Professional Documents
Culture Documents
Lakewood, CO 80401
P: 303.532.5300
Technical Memorandum
T O: Project Files
FROM: Alcides Panez, Dante Bolanos P.E.
REVIEWED BY: Troy Meyer P.E.
DATE: 2021/11/10
PROJECT
NAME: Veladero Dam Safety Review
PROJECT NO.: 713.001
SUBJECT: Slope Stability Analysis –Phase 1 and Phase 6 Embankment
CC: Julio Torino, Miguel Gutierrez, Julio Juarez
ATTACHMENTS: A: Stability Analysis Cross-Section Location
B: Analysis for Phase 1 Embankment
C: Analysis for Phase 6 Embankment
D: Analysis for Phase 6 Embankment Downstream Slope
E: Analysis for Phase 6 Embankment Foundation Strength
1.0 Introduction
Tierra Group International, Ltd. (Tierra Group) completed slope stability analyses to support the
dam safety review (DSR) for the Veladero Valley Heap Leach Facility (HLF). The current facility
was constructed in six phases, including two in-heap solution storage ponds with retention
embankments, one at Phase 1 and the second at Phase 6. Phases 1 through 6 are currently
operating. Phase 7 construction is scheduled to start by the fourth quarter of 2021.
The objective of the slope stability analyses is to evaluate the overall physical stability of the
solution pond retention embankments under static and seismic conditions. This memorandum
presents the slope stability analysis for the solution pond retention embankments for Phase 1 and
Phase 6 (Phase 1 Embankment and Phase 6 Embankment).
Table 3.3 lists the minimum required FOS for embankments according to the Canadian Dam
Association (CDA, 2019) Guidelines for comparison with Table 3.1 (provided for reference only).
SHA for the soil foundation underlying the pregnant solution storage area (Phase 1 In-
Heap Solution Pond) using an average shear wave velocity in the upper 30 meters (m)
(VS,30 = 500 meters per second (m/s)); and
SHA for shallow bedrock site using a VS,30 = 1,000 m/s.
Table 3.4 summarizes the peak ground accelerations (PGAs) estimated by Golder.
50th
Foundation Condition 1/475 1/2,475 84th Percentile [1]
Percentile [1]
VS,30 = 500 m/s 0.48g 0.82g 0.45g 0.83g
VS,30 = 1,000 m/s 0.33g 0.57g 0.33g 0.62g
[1]
Note: Weighted average of ground-motion predictions. 50th percentile is the median and 84th percentile is the
median plus one standard deviation.
Tierra Group performed a review of the SHA completed by Golder (Golder, 2017). Based on
recommendations from this SHA and the geotechnical assessment completed by Knight Piesold
for the Phase 6 design, Tierra Group adopted PGAs estimated for VS,30 = 500 m/s and 1,000 m/s.
A simplified deformation calculation method was determined using the Jibson (2011) approach.
The approach is based on the period ratio (Ts/Tm), which is the fundamental site period (Ts) divided
by the mean period of the earthquake motion (Tm). The site period is calculated using the
maximum vertical distance between the ground surface and the slip surface, and the shear-wave
velocity of the material above the slip surface. The mean period is calculated based on the
earthquake moment magnitude and the source distance. In theory, a coupled analysis offers the
best results; however, for period ratios below 0.1, when the landslide acts as a rigid block, the
rigid-block method is more appropriate (Jibson, 2011).
The calculated period ratios were estimated to be greater than 0.1, indicating that a coupled
analysis method would provide the best results. Tierra Group selected the Bray and Travasarou
(2007) method (a coupled analysis model), included in the Seismic Landslide Movement Modeled
using Earthquake Records (SLAMMER) program developed by the United States Geologic
Survey (USGS, 2013).
LLDPE single side textured geomembrane versus soil liner. Testing completed in November 2015 and
reported in 2016 (Knight Piésold, 2016).
It is unclear how the 30-degree friction angle for Phase 6 Embankment foundation was estimated.
During the October 2021 site visit, Tierra Group requested additional details for the foundation
strength properties from Knight Piésold. At the time this document was prepared, the requested
information was yet not available.
