10000103689-PDC-000
TABLE OF CONTENTS
1. PURPOSE .......................................................................................................................................... 4
2. DEFINITIONS ..................................................................................................................................... 4
3. RESPONSIBILITY ............................................................................................................................. 4
This document contains Aker Solutions legal entity proprietary and confidential information that is legally privileged and is intended
only for the person or entity to which it is addressed and any unauthorised use is strictly prohibited. It is provided for limited purpose
and shall not be reproduced, stored electronically, transferred to other documents, disseminated or disclosed to any third parties
without the prior written consent of the relevant Aker Solutions legal entity. Any attachments are subject to the specific restrictions and
confidentiality regulations stated therein and shall be treated accordingly. The document is to be returned upon request and in all
events upon completion of use for which it was provided.
Document: 10000103689-PDC-000
Supplier Documentation Specification Version: 10 - Re-issued Constr
Issue date: 2014.11.25
Global DM Procedure Page: 2 of 21
2. ADDITIONAL ATTACHMENTS....................................................................................................... 21
A1 Supplier Master Document List (SMDL).......................................................................................... 21
A2 Cover sheet ..................................................................................................................................... 21
A3 Manufacturing Record Book, Table of contents .............................................................................. 21
Document: 10000103689-PDC-000
Supplier Documentation Specification Version: 10 - Re-issued Constr
Issue date: 2014.11.25
Global DM Procedure Page: 4 of 21
1. PURPOSE
This global specification defines the administrative requirements for documentation submitted by
SELLER on the basis of a purchase order, frame agreement or contract placed by Aker Solutions
(hereby referred to as BUYER).
2. DEFINITIONS
Abbreviation Definition
BUYER The company stated as such in the Purchase Order Form or its successors or
permitted assigns, also called “Aker Solutions”
CLIENT A third party with whom BUYER has a contract to provide the WORK
DC Document Control
(used throughout this specification for BUYER’s Document Control)
FTP File Transfer Protocol
MDRL Material Documentation Requirements List
MIR Material Information Requirements
MRB Manufacturing Record Book
PO Purchase Order
SELLER The company or person stated as such in the PURCHASE ORDER Form or its
successors or permitted assigns, also referred to as “supplier”
SDRL Supplier Document Requirements List
SMDL Supplier Master Document List
3. RESPONSIBILITY
SELLER shall comply with the requirements given in this specification with regards to production
and submission of documentation.
Note:
In case the SELLER does not comply with the instructions given in this specification, the
documents will be put on hold until the issues have been sorted out.
Document: 10000103689-PDC-000
Supplier Documentation Specification Version: 10 - Re-issued Constr
Issue date: 2014.11.25
Global DM Procedure Page: 5 of 21
Generic documents are to be submitted only once to BUYER (per revision), regardless of number
of purchase orders, sales orders or projects. This is to ensure a one-to-one relationship between
the SELLER’s document and the entry in BUYER’s document system. In cases where the generic
document is not suitable for a PO, a new document shall be issued to BUYER covering the scope
of the current PO.
If the generic document is not approved by BUYER (or CLIENT), SELLER will have to either:
Generic documents shall not be submitted with BUYER specific cover sheet (attachment A2),
unless key information is not available in the document itself (see chapter 8 for more info).
Note:
SELLER shall wait for approval of the generic document before commencing production or other
related activities for the current PO.
Document: 10000103689-PDC-000
Supplier Documentation Specification Version: 10 - Re-issued Constr
Issue date: 2014.11.25
Global DM Procedure Page: 6 of 21
6. NAMING CONVENTION
The SELLER shall use logical document names for the documents submitted. The title for
documents submitted to BUYER typically consists of 3 document title lines.
Description Content
Document title line 1 Describes the document type and content. Examples would be “FAT
procedure”, “Wiring diagram”, “Weight certificate”, etc.
Document title line 2 Describes which product the document is referring to (if applicable).
Examples would be “Hybrid penetrator”, “Subsea Control Module”,
“Expanding Gate Valve”, etc.
Document title line 3 Additional information about document or material.
Note:
Due to an ongoing system upgrade, SELLER will receive either a requirement for an SMDL or an
MDRL. It will be specified in the PO which system to use. This is an interim solution and the end
goal would be to use the MDRL approach for all POs.
Chapter 7.1 will only be applicable for those orders with the SMDL requirement, while chapter 7.2
is only applicable for orders with an MDRL attached. For easy reference, the SMDL and MDRL will
only be referred to as “document list” throughout this specification.
The SMDL shall be issued in accordance with the delivery requirements given in the SDRLs, but no
later than 10 working days after the issue date of the PO.
Note:
Purchase orders requiring only a single CoC do not need an SMDL. Information about this will be
available in the PO.
