Professional Documents
Culture Documents
BY
THESIS
Advisor: Prof. George Gross
i
FOREWORD
This technical report is a reprint of the thesis written by Anna Barbara Ihrig as the
G. Gross
Thesis Advisor
June 2002
ii
ACKNOWLEDGEMENTS
I would like to first thank my thesis advisor, Professor George Gross, for his
knowledge and helpful guidance during my studies. Doing research with him was an
invaluable experience.
I would also like to thank all my friends at the University of Illinois for their support,
especially Mary and my fellow students in the Power Group. Finally, I would like to
thank my family and Niels for constantly encouraging me and being there when I needed
them.
iii
ABSTRACT
The restructuring of the electricity industry in the U.S. has made the problem of
competitive markets and typically high costs are associated with it, which have to be
eventually borne by the consumers. This thesis aims to investigate the impacts of
congestion on the electricity markets in one of the major power systems of the northeast,
the New England system. We give a brief review of the structure of the New England
system and the entity in charge of operation and control, the ISO-NE. We describe how
the ISO-NE administers the energy market and manages congestion. A general definition
of congestion is provided and the congestion metrics and market power mitigation
procedures used in New England are discussed. The main effort lies in the analysis of
congestion data over a 26-month period. Congestion quantities and costs are analyzed in
detail and examined for discernible monthly and hourly patterns. A high volatility is
found in both metrics and no distinct seasonal or hourly patterns can be detected. The
geographic characteristics of the New England transmission area are discussed with
respect to the distribution of congestion across the various transmission areas in the
region. Three major congested areas are identified and examined. The role of generation
found. In addition, the impacts of the ISO-NE’s market power mitigation on the
congestion costs are also reviewed. The thesis concludes with a set of recommendations
iv
TABLE OF CONTENTS
1. INTRODUCTION ...................................................................................................... 1
2.1 A brief history of the New England markets and the ISO-NE ............................... 7
3. CONGESTION ......................................................................................................... 19
v
4.4 Selected transmission regions ............................................................................... 73
5. CONCLUDING REMARKS.................................................................................... 84
REFERENCES ................................................................................................................. 88
APPENDIX A................................................................................................................... 91
APPENDIX B ................................................................................................................... 95
APPENDIX C ................................................................................................................... 97
vi
LIST OF FIGURES
vii
Figure 4.11: Monthly congestion and mitigated congestion costs for May 1999 –
June 2001 .................................................................................................................. 47
Figure 4.12: Daily mitigated congestion costs and the monthly averages for May 1999 –
June 2001 .................................................................................................................. 49
Figure 4.13: Mitigated cost duration curve for May 1999 – June 2001 ........................... 50
Figure 4.14:Mitigated cost duration curve for March 2000.............................................. 51
Figure 4.15: Mitigated cost duration curve for April 2000............................................... 52
Figure 4.16: Mitigated cost duration curve for May 2000................................................ 52
Figure 4.17: Monthly per MWh mitigated costs for May 1999 – June 2001 .................... 54
Figure 4.18: The general upward trend of the monthly per MWh mitigated costs for
May 1999 – April 2000............................................................................................. 54
Figure 4.19: The lack of a definite trend in the monthly mitigated costs per MWh for
May 2000 – June 2001.............................................................................................. 55
Figure 4.20: Seasonal behavior of the monthly per MWh mitigated costs for May 1999 –
June 2001 .................................................................................................................. 56
Figure 4.21: Daily per MWh mitigated costs and monthly averages for May 1999 –
June 2001 .................................................................................................................. 57
Figure 4.22: Per MWh mitigated cost duration curve for May 1999 – June 2001............ 58
Figure 4.23: Per MWh mitigated cost duration curve for May 1999 – April 2000........... 59
Figure 4.24: Per MWh mitigated cost duration curve for May 2000 – June 2001............ 60
Figure 4.25: Average hourly system load for May 1999 .................................................. 61
Figure 4.26: Average hourly congestion for March, April and May 2000 ....................... 62
Figure 4.27: Average hourly congestion for August and November 2000....................... 62
Figure 4.28: Average hourly system ECP and load for May 1999................................... 63
Figure 4.29: Average hourly per MWh mitigated costs and ECP for August 2000.......... 64
Figure 4.30a: Average hourly per MWh mitigated costs and congestion for March 2000 .. 65
Figure 4.30b: Average hourly normalized mitigated congestion costs for March 2000 .. 65
Figure 4.31a: Average hourly per MWh mitigated costs and congestion for April 2000 .. 65
Figure 4.31b: Average hourly normalized mitigated congestion costs for April 2000 .... 65
Figure 4.32a: Average hourly per MWh mitigated costs and congestion for August 2000 .. 66
Figure 4.32b: Average hourly normalized mitigated congestion costs for August 2000 . 66
viii
Figure 4.33: Distribution of congestion in MW within transmission areas....................... 67
Figure 4.34: The contribution of transmission areas to the monthly congestion for
May 1999 – June 2001.............................................................................................. 68
Figure 4.35: Distribution of mitigated costs within transmission areas............................ 70
Figure 4.36: Per MWh mitigated costs and total mitigated costs for each area for
May 1999 – June 2001.............................................................................................. 70
Figure 4.37: The contribution of the transmission areas to the total monthly mitigated
congestion costs for May 1999 – June 2001............................................................. 72
Figure 4.38: Unmitigated and mitigated monthly congestion costs for May 1999 –
June 2001 .................................................................................................................. 76
Figure 4.39: Percentage of reduction of monthly unmitigated costs by mitigation.......... 77
Figure 4.40: Daily outaged capacity for September 1999 – June 2001 ............................ 80
Figure 4.41: Daily congestion versus daily outaged capacity for September 1999 –
June 2001 .................................................................................................................. 83
ix
LIST OF TABLES
x
1. INTRODUCTION
In this chapter we review the nature of congestion and its impacts on electricity
markets. We discuss the state of the art of the literature in congestion and present a brief
summary of the previous work that was conducted in this field. In the last section, we
outline the objectives, the scope and the contributions of this thesis.
The restructuring of the electricity industry in the US has created a new regime with
many new players. The myriad changes brought huge shifts in the planning, operations
and management of power systems. The introduction of competitive markets did not only
bring benefits, but also made the industry face unprecedented problems. Unlike other
markets, the electricity market has salient characteristics, which make the operation of
competitive markets a major challenge. The lack of major storage capability, the just-in-
time-manufacturing nature of electricity and the central role the transmission and
congestion. With the increasing number of market participants, the number of desired
transactions between the various players is growing. Each transaction requires energy to
be transferred from a sending point to a point of receipt. The sellers and buyers of energy
rely on the transmission network for the transportation of their goods as sellers and
buyers in other markets rely on trucks or trains. In the days before restructuring, the
1
power grid used to be operated by vertically integrated utilities, who had control over
both generation and transmission facilities. Since the unbundling of generation and
challenge to coordinate and operate the system. The current transmission networks were
not originally planned for trading in a competitive market. In addition, one of the key
characteristics of the electricity market is that the good that is traded, energy, will not
necessarily take the direct route from the sender to the receiver, but will travel across the
interconnected network -- likely to result in loop flows and affect various parts of the
transfer energy between various points in the network, the realization of all schedules
might lead to violations of one or more limits of the transmission system. This situation is
called transmission congestion. Whenever this is the case, not all of the desired
transactions can be realized. The market players value the transmission of energy
differently and the fact of not being able to realize certain transactions can have severe
impacts and cause high additional costs. Energy that cannot be purchased from the
supplier who offers it at the lowest price because the current state of the transmission
system does not allow the transfer, has to be purchased from an alternative resource at a
higher price. The situation is especially severe if an area with high demand does not
posses sufficient generation and relies on the import of energy from neighboring systems
to serve the network load. In this case, congestion on the tie lines between the two
regions can significantly endanger the ability of the system to meet its demand.
2
Since the opening of the transmission grid to independent market players, different
power market systems and congestion management schemes have been developed in the
U.S. to administer competitive market operations and at the same time maintain system
reliability at the desired level. After some years of restructuring, operating rules and
procedures are still constantly changing. The main effort lies in providing an effective
market design for the restructured environment. One of the key requirements for the
Several studies have explored the impacts of congestion and different transmission
and congestion management approaches. The study in [1] discusses three transmission
management models that are implemented today and their impacts on the economics of
the energy market: the optimal power flow model found in the United Kingdom and parts
of the United States, the price area congestion control model used in Norway and Sweden
and the U.S. transaction-based model. The work in [2] reviews different congestion
management schemes and the associated pricing mechanisms in several countries and in
some states of the U.S., and provides a unified framework for the study of various
developed to assess the efficiency of the various schemes and the effectiveness of the
market signals provided to the market participants. The paper in [3] provides background
on the market structure in California and discusses the role of the California Independent
System Operator as the facilitator of its congestion management process. In [4] the author
3
conducts an analysis of transmission congestion in the PJM market (Pennsylvania, New
Jersey, Maryland, Delaware, D.C., Virginia) and discusses the method of flowgates as a
market power. The occurrence of congestion can create the potential for certain market
players to exercise market power for their own profit and thereby lower the benefits to
consumers. This is asserted in the study of [5], which finds that transmission capacity
limits have significant effect on outcomes of market gaming and that relieving
transmission congestion can discourage the exercise of market power. The work in [6]
critically discusses the existence of market power in electricity markets and presents a
method to test for the exercise of market power examining optimal generator behavior by
taking price as a given exogenous input. The study in [7] assesses the New England
The study measures market performance by estimating the difference between actual
prices and prices that would result if no market power were exercised. Congestion is
study on the various effects of transmission congestion in the U.S. [8]. Major
transmission bottlenecks throughout the country were identified and the costs arising
from congestion assessed. A study conducted for the Department of Energy recently
investigated the transmission system in the U.S. and identified measures to eliminate
4
role of assessing constraints and encouraging new transmission investment. Supportive
papers discuss, for example, transmission planning and siting, transmission technologies
In this thesis we study the nature and impacts of congestion in one of the major
northeastern power systems -- the New England system. This system was one of the early
harnessing the competition in wholesale electricity markets. Our objectives are to obtain
a better understanding of the congestion in the New England system, to explore the
impacts and ramifications of congestion on the New England markets and to quantify the
effects of mitigation. The scope of our work focuses on the 26-month period of May 1999
to June 2001. We discuss the two metrics for congestion: total energy quantities and the
associated costs. Congestion data are analyzed over the 26-month period and the
possible causes and explanations for the observed congestion situations. We discuss
regional characteristics of congestion in the New England power system. We analyze the
Our study gives a detailed assessment of the occurrences of congestion in the New
England market and the resulting costs during the 26-month period of study. This can
5
provide a basis and encouragement for further efforts to improve the efficiency of
The thesis has three more chapters. Chapter 2 gives an overview over the background
of the New England markets, the ISO-NE and the functioning of the transmission-
measures for congestion used in New England. We also describe the market power
mitigation procedures applied by the ISO-NE. In Chapter 4, we study the congestion data
in detail to analyze the principal characteristics including the presence of monthly and
daily patterns. We present the findings on the geographic distribution of congestion in the
distinct transmission areas of the New England system and discuss the importance of
three specific areas in detail. We show the impacts of market power mitigation on
congestion costs and investigate the implications of generation availability on the amount
of congestion. The last chapter summarizes the key findings and points out directions for
future work.
