Professional Documents
Culture Documents
2, 2020
Richa Sharma
Department of Mechanical Engineering,
Amity University,
Noida, Uttar Pradesh 201313, India
Email: richasahnivirgo@gmail.com
Abstract: Total productive maintenance (TPM) has provided a quantitative metric
tool which is known as overall equipment effectiveness (OEE). OEE provides an
efficient and effective way of measuring and analysing the efficiency of a single
machine cell or an integrated manufacturing system. The objective of this paper is
to highlight the OEE measurement in flexible manufacturing systems of a selected
automobile manufacturing plant by enhancing the equipment and plant reliability
by eliminating all the losses incurred. In this study, a methodology is presented
for analysis of OEE of TPM manager model machines in a selected semi-
automated cell. In this paper, an approach is developed to identify and address the
losses and failures which are responsible for lowering the OEE. The results show
that there was a significant improvement in OEE measurement of TPM manager
model machines in the semi-automated cell by addressing the six big losses. The
findings of the research determine a significant contribution due to OEE
measurement and assessment of losses and therefore were quite useful for the
organisation to initiate TPM improvement activities to enhance the overall plant
efficiency.
The principal objective of this research was to measure the OEE of TPM manager model
machines and to assess the losses which were responsible for lowering the OEE.
2 Literature review
The correct and precise estimation of equipment utilisation plays a significant role in
industries since the identification and analysis of hidden time losses are initiated from these
estimates. The objective of the TPM is to maximise OEE. So, OEE provides an efficient
way of measuring and analysing the efficiency of a single machine/cell or an integrated
manufacturing system. The findings of various literatures related to these investigations are
presented. Wang (2006) concluded that OEE metric act as an indicator of the reliability of
the production system. Blanchard (1997) studied and concluded that the calculation of OEE
is performed by obtaining the product of availability of the equipment, performance
efficiency of the process and rate of quality products.
The author investigated a sample of data of machines in Esfahan Steel Company, which
includes wastes rate, production rate, and stoppage rate. Singh and Ahuja (2014) aimed at
developing an insight into the prevalent quality maintenance practices adopted in the
contemporary Indian manufacturing industry. The study reveals that Indian entrepreneurs
have been reasonably successful in improving the business performances in the
organisations by implementing combination of TQM and TPM, as TQM support to TPM is
much effective and this improvement initiative have significantly contributed towards
enhancing the overall manufacturing performance. Sugumaran et al. (2014) investigated an
integration of quality function deployment (QFD) and analytic hierarchy process (AHP)
with TPMOverall equipment effectiveness
in an automotive measurement of
accessories manufacturing TPM manager
company. modelis concluded
The author 209
by claiming that implementation of AMQFD will enable the companies to perform at world
class manufacturing (WCM) level. Muniswamy et al. (2014) developed a computer-based
TPM model to improve electrical motors readiness and uptime while reducing capital
overhead. It was observed that The TPM model will be a useful tool to predict the
degradation in motor life due to deterioration in insulation, bearing, rotor bar and stator
windings of the motor. Singh and Ahuja (2014) studied a detailed case study on TPM
implementation in a food processing industry to evaluate the exploits of TPM
implementation. This study reveals the exploits of Indian entrepreneurs with TPM practices
and highlights the contributions of TPM in realising the overall organisation’s goals and
objectives. The findings indicated that TPM is a strong contributor to an organisation
competitiveness and manufacturing performance. Singh et al. (2017) identified eight KSFs
from the literature review, questionnaire survey and experts' (academia and industry)
opinion. Interpretive structural modelling (ISM) is used as an approach to establish the
hierarchical structure for analysing the interrelationship among the various KSFs of TPM
implementation in Indian small and medium scale enterprises (SMEs) and also develop an
integrated model. Azizi (2015) focused on evaluation improvement of production
productivity performance in an agile manufacturing company. The implementations of SPC,
OEE, and AM have minimised the defect rates of chipping BF and maximise the brushing
machine performance, which improves the effectiveness production performance. Jain et al.
(2015) have evaluated mobile maintenance a new concept of TPM implementation practice,
especially in SMEs for enhancing OEE of equipments to improve the competitiveness of
SMEs in a globalised market. The irrigation pipe manufacturing plant has been adopted to
carry out this study. Availability, performance, quality rate and OEE have increased by
taking this new maintenance concept.
