INFRASTRUKTUR
ASRI RESIDENT TAMANSARI & PADAYUNGAN
HARGA SATUAN SUB. TOTAL
KODE JENIS PEKERJAAN SATUAN VOLUME TOTAL TOTAL JUMLAH PRESENTASE (%)
UPAH (Rp.) BAHAN (Rp.) UPAH (Rp.) BAHAN (Rp.)
a b c d e f g (d x e) (d x f) (d x e) + (d x f) g h
A PEKERJAAN DI DALAM SITE PLAN TAMANSARI
A.1 PEKERJAAN SARANA JALAN
1 M2 Pek. LPA M2 993,71 7.100,00 27.475,00 34.575,00 7.055.341,00 27.302.182,25 34.357.523,25 13,86%
1 M2 Pek. LPB M2 993,71 5.750,00 9.625,00 15.375,00 5.713.832,50 9.564.458,75 15.278.291,25 6,16%
1 M2 Pek. Hotmix M2 993,71 12.600,00 72.630,00 85.230,00 12.520.746,00 72.173.157,30 84.693.903,30 34,16%
A.1 25.289.919,50 109.039.798,30 134.329.717,80 134.329.718 54,19%
PEKERJAAN DI LUAR SITE PLAN TAMANSARI
A.2 PEKERJAAN SARANA JALAN
1 M2 Pek. LPA M2 245,20 7.100,00 27.475,00 34.575,00 1.740.920,00 6.736.870,00 8.477.790,00 3,42%
1 M2 Pek. LPB M2 245,20 5.750,00 9.625,00 15.375,00 1.409.900,00 2.360.050,00 3.769.950,00 1,52%
1 M2 Pek. Hotmix M2 245,20 12.600,00 72.630,00 85.230,00 3.089.520,00 17.808.876,00 20.898.396,00 8,43%
A.2 6.240.340,00 26.905.796,00 33.146.136,00 33.146.136 13,37%
B PEKEJAAN PADAYUNGAN TAHAP II
PEKERJAAN SARANA JALAN
1 M2 Pek. LPA M2 595 7.100,00 27.475,00 34.575,00 4.224.500,00 16.347.625,00 20.572.125,00 8,30%
1 M2 Pek. LPB M2 595 5.750,00 9.625,00 15.375,00 3.421.250,00 5.726.875,00 9.148.125,00 3,69%
1 M2 Pek. Hotmix M2 595 12.600,00 72.630,00 85.230,00 7.497.000,00 43.214.850,00 50.711.850,00 20,46%
B 15.142.750,00 65.289.350,00 80.432.100,00 80.432.100 32,44%