6
2. THE NEW ENGLAND POWER SYSTEM
In this chapter we provide an overview of the New England power system. We briefly
review the characteristics of the region, the organizational structure and the different
unconstrained energy market and give an example on strategic bidding behavior in which
2.1 A brief history of the New England markets and the ISO-NE
In 1971, the electric utilities in the six New England states Connecticut, Maine,
Massachusetts, New Hampshire, Rhode Island and Vermont formed an association called
NEPOOL or the New England Power Pool, covering an area of 66,672 square miles. The
New Hampshire
Vermont
Maine
Massachusetts
Rhode Island
Connecticut
7
objective was to establish a single regional network and centrally dispatch the generating
units of the Pool [10]. NEPOOL operates as a “tight” power pool, in which Pool
members coordinate their planning and the network monitors and directs the operations
Today the Pool generation system comprises 350 generating units with a total
capacity of 28,500 MW. To meet load requirements, the New England system must
import power from its neighboring systems New York, New Brunswick and Quebec [7].
The 6.5 million customers are served using more than 8,000 miles of transmission lines.
On August 9, 2001, New England experienced its record peak load of 25,038 MW. A
The New England transmission region is split into twelve transmission areas. These
are shown in Table 2.1.
EAST East
WEST West
NORTH North
SOUTH South
VT Vermont
CONN Connecticut
MAINE Maine
8
On July 1, 1997 the Independent System Operator New England (ISO-NE) was
from NEPOOL. This was done in response to Orders 888 and 889 issued by the Federal
A.
Since May 1, 1999, the ISO administers, as required by FERC’s Order 888, the
“NEPOOL Open Access Transmission Tariff” [11] according to the “Interim Independent
System Operator Agreement” with NEPOOL [12]. ISO-NE operates and controls the
region’s power grid, provides operational planning services and administers the
wholesale electricity markets. The fact that ISO-NE both controls the transmission grid
and decides about transactions in the market makes it a very powerful entity.
• reserve markets:
• installed capability
9
The ISO-NE is at the moment developing a new market design and planning to join in
the formation of a regional transmission organization (RTO) in the northeast, that would
The market for energy in New England is a residual market. Market participants, who
generate power in excess of the demand of their customers, may sell it in the wholesale
market to other participants. Participants, who do not generate sufficient power to serve
the demand of their customers, may buy it in the market. In this way, only the residual
amounts are traded in the market. To give a feeling of the scope of this market, the
percentage of energy traded in this market rose from 16% of the total energy usage in
The New England energy market is a single real-time market operated typically every
five minutes. Other regions as, for instance, the PJM (Pennsylvania, Jersey, Maryland
and Delaware) region and California trade energy in more than one single market. PJM
administers two distinct day-ahead and real-time markets. The time line in Fig. 2.2 is
used to explain the sequence of operations in the energy market performed by the ISO-
NE. Fig. 2.3 shows the information flow in the market. In this section we discuss the
transmission-unconstrained market.
10
publish forecast
schedule
month
hour 12:00 00:01 24:00 end
schedule day up to
day ahead
a month
bilateral
transactions
ISO-NE
dispatching
real-time dispatch,
energy clearing prices
11
According to ISO-NE Market Rules and Procedures [13], all generator offers1 and
bilateral transactions information for the next day have to be submitted by the trading
deadline, which is 12 noon. An “offer” is defined as all the information related to price,
quantity, technical parameters and timing of offers to provide special services. An offer
must contain prices for the range of output from 0 MW to a certain upper limit2. The
output may be provided in more than one segment (block), each with its own distinct
price. Since NEPOOL is a mandatory pool, each generator that has an available capacity
After the day-ahead trading deadline, the ISO determines and publishes the forecast
schedule based on its load forecast, reserve requirements, offer and bilateral contracts
redeclarations of their offers any time an offer variable or parameter changes due to
changing generator status. A redeclaration may contain changes related to the physical
capabilities of a unit, but may not change any prices past the trading deadline. The ISO-
NE performs at least five forecast schedule updates throughout the day based on actual
The schedule day is the 24-hour dispatch period starting at midnight. The ISO
reviews the forecast schedule and updated system information hourly during the day.
Dispatch points for generators are typically calculated once every five minutes, taking
1
Note that the ISO-NE in its publications and its web site [10] is incorrectly using the term “bid” for what is in fact a generator’s offer
to supply power at a specified price. In this thesis, wherever the term “bid” is used, it is done in compliance with ISO-NE
terminology; the reader should keep in mind that generators are on the supply-side of the market and they submit offers to sell
their power. In general, we try to use the term offer.
2
The upper limit is the higher of the high operating limit or the claimed capability; the definition of these variables are given in
“NEPOOL Market Rules and Procedures” [13].
12
into account the following system conditions: the NEPOOL Area Control Error (ACE)3,
generator outputs and transmission constraints. Generators must obey the ISO’s dispatch
instructions and are required to immediately notify the ISO if certain requests cannot be
implemented. Hourly energy prices are determined as the average of the real time
In the following we give a basic example of how energy prices are determined in the
offered quantities are given in terms of energy per hour, denoted by MWh/h or, for short,
To minimize total production costs, we consider lowest price offers first. Dispatching
units in an ascending offer order is called merit order dispatch. In our example, the lowest
offer is A, offering to serve 30 MW at a price of 5 $/MWh. The next higher offer is B over
finally E over 55 MW at 30 MWh. Fig. 2.4 shows the aggregated supply curve of offers A
to E.
3
The area control error is “the instantaneous difference between net actual and scheduled interchange, taking into account the effects
of frequency bias including a correction for meter error” [13].
13
$/MWh
E
55 @ 30
D
C 20 @ 20
B 25 @ 15
A 50 @ 10
30 @ 5
MWh/h
Consider a fixed system load of 100 MW. The least-price dispatch for this load
consists of the dispatch offers A and B and 20 MW of offer C to meet the demand. As
seen from the supply curve in Fig. 2.4, this dispatch corresponds to the merit order
dispatch constructed from the offers. We say that offers A, B and C are dispatched in
merit order.
The market clearing price is determined by the equilibrium point at which supply
equals demand. Therefore suppliers willing to sell at or below this price are able to sell
all of their offered quantity to the bidders who are willing to buy at or above this price.
All quantities bought and sold are priced at the uniform market clearing price. The
corresponding quantity sold and bought is called the market clearing quantity. The
interpretation of the market clearing price is the marginal price of energy in the market.
The ISO-NE defines the energy clearing price (ECP) to be the market clearing price
established with all offers in the merit order. Therefore the ECP is defined as the price of
14
one additional MW4, which may be dispatched in merit order, should the load be
Therefore the next MW of generation would be supplied by offer C, determining the ECP
$/MWh
E
55 @ 30
D
C 20 @ 20
ECP 15
B 25 @ 15
A 50 @ 10
30 @ 5
MWh/h
100
Costs are proprietary information and each generator may freely choose its offer
price. Due to this fact the price for energy is affected by the bidding strategies of the
market participants. In the following we give a basic example of how strategic bidding
behavior can have a significant impact on the energy clearing price. We assume two sets
4
The ECP is the time weighted average of the real-time marginal prices during an hour. “NEPOOL Market Rules and Procedures”
Section 5.3.2 [13] defines the real-time marginal price under “normal system conditions” as the “next least expensive MW that
may be dispatched above the Desired Dispatch Points”. “Under capacity deficiency conditions the Real-time Marginal Price
(RTMP) is the price of the last most expensive MW … Under Excess Generation conditions, the RTMP is the price of the last
least expensive MW …” In this thesis, we assume “normal system conditions” and assume the real-time marginal price to be the
price of an additional MW.
15
of offers for Example 2, Set 1 and Set 2, given in Table 2.3. We display the supply curve
resulting from offer Set 1 in Fig. 2.6, starting with A offering to supply 30 MW at a price
SET 1 SET 2
quantity price quantity price
offer offer
(MW) ($/MWh) (MW) ($/MWh)
A 30 5 A’ 30 5
B 50 10 B’ 40 10
C 25 15 C’ 25 15
D 10 30 D’ 10 30
offer D over 10 MW at 30 $/MWh. With a system load of again 100 MW, offers A, B and
C will be considered. We notice that offer D will not be needed to serve the system load.
$/MWh
D
10 @ 30
C
ECP 1 15
B 25 @ 15
A 50 @ 10
30 @ 5
MWh/h
100
16
Now we assume that offers B and D come from the same company. The offers B and
D may be outputs of two different generating units or two different blocks of the same
unit. In Set 2 we consider the case, where in trying to maximize their profits, the
MW. This reduction results in the need for an additional 10 MW to serve the system load.