PEAK
1,800
1,600
1,400
Shear Stress (kPa) 1,200
1,000
800
600
400
200
0
0 500 1,000 1,500 2,000 2,500 3,000 3,500
Normal Stress (kPa)
Phase1(2002)‐GSE 80mil LLDPE smooth Geomemb. vs Soil Liner
Phase2(Aug2006)‐GSE 80mil LLDPE SST Geomemb. Textured side vs Geocomposite
Phase2B&2C(Feb2008)‐80mil LLDPE SST Geomemb. Textured side vs Soil Liner
FIGURE 3.1: PHASE 1 - NORMAL STRESS VERSUS SHEAR STRESS (PEAK STRENGTH)
RESIDUAL
1,800
1,600
1,400
Shear Stress (kPa)
1,200
1,000
800
600
400
200
0
0 500 1,000 1,500 2,000 2,500 3,000 3,500
Normal Stress (kPa)
Phase1(2002)‐GSE 80mil LLDPE smooth Geomemb. vs Soil Liner
Phase2(Aug2006)‐GSE 80mil LLDPE SST Geomemb. Textured side vs Geocomposite
Phase2B&2C(Feb2008)‐80mil LLDPE SST Geomemb. Textured side vs Soil Liner
FIGURE 3.2: PHASE 1 - NORMAL STRESS VERSUS SHEAR STRESS (RESIDUAL STRENGTH)
PEAK
1400
1200
Shear Stress (kPa)
1000
800
600
400
200
0
0 500 1000 1500 2000 2500
Normal Stress (kPa)
(Nov 2015)‐(A1) 2.0mm LLDPE SST Geomemb. Textured side vs Soil Liner
(Nov 2015)‐(B1‐1) 2.0mm LLDPE SST Geomemb. Smooth side vs 270 g/cm2 Geotext.
(Nov 2015)‐(B1‐2) 2.0mm LLDPE DST Geomemb. vs 270 g/cm2 Geotext.
(C1) 2.0mm LLDPE SST Geomemb. vs Geocomposite
FIGURE 3.3: PHASE 6 - NORMAL STRESS VERSUS SHEAR STRESS (PEAK STRENGTH)
RESIDUAL
700
600
Shear Stress (kPa)
500
400
300
200
100
0
0 500 1000 1500 2000 2500
Normal Stress (kPa)
(Nov 2015)‐(A1) 2.0mm LLDPE SST Geomemb. Textured side vs Soil Liner
(Nov 2015)‐(B1‐1) 2.0mm LLDPE SST Geomemb. Smooth side vs 270 g/cm2 Geotext.
(Nov 2015)‐(B1‐2) 2.0mm LLDPE DST Geomemb. vs 270 g/cm2 Geotext.
(C1) 2.0mm LLDPE SST Geomemb. vs Geocomposite
FIGURE 3.4: PHASE 6 - NORMAL STRESS VERSUS SHEAR STRESS (RESIDUAL STRENGTH)
Interface testing for 80-mil LLDPE geomembrane versus soil liner for Phase 2 was not
completed due to the laboratory equipment capacity limit; and
Interface testing for Phase 6 was completed for preliminary liner configurations (Knight
Piésold, 2016). Liner configurations were later modified for the final design (2019b) and
construction. No interface testing was completed for the modified liner configurations.
4.0 Results
Table 4.1 summarizes the slope stability analysis results under static, pseudo-static, and post-
earthquake loading conditions. Pseudo-static PGAs of 0.83g (Phase 1 Embankment) and 0.62g
(Phase 6 Embankment), approximately the 84th percentile of the MCE, was adopted for the
pseudo-static analyses. Failure of the analyzed ore heap slopes can impact the containment of
the pregnant solution storage areas (Basins of the In-Heap Solution Pond #1 and #2) and the
stability of the embankments.
Pseudo-static analyses tend to be conservative because they assume that the horizontal force
acting on the slope is permanent and in one direction. Dynamic loads due to an earthquake are
momentary and happen for a short period of time. Therefore, a pseudo-static FOS equal to or
less than 1.0 does not necessarily imply that failure of the slope is imminent but rather the potential
for some permanent downward slope movement.