Document: 10000103689-PDC-000
Supplier Documentation Specification Version: 10 - Re-issued Constr
Issue date: 2014.11.25
Global DM Procedure Page: 7 of 21
The MDRL shall be issued in accordance with the delivery requirements given in the MDRL itself,
but no later than 10 working days after the issue date of the PO.
A guideline for how to read and complete the MDRL is found in appendix 2.
8. INFORMATION REQUIREMENTS
All documents delivered by SELLER to BUYER shall meet the minimum requirements for
information related to identification and registration of the documents.
The information shall be identified on the first page of the document provided by SELLER.
Documents not meeting this requirement will be returned to SELLER for correction.
Documents of administrative and generic character shall have the following information available:
SELLER document number
SELLER document revision
Revision date
Equivalents of “Made by”, “Checked by” and “Approved by”
The SELLER shall only utilize the cover sheet (attachment A2) provided by BUYER for documents
not meeting the minimum requirements for information. Information on how to fill in the cover sheet
is found in appendix 3
Note:
Cover sheets shall not be used for document lists or drawings.
Drawings produced by SELLER are considered generic unless they are in status as-built. There
shall not be any BUYER specific information included on the drawing unless it is clearly mentioned
in the PO or any other attachment to the PO.
Receipt acknowledgment of the documentation will be done by means of returning an e-mail with a
statement that the documentation was received by BUYER. If no such acknowledgement is
received within 2 working days, there is no guarantee that the document has been received
successfully. In such cases, please contact BUYER for verification.
Documentation submitted through e-mail cannot exceed 25MB per e-mail. Documentation which is
larger than 25MB needs to be submitted through FTP. Access to BUYER’s FTP is granted by
contacting BUYER.
Note:
Paper copies will not be handled by BUYER. All official documentation shall always be submitted in
electronic format through the formal interface stated in BUYER’s “Administrative Requirements”
(10000109640/10000228239).
The PDF format shall be in compliance with ISO 19005-1, ISO 19005-2 or ISO 19005-3 – the
PDF/A standard.
SELLER is allowed to submit completed documents at any time, but no later than the agreed
timeframe according to the document list. SELLER does not need BUYER’s document number
prior to submitting the documentation.
The content and bookmarks of the MRB shall be in accordance with the agreed MRB table of
contents. The MRB table of content is a separate document, which shall be included in the
document list and submitted to BUYER (if specified in the initial document requirements).
Note:
All MRBs shall include a table of contents, regardless of the requirement for a separate table of
contents to be submitted.
Subsequent issues shall be “Re-issued for Acceptance” until the documentation achieves
acceptance code 1. The content of the last accepted revision shall reflect the true status of the
components/delivery or process.
BUYER will not revert with an acceptance code on documents submitted for information unless
major discrepancies are found in documentation. BUYER has the right to revert with comments to
documents submitted for information at any time during PO execution.
In certain cases BUYER will require a new version from SELLER when a document is voided. This
will however be communicated to SELLER at that point.
SELLER shall notify BUYER on completion of the retained documentation. The PO is not
considered complete until this notification has been given and acknowledged by BUYER. Retained
documentation might also be a part of a Quality Surveillance inspection or requested by BUYER to
be submitted at any time after the document completion date.
Textual documents which are revised shall have all changes marked with a 1-mm wide vertical line
in the left-hand margin. A summary of the changes shall be added at the end of the document.
Changes in the document list shall be marked with a yellow cell background. In addition the
document list has a separate comment tab which shall be used to communicate changes to
BUYER.
When the document list is revised by SELLER, the latest returned revision from BUYER shall be
used by SELLER to update the document list. This is to ensure that information added to the
previous revision by BUYER is included in the new revision of the document list.
Document: 10000103689-PDC-000
Supplier Documentation Specification Version: 10 - Re-issued Constr
Issue date: 2014.11.25
Global DM Procedure Page: 11 of 21
BUYER will not return any documents signed or stamped after review. BUYER will only return a
transmittal stating the official acceptance. The transmittal and comments will only be returned to
the original sender at SELLER.
Note:
BUYER’s acceptance of SELLER documents does not constitute approval in the sense that
BUYER assumes responsibility for the correctness of the content, conformance with stated
requirements, nor does it constitute permission to deviate from order requirements.
Document: 10000103689-PDC-000
Supplier Documentation Specification Version: 10 - Re-issued Constr
Issue date: 2014.11.25
Global DM Procedure Page: 12 of 21
12. REFERENCES
BUYER document Document title
number
10000109640 Administrative Requirements for Major Purchase Orders
13. CHANGES
Rev. Change
10 Requirement for cover sheet removed and requirement for information implemented
Note:
The SDRL is a document type list and is not necessarily identifying the specific number of
documents to be submitted for the PO.
