10.49%, the the positive net cash flow is
expected.
- Therefore, it is expected that the economic value of this investment decision will
exist because the net present value (NPV) of the investment exceeds the net
present value zero (0).
(unit: USD)
- 144 -
4.4. Results of the economic feasibility study based on IRR method
- 145 -
❍ IRR calculation result
- The discount rate IRR at which the net present value (NPV) becomes zero is
calculated as 12.51%.
❍ The value of equity capital under the NPV law can be most sensitive to the
discount rate and the rate of change in land prices at the end of the estimated
period. In particular, since the value of land price sale includes the value of using
existing PV facilities, this value is reflected in the land price, which is reflected as
a key sensitivity factor.
❍ The results of the analysis of the value of equity and NPV sensitivity in the
investment based on the above two major variables are as follows.
[NPV in investment]
Annual Discount rate
average rate
of increase 8.49% 10.49% 12.49%
in land
3.00% 840,829 307,565 (22,782)
4.00% 939,965 364,875 10,676
5.00% 1,070,977 440,613 54,893
<Table 56> Sensitivity of discount rate
- 146 -
Appendix
Original
Item of Amount used Balance Percentage of Reasons for
intention
Particulars (thousand (thousand use
expenditure (thousand fluctuation
won) won) (% )
won)
Base material,
48,000,000 45,593,493 2,406,507 95.0
facility/service cost
Material cost - - - -
technical intelligence
25,325,000 25,348,368 -23,368 100.1
activity cost
Indirect
Indirect cost - - - -
expense
※ You are permitted to indicate any changes in the amount used, compared to the original intention in
‘Reasons for fluctuation’ above clearly or in a separate form.
- 147 -
1. This Report is the final report of the New and Renewable Energy