Additional pseudo-static analyses, using a less conservative return period of 1 in 475 years
(PGA=0.48g and 0.33g), and determination of yield acceleration were performed. The yield
acceleration is the horizontal acceleration of the slope under the influence of a postulated
earthquake at which movement is imminent.
Results of these additional analyses (PGA = 0.48g and 0.33g) are compared with the initial results
of the pseudo-static stability analysis (PGA = 0.83g and 0.62g), and a further simplified
deformation analysis was completed to evaluate if predicted deformations are acceptable.
Tables 4.2 and 4.3 summarize the analysis results for Phase 1 and Phase 6 Embankments,
respectively.
The simplified seismic-induced deformation analyses for Phase 1 Embankment indicate mean
deformations less than 30 centimeters (cm) which are within the expected MCE range.
Deformation for Phase 6 Embankment was estimated to be greater than 100 cm (109 cm). Slope
stability analysis results for Phase 1 and Phase 6 Embankments are reported in Attachments B1
and C1, respectively. Deformation analysis results for Phase 1 and Phase 6 Embankments are
presented in Attachments B2 and C2, respectively.
The Phase 6 Embankment was evaluated with different downstream slopes (2.5H:1V, 4.0H:1V,
and 5.0H:1V [horizontal:vertical]). The evaluation included slope stability analyses (static,
pseudo-static, post-earthquake conditions) and simplified deformation analysis. A PGA of 0.62g
(MCE) was adopted for the pseudo-static analysis. The results of the slope stability and
deformation analysis are presented in Attachment D. Table 4.4 summarizes these results.
Additionally, a sensitivity pseudo-static slope stability analysis for different foundation effective
friction angles was performed. Figure 4.1 depicts the results of this analysis.
Phase‐6 HLF Pond Embankment
Pseudo‐Static Analisis, Coefficient=0.31g (1/2 PGA)
Sensitivity Analysis
1
0.95
Computed Pseudo‐Static FOS
0.9
0.85
0.8
0.75
0.7
0.65
0.6
0.55
0.5
30 31 32 33 34 35 36 37 38 39 40
Foundation Effective Friction Angle (°)
FIGURE 4.1: PHASE 6: FOUNDATION FRICTION ANGLES VERSUS COMPUTED PSEUDO-STATIC FOS
Due to the high MCE, all pseudo-static FOS were computed below the minimum required FOS
(1.1). In addition to the pseudo-static slope stability analyses, static, post-earthquake analysis
and simplified deformation analysis were completed for foundation friction angles of 35° and 40°.
The results of the slope stability and deformation analysis are presented in Attachment E. The
results are summarized in Table 4.5.
Despite the computed pseudo-static FOS not meeting the required minimum FOS, the estimated
mean deformations for 35° and 40° foundation friction angles are significantly less than what was
estimated for 30° (109.3 cm).
Computed FOS under static conditions meet or exceed the minimum required FOS
recommended by Barrick and CDA guidelines.
Pseudo-static analyses under the MCE resulted in FOS less than the minimum required
FOS recommended by Barrick and CDA guidelines.
Under an earthquake of the 475-year return period, all pseudo-static analyses resulted in
FOS equal or greater than the minimum required FOS recommended by Barrick and CDA
guidelines. A 475-year return period is typically adopted as the operational basis
earthquake (OBE) for HLFs. However, the embankments should be evaluated as dams
following the guidelines applicable to these structures based on hazard classification.
In general, results for Phase 1 Embankment indicate global failure is not expected under
MCE loading; however, damage to the structure and the liner system may occur. This is
allowable based on the project design criteria.
In addition, these analyses assume the saturated ore will not liquefy under earthquake
loading, which has not been verified with field investigations and engineering studies.
Liquefaction susceptibility of the saturated ore should be studied with a suitable field
program and engineering analyses.
5.2 Phase 6 Embankment
It is unclear how the 30° friction for Phase 6 Embankment foundation was estimated.