2. REVISION HANDLING
Changes in submission dates and new revisions of documents already on the document list do not
trigger a new revision of the document list.
C5 Supplier Mandatory. SELLER’s 6 digit identification code and 101214 ACME Ltd.
company name.
F3 Supplier doc. no. Mandatory. SELLER’s own internal document number 14-DL08491
identifying the SMDL.
C Initial revision Where applicable. SELLER’s relevant revision for Whatever revision
the document listed. The field shall only be system used by
populated for generic documents. SELLER
D Document title, Mandatory. The title of the document describing Heat Treatment
line 1 what kind of document it is. Procedure
E Document title, Where applicable. Shall be used to describe the Lubricator Valve
line 2 product ordered for verification documents (refer
chapter 5).
G Information type Mandatory. Reference to which information type(s) A07, A08, C05, W10
code the document covers. Multiple entries shall be
separated with comma.
H PO item number Mandatory. Reference to the actual purchase 10, 30, 50-80, 120-150
order item line(s) the document relates to. Multiple
entries shall be separated with comma, or add
them by using a “from-to” format and separate
them with a dash.
Note:
In case of planned split deliveries of a PO item, verification documents for each delivery shall be
identified on the document list.
If the SELLER unexpectedly submits documents (same type as already defined on the document
list) for a partial order, BUYER’s Document Control will plan for the extra documents and no update
to the document list is needed. BUYER’s Document Control will inform SELLER about the added
documents by returning the latest document list including the new documents.
M Material revision Where applicable. The material revision for the 03, 01
above referenced material(s).
C SMDL revision Mandatory. Revision of the SMDL at the time the A, B, C etc.
comment was made.
D Company Mandatory. Defines which company has made the Aker Solutions
comment. SELLER’s name
E Originator Mandatory. Name of the person who made the Ema Nymton
comment.
3. EXPLANATION OF COLUMNS
Column Name Description Action for SELLER
C PO Items PO items which the documents relates to. For information only
D PO Items Material Material numbers the documents relate to. For information only
No.
F Document Title The title of the document. Shall match the title Check and update
printed on the actual document. document title
Document: 10000103689-PDC-000
Supplier Documentation Specification Version: 10 - Re-issued Constr
Issue date: 2014.11.25
Global DM Procedure Page: 18 of 21
K Info Type Code for the specific document type. For information only
M LCI Specifies whether the document will be subject for For information only
BUYER’s client review.
N Reviewer Defines who should review the document at For information only
BUYER.
Reason for issue Specifies for which action the document is released. “Issued for
acceptance”
“Issued for
information”
“Issued for void”
Field Description
Serial / Bach number Either serial number or batch number according to the traceability code for the
specific material. Batch numbers are referring to the SELLER’s production
batch and not deliveries. This shall be the exact same numbers as
stamped on the goods. The serial/batch numbers shall be in accordance with
the instructions given in the “Traceability Specification for Suppliers”
(10000108841).
Document: 10000103689-PDC-000
Supplier Documentation Specification Version: 10 - Re-issued Constr
Issue date: 2014.11.25
Global DM Procedure Page: 20 of 21
Field Description
Document title Title of the document. Shall be identical with the title provided in the document
list and according to the naming convention as stated in chapter 6.
Document number SELLER’s own document number. Shall be in accordance with the information
given in the document list.
Open section left of Empty area set aside for BUYER’s QS inspectors or external inspection
SELLER’s name / logo field. companies.
Document: 10000103689-PDC-000
Supplier Documentation Specification Version: 10 - Re-issued Constr
Issue date: 2014.11.25
Global DM Procedure Page: 21 of 21
2. ADDITIONAL ATTACHMENTS
A1 Supplier Master Document List (SMDL)
A2 Cover sheet
A3 Manufacturing Record Book, Table of contents
1 of 2
SUPPLIER MASTER DOCUMENT LIST
SMDL v1.5
Information to be verified/completed by supplier Traceability Information To be completed by Aker Solutions Reserved for client
Relevant Information type Action/ Sub-supplier document Material Sub-assembly material Aker Solutions Document entry Project document Client document Notes from Aker
Supplier document number Document title, line 1 Document title, line 2 Document title, line 3 PO item number Initial submission date Material number Responsible reviewer Network/ activity code Notes from client
revision code Reason for issue number revision number document number accepted number number Solutions
:END
2 of 2
SUPPLIER MASTER DOCUMENT LIST
Comments
SMDL Supplier document Aker Solutions
Date Company Originator Document title Revision Information type code Comment
revision number document number
Issue date Reason for issue Made by Checked by Approved by
TRACEABILITY INFORMATION
DOCUMENT DATA
Document title:
[logo / name]
Supplier:
This index shall be compiled according to the given SDRL in the Purchase Order. If certain
sections are not applicable they are required to be listed as N/A.