To accomplish this goal, offer D will also be considered. Fig. 2.7 shows the new situation
The new energy price being paid to all units dispatched in merit order is the offer
price of the next MW that would be dispatched in merit order, were the load raised by one
load, D would supply the next MW. Therefore, offer D determines the energy clearing
price of offer
$/MWh D determines
D 30 the energy
ECP 2 clearing price
10 @ 30
C
ECP 1: 15
B 25 @ 15
A 40 @ 10
30 @ 5
MWh/h
100
doubles the system-wide price for energy from 15 $/MWh in the base case to 30 $/MWh.
17
This example is useful in illustrating the great influence a particular offer has on
shaping the ECP. Note that with a small block of generation, offer D can establish the
18
3. CONGESTION
its impacts. We describe the transmission-constrained market in New England and the
metrics used by the ISO-NE to measure congestion. In addition, the market power
congestion is explained.
So far we discussed the dispatch of generation and the determination of energy prices
primarily of a reliability nature it is not always possible to use the dispatch determined in
Congestion occurs whenever one or more constraints are violated under which the
system operates in the “normal” state or in any of the contingency cases in a list of
specified contingencies. These constraints can either be physical limits like thermal or
voltage limits or specified limits to ensure system security and reliability [1,2].
We illustrate the basic notions of congestion with respect to the simple 2-bus system
of Fig.3.1 in Example 3a. The system has a seller at bus 1 and a seller at bus 2. A buyer
intending to buy 150 MW is located at bus 2. The seller at bus 1 offers to sell power at a
price of 5 $/MWh and the seller at bus 2 offers power for 10 $/MWh.
19
no line flow limit
bus 1 bus 2
Seller 1 ~ Seller 2 ~
5 $/MWh 10 $/MWh
150 MW 0 MW Buyer
150 MW
unconstrained market (Section 2.2). Seller 2 offers more expensive power than seller 1
and will therefore not be dispatched. Seller 1 sells 150 MW to the buyer at bus 2. Thus the
the power transfer on the line between bus 1 and bus 2. Suppose the limit is 100 MW as
illustrated in Fig. 3.2. The optimal dispatch point to minimize total costs is still the same
as in the previous example: the seller at bus 1 at 150 MW and the seller at bus 2 not
dispatched. But in this case a transaction of 150 MW between the seller at bus 1 and the
buyer at bus 2 is not feasible, since it would result in a line overload of 50 MW.
limit of 100 MW
bus 1 bus 2
Seller 1 ~ Seller 2 ~
5 $/MWh 10 $/MWh
100 MW 50 MW Buyer
150 MW
20
To eliminate this overload, we reduce the sale from seller 1 by 50 MW and instead
dispatch the higher priced power of seller 2. With this new dispatch, total costs amount to
$1,000. The additional constraint on the transmission line led to congestion and an
We can basically measure congestion in two different metrics. Congestion is, on the
one hand, the difference in megawatts of the power scheduled to flow on a transmission
line and the actual transfer which is allowed on the line without violating any constraints.
On the other hand, we can determine congestion costs as the difference in the costs for
securing power to serve the system load without having to consider any constraints and
In the 2-bus system in Example 3b, congestion in the amount of 50 MW5 occurs,
straightforward. However, real systems are much more complex and require a higher
effort to analyze. To go only one step further from the previous example, we want to
illustrate the case of a power system with five buses, five sellers and three buyers. Fig.
3.3 shows the network for the 5-bus system of Example 4a and Table 3.1 gives the
quantities requested by the buyers and the prices at which the sellers are willing to sell.
We assume a lossless system. The buyer with the highest demand is at bus 5, intending to
buy 450 MW. The seller offering for the highest price, 40 $/MWh, is also located at bus 5.
Seller 4 has the lowest price offer with 5 $/MWh. The following scenarios are simulated
with PowerWorld software using its Economic Dispatch and OPF functions [15].
5
As mentioned in Chapter 2, congestion is measured in units of energy; since we focus on one hour of dispatch, we use MWh/h, or,
for short, MW.
21
Figure 3.3: Unconstrained 5-bus system of Example 4a
again determine the optimal dispatch as in Examples 1 and 2 of Section 2.2. The result is
22
straightforward. Only the generator that offers to sell power for the lowest price will be
dispatched (assuming a high enough output limit). In this case, all transactions will take
place between the buyers and the seller at bus 4. The seller at bus 4 will sell in total 850
The values on the lines in Fig. 3.3 show the respective line loading. To accommodate
the transactions between seller 4 and buyers 3 and 5, the transmission lines connecting
bus 4 with buses 3 and 5 experience a higher power flow than the other lines, carrying
remaining lines.
Next, we consider the line flow limits of 100 MW on each line of the network for
Example 4b. We use the optimal power flow function of the PowerWorld software,
which minimizes total system costs subject to transmission constraints. We expect the
power flow of the system to change, because the flows on two lines in the transmission-
unconstrained solution violated the line limit of 100 MW. The results of the optimal
power flow for the 5-bus system of Example 4b are shown in Fig. 3.4.
The pie charts show the percentage of line flow on each line according to its limit. As
we can see, each line except that between buses 1 and 2 has flows exactly at the limiting
Example 4a, since seller 4 cannot be the only one selling its power, but also sellers with
The new costs per hour are $19,000, which is more than four times those of the case
23
Figure 3.4: Constrained 5-bus system of Example 4b
We see that the presence of congestion can substantially change the dispatch within
the system, forcing inefficient and expensive units to run. This results in significantly
higher costs of securing the power needed to serve the system demand.
Assume we try to purchase power from one or more sellers with the lowest offer
prices to minimize our total costs of serving the system demand. If sufficient transmission
facilities connecting the sellers with the buyers do not exist, line limits will be violated, if
we keep the intended dispatch. If, on the other hand, there were sellers who offer power
at low prices located close to the buyers, we would not need high transmission capacity to
serve the system demand. Therefore, the problem of congestion lies in insufficient
24
transfer capability of the transmission system. We can see that generation and
The problem of controlling operations at the lowest cost so that the system remains
secure (no limits are violated), was present before restructuring. Why is congestion more
significant now in the restructured system? Before restructuring, utilities were vertically
integrated, owning and controlling both generation and transmission [1]. A utility
minimized costs by optimally dispatching generation, knowing all the constraints in the
transmission system. Conflicts between security and economics could be solved by one
decision-making entity. The method used for the solution of the problem is the optimal
power flow tool6. It resulted in a “first-best” solution by maximizing the social surplus or
minimizing the total production costs [2]. In a competitive market, however, where
transmission and generation are unbundled, many market players offer to sell power and
make use of the transmission grid. With a growing number of independent competitors, it
is a challenge for the transmission system operator to maintain system reliability while
minimizing costs. To ensure system reliability without being able to rely on a single
entity with control over all facilities, efficient rules must be established to coordinate the
Congestion management is concerned with approaches for dealing with this problem.
Various schemes have been adopted by the system operators in the U.S. regional systems
6
An explanation of the optimal power flow method can be found in any standard textbook, e.g. see Wood and Wollenberg [16].
25
3.2 The Congestion Metrics used by the ISO-NE
concept of out-of-merit-order dispatch. We started the explanation with the merit order
dispatch under which the system dispatches generation blocks in the order of ascending
offer prices in Section 2.2. Due to reasons of reliability requirements, it is not always
possible to maintain such dispatch. To avoid any violations of the network constraints
either in the “normal” state or in any of the contingency cases in the list of specified
contingencies, the ISO must redispatch the outputs of units. Since this necessitates the
use of some of the offers of higher priced units to serve load and overcome the limitations
The energy clearing price is the offer price of the generating block that would serve
an additional MWh of energy when merit order dispatch is used. The prices of the
generating blocks that are dispatched out of merit order so as to relieve congestion,
cannot contribute toward the determination of the energy clearing price. All blocks with
offer prices above the ECP are paid the price for which they offered to sell.
system of Fig. 2.4 with the same set of offers as in Example 1 in Section 2.2 (Table 2.2).
The difference is that now offer B cannot be considered due to transmission constraints
not allowing B’s power to be transported over the lines connecting it to the load. Assume
we need to dispatch offer E to relieve the congestion and serve the system load. The new
26
$/MWh
E
55 @ 30
15
C
ECP
20 @ 15
A
30 @ 5
MWh/h
100
Figure 3.5: The supply curve with out-of-merit-order dispatch incorporating offer E
It is important to distinguish between the in-merit status of offer A and C and the out-
power transfer limit, its price cannot be used in the determination of the energy clearing
An interesting side effect of the determination of the ECP is that in certain cases the
illustrated in Fig. 3.6, consider the case that the power transfer limit constrains the ISO to
$/MWh
E
55 @ 30
10
B
ECP
A 25 @ 10
30 @ 5
MWh/h
100
Figure 3.6: The supply curve resulting in a lower ECP with transmission constraints
considered
27
accept only half the block of offer B and no part of C. Then, as before, offer E is
price of offer B to serve an additional MWh of demand using in merit order dispatch. The
The ISO-NE uses two congestion measures to quantify congestion. We illustrate the
use of the two measures with respect to Example 5 illustrated in Fig. 3.5. One measure of
congestion is the measure of the energy/hour (MWh/h) that must be redispatched from
express this quantity in MW rather than MWh/h. The New England system defines
3.5, there is consequently congestion of 50 MW, which is the dispatched capacity of the
The second measure is congestion costs. These are defined as the costs of the energy
produced by blocks dispatched out of merit order. These costs arise due to the higher
prices for the energy generated by the out-of-merit order blocks; these blocks are paid the
offer prices.
The ISO-NE refers to these costs as congestion uplift costs. The formula for the total
costs is given by
where κ denotes the capacity of block b used in out-of-merit-order dispatch and the
28
In Example 5, the offer price of the generation dispatched out of merit order is 30
$/MWh and the ECP is 15 $/MWh. With 50 MW of congestion, this results in congestion
50 MW
$/MWh offer price : 30
E
congestion costs
C [(30-15)*50] = 750
20 @ 15
A ECP: 15
30 @ 5
MWh/h
100
Section 24 of the “NEPOOL Open Access Transmission Tariff” [11] requires that the
total congestion costs be allocated to all market participants in proportion to their share of
the network load. This socialization of costs is controversial, since all consumers are
billed for congestion, even those who are not located in the congested area.