It has been concluded that several researchers have investigated the TPM
implementation strategies and other researchers have discussed the savings, gains/profits,
production output rate, and overall equipment efficiency by implementing a more efficient
maintenance approach. Nowadays many industries are employing this new methodology of
TPM. Therefore, there is a great need for the design and implementation of overall
maintenance planning system, which investigates the causes of failures as well as integrates
the resources. By keeping this view in mind, the present work is focused to provide an in-
depth case study of TPM implementation in flexible manufacturing environment with the
measurement of OEE of TPM manager model machines through TPM approach.
3 Overview of OEE
OEE is considered as the most efficient and effective tool (McKone et al., 1999) for driving
plant improvement and it continuously focuses the plant on the concept of zero waste. The
six major losses that result in lowering the OEE are discussed and elimination of these losses
are the major objective of the TPM, as also represented in Figure 1. The elimination of these
losses may result in a dramatic improvement in the OEE. The calculation of OEE is
performed by obtaining the product of availability of the equipment, performance efficiency
of the process and rate of quality of products (Ljungberg, 1998; Dal et al., 2000) which may
be expressed as:
In a manufacturing scenario, the desirable productivity, cost, inventory, quality and delivery
all depend on the efficient functioning of the company’s facilities. The objective of OEE
measurement and analysis is to reduce the equipment-related losses, abnormalities or
defects. Numerous losses were determined, but all such losses have been categorised into
six major categories, which are known as ‘six big losses’. These losses, which affect the
overall performance of the equipment, are presented as follows:
• equipment failure or breakdown loss
• set up and adjustment loss
• idling and minor stop loss
• reduced speed loss • defects in process and rework
• reduced yield.
The six big losses originated from the TPM philosophy. Seiichi Nakajima developed TPM
and six big losses in 1971. These losses are the functions of availability, performance
efficiency, and rate of quality of the machine.
In this paper, a case study has been conducted in a two-wheeler automobile manufacturing
industry in North India, which is engaged in the country’s largest manufacturer of
motorbikes. The TPM implementation has made the selected organisation a globally
competitive and world class manufacturing industry. The present selected industry has
successfully implemented TPM initiatives and achieved the TPM Excellence award. The
case study was carried out in a selected semi-automated cell known as machine shop area
consisting of TPM manager model machines. The objectives of this present study are listed
below:
• The objective of the present work is to highlight the OEE measurement in flexible
manufacturing system of selected automobile manufacturing plant by enhancing the
equipment and plant reliability by eliminating all the losses incurred.
• The present study involves identifying and addressing the losses and failures which
are responsible for lowering the OEE.
• An important aspect investigated from this study was significant improvement in OEE
measurement of TPM manager model machines in semi automated cell by addressing
the six big losses.
Overall equipment effectiveness measurement of TPM manager model 211
6 Research methodology
The OEE methodology is a very effective strategy for improving plant efficiency. The
primary study involves tabulation and calculation of all components of the OEE and
productivity index of the system and its direct influence in determining the efficiency of the
existing system. There are more than 300 equipments in the selected two-wheeler
automobile industry. There are different sections in the plant in which production processes
are carried out in machine shop, weld shop, paint shop, engine assembly and frame assembly
areas. Among all these sections, machine shop has flexible setup for manufacturing multi-
model engines and robots have been deployed for loading and unloading operations. The
case study was carried out in a machine shop area consisting of TPM manager model
machines.
The selected plant and cell were put under observation to track OEE of the overall plant
so that the massive losses were identified and eliminated by involving the highly motivated
entire workforce to increase the customer satisfaction level. The first step of this task is the
selection of appropriate machines, which are known as TPM manager model machines on
which this study is conducted. The three types of equipment, which were taken as a TPM
manager model machines in machine shop area, are as follows:
• Broaching machine 1 – 9201169 (M/c SAP no.)
• CNC lathe machine 2 – 9201192 (M/c SAP no.)
• 4 spindle gun drilling machine 3 – 9201176 (M/c SAP no.)
