PROJECT : PENGADAAN PEKERJAAN EPC TIE IN SUMUR HCE-10A, DIENG

TIMELINE FOR EPC TIE IN SUMUR HCE-10A DIENG UNIT-1


Quantity 2023
detail
Description Sisa Unit February
sisa
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Instalasi Area Pipeline

Area Jalur PAD 33 ke Gunung Belah (Pipa 18")


72 joint Fitup, Welding, PAUT, Insulation
heri
6 6 6 6 6 6 6 6 6 6 6 6 0 0 0 0 0 0

Area Jalur Gunung belah ke Qiano (Pipa 18")


eko Fitup, Welding, PAUT, Insulation

248 134 joint 11 11 11 11 11 11 11 11 11 11 11 11 0 0 0 0 0 0

Area Jalur Qiano ke Gardu Pandang (Pipa 18")


eko

Area Jalur Gardu Pandang ke PAD 29 (Pipa 18")


42 joint Fitup, Welding, PAUT, Insulation
ebi
4 4 4 4 4 4 4 4 4 4 4 4 0 0 0 0 0 0

Area Jalur PAD 29 ke PAD 7 (Pipa 18")


66 66 joint Fitup, Welding, PAUT, Insulation
heri
6 6 6 6 6 6 6 6 6 6 6 6 0 0 0 0 0 0

Area Jalur PAD 33 ke Gunung Belah (Pipa 3")


114 joint Fitup, Welding, PAUT, Insulation
heri
9 9 9 9 9 9 9 9 9 9 9 9 0 0 0 0 0 0

Area Jalur Gunung belah ke Qiano (Pipa 3")


joint Fitup, Welding, PAUT, Insulation
eko

392 212 18 18 18 18 18 18 18 18 18 18 18 18 0 0 0 0 0 0

Area Jalur Qiano ke Gardu Pandang (Pipa 3")


eko

Area Jalur Gardu Pandang ke PAD 29 (Pipa 3")


66 joint Fitup, Welding, PAUT, Insulation
ebi
6 6 6 6 6 6 6 6 6 6 6 6 0 0 0 0 0 0

Area Jalur PAD 29 ke PAD 7 (Pipa 3")


105 105 joint Fitup, Welding, PAUT, Insulation
heri
9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9

Target progress (excl. Pad-10 to 33)


Welding 18" Pipeline Plan joint 26 26 26 26 26 26 26 26 26 26 26 26 0 0 0 0 0 0
Welding 3" Pipeline Plan joint 41 41 41 41 41 41 41 41 41 41 41 41 0 0 0 0 0 0