The main purpose of restructuring the electricity system into a competitive market is
to increase benefits to consumers. But replacing the regulated rates for electricity by
competitive prices also raises the problem of market power. Definitions of market power
29
can be found in the literature [6,18,19]. The exercise of market power denotes the ability
of a supplier to charge prices above competitive market levels for sustained periods. This
is precisely the opposite of perfect competition where each participant is a price taker. An
entity with market power is a price setter. In general, a high concentration of the
ownership of resources can facilitate the exercise of market power. However, the
transmission network plays a vital role in the functioning of competitive markets. In fact,
position of market concentration, but solely because of the occurrence of congestion [20].
If an area is isolated from low priced energy supply due to congestion, local suppliers
may have the potential to exploit this situation for their own benefits. Any exercise of
market power interferes with the competitiveness of markets and can thereby
significantly reduce the benefits to consumers that are the goal of introducing competition
to electricity markets.
Since the beginning of operations in 1999, the ISO-NE practiced market power
mitigation by monitoring the offers of generating units that are necessary to relieve
congestion and may therefore have the potential to exploit this situation and exercise
market power by significantly raising their offer prices. Whenever the ISO-NE assumed
that a supplier exercised market power, the respective generating unit did not receive the
full offer price for its energy, but a reduced price determined by the ISO-NE. These
actions were taken to foster competition by monitoring and, if necessary, modifying any
operations.
30
FERC found that the existing market rules allowed the ISO-NE too much discretion
in determining when market mitigation will be imposed and required the ISO-NE to
disclose clear criteria for market power mitigation actions. The ISO-NE then proposed
the Revised Market Rule 17 of “NEPOOL Market Rules and Procedures” [13], which is
in effect since May, 2001. We ignore the mitigation procedures undertaken before this
date and we focus on the Revised Market Rule. It provides the ISO with a clear
framework used for detecting and mitigating the exercise of market power. The two basic
ways of exercising market power are physical and economic withholding. Physical
operating parameters, which will prevent the block from being dispatched, although
absent such false declarations the block would be dispatched in economic merit order. A
prime example is the scheduling of maintenance: sellers can exercise market power by
strategically planning outages [7]. The ISO-NE has promulgated regulations that require
the sellers to provide certifiable reasons for generation outages and that require that
current and historical data be compared to detect and analyze changes in the resource’s
raised to such a high level as to effectively remove it from the merit order dispatch.
provides market participants with the opportunity to exercise market power. Consider a
transmission lines, but where one or more local generating units are physically required
to serve the load in this area. Since the sellers of the area’s generation know that their
offers are dispatched irrespective of their prices, nothing prevents them from submitting
31
high-priced offers to maximize their profits. Consider again the five-bus example of Fig.
3.4. The seller at bus 5 can raise its offer price to any value, since the transmission
constraints allow a limited amount of power imports and this amount is less than the load
According to the regulation in Market Rule 17 of the “NEPOOL Market Rules and
Procedures” [13] each out-of-merit-order block be subject to two market power screens --
a structural and a price screen. The ISO-NE must first apply a structural screen to
determine if all requirements could have been met without the block in question. If this is
the case, the blocks of alternative resources are identified. The rules require the
satisfy the transmission constraints. The ISO may raise this number to five bidders, if the
constraint is “reasonably foreseeable”7. This screen therefore ensures that the block has
passed to receive its offer price. If the block is unable to pass this screen, an additional
price screen must be applied by the ISO-NE. This second screen distinguishes between
blocks of resources that are generally dispatched in merit order and those that seldom are
in merit order. In either case the offer price of the block is compared with a screen price,
which is a percentage of a reference price whose level depends on the number of hours
the block was operated out of merit order during the past 90 days. The reference price is
the weighted average of the in-merit offers during the most recent 30 days. If the block’s
offer price lies below the screen price, it may receive its offer price. Otherwise, the offer
price must be replaced by the particular screen price, or under certain cases by a price
negotiated by the offerer and the ISO. The costs resulting from the prices actually paid to
7
“NEPOOL Market Rules and Procedures”, Section 17.3.2.1 c. It is not explained in any greater detail as to under which
circumstances a constraint would be classified as being “reasonably foreseeable”, leaving room for disputes to arise.
32
the out of merit order blocks are the mitigated congestion costs calculated with the
formula given by
where offer price’ denotes the price actually paid to the out of merit order blocks.
Note that we call the costs resulting from the total mitigated uplift costs in one hour
divided by the total amount of congestion in the respective hour the per MWh mitigated
∑κb
b
During some months the mitigation measures reduced congestion payments after the
fact by 50% of the initial costs. Bushnell and Saravia claim that the competitiveness of
the New England markets was definitely improved by the mitigation procedures of ISO-
NE, as can be found from comparison with other markets with less intense market power
in Fig. 3.8.
We see that the ISO-NE is aiming at mitigating possible market power by applying
the described mitigation procedure. However, this does not mean, that necessarily each
entity whose offers are mitigated by the ISO-NE has really been engaged in exercising
market power. Likewise there is no guarantee that the ISO-NE screening processes detect
33
• identify out-of-merit
order blocks
• define the particular
constraint
• identify alternative
blocks
STRUCTURAL
SCREEN TEST no
Could the requirement
have been met without
running the selected
resource?
yes
no
PRICE
SCREEN TEST
Is the offer price of the
resource smaller or equal
yes the screen price?
no
34
4. CONGESTION DATA ANALYSIS
In the previous chapters we have described the New England power system and the
key roles of the independent system operator, the ISO-NE. We also discussed the market
congestion. We next focus on the study of the congestion data in the New England
system. To start with, we describe the available data that we use in our study. Using the
two metrics discussed in Chapter 3, we quantify the congestion. Our analysis consists of
the detection of monthly and hourly patterns of congestion quantities and costs. We
examine the distribution of congestion across the twelve transmission areas of New
England and the impacts of the ISO-NE’s market power mitigation on the congestion
All the data used in this study are taken from congestion reports published by ISO-NE
[21]. Each report consists of a spreadsheet that provides the following data:
The data are available in daily and hourly forms. Each daily value is the sum of the 24
hourly values and the computation is made for the total congestion and the total
8
The footnote 5 of Chapter 3 applies to all the discussion and plots of congestion in this chapter.
35
congestion costs. In addition, the daily average values of the congestion costs per MWh
are given. The values of the unmitigated costs and the mitigated costs are given. The
information about the type of congestion is very generic and not closer specified and
therefore it does not provide satisfactory details on the reasons of particular congestion
occurrences.
The congestion reports are available for the twelve separate transmission areas of the
New England system presented in Table 2.1. For three of these areas -- MAINE,
NEMASS/BOST and ME/NH -- only daily but no hourly data are reported. All other
areas have both daily and hourly data available. All the data available at the time of this
study from the beginning of the operation of the ISO-NE in May, 1999, to June, 2001,
In this section we analyze data on monthly and daily congestion quantities, monthly
and daily mitigated costs and monthly and daily per MWh mitigated congestion costs.
The New England Power System experienced 9.3 million megawatts of accumulated
congestion in the 26 months from the beginning of the restructured markets in May,
We used the daily congestion reports to compute the monthly congestion metrics over
the period of the analysis. We give the monthly congestion quantities in MW in the chart
of Fig.4.1.
36
monthly congestion in 1,000 MW
900
800
700
600
500
400
300
200
100
0
May-99
May-00
May-01
Sep-99
Nov-99
Sep-00
Nov-00
Mar-00
Mar-01
Jul-99
Jan-00
Jul-00
Jan-01
Figure 4.1: Monthly congestion for May 1999 – June 2001
• the highest values were attained in March, April and May, 2000 (620,000
MW, 720,000 MW and 770,000 MW, respectively), some lower high values
occurred in December, 1999, June, 2000, August, 2000, and June, 2001
• during the first four months of operation (May to August, 1999) monthly
these small values may be indicative of the fact that trading in the new
markets was in its incipient stages and participants still had to become
37
We analyze the changes in congestion in the 26 months of the observed period in the
graphs in Fig. 4.2 and 4.3. Fig. 4.2 shows the monthly congestion in the first 12 months
from May, 1999, to April, 2000, and Fig. 4.3 shows the values for the following 14
900
monthly congestion in 1,000 MW
800
700
600
500
400
300
200
100
0
May-99
Aug-99
Sep-99
Nov-99
Feb-00
Mar-00
Apr-00
Jun-99
Jul-99
Jan-00
Dec-99
Oct-99
During the first year of operation the monthly congestion amounts were growing, as
can be seen in Fig. 4.2. Fig. 4.3 shows that during the second year, which started out with
the peak month of the 26-month period (May, 2000), the monthly values were decreasing.
The last two of the observed months, May and June, 2001, experienced an increase in
monthly congestion again, but data for the following months would be necessary to detect
further developments.
38
900
monthly congestion in 1,000 MW 800
700
600
500
400
300
200
100
0
May-00
May-01
Aug-00
Sep-00
Nov-00
Jul-00
Apr-01
Jun-00
Dec-00
Jan-01
Feb-01
Mar-01
Jun-01
Oct-00
The peak months of congestion occurred in winter, spring and summer. To compare
the seasonal behavior in each year of the 26-month period, we show the MW quantities of
The winter months December, January and February experienced similar amounts of
congestion in each year. This can be seen from the closeness of the lines showing the
congestion amounts during the different years. The months of spring, March, April and
May, however, show high congestion with more than 600,000 MW each month in 2000,
but relatively lower congestion with less than 400,000 MW in 2001. The summer months
June, July and August also experienced very different amounts of congestion in each
year. In 1999 congestion during the summer was very low, ranging below 100,000 MW.
In 2000, congestion in summer was not especially low with values between 450,000 MW
39
and 560,000 MW each month, but summer was not the peak period of congestion during
that year.