The OEE of the machines mentioned above were evaluated to understand the present
situation. Three bottlenecks machines have been identified and studied using OEE
calculations. The bottlenecks machines were selected based on the criticality of high
breakdown, high set up time or tool changeover time and higher cycle time than standard
takt time. The efficiency and performance of these selected machines were quite low. The
production operators carry out autonomous maintenance such as cleaning, checking water,
oil and coolant. Before taking down the necessary readings to evaluate OEE, each machine
was studied thoroughly to identify each part and to understand the working of each and every
component. Figure 2 signifies the conceptual framework for measurement of OEE of TPM
manager model machines with special regard to TPM methodology.
Planning and
scheduling of TPM
activities
Planned and
Production and Continuously monitoring and addressing
focused
maintenance six big losses/failures for lowering the
improvement
management OEE.
TPM team
For measurement of OEE, the entire data of operation of a shift is taken of 450 mins duration,
which includes 45 mins of food break (meal + tea) and 15 mins of doing routine autonomous
maintenance tasks, such as cleaning, lubrication, inspection and tightening (CLIT). The data
has been collected manually in Excel sheets with the help of production operators and TPM
212 R. Sharma
practitioner.
C Meal breaks 45 45
D Downtime 78 58
F Reject pieces 8 2
Support variables
OEE components
C Meal breaks 45 45
D Downtime 50 28
E Total pieces 230 260
F Reject pieces 18 5
Support variables
Table 4 OEE for 4 spindle gun drilling machine before and after TPM implementation
(continued)
After TPM
Before TPM implementation (minutes)
implementation
OEE components
N OEE = Availability × Performance efficiency × Rate of quality OEE = Availability
83.3% ×79.9% × 96% = 63.8% × Performance
efficiency × Rate of
quality 92.8% ×
85.6% × 98.6% =
72.1%
214 5 R. Sharma
Table Representation of OEE data before and after TPM implementation
OEE before TPM OEE after TPM
TPM manager model machine implementation implementation
Broaching machine I 58.7% 70%
The present study reveals an improvement in OEE as a result of strategic TPM initiatives
from 63% at the time of start of TPM implementation program to 74.3% after the successful
TPM implementation as shown in Table 5. It has been observed from Table 5 that the OEE
of the broaching machine is the lowest one as compared to CNC lathe and 4 spindle gun
drilling machine before TPM implementation. It has been observed that it was due to the
following reasons:
• The actual running speed of the machine was lower than the optimum speed.
• There were minor equipment stops and small irregular jams, which resulted in the loss
of productivity.
• Owing to unplanned downtime occurrences which were the real factors that resulted
in decreasing the OEE. This was because it took a huge amount out of a planned
production time.
• Owing to the problems associated with the computer panel system in CNC which
results in lowering down the OEE. Most of the time the inbuilt computer with CNC
gave an error due to the virus or other problem. Hence, the operating system required
periodically updating and re-installation.
• The production operators were taking extra time during lunch breaks which was the
common problem determined in all machines. For this reason, they often take a longer
time to restart a machine.
Another method to enhance OEE was to incorporate quick release pneumatic connectors,
and thumbscrews, and also, a robot and effectors can be removed and replaced with new end
effectors to handle a different product in few minutes. All such factors have contributed a
lot to enhance the OEE to a certain level.
In order to enhance OEE, there is a need to focus on three elements of the OEE, which are
as follows a availability b performance efficiency c rate of quality.
Figure 3 represents the relationship between six big losses and OEE. The first two losses are
known as downtime loss and are used to calculate the availability of a machine. The third
and fourth losses are speed losses that determine the performance efficiency and the final
two losses are considered to be failures due to defects in the product.
Figure 3 OEE and the six big losses (see online version for colours)
Overall equipment effectiveness measurement of TPM manager model 215
Figure 4 shows the losses that occurred frequently and were the real causes for lowering the
OEE in broaching machine, CNC lathe machine and 4 spindle gun drilling machine. These
losses were continuously under observation and reduced by a planned and focused
improvement TPM team member by suggesting Kaizens and small improvements. It has
been observed that first three maximum time-consuming failures came under the category
of availability and performance efficiency which resulted in decreasing OEE. Following
below are the three major significant time consuming losses:
• set up and adjustment losses
• alignment problem
• minor stoppages.