During the October 2021 site visit, Tierra Group requested Knight Piésold provide
additional details and is currently waiting to receive this information.
The slope stability analyses to support the final Phase 6 design were completed using
interface data for the preliminary liner configurations, which were modified for the final
design. It is recommended to perform interface testing for the liner configurations used for
the final design and/or used for the construction (current existing liner configurations).
Computed FOS under static conditions meet or exceed the minimum required FOS
recommended by Barrick and CDA guidelines.
Pseudo-static analyses under the MCE resulted in FOS less than the minimum required
FOS recommended by Barrick and CDA guidelines.
Under an earthquake of 475-year return period, with the exception of the pseudo-static
analysis for Phase 6 Embankment (FOS = 0.89), all pseudo-static analyses resulted in
FOS equal or greater than the minimum required FOS recommended by Barrick and CDA
guidelines.
Slope stability analyses for the Phase 6 Embankment resulted in pseudo-static FOS less
than the minimum required. Simplified deformation analysis, adopting the MCE peak
ground acceleration (PGA=0.62g), resulted in a mean deformation of approximately
109 cm. To support the design of the Phase 6 Embankment, Knight Piésold (2019b)
completed slope stability analyses under static and seismic conditions, and the lowest
FOS was estimated to be 1.4 and 1.0, respectively. Minimum FOS of 1.5 and 1.1 for static
and pseudo-static were adopted by Knight Piésold. Simplified deformation analysis
(Newmark, 1965) resulted in estimated deformations less than 10 cm. Knight Piésold
completed these analyses under an earthquake of 475-year return period (PGA=0.33g).
For Phase 6 Embankment and under MCE, deformation analysis indicates estimated
displacement greater than 100 cm. Under normal operational conditions, the solution is
not expected to reach maximum design levels. However, a worst-case scenario that
combines MCE with the solution at maximum levels could potentially result on the release
of the solution to the environment.
The additional slope stability analyses performed for the Phase 6 Embankment to evaluate
different downstream slopes and foundation with higher strength did not result in pseudo-
static FOS equal or greater than the minimum required. However, the simplified seismic-
induced deformation analyses resulted in mean displacement below 100 cm.
As mentioned in Section 3.6; it is unclear how the 30° friction angle for Phase 6
Embankment foundation was estimated by Knight Piésold. Additional geotechnical
investigation, including fieldwork, laboratory, and engineering analyses may be required if
the strength properties for the foundation are not properly verified.
Tierra Group understands that the interface testing for the Phase 6 design was completed
for preliminary liner configurations (Knight Piésold, 2016). These configurations were later
modified for the final design (Knight Piésold, 2019b) and construction. No interface testing
was completed for the modified liner configurations. Tierra Group recommends completing
interface testing for the modified liner configurations as soon as possible and updating the
slope stability as needed.
6.0 References
Barrick Gold Corporation (Barrick), 2016. Tailings and Heap Leach Management Standard.
Barrick Document Reference BCG-MI-ST-01. Effective date 11 March 2016.
Bray, J.D. and T. Travasarou, 2007. Simplified Procedure for Estimating Earthquake-Induced
Deviatoric Slope Displacements. Journal of Geotechnical and Geoenvironmental
Engineering, Vol. 133, pp. 381-392.
Canadian Dam Association Guidelines, 2019. Technical Bulletin: Application of Dam Safety
Guidelines to Mining Dams, Canada, 2019 Edition.
GEOSLOPE International Ltd., 2021. GEOSLOPE International Software, Slope Stability
Analysis (SEEP/W and SLOPE/W), Version 11, http://www.geoslope.com/.
Golder Associates, 2002. Heap Leach Facility Design, Technical and Economical Evaluation,
Volume III of IV, September 2002.
Golder Associates, 2012. Informe de Inspeccion – Plan de Acción Durante Emergencias
(PADE), October 2012.
