IS Code-IS 456:2000
Material selection
All material is selected as per design mix requirement and type of work
Sand- ( maybe coarse sand, river sand, zone-1 zone -II zone _III sand etc)
Coarse aggregare- ( mazmium size of aggregate depend upon type work and should be well gap
graded
Water- ph vale
Batching
Controlling the quantity of each material required for making concrete mix in each batch
Aggregate , water, admixture should be measured with an accuracy of +/- 3% of batch quantity.
Volume batching
Suitable for small job, gauge box is used for measurement, correction for bulking for sand is applied,
amount of each solid ingredient is measured by loose volume(not compacted)
Weigh batching
MIXING
Concrete mixer are specified by volume of discharge concrete in cum.1.0/7.5 means 1cum of
unmixed raw materials gives 0.75 cum of mixed concrete in each batch
Tranportation
CHUTES are steel shafts used for depositing concrete below GL at higher depth
CONCRETE PUMPS is commonly used for continuous conveying at inaccible location . pumping is the
best method for transportation.
Vertical serving-80m
TRANSIT MIXER
PLACING
Delayed placing of concrete gives gain in ultimate compressive strength if properly compacted
As per IS :456 maximum permissible free fall of concrete is 1.5m, otherwise segregation happens
COMPACTION
Removal of entrapped air from the concrete mix to gate a homogenous dense mass
Form vibrator(shutter/external)
Vibrating table
spinning
FFINISHING
Process of smoothing ane levelling off the top surface of freshly freshly placed concrete for good
appearance
Screeding-to maintain proper grade up top surface and to remove ham and hollows the striking of
excess concrete
CURING
Process of preventing the loss of moisture from the concrete while maintaining a satisfactory
temperature by supplying additional moisture or heat to accelerate the gain of strength curing result
in increase the strength and decreased permeability and it promotes process of hydration of cement
curing shoot start after 24 hours of casting and should contain generally for minimum 7 days to 2
maximum 28 days
Maturity of concrete
strength of concrete depends on the boat period of Curie and temperature during hydration it
measured in degree Celsius
yield of concrete--It's it's thumb Rule to find out the yield of concrete from a given concrete mix
cement:sand:coarse agg= a:b:c then the produced concrete will have volume of 2/3(A+B+C)