You are on page 1of 3

Methods Stament forAutoclaved Aerated Concrete (AAC)

1-Objective:

This method statement to define the requirements for execution of Autoclaved Aerated Concrete (AAC)
block works.

2-Scope:

For internal and external block walls of the High Rise Building under the scope of the contract.

3- References:

1- Project approved drawings.


2- Disaster Code, Typhoon and Earthquakes Resisting Materials

4 – Procedure:

4.1 Submittals

4.1.1 Contactor will submit AAC blocks supplier and sample for the consultant's approval.

4.1.2 Contractor will submit AAC blocks Adhesive for the consultant's approval.

4.2 Preparations

4.2.1 The area/floor proposed to start the block work activity in, should be cleaned from

any debris, old mortar, dust …

4.2.2 The surveyor will set out all the required axes, offset lines and points.

4.2.3 The block work area will be wetted with water.

4.2.4 Surface of AAC blocks to be joined with mortar is to be wetted.

4.2.5 The mortar for AAC block will be blocks adhesive.

4.2.6 The base bed courses must invariably be laid in ordinary mason's mortar, the

Composition of bedding mortar 1:1:6 (1 cement: 1 lime: 6 sand).

4.2.7 The joint adhesive thickness should be approximately 2-3 mm, and the thickness of

joint for base course bed should be at least 12.5 mm.


4.3 Connections

4.3.1 Wall to Wall connections: In case of L connection interlocking bond will be used,

and the galvanized steel ties will be used every three courses in case of T

connection.

4.3.2 Wall to column Connection: Mason's mortar should be used at all wall to column

Interface joints, columns should be brushed dust-free, and if necessary roughened

by basting to ensure good bond. Walls should be mechanically tied to columns with

30 cm steel anchor rods 2T10 mm every two courses.

4.3.3 In case of Wall to beam Connections and wall to floor soffit connections: ordinary

mason's mortar should be used.

4.4 Block laying:

4.4.1 The first course of the block will be laid in a full bed of ordinary mortar. This

will be inspected for internal dimensions, door sizes, distances …

4.4.2 The block mason will complete the wall on the approved first course.

4.4.3 The maximum height to be built in one day is 1.6 m (8 courses).

4.4.4 For the walls not have opening for doors and windows the heights more than 3 m

a concrete tie beam 200 mm depth will be poured for stiffness purposes.

4.4.5 For the walls have opening for doors and/or windows the overhead lintels should

be continue along the wall and in this case no need for concrete tie beams.

4.4.6 In-situ reinforced concrete lintels and beams should be 4T10 and T8/30 cm stirrups.

4.4.7 Cast-in-situ reinforced concrete windowsills with 200 mm depth, 4T10 and T8/30

cm stirrups.

4.4.8 Keep AAC unit work free of mortar droppings as work progresses and, at completion

of work, rub AAC unit to remove excess mortar.


4.4.9 The block walls will be finally inspected by Engineer for verticality, alignment.

4.4.9 Tolerances:

1. Maximum variation from plumb: 0.6mm in 3 m, not exceeding 0.9mm in 6m.

2. Maximum variation from level: 0.6 mm in 6m, not exceeding 12.5mm in 15 m

or more.

5 – Inspection for block works

5.1 Cleaning of concrete surface.

5.2 Setting out the first course.

5.3 Inspection of the block wall.

You might also like