Golder Associates, 2017. Seismic Hazard Assessment Veladero Mine VFL Facility Site, San
Juan Province, Argentina. Report prepared for Barrick Veladero, San Juan, Argentina,
20 February 2017.
Jibson, R.W., 2011. Methods for Assessing the Stability of Slopes During Earthquakes – A
Retrospective. Engineering Geology, Vol. 122 (2), pp. 43-50.
Knight Piesold Argentina Consultores S.A., 2016. Estudios de Factibilidad Fase 6 a 9 SLV e
Ingenieria de Detalle Fase 6. Informe de Estudios Geotecnicos, June 2016.
Knight Piesold Argentina Consultores S.A., 2019a. Engineer of Record Inspection Annual
(2018), October 2019.
Knight Piesold Argentina Consultores S.A., 2019b. Ingenieria de Detalle Fase 6, Análisis de
Estabilidad: Muro de Cierre, Apilamiento y Traza de Aducción, January 2019.
Knight Piesold Argentina Consultores S.A., 2020. Valley Leach Facility (VLF) Phase 6-9
Expansion – Design Basis Report, June 2020.
Newmark, N.M., 1965. Effects of Earthquakes on Dams and Embankments. Geotechnique,
Vol. 15, No. 2, pp 139-159.
United States Geological Survey (USGS), 2013. Seismic Landslide Movement Modeled using
Earthquake Records (SLAMMER) Software, USGS Techniques and Methods 12-B1.
Vector Argentina S.A., 2006. Ingenieria de Detalle, Sistema de Lixiviación, Fase 2,
Setiembre 2006.
Vector Argentina S.A., 2008. Ingenieria de Detalle, Sistema de Lixiviación en Valle, Fase 2B &
2C, Junio 2008.
This memorandum has been prepared for the exclusive use of Minera Andina del Sol S.R.L. for specific application to
the area within this memorandum. Any use which a third party makes of this memorandum, or any reliance on or
decisions made based on it, are the responsibility of such third parties. Tierra Group International, Ltd. accepts no
responsibility for damages, if any, suffered by any third party as a result of decisions made or actions based on this
memorandum. It has been prepared in accordance with generally accepted engineering practices. No other warranty,
expressed or implied, is made.
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
4,100
4,000
3,900
3,800
3,700
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
References:
Bray and Travasarou, 2007, Simplified Procedure for Estimating Earthquake-Induced Deviator Slope Displacements. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE
Jibson, Randall, 2011. Methods for Assessing the Stability of Slopes During Earthquakes - A Retrospective. Engineering Geology, v.122, p.43-50.
SimpliedDeformationAnalyses_NoLargeButtress.xlsx
Simplified Deformation Analyses
References:
Bray and Travasarou, 2007, Simplified Procedure for Estimating Earthquake-Induced Deviator Slope Displacements. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE
Jibson, Randall, 2011. Methods for Assessing the Stability of Slopes During Earthquakes - A Retrospective. Engineering Geology, v.122, p.43-50.
SimpliedDeformationAnalyses_NoLargeButtress.xlsx
Simplified Deformation Analyses
References:
Bray and Travasarou, 2007, Simplified Procedure for Estimating Earthquake-Induced Deviator Slope Displacements. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE
Jibson, Randall, 2011. Methods for Assessing the Stability of Slopes During Earthquakes - A Retrospective. Engineering Geology, v.122, p.43-50.
SimpliedDeformationAnalyses_NoLargeButtress.xlsx
ATTACHMENT C
ANALYSIS FOR PHASE-6 EMBANKMENT
1.74
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.10
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
0.71
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.00
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.74
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.74
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.11
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
0.81
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.00
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.50
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.46
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
0.89
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
0.64
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.00
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.46
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
References:
Bray and Travasarou, 2007, Simplified Procedure for Estimating Earthquake-Induced Deviator Slope Displacements. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE
Jibson, Randall, 2011. Methods for Assessing the Stability of Slopes During Earthquakes - A Retrospective. Engineering Geology, v.122, p.43-50.
SimplifiedDeformation‐Phase6_20210920.xlsx
Simplified Deformation Analyses
References:
Bray and Travasarou, 2007, Simplified Procedure for Estimating Earthquake-Induced Deviator Slope Displacements. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE
Jibson, Randall, 2011. Methods for Assessing the Stability of Slopes During Earthquakes - A Retrospective. Engineering Geology, v.122, p.43-50.