Figure 4.4: Seasonal behavior of monthly congestion for May 1999 – June 2001
900
monthly congestion in 1,000 MW
800
700
600
1999
500
2000
400
2001
300
200
100
0
May
Aug
Sep
Nov
Apr
Jan
Feb
Mar
Jun
Jul
Dec
Oct
From this analysis of the seasonal behavior of the congestion quantities during the
Next we examine the daily data. We illustrate the daily congestion amounts together
The study of the daily congestion values leads to the following findings:
• the average daily amount of congestion is 11,770 MW and the range is from 0
MW to 51,799 MW;
• the highest value was attained on June 27, 2001, with 51,799 MW, some lower
high values (each above 30,000 MW) occurred during December 8, 1999,
40
March 13, April 27 and 28, May 1, 2, 4, 10, 11 and 16, 2000, August 9, 2000
• during the first four months of operation (May to August, 1999) daily
congestion stayed below 10,000 MW with the exception of May 2, 1999, when
congestion; these small values may be indicative of the incipient stages of the
60
congestion amounts in 1,000 MW
50
40
30
20
10
0
1-May-1999
1-May-2000
1-May-2001
1-Sep-1999
1-Sep-2000
1-Nov-1999
1-Nov-2000
1-Jul-1999
1-Mar-2000
1-Jul-2000
1-Mar-2001
1-Jan-2000
1-Jan-2001
Figure 4.5: Daily and monthly average congestion for May 1999 – June 2001
41
In order to examine how the daily congestion quantities account for the monthly
amounts, we analyze the frequency of the daily congestion values for the 26 months of
the studied period and separately for the three highest congested months, March, April
and May, 2000. Such a discussion requires the introduction of a new curve. We define the
congestion duration curve to be the rearranged plot of the congestion amount from the
highest to the lowest value. Such a curve has a nice interpretation in terms of probability
distribution if the ordinate is interpreted as a percentage of the total period under study.
60
daily congestion in 1,000 MW
50
40
30
A
20
10
0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 10 0%
percentage of days in the May 1999 - June 2001 period
Figure 4.6: Congestion duration curve for May 1999 – June 2001
For example, we rearrange the daily congestion plotted in Fig. 4.5 as the congestion
duration curve for the 26-month duration, shown in Fig. 4.6. The 100% on the x-axis
means the entire 26-month period. The point A on the curve indicates that daily
congestion was at or above the 20,000 MW level about 15% of the days of the 26-month
period.
42
The flatness over most of the congestion duration curve indicates a rather limited
variability: for over 80% of the days in the 26-month period the congestion is below
20,000 MW. For the remaining 15% there is a considerable volatility making the
congestion vary between 20,000 and 50,000 MW. In Table 4.1 we divided the daily
congestion quantities into sections of 10,000 MW. We provide the percentage of days that
Table 4.1: Frequency information for congestion over the May 1999 – June 2001 period
March 2000 0 58 36 6
April 2000 0 17 70 13
May 2000 6 16 52 26
We also studied the volatility of daily congestion quantities in the three highest
congested months. Fig. 4.7 to 4.9 show the duration curves of the daily congestion
amounts during March, April and May, 2000. For these months, the curves also exhibit
flatness over most of the period: for nearly 70% of the days in May, 2000, and for over
80 % of the days in March and April, 2000, the congestion is between 10,000 and 30,000
MW. We can further explain the high accumulated amounts of congestion during these
months by comparing the frequency of daily congestion values in each month with that
during the entire observed period. While 48% of the days in the time between May, 1999,
43
60
50
daily congestion in 1,000 MW
40
30
20
10
0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
percentage of days in March 2000
60
50
daily congestion in 1,000 MW
40
30
20
10
0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
percentage of days in April 2000
44
60
50
daily congestion in 1,000 MW
40
30
20
10
0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
percentage of days in May 2000
to June, 2001, experienced less than 10,000 MW of daily congestion, no day during
March and April, 2000, and only 6% of the days in May, 2000, experienced an equally
low amount of congestion. The percentage of days that had more than 20,000 MW of
daily congestion is substantially higher during the three highly congested months than
during the observed 26 months, as can be seen in Table 4.1. Especially the percentage of
days that experienced daily congestion of more than 30,000 MW is substantially higher in
these months, ranging from 6% in March, 2000, to 26% in May, 2000, as opposed to only
We next turn our attention to the study of congestion costs. Total mitigated
congestion costs accumulated to $233 million during the observed 26-month period from
45
May, 1999, to June, 2001. We give the monthly mitigated congestion costs in the chart of
Fig. 4.10.
• the monthly average is $9 million of mitigated congestion costs and the range is
• the highest values were attained in March, April and May, 2000 ($21.9 million,
$19.8 million and $20.3 million, respectively), some lower high values occurred
in December, 1999, June, 2000, December, 2001, and June, 2001 ($11 to $14
million);
monthly mitigated congestion costs in million $
25
20
15
10
0
May-99
May-00
May-01
Sep-99
Nov-99
Sep-00
Nov-00
Jul-99
Jul-00
Jan-00
Mar-00
Jan-01
Mar-01
Figure 4.10: Monthly mitigated congestion costs from May 1999 – June 2001
• during the first four months of operation (May to August, 1999) monthly
mitigated congestion costs stayed below $1.1 million, being as low as $360,000 in
46
July; these small values may be indicative of the same fact as described for the
The mitigated congestion costs show roughly the same changes over the studied 26-
investigated in the previous section. This can be seen from Fig. 4.11, which plots monthly
mitigated congestion costs and monthly congestion quantities on the same chart.
The analysis of the mitigated congestion costs allows us to make equivalent findings
May-00
May-01
Sep-99
Nov-99
Mar-00
Sep-00
Nov-00
Mar-01
Jul-99
Jan-00
Jul-00
Jan-01
47
During the first year of operation the monthly mitigated congestion costs were
growing, then decreasing in the second year. The last two of the observed months
experienced increasing costs, but no assumptions about further development of the costs
can be made from the available data. Note that the month that experienced the highest
mitigated congestion costs is March, 2000, while the month with the highest congestion
quantity is May, 2000. We discuss this observation in the following section on daily
mitigated congestion costs. Similar to the monthly congestion quantities, we can find no
indication for a concentration of high monthly costs on a particular season of the year.
In the next section we examine the daily data. We illustrate the daily mitigated
congestion costs together with the monthly averages for the studied period in Fig. 4.12.
The study of the daily mitigated congestion costs leads to the following findings:
• the average daily mitigated congestion costs are $300,500 and the range is
• the highest value was attained on March 13, 2000, with $1.6 million, some
lower high values occurred during June 27, 2001 ($1.5 million), February 28,
2000 ($1.4 million) and March 6 to 10 and 14, 2000 (each between $1.0 and
$1.4 million);
• during the first four months of operation (May to August, 1999) daily
mitigated congestion costs stayed below $0.2 million, three days experiencing
$0 of congestion costs; these small values may be indicative of the same fact
as described above.
48
1.8
1.6
mitigated congestion costs in million $
1.4
1.2
0.8
0.6
0.4
0.2
0
1-May-99
1-May-00
1-May-01
1-Sep-99
1-Nov-99
1-Sep-00
1-Nov-00
1-Jul-99
1-Jul-00
1-Jan-00
1-Mar-00
1-Jan-01
1-Mar-01
mitigated daily costs monthly average
Figure 4.12: Daily mitigated congestion costs and the monthly averages
for May 1999 – June 2001
analogously to the congestion duration curves defined above: With such curves, we can
analyze the frequency of the daily values of congestion costs for the 26 months of the
studied period and separately for the three highest congested months, March, April and
May, 2000. For example, the plot in Fig. 4.13 shows the congestion cost duration curve
We notice a similar flatness over most of the congestion cost duration curve as we did
for the congestion amounts indicating a rather low variability: 74% of the days
49
experienced costs below $0.4 million. The remaining 26%, however, exhibit high
volatility, making the daily congestion costs vary from $0.4 to over $1.6 million.
1.8
daily mitigated congestion costs in million $
1.6
1.4
1.2
0.8
0.6
0.4
0.2
0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
percentage of days in the May 99 - June 01 period
Figure 4.13: Mitigated cost duration curve for May 1999 – June 2001
Table 4.2: Frequency information for daily mitigated congestion costs over the May 1999
– June 2001 period
percent of days with mitigated congestion costs
period below $0.4 between $0.4 million between $0.8 million above $1.2
million and $0.8 million and $1.2 million million
March 2000 19 45 19 16
April 2000 0 80 20 0
May 2000 16 45 39 0
50
In Table 4.2 we divided the daily mitigated congestion costs into sections of $0.4
million. We provide the percentage of days that fall under each section within the given
period of time.
In order to examine how the daily mitigated congestion costs during the peak months
account for the high monthly costs, we constructed the congestion cost duration curves of
the daily mitigated congestion costs for March, April and May, 2000. These are shown in
Fig. 4.14 to 4.16. We can explain the high values of monthly costs by comparing the
frequency of the daily values of the costs in each month with that during the entire
observed period. The numbers for that are also given in Table 4.2. While 74% of the days
during the 26 months from May, 1999, to June, 2001, experienced daily mitigated costs
below $0.4 million, no day in April, 2000, and less than 20% of the days during March
1.8
daily mitigated congestion costs in million $
1.6
1.4
1.2
0.8
0.6
0.4
0.2
0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
percentage of days in March 2000
51
1.8
1.4
1.2
0.8
0.6
0.4
0.2
0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
percentage of days in April 2000
1.8
daily mitigated congestion costs in million $
1.6
1.4
1.2
0.8
0.6
0.4
0.2
0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
percentage of days in May 2000
52
The percentage of days that had more than $0.8 million of daily costs is substantially
higher during the peak months than during the entire observed period. The fact that
March, 2000, experienced the highest monthly mitigated congestion costs, is caused by
the high percentage of days with more than $1.2 million, which was 16% as opposed to
So far, we have analyzed the monthly and daily data about congestion quantities and
associated costs. The total congestion costs are a function of the amount of congestion
and the per MWh mitigated congestion costs as described in Section 3.3. We next
examine the nature of the monthly and daily per MWh mitigated costs of congestion. We
refer to the per MWh monthly mitigated costs of congestion in Figure 4.17.
• monthly per MWh mitigated costs of congestion range from 18.68 $/MWh to
37.50 $/MWh;
• the highest values were attained in March, 2000, and January, 2000, with 37.50
November, 1999, December, 2000, January, 2001, and May, 2001 (32.00 $/MWh
to 33.00 $/MWh).