1 Set up and adjustment losses: setting up adjustment losses are known as stoppage
losses occurring during setup procedures such as retooling etc. The reasons for the
setup adjustment loss were due to the accumulation of slight errors in precision such
as equipment settings. Owing to lack of consistency in the standards for measurements
in operation and maintenance procedures, were one of the reasons for adjustment
losses. The solution of such problems is to set clear, consistent and precise standards
for all procedures. It has been observed that during meal breaks, the operator usually
takes longer time from their scheduled time and it automatically causes a delay to
restart the production. It has been advised to maintain the log registers in each
assembly line so as to monitor the operators in time and out time.
2 Alignment problem: another loss which was highlighted is alignment problem. The
primary goal of all the equipments is to align the parts, tools, accessories and work
piece within accurate and precise tolerances at operating conditions. The reasons for
the alignment problems which were observed were due to the chuck when it is not
properly aligned with the tailstock or the tool holder. The centreline misalignment,
angular misalignment and parallelism misalignment are different alignment factors
which result in lowering the overall efficiency of the machine.
3 Minor stoppages: a minor stoppages loss signifies the small operational disturbances
in which machine stops temporarily due to functional stoppage. It has been observed
that temporarily jamming of work, errors in data communication, small mistakes in
setting of NC programs, etc., were the common reasons found for minor stoppages in
selected manager model machines. These losses are found to be temporary and
resolved in less than five minutes by removal of abnormal work pieces, resetting and
eliminating minor defects. This type of loss directly affects the performance efficiency
of the equipment resulting decreasing in OEE.
Figure 4 Pareto chart showing the major losses occurrence (see online version for colours)
216 R. Sharma
10 Conclusions
It has been seen throughout the study that OEE has been a significant performance
measurement tool. OEE is a key performance indicator (KPI) that indicated the equipment’s
overall operational performance. The empirical case study was conducted on three selected
TPM manager model machines as per designed TPM Master Plan in semiautomated cell
known as machine shop area. It involved calculation of all parameters of OEE and revealed
the losses which were responsible for lowering the OEE. The study has led to an
improvement in OEE from 63% which was at the beginning of OEE to 74.3% after the
successful TPM initiatives. There are various factors which have contributed to enhance the
OEE such as improvement in minor irregular equipment stoppages and by re-installing and
updating the operating system of CNC machines.
It has been concluded that top three losses which were the real causes for lowering the
OEE in selected manager model machines were set up adjustment loss, an alignment
problem and minor stoppages. These losses were continuously under observation and
reduced by systematic approach and with the help of team members of focused improvement
TPM pillar. Finally, it was believed that this method of OEE measurement and assessment
of losses was quite useful for the organisation to initiate TPM improvement activities to
enhance the overall plant efficiency of flexible manufacturing environment.
10.2 Originality/value
TPM is one of the best manufacturing practices followed by most of the world’s successful
organisations to achieve business excellence. TPM has proven to be the manufacturing
strategy that has been successfully employed globally for the last three decades for achieving
organisational objectives of achieving core competence in dynamic environments (Ahuja
and Khamba, 2008b). Based on the literature it has been concluded that the present study
provides an in-depth case study of TPM implementation in flexible manufacturing
environment with the measurement of OEE of TPM manager model machines through TPM
approach.
Acknowledgements
The authors are sincerely grateful to the reviewer(s) for giving their valuable suggestions for
improving the manuscript. The authors would like to especially express the gratitude to
industrial resource persons, executives and supporting staff for their support, cooperation
and encouragement throughout the research span.
References
Ahuja, I. and Khamba, J. (2007) ‘An evaluation of TPM implementation initiatives in an Indian
manufacturing enterprise’, Journal of Quality in Maintenance Engineering, Vol. 13, No. 4,
pp.338–352.
Ahuja, I. and Khamba, J. (2008a) ‘An evaluation of TPM initiatives in Indian industry for enhanced
manufacturing performance’, International Journal of Quality & Reliability Management, Vol.
25, No. 2, pp.147–172.
Ahuja, I. and Khamba, J. (2008b) ‘An assessment of maintenance management initiatives in Indian
manufacturing industry’, International Journal of Technology, Policy, Management, Vol. 8, No.
3, pp.250–278.
Ahuja, I. and Khamba, J. (2008c) ‘Total productive maintenance: literature review and directions’,
International Journal of Quality & Reliability Mgmt, Vol. 25, No. 7, pp.709–756.
Ananth, G. and Vinayagam, B. (2015) ‘Effectiveness improvement through total productive
maintenance using particle swarm optimization model for small and micro manufacturing
enterprises’, International Journal of Productivity and Quality Management, Vol. 16, No. 4,
p.473.