SimplifiedDeformation‐Phase6_20210920.xlsx
Simplified Deformation Analyses
References:
Bray and Travasarou, 2007, Simplified Procedure for Estimating Earthquake-Induced Deviator Slope Displacements. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE
Jibson, Randall, 2011. Methods for Assessing the Stability of Slopes During Earthquakes - A Retrospective. Engineering Geology, v.122, p.43-50.
SimplifiedDeformation‐Phase6_20210920.xlsx
ATTACHMENT D1
DOWNSTREAM SLOPE, STABILITY ANALYSIS
VELADERO VALLEY HEAP LEACH FACILITY
Color Name Slope Stability Unit Effective Effective Strength Function
PREGNANT SOLUTION STORAGE AREA #2 (PHASE 6)
Material Model Weight Cohesion Friction SLOPE STABILITY ANALYSIS
(kN/m³) (kPa) Angle (°)
03a. Static (Embankment) (2)
Impenetrable Bedrock
(Impenetrable)
Embankment Slope 1V:2.5H Downstream
Phase6 (80mil Textured Shear/Normal Fn. 19 Phase6 (80mil
LLDPE/SL)-Peak Textured
LLDPE/SL)-Peak
1.57
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
0.65
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.00
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.57
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.89
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
0.73
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.00
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.89
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
2.12
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
0.78
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
1.00
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
2.12
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400 2,500
DISTANCE (M)
References:
Bray and Travasarou, 2007, Simplified Procedure for Estimating Earthquake-Induced Deviator Slope Displacements. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE
Jibson, Randall, 2011. Methods for Assessing the Stability of Slopes During Earthquakes - A Retrospective. Engineering Geology, v.122, p.43-50.
SimpDef‐Phase6DamFoundationFA_20211108.xlsx
Simplified Deformation Analyses
References:
Bray and Travasarou, 2007, Simplified Procedure for Estimating Earthquake-Induced Deviator Slope Displacements. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE
Jibson, Randall, 2011. Methods for Assessing the Stability of Slopes During Earthquakes - A Retrospective. Engineering Geology, v.122, p.43-50.
SimpDef‐Phase6DamFoundationFA_20211108.xlsx
ATTACHMENT E
ANALYSIS FOR PHASE-6 EMBANKMENT
FOUNDATION STRENGTH
1.75
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
0.77
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.00
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.75
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
2.08
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
0.91
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.00
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
2.08
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
2.08
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.28
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
0.91
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
1.00
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
2.08
4,400
ELEVATION (MASL)
4,300
4,200
4,100
4,000
0 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800 1,900 2,000 2,100 2,200 2,300 2,400
DISTANCE (M)
References:
Bray and Travasarou, 2007, Simplified Procedure for Estimating Earthquake-Induced Deviator Slope Displacements. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE
Jibson, Randall, 2011. Methods for Assessing the Stability of Slopes During Earthquakes - A Retrospective. Engineering Geology, v.122, p.43-50.
SimpDef‐Phase6DamSlope_20211108.xlsx
Simplified Deformation Analyses
References:
Bray and Travasarou, 2007, Simplified Procedure for Estimating Earthquake-Induced Deviator Slope Displacements. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE
Jibson, Randall, 2011. Methods for Assessing the Stability of Slopes During Earthquakes - A Retrospective. Engineering Geology, v.122, p.43-50.
SimpDef‐Phase6DamSlope_20211108.xlsx
Simplified Deformation Analyses
References:
Bray and Travasarou, 2007, Simplified Procedure for Estimating Earthquake-Induced Deviator Slope Displacements. Journal of Geotechnical and
Geoenvironmental Engineering, ASCE
Jibson, Randall, 2011. Methods for Assessing the Stability of Slopes During Earthquakes - A Retrospective. Engineering Geology, v.122, p.43-50.
SimpDef‐Phase6DamSlope_20211108.xlsx