Professional Documents
Culture Documents
: 00
ELV System Date of Issue: 25.01.09
TABLE OF CONTENTS
1 INTRODUCTION................................................................................................................... 2
2 PREREQUISITES TO PROCEDURE......................................................................................... 2
2.1 INSTALLATION & CABLING........................................................................................... 2
2.2 PERMANENT POWER.................................................................................................. 2
2.3 MCC COMMISSIONING............................................................................................... 2
2.4 EQUIPMENT COMMISSIONING......................................................................................2
2.5 AIR & WATER BALANCING.......................................................................................... 2
3 DESIGN PARAMETERS........................................................................................................ 3
3.1 SPECIFICATION REFERENCE.......................................................................................3
4 REFERENCE DOCUMENTS/DRAWINGS..................................................................................3
4.1 SEQUENCE OF OPERATION......................................................................................... 3
4.2 DATA POINT SCHEDULE.............................................................................................. 3
5 PRE START CHECKS/PRE-COMMISSIONING..........................................................................3
5.1 PRECOMMISSIONING................................................................................................... 3
6 COMMISSIONING/TEST PROCEDURES...................................................................................4
6.1 POWER-UP CONTROLLER........................................................................................... 4
6.2 DOWNLOAD SOFTWARE AT CONTROLLER....................................................................4
6.3 CONNECT FIELD WIRING AT DDC CONTROLLER & CHECK...........................................4
6.4 SEQUENCE OF OPERATION CHECK.............................................................................5
6.5 NETWORK CHECK...................................................................................................... 5
7 INTERFACE PROCEDURE..................................................................................................... 6
8 DOCUMENTATION............................................................................................................... 6
8.1 COMMISSIONING TEST SHEETS ( SEE ATTACHEMENT)...................................................6
9 DEMONSTRATION PROCEDURES.......................................................................................... 6
10 INSTRUMENTATION............................................................................................................. 7
10.1 MULTIMETER & LAPTOP FOR DDC SOFTWARE DOWNLOADING......................................7
10.2 CALIBRATION............................................................................................................. 8
11 STAFFING........................................................................................................................... 8
11.1 RESPONSIBILITIES...................................................................................................... 8
12 SAFETY ASPECTS & PERMIT TO WORK REQUIREMENTS.......................................................9
12.1 SAFETY RULES DURING TESTING:...............................................................................9
12.2 SAFETY LIGHTING...................................................................................................... 9
12.3 EMERGENCY ARRANGEMENTS....................................................................................9
13 ATTACHMENTS................................................................................................................. 10
13.1 Commissioning Report...........................................................................................10
METHOD STATEMENT FOR Rev.: 00
ELV System Date of Issue: 25.01.09
1 Introduction
This document covers the installation ,commission and testing of the ELV system at
Jumeirah Lake Tower at Plot F1.
2 Prerequisites to Procedure
2.1 Installation & Cabling
3 Design Parameters
3.1 Specification Reference
3.1.1 Approved Engineering Submittal.
3.1.4 Specifications.
4 Reference Documents/Drawings
4.1 Sequence of operation
5.1.1 Installation
5.1.2 Cabling
Check all field instruments cable for end-to-end continuity, breaks and
shorts before termination at field instruments.
Check all field instruments for correct number of cables as mentioned
in Cable Schedule given by Honeywell.
Check all field instruments for correct wiring termination of field
instruments as instructed in the installation details.
Check all field instruments for dressing, ferruling and crimping of
wiring of field instruments as instructed by Honeywell.
Install DDC Controller Housing, CPU, Power Supply, MMI and I/O
modules as per installation details provided by Honeywell.
5.1.4 Cabling
6 Commissioning/Test Procedures
6.1 Power-up Controller
The detail Test report for each system / item of plant will be submitted as
per the Inspection and Test Plan.
When all field have been verified and checked, check the
sequence of operations as described in the Engineering
Submittal and the O&M Manual. The detail check (Like
Temperature control loop, Heat exchanger valve control loop
etc.) for each system / item of plant will be checked as per the
sequence of operation. The computer printouts of the alarms
and data logs will be submitted as part of the sign off
documentation.
When all field DDC Controllers have been verified and checked,
Network connection of the controllers shall be done.
Before connection Al habtoor will make sure for the network
cable continuity.
7 Interface Procedure
MEP contractor to terminate the 3rd party equipment as per the BMS
data point schedule.
8 Documentation
8.1 Commissioning Test sheets ( see attachement)
9 Demonstration Procedures
Precommissioing and commissioning shall be carried out as per the
procedure in 5&6
Start
Power on at all
panels.
Stop
10 Instrumentation
10.1 Multimeter & Laptop for DDC software downloading
METHOD STATEMENT FOR Rev.: 00
ELV System Date of Issue: 25.01.09
10.2 Calibration
11 Staffing
11.1 Responsibilities
13 Attachments
13.1 Commissioning Report