Anvari, F., Edwards, R. and Starr, A. (2010) ‘Evaluation of overall equipment effectiveness based on
market’, Journal of Quality in Maintenance Engineering, Vol. 16, No. 3, pp.256–270.
Ayane, N. and Gudadhe, M. (2015) ‘Review study on improvement of overall equipment effectiveness
in construction equipments’, International Journal of Engineering Development and Research
(IJEDR), Vol. 3, No. 2, pp.487–490.
Azizi, A. (2015) ‘Evaluation improvement of production productivity performance using statistical
process control, overall equipment efficiency and autonomous maintenance’, in Procedia of 2nd
International Materials, Industrial and Manufacturing Engineering Conference, MIME 2015,
Bali, Indonesia, pp.186–190.
Badiger, A., Gandhinathan, R. and Gaitonde, V. (2008) ‘A methodology to enhance equipment
performance using the OEE measure’, European J. Of Industrial Engineering, Vol. 2, No. 3,
p.356 [online] http://dx.doi.org/10.1504/ejie.2008.017690 (accessed 25 December 2017).
Baglee, D. and Knowles, M. (2013) ‘Maintenance strategy development in the UK food and drink
industry’, International Journal of Strategic Engineering Asset Management, Vol. 1, No. 3,
p.289.
Bamber, C., Castka, P., Sharp, J. and Motara, Y. (2003) ‘Cross-functional team working for overall
equipment effectiveness (OEE)’, Journal of Quality in Maintenance Engineering, Vol. 9, No. 3,
pp.223–238.
Blanchard, B. (1997) ‘An enhanced approach for implementing total productive maintenance in the
manufacturing environment’, Journal of Quality in Maintenance Engineering, Vol. 3, No. 2,
pp.69–80.
Braglia, M., Frosolini, M. and Zammori, F. (2008) ‘Overall equipment effectiveness of a
manufacturing line (OEEML)’, Journal of Manufacturing Technology Management, Vol. 20, No.
1, pp.8–29.
Cesarotti, V., Introna, V., Rotunno, R. and Scerrato, G. (2016) ‘Investigating the relationship between
energy consumption and overall equipment effectiveness for improving manufacturing systems'
productivity: an application in the thermoforming process’, International Journal of Productivity
and Quality Management, Vol. 18, Nos. 2/3, p.279.
Chiarini, A. (2015) ‘Improvement of OEE performance using a lean six sigma approach: an Italian
manufacturing case study’, International Journal of Productivity and Quality Management, Vol.
16, No. 4, p.416.
Chong, K.E. and Choi, K.N. (2016) ‘Relationship between overall equipment effectiveness,
throughput and production part cost in semiconductor manufacturing industry’, IEEE
International Conference on Industrial Engineering and Engineering Management (IEEM), Bali,
Indonesia, DOI: 10.1109/IEEM.2016.7797839.
Dal, B., Tugwell, P. and Greatbanks, R. (2000) ‘Overall equipment effectiveness as a measure of
operational improvement – a practical analysis’, International Journal of Operations &
Production Management, Vol. 20, No. 12, pp.1488–1502.
Domingo, R. and Aguado, S. (2015) ‘Overall environmental equipment effectiveness as a metric of a
lean and green manufacturing system’, Sustainability, Vol. 7, No. 7, pp.9031–9047 [online]
http://dx.doi.org/10.3390/su7079031 (accessed 20 December 2017).
Dutta, S. and Dutta, A. (2016) ‘A review on the experimental study of overall equipment effectiveness
218 of various
R. Sharma
machines and its improvement strategies through TPM implementation’, International
Journal of Engineering Trends and Technology (IJETT), Vol. 36, No. 5, pp.224–232.
Huang, S., Dismukes, J., Shi, J., Su, Q., Razzak, M., Bodhale, R. and Robinson, D. (2003)
‘Manufacturing productivity improvement using effectiveness metrics and simulation analysis’,
International Journal of Production Research, Vol. 41, No. 3, pp.513–527.
Jain, A., Bhatti,R. and Singh, H. (2015) ‘OEE enhancement in SMEs through mobile maintenance:
a TPM concept’, International Journal of Quality & Reliability Management, Vol. 32, No. 5,
pp.503–516.
