You are on page 1of 1

Chapter no 10 Internal Business Process performance

1- Throughput Time = PIMQ = Process + Inspection + Move + Queue


= 2.8 + 0.5 + 0.7 + 4.0
=8
2- MCE = Process Time/TPT = 2.8/8
= 0.35
3- NVAA = 1 – MCE = 1 – 0.35 = 0.65*100 = 65%
4- TPT + wait time = 8 + 16 = 24
5- MCE = PT/TPT
TPT = PIMQ
PIM = 2.8 + 0.5 + 0.7 =
TPT hat = 4
MCE hath = PT/TPT hath = 2.8/4 = 0.7