Similar to the monthly congestion quantities and total costs, the monthly per MWh
mitigated costs were growing in the first year of operation, from May, 1999, to April,
53
monthly mitigated costs in $/MWh monthly mitigated costs in $/MWh
0
5
10
15
20
25
30
35
40
0
5
10
15
20
25
30
35
40
May-99
May-99
Jul-99
Jun-99
Sep-99
Jul-99
Nov-99
Aug-99
Jan-00
Sep-99
Mar-00
Oct-99
54
May-00
Nov-99
Jul-00
Dec-99
Jan-00 Nov-00
Feb-00 Jan-01
Mar-00 Mar-01
Figure 4.17: Monthly per MWh mitigated costs for May 1999 – June 2001
Apr-00 May-01
Figure 4.18: The general upward trend of the monthly per MWh mitigated costs
Fig. 4.19 shows, that in the second year monthly per MWh costs did not decrease like
the monthly congestion amounts and total costs did as we have found from our analysis
above.
40
monthly mitigated costs in $/MWh
35
30
25
20
15
10
0
May-00
May-01
Aug-00
Sep-00
Jul-00
Nov-00
Feb-01
Jun-00
Jan-01
Jun-01
Mar-01
Apr-01
Dec-00
Oct-00
Figure 4.19: The lack of a definite trend in the monthly mitigated costs per MWh
for May 2000 – June 2001
The seasonal behavior of the monthly per MWh mitigated costs is slightly more
distinct than of the monthly congestion quantities and total costs. Fig. 4.20 shows the
monthly per MWh costs for each month during the observed 26-month period. We can
see that per MWh mitigated congestion costs were less during the summer months June to
September than during the rest of the year. May, 1999, and November, 2000, experienced
55
40
30
25
1999
20 2000
2001
15
10
0 May
Aug
Sep
Nov
Apr
Jul
Jan
Feb
Mar
Jun
Dec
Oct
Figure 4.20: Seasonal behavior of the monthly per MWh mitigated costs
for May 1999 – June 2001
We next analyze the daily per MWh mitigated costs. The chart in Fig. 4.21 plots
daily per MWh mitigated congestion costs together with the monthly average values.
• the average of the daily per MWh mitigated congestion costs is 25.60 $/MWh and
• the highest value was attained on October 16, 1999, with 92.89 $/MWh, some
lower values occurred on July 19, 1999 (85.96 $/MWh), August 17,1999 (85.84
56
• costs below 10 $/MWh occurred nearly exclusively during the months in 19999.
100
90
80
daily mitigated congestion costs in $/MWh
70
60
50
40
30
20
10
0
1-May-99
1-May-00
1-May-01
1-Mar-00
1-Mar-01
1-Sep-99
1-Nov-99
1-Sep-00
1-Nov-00
1-Jul-99
1-Jan-00
1-Jul-00
1-Jan-01
Figure 4.21: Daily per MWh mitigated costs and monthly averages
for May 1999 – June 2001
The graph in Fig. 4.21 shows a concentration of extraordinarily high daily per MWh
mitigated costs during the first half of the studied period. We analyze this as before with
the help of duration curves of the daily values. We plot the per MWh mitigated cost
duration curve for the entire studied period from May, 1999, to June, 2001, in Fig. 4.22.
57
Note that 60.2% of all days in the 26-month period experienced daily per MWh
mitigated congestion costs between 20 $/MWh and 40 $/MWh. Only 9.2% of the days
experienced higher values. The percentage values are given in Table 4.3.
100
90
per MWh mitigated costs in $/MWh
80
70
60
50
40
30
20
10
0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
percentage of days in the May 1999 - June 2001 period
Figure 4.22: Per MWh mitigated cost duration curve for May 1999 – June 2001
Table 4.3: Frequency information for daily per MWh mitigated congestion costs over the
May 1999 – June 2001 period
percent of days with per MWh mitigated congestion costs
period below 20 between 20$/MWh between 40 $/MWh above 60
$/MWh and 40 $/MWh and 60 $/MWh $/MWh
constructed the per MWh mitigated cost duration curves for the first 12 months in Fig.
58
4.23 and for the following 14 months in Fig. 4.24. The percentage per range is given in
Table 4.3.
We notice that 13.9% of the days during the first year of operation experienced daily
per MWh mitigated congestion costs of more than 40 $/MWh, whereas in the following
100
per MWh mitigated costs in $/MWh
90
80
70
60
50
40
30
20
10
0
0% 10% 20% 30% 40% 50% 60 % 70 % 80% 90% 100%
percentage of days in the May 1999 - April 2000 period
Figure 4.23: Per MWh mitigated cost duration curve for May 1999 – April 2000
Especially costs above 60 $/MWh occurred on 3.8% of the days of the first year, but
during only 0.5% of the days in the following 14 months. Interestingly, the number of
days with congestion costs below 20 $/MWh is also higher during the first year than
during the second half of the studied period. This indicates a higher volatility of daily per
MWh mitigated congestion costs during the first year of operation than later on. This may
be again indicative of the fact, that trading in the new markets was in its incipient stages
59
100
Figure 4.24: Per MWh mitigated cost duration curve for May 2000 – June 2001
In this section we have analyzed monthly and daily data on congestion quantities,
total mitigated costs and per MWh mitigated costs. We found the months with highest
congestion to be March, April and May, 2000. We could not detect any definite trend or
seasonal pattern in congestion quantities and total costs over the 26-month period. Per
MWh mitigated costs were slightly lower during the summer months than during other
We are interested in finding the time of the day that congestion is most likely to
occur. In this section we study the hourly behavior of congestion quantities and costs and
We first examine the hourly demand pattern. For this we use the hourly data for
system load and energy clearing prices, which are published as the System Hourly
60
Clearing Price Reports by ISO-NE for each day [22]. The typical system load reaches its
lowest point at night and rises around 7am, when the workday starts; it experiences a
small peak in the evening around 9pm. Fig. 4.25 shows the average hourly load for May,
1999.
16,000
hourly average system load in MW
14,000
12,000
10,000
8,000
6,000
4,000
2,000
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
hour
If we consider that the demand for energy is low at night and therefore less energy
has to be dispatched, we expect the transmission network to be less intensively used and
therefore with little if any congestion. To check this assumption, we determined the
average hourly congestion quantities for each month and normalized them with the
respective lowest hourly congestion in each month. Thus a value of 1.0 corresponds to
the lowest average hourly value. We are normalizing so as to have some basis for
comparing across months. We found that the assumption of lower congestion at night is
true for several months, but not for all. For example, the months with the highest amount
of congestion, March, April and May, 2000, experienced lower congestion during the
61
hours of night than during the day (Fig. 4.26). The average values during the night hours
increased by nearly 40-50% for the peak daily hours in March and April, 2000, and by
2.4
normalized hourly congestion quantity
2.2
1.8 Mar-00
Apr-00
1.6 May-00
1.4
1.2
1
0 2 4 6 8 10 12 14 16 18 20 22 24
hour
Figure 4.26: Average hourly congestion for March, April and May 2000
2.4
normalized hourly congestion quantity
2.2
1.8
Aug-00
1.6 Nov-00
1.4
1.2
1
0 2 4 6 8 10 12 14 16 18 20 22 24
hour
Figure 4.27: Average hourly congestion for August and November 2000
62
Such an assumption clearly does not hold in August and November, 2000 (Fig. 4.27),
since congestion was typically higher at night than during the day. Average hourly
congestion quantities at night exceeded the values during the day by 40-50% in August,
2000. November, 2000, exhibited volatile average hourly congestion quantities, showing
the highest peak during the night hours and a lower one during the day.
Based on these observations, congestion is random during the hours of a day and fails
to follow a distinct pattern. More surprisingly, the hourly congestion amount is not
The hourly energy clearing price is typically strongly correlated with the hourly
system load: as the demand rises so does the ECP. Fig. 4.28 shows as an example the
average hourly ECP and the average hourly system load for May 1999.
35 16,000
12,000
25
10,000
20
8,000
15
6,000
10
4,000
5 2,000
0 0
0 2 4 6 8 10 12 14 16 18 20 22 24
hour
Figure 4.28: Average hourly system ECP and load for May 1999
63
Since the total hourly congestion costs do not provide very detailed information, we
computed the average hourly per MWh mitigated costs of congestion from the ISO-NE
congestion reports for each month of the study period. We found out that per MWh
mitigated costs were typically slightly higher at night than during the day. This behavior
is opposite to the behavior of the ECP. A representative curve is shown for August 2000
in Fig. 4.29.
60
average hourly costs and prices in $/MWh
50
40
30
20
10
0
0 2 4 6 8 10 12 14 16 18 20 22 24
hour
Figure 4.29: Average hourly per MWh mitigated costs and ECP for August 2000
How do these findings affect the total resulting congestion costs? We first illustrate
this for March and April, 2000. As we found above, these months experienced lower
congestion during the hours of night than during the day. Hourly per MWh mitigated
congestion costs were slightly higher during the night hours than during the day. As a
64
result the two months do not show a discernible pattern of average hourly total
congestion costs. Figures 4.30a and 4.30b show average hourly congestion quantities and
per MWh costs and the resulting average hourly total congestion costs for March and
April, 2000.