Ljungberg, O. (1998) ‘Measurement of overall equipment effectiveness as a basis for TPM activities’,
International Journal of Operations & Production Management, Vol. 18, No. 5, pp.495–507.
Mathur, A., Dangayach, G.S., Mittal, M.L. and Sharma, M.K. (2011) ‘Performance measurement in
automated manufacturing’, Measuring Business Excellence, Vol. 15, No. 1, pp.77–91.
McKone, K.E., Schroeder, R.G. and Cua, K.O. (1999) ‘Total productive maintenance: a contextual
view’, Journal of Operations Management, Vol. 17, No. 2, pp.123–144.
Muniswamy, A., Gopalakrishnan, B., Chaudhari, S., Jaridi, M., Crowe, E. and Gupta, D. (2014) ‘A
computer-based total productive maintenance model for electric motors’, International Journal
Of Productivity And Quality Management, Vol. 13, No. 2, pp.178 [online]
http://dx.doi.org/10.1504/ijpqm.2014.059173 (accessed 20 December 2017).
Naik, G.R., Raikar, V.A. and Naik, P.G. (2015) ‘A simulation model for overall equipment
effectiveness of a generic production line’, Journal of Mechanical and Civil Engineering, Vol.
12, No. 5, pp.52–63.
Nallusamy, S. and Majumdar, G. (2017) ‘Enhancement of overall equipment effectiveness using total
productive maintenance in a manufacturing industry’, International Journal of Performability
Engineering, Vol. 13, No. 2, pp.173–188.
Pomorski, T.R. (2004) Total Productive Maintenance (TPM) Concepts and Literature Review,
Brooks Automation, Inc. USA.
Raja, P., Kannan, S. and Jeyabalan, V. (2010) ‘Overall line effectiveness- a performance evaluation
index of a manufacturing system’, International Journal of Productivity and Quality
Management, Vol. 5, No. 1, p.38.
Shahin, A. and Isfahani, N. (2015) ‘Estimating overall equipment effectiveness for continuous
production lines: with a case study in Esfahan Steel Company’, International Journal of Services
and Operations Management, Vol. 21, No. 4, p.466.
Singh, H., Jain, A. and Bhatti, R. (2017) ‘An ISM approach to identify key success factors behind the
TPM implementation in Indian SMEs’, International Journal Of Productivity and Quality
Management, Vol. 22, No. 1, p.42 [online] http://dx.doi.org/10.1504/ijpqm.2017.10006238
(accessed 20 December 2017).
Singh, K. and Ahuja, I. (2014) ‘Assessing the business performance measurements for transfusion of
TQM and TPM initiatives in the Indian manufacturing industry’, International Journal of
Technology, Policy and Management, Vol. 14, No. 1, p.44.
Singh, U. and Ahuja, I. (2015) ‘Evaluating the contributions of total productive maintenance on
manufacturing performance’, International Journal of Process Management and Benchmarking,
Vol. 5, No. 4, p.425.
Sohal, A., Olhager, J., O’Neill, P. and Prajogo, D. (2010) ‘Implementation of OEE–issues and
challenges’, Competitive and Sustainable Manufacturing Products and Services, pp.1–8,
Poliscript No. 1997, Milano.
Sugumaran, C., Muthu, S., Devadasan, S., Srinivasan, K., Sivaram, N. and Rupavathi, N. (2014)
‘Integration of QFD and AHP with TPM: an implementation study in an automotive accessories
manufacturing company’, International Journal of Productivity and Quality Management, Vol.
14, No. 3, p.263 [online] http://dx.doi.org/10.1504/ijpqm.2014.064806 (accessed 24 December
2017).
Tsarouhas, P. (2013) ‘Equipment performance evaluation in a production plant of traditional Italian
cheese’, International Journal of Production Research, Vol. 51, No. 19, pp.5897–5907.
Tsarouhas, P. (2015) ‘Evaluation of maintenance management through the overall equipment
effectiveness of a yogurt production line in a medium-sized Italian company’, International
Journal of Productivity and Quality Management, Vol. 16, No. 3, p.298.
Wang, F.K. (2006) ‘Evaluating the efficiency of implementing total productive maintenance’, Total
Quality Management & Business Excellence, Vol. 17, No. 5, pp.655–667.