60 1,400 2.4
1,000 2
40
800 1.8
$/MWh
costs
MW
30
600 1.6
20
400 1.4
10 200 1.2
0 0 1
0 2 4 6 8 10 12 14 16 18 20 22 24 0 2 4 6 8 10 12 14 16 18 20 22 24
hour hour
Figure 4.30a: Average hourly per MWh mitigated Figure 4.30b: Average hourly
costs and congestion for March 2000 normalized mitigated congestion
costs for March 2000
60 1,400 2.4
average hourly normalized total
hourly average congestion in
1,200 2.2
hourly average costs per
50
1,000 2
MWh in $/MWh
40
1.8
costs
800
MW
30
1.6
600
20 1.4
400
10 1.2
200
1
0 0
0 2 4 6 8 10 12 14 16 18 20 22 24
0 2 4 6 8 10 12 14 16 18 20 22 24
hour
hour
Figure 4.31a: Average hourly per MWh mitigated Figure 4.31b: Average hourly
costs and congestion for April 2000 normalized mitigated congestion
costs for April 2000
65
We get a different result for August, 2000. We found in our analysis above, that
average hourly congestion quantities were lower during the hours of the day than at night
in this month. Average hourly per MWh mitigated congestion costs were slightly higher
at night than during the day. In this case we get as a result average hourly total costs that
are substantially higher during the hours of night than during the day. We illustrate this in
60 1,400 2.4
50
1,000 2
MWh in $/MWh
40
800 1.8
costs
MW
30
600 1.6
20 1.4
400
10 1.2
200
1
0 0
0 2 4 6 8 10 12 14 16 18 20 22 24
0 2 4 6 8 10 12 14 16 18 20 22
hour
hour
Figure 4.32a: Average hourly per MWh mitigated Figure 4.32b: Average hourly
costs and congestion for August 2000 normalized mitigated congestion
costs for August 2000
The analysis of the hourly data in this section shows that congestion and its associated
costs do not occur in a predictable pattern throughout the day. Congestion quantities do
not follow the same pattern as system load. Also, total congestion costs do not follow the
may not be equivalent to improvement of congestion. The results of this section can be
66
used for further studies on effective measures for determining economically efficient
levels of congestion.
The occurrence of congestion is not uniform in the entire ISO-NE region. In this
section, we study the distribution of congestion within the twelve transmission regions of
New England based on the 26 month data used in our investigation. For the names of the
transmission areas please refer to Table 2.1 in Section 2.1. Three regions are responsible
for the majority of the congestion in the New England system. We first study the
NEMASS/BOST
42.90%
SW CONN
19.95%
CONN
22.49%
67
The pie chart in Fig. 4.33 shows the percentage of the total amount of congestion that
occurred in each transmission area. 85% of the total system-wide congestion occurred in
only three of the twelve areas. The NEMASS/BOST area experienced the biggest portion
with a 43% share of the total amount. The CONN area had 22% and SW CONN had
The pie chart in Fig. 4.33 presents in a telling manner that the amount of congestion
in the three areas NEMASS/BOST, CONN and SW CONN is nearly six times the
amount of the nine other areas. To see the occurrence of congestion in these three areas
we plotted the monthly congestion amounts as a function of time over the period from
May, 1999, to June, 2001. These plots are shown in Fig. 4.34. Note that the SW CONN
area basically experienced significant congestion during 2000 with peaks in March and
April as well as July, August and September and a lower one in December.
Figure 4.34: The contribution of transmission areas to the monthly congestion for May
1999 – June 2001
68
Significant congestion in the CONN region, however, was concentrated in a small
number of months. The largest congestion quantities occurred during February to June,
2000, lower peaks were experienced in December, 1999, and February and March, 2001.
The other transmission areas did not experience larger amounts of congestion during
1999, during the months of 2000 congestion values rose, but fell again during the first
half of 2001.
From this distribution we can detect which transmission areas were the main causes
for the system-wide peaks of congestion. Since the dense NEMASS/BOST area
experienced uniformly high levels of congestion from September, 1999, on, it did not
account for the extraordinary high peaks of congestion. The three highly congested
months in 2000 were clearly the result of high congestion in the CONN and SW CONN
transmission areas. The high values in March were mainly caused by the two regions
together, whereas the high quantities in April and May mostly resulted from congestion
in the CONN area, together with also higher than usual congestion in the other
We next examine the distribution of the total congestion costs across the twelve
transmission areas. There are some additional insights we gain from the cost data. We
summarize the cost distribution in the pie chart in Fig. 4.35. Here, 85% of the system-
wide costs constitute the share of NEMASS/BOST and the Connecticut areas. The
NEMASS/BOST area, which experienced 43% of the total system congestion, accounted
for 53% of the resulting costs. The two Connecticut regions have a share of 32% of the
costs with 19% being the share of the congestion costs for CONN and 13% the share of
69
NORTH ME/NH 345 & 115 kV
0.88% SEMA/RI
W MASS 0.26%
2.08%
EAST 0.22% MAINE
0.14% 3.18%
VT
6.98%
SW CONN
13.33%
NEMASS/BOST
53.45%
CONN
19.46%
180 120
kV
ST
VT
TH
TH
T
R
N
ES
AS
N
A/
BO
EA
U
R
AI
5
O
O
M
11
W
M
SO
O
C
M
S/
SE
N
SW
%
AS
5
EM
34
N
H
N
E/
Figure 4.36: Per MWh mitigated costs and total mitigated costs for each area
for May 1999 – June 2001
70
The interplay of congestion amounts given in Fig. 4.33 and Fig. 4.34 and the
congestion costs in Fig. 4.35 need to be related to the per MWh costs plotted in Fig. 4.36
for each transmission area. The total costs of congestion over the 26-month period are
We observe that while the areas EAST and NORTH experienced the highest per
MWh costs, they had negligible total costs. This is due to the fact that congestion in these
areas occurred only during a few days, resulting in extraordinarily high per MWh costs.
Of the three highest congested areas NEMASS/BOST, CONN and SW CONN, none
shows particularly high per MWh costs, but each experienced congestion on a high
number of days. The number of days with congestion and the number of days with a
certain range of per MWh costs are given in Table 4.4 for the discussed areas. The total
Table 4.4: Number of days with per MWh mitigated costs in certain range over the May
1999 – June 2001 period
number of days with respective range of costs
days with between between between
area below 120 above 900
congestion 120 and 200 200 amd 400 and 900
$/MWh $/MWh
$/MWh 400 $/MWh $/MWh
EAST 14 9 1 0 4 0
NORTH 38 31 1 1 1 4
71
Figure 4.37: The contribution of the transmission areas to the total monthly mitigated
congestion costs for May 1999 – June 2001
The distribution of the shares of mitigated congestion costs from Figure 4.35 across
time is shown in the plots of Figure 4.37. In the study of these plots and in comparison
costs over the 26 months than in congestion amounts due to the time
• The share of congestion amounts and that of costs of the CONN region are
essentially the same across the study period with peaks experienced during the
72
• The SW CONN region has a distribution of the share of the congestion costs
substantial congestion occurred during the entire year of 2000, the major part
• The other nine transmission areas had a small share of the congestion costs
with substantial increases in the months of October, 1999, and May, 2000.
twelve transmission areas in New England. We found that 85% of the system-wide
congestion amounts and costs during the observed study period were experienced in the
three areas NEMASS/BOST, CONN and SW CONN. The NEMASS/BOST area had
uniformly high monthly levels of congestion amounts from September, 1999, onwards.
Congestion costs in this area were more volatile. The Connecticut areas experienced high
amounts and costs of congestion concentrated in a few months. We also found that the
highest congested areas did not experience extraordinarily high per MWh costs.
In this section we briefly examine the conditions in the major congested areas
the causes for congestion in these regions in their annual market reports [14,23].
The region around Boston is a densely populated area with a high demand for energy.
73
It accounts for more than fifty percent of the mitigated congestion costs in the whole
system. In two market reports ISO-NE provides causes for congestion in the
transmission facilities (load pocket), maintenance, construction and high voltage control.
During the period from September, 1999, to April, 2000, the ISO determines that about
40% of the congestion was attributable to the existence of load pockets and almost the
generation and transmission facilities. According to the ISO the situation changed during
the time from May, 2000, to April, 2001. During this period the major reason for
congestion was inadequate transmission facilities. These numbers clearly show the dire
need for expansion of the transmission grid in this critical transmission area.
The market reports do not distinguish between the CONN and the SW CONN area.
The whole Connecticut region experienced roughly the same distribution of causes for
from May, 1999, to June, 2001, the area experienced 1.7 million MW of congestion,
which is 20% of the system-wide value. This resulted in mitigated congestion costs of
Connecticut, a margin that will even grow with the addition of power plants currently
under construction [24,25]. Most of the state is served by 345-kV transmission lines,
which generally allow large quantities of power to be transported. However, the situation
in southwestern Connecticut is different from other regions in the state. The area
74
(particularly Lower Fairfield County) generally has a supply deficiency and its ability to
import power is limited. The region’s power plants are mainly old and relatively
inefficient. But none of the plants under construction in Connecticut are located in the
southwestern region to provide more efficient generation and there are no proposals for
any so far. Unlike in the rest of the state, the region’s transmission system primarily
consists of 115-kV lines, which causes frequent constraints to the import of power.
Proposals for 345-kV lines to alleviate the constraints exist. Currently, approval of new
transmission lines is under the authority of the states and can take a long time.
In our analysis of congestion costs we have studied the costs that arose from
market power mitigation procedures that we described in Section 3.3. These are the costs
that are charged to the market participants. The unmitigated costs are based on the offer
prices of the generating blocks, which have to be dispatched out of merit order. The
mitigated costs adjust those prices in line with the rules and consequently result in lower
ones. The mitigation process aims to eliminate any charges that can be considered to arise
from the exercise of market power. In this section we quantify the impacts of the
mitigation provided by the ISO-NE in terms of reductions effected in the total congestion
costs.
75
We compare the total unmitigated to the mitigated costs over the 26-month period.
We provide the plots of the monthly charges in Fig. 4.38. The shaded region of the
In the period from May, 1999, to June, 2001, the New England system experienced
total unmitigated costs of $310 million. The ISO-NE applied market power mitigation
procedures to all the generating blocks that were dispatched out of merit order to alleviate
congestion. After mitigation these costs were reduced by nearly 25%, resulting in the
$233 million of costs shown in the figure. This indicates that the prevention of the
possible exercise of market power was able to reduce the costs by $77 million. These
savings were brought about by the application of the ISO-NE procedures for identifying
76
Fig. 4.39 shows the percentage of reduction of costs by the mitigation procedures in
each month. During four months in 1999 mitigation had no impacts. That means, that the
generating blocks out of merit order received their offer prices. Mitigation had the highest
impact on congestion costs in January of 2001, when the reductions constituted 59% of
70%
60%
average reduction
50% May 99 - June 01
40%
30%
20%
10%
0%
May-99
May-00
May-01
Aug-99
Sep-99
Nov-99
Aug-00
Sep-00
Nov-00
Apr-00
Apr-01
Jul-99
Feb-00
Jul-00
Feb-01
Jun-99
Mar-00
Dec-99
Jan-00
Jun-00
Dec-00
Jan-01
Mar-01
Jun-01
Oct-99
Oct-00
These findings show, that the mitigation procedures substantially reduced congestion
costs. Total unmitigated costs during the 26-month period were lowered by 25%, which
resulted in significant savings of $77 million. The average monthly reduction was 20.5%
of the unmitigated costs. Monthly mitigation results show a high volatility, ranging from
as low as zero reduction up to 59% of the unmitigated costs. As many as 14 out of the 26
77
4.6 Impacts of generation availability
In the previous sections we examined monthly and daily congestion data for possible
patterns and analyzed the distribution across the transmission areas. In this section we
part of the system load. If a generator is not available, we call it an outage. Such an
Whenever an outage occurs at a generating unit, one or more other units must take over
the generation to satisfy the system demand. Depending on the location of the outaged
unit, power flows on the system will be impacted. As a result, transmission constraints
which were not binding when the outaged unit was dispatched in the pre-outage state, can
become binding and congestion may result in the post-outage state. Therefore, we are
the amount of congestion in the system. We explore the relationship between generation
outages and congestion and between total available capacity and congestion. Total
available capacity is basically the sum of installed generating capacity reduced by the
outaged capacity10.
In 2001 two studies were conducted on generation availability in the New England
system. The study initiated by the ISO-NE found that average availability of plants
10
The ISO-NE determines the total available capacity in the daily Morning Reports as the sum of installed generating capacity and
dispatchable loads, reduced by generation outages and reductions, unavailable generation due to start time and net deliveries
(sales to minus purchases from neighboring systems). For further definitions please refer to ISO-NE documentations
[10,11,12,13].
78
increased slightly from 1995 to 2000 [26]. The second study concluded that the amount
of capacity out of service rose since the beginning of the competitive wholesale market in
withholding of capacity and thereby exercising market power [27]. Neither of the two
congestion.
The ISO-NE publishes outage data in the so-called daily Morning Reports for each
day [28]. The available data include total generating unit outages and partial capacity
reductions. In the following, we will use the term outages jointly for outages of a
complete generating unit and partial output reductions. The reports do not distinguish
between forced outages and those that were scheduled for maintenance. Therefore our
study can only examine the possible correlation between congestion and the total capacity
of outage.
Data from Morning Reports are available from September, 1999, onwards. We
examined the outages and congestion data between September, 1999, and June, 2001. We
constructed the chart shown in Fig. 4.40 from the Morning Reports data. The chart shows
daily outaged capacity in MW during the period from September, 1999, to June, 2001.
The daily values range from 1,075 MW on August 15, 2000, to 9,887 MW on May 20,
2000. 90% of the days experienced outages between 2,000 MW and 8,000 MW.
Outages in summer are usually lower and the high outage values occur during spring.
The pattern is less distinct in winter, but also shows outages concentrated in fall and early
winter. This is true due to very little maintenance planned for the summer and for winter
and the effort to concentrate maintenance during the off-peak seasons [26].
79
12,000
10,000
daily outages in MW
8,000
6,000
4,000
2,000
0
10 /99
11 /99
12 /99
1/ 9
2/ 0
3/ 0
4/ 0
5/ 0
6/ 0
7/ 0
8/ 0
9/ 0
10 /00
11 /00
12 /00
1/ 0
2/ 1
3/ /01
4/ /01
5/ /01
6/ /01
1
0
0
0
0
0
0
0
0
0
/9
/0
/0
3/
3/
5/
5/
6/
6/
7/
7/
9/
1
9
/2
/2
/3
/8
/8
/9
12
12
13
13
9/
Figure 4.40: Daily outaged capacity for September 1999 – June 2001
congestion quantities and the daily outages for each month. The monthly correlation
rm =
( )( )(
∑ xi * yi - ∑ xi * ∑ yi )
σ mx * σ my
Here the summation is done over all days of month m. The congestion value for day i is
denoted by xi, the outage value for day i is denoted by yi. The month m standard
deviations are denoted by σ mx and σ my for the congestion and outage amounts,
respectively.
80
The correlation coefficient provides a measure for the linear relationship between two
variables [29]. However, it must be used carefully, since it is only meaningful if variables
are correlated and not if they are not. That means a correlation which happens only by
probability of a real correlation between outages and congestion. The statistical methods
between two variables. A value of zero shows no correlation at all. Negative values are
related to negative correlation and indicate opposite actions (one variable increases and
the negatively correlated variable decreases and vice versa). To show meaningful
0.7 ≤ rm ≤ 1
congestion and outage amounts in Table 4.5 together with the values of rm.
Table 4.5: Months with significant correlation between congestion and outages
month rm
Sep-99 0.45564
Oct-99 - 0.38388
Sep-00 - 0.36692
Apr-01 0.49738
Jun-01 - 0.45248
These five rm‘s out of the 22 studied have a probability high enough to assume actual
correlation between generation outages and congestion quantities. Of these months, none
81
has a correlation coefficient whose absolute value exceeds 0.5. We note that both positive
The five months indicating some correlation are spread over the 22 months of the
sample studied. None of these months are among the highest congested months. The peak
congested months March, April and May, 2000, had lower correlation coefficients.
March and April had correlation coefficients of 0.3 and 0.25, respectively, but the
significance test showed a relatively high probability for an only random relationship.
The correlation coefficient for the highest congested month of the observed two-year
period, May, 2000, was extremely low at 0.07, showing basically no correlation between
These results do not indicate a clear correlation between the occurrence of congestion
and the daily generation outages11. From this study there is no data to indicate that high
quantities of congestion occur especially during days with a high amount of outaged
capacity.
We also studied the possible relationship of total available capacity and congestion.
We show a scatter diagram of the daily amounts of congestion versus the reported daily
amounts of outages in Fig. 4.41. We see that the total available capacity values do not
show any obvious relation to the amount of congestion. Surprisingly, outliers of high
11
Note that we have only investigated a simple linear relationship. The result does not exclude the possibility of a more complex
nonlinear relationship.
82
60,000
50,000
daily congestion in MW
40,000
30,000
20,000
10,000
0
0 5,000 10,000 15,000 20,000 25,000 30,000
daily total available capacity in MW
In this section we have analyzed the relationship between daily congestion quantities and
daily outaged capacity as well as daily total available capacity. We found that neither the
daily outaged capacity nor the daily total available capacity is significantly correlated to
daily congestion quantities. Especially the peak months of congestion show no indication
that high quantities of congestion occur during days with a high amount of outaged
capacity. From these findings we can see that there is no guarantee for a reduction in
83
5. CONCLUDING REMARKS
In this thesis we focused on the analysis and quantification of congestion in one of the
major power systems in the United States, the New England power system. Our study of
the May 1999 – June 2001 period provided a good basis for identifying the principal
In our analysis of the congestion data for the study period we found that neither
congestion quantities nor costs follow a distinct seasonal pattern. Only the per MWh
mitigated costs exhibited slightly lower values during the summer months than during
other months. Daily congestion quantities and costs also vary significantly within a wide
range of values during the 26-month period. We found that the majority of days exhibit a
rather low variability in congestion quantities and costs, but that the remaining days
quantities and costs using the frequency information gained by the construction of
duration curves. The months that had highest congestion and associated costs typically
experienced a lower percentage of days with low values and a higher percentage of days
Whereas the system load peaks occur, typically, during the same time slot each day,
the hourly congestion data do not allow any predictable patterns on the course of
congestion. We found certain months that had high congestion during the day and other
months that experienced high congestion only at night. Another interesting finding is that
the values of the congestion costs do not necessarily track the hourly congestion
quantities. A topic for future work is to investigate the nature and level of correlation
84
between congestion costs and quantities. It is also necessary to analyze the effectiveness
of the ISO-NE congestion management and to examine the adequacy of the congestion
Our study attempted to investigate possible causes of congestion and, for that
found no statistically significant correlation between the amount of outaged capacity and
the quantity of congestion. This finding does not allow us to impute that generator
outages can be considered a major factor in causing congestion. Therefore, it is not clear
on the basis of available data that these could be a big potential for reducing congestion
region and found that a significant part (85%) of the system-wide congestion amounts
and costs during the May 99 – June 2001 period was experienced in three areas. The
three areas lie in the Northeast Massachusetts, Boston and the Connecticut region and are
resources. The high congestion figures in these areas clearly provide signals for the need
to implement effective incentives and support for expansion of the transmission grid
The total actual post mitigation congestion costs during the entire study period were
$233 million and represent a $77 million savings from the unmitigated costs of $310
million. Due to the fact that there is insufficient information available on the offer data, it
is difficult to establish how much market power exercise was actually prevented by the
ISO-NE’s market power mitigation procedures and how much went undetected. Such
85
determination could be made if the ISO-NE would be able to publish more detailed
information on offer prices and quantities if even with a certain delay after the
existence and the impacts of exercising market power in the New England region.
The existence of market power is a big issue not only in New England, but in all the
restructured electricity markets and deserves much attention in future studies. The
and proper schemes for preventing players from exercising market power need to be
harnessed.
The electricity markets are subject to continuous review and rule changes. ISO-NE
has been continuously reviewing the market performance of the New England electricity
markets from its inception. From the experience of the first years of operation and the
comparison with other systems in the United States ISO-NE identified several aspects
that need to be improved. The newly proposed Standard Market Design (SMD) includes
the implementation of separate day-ahead and real-time energy markets and locational
filed with the Federal Energy Regulatory Commission in June, 2002, and targeted for
The new market design implementation should be tracked closely by a study of how
the quantities and costs of congestion are affected and the effectiveness of the new
congestion management scheme. A study similar to the one presented in this thesis can
provide insights into the effectiveness of the new market design with respect to
86
transmission congestion. Future work must assess the capability of the congestion
A major development in the northeast electricity markets in the coming years will be
include the New England System, the New York Power Pool and PJM into a single large
geographic entity. The formation of an organization of such size raises many new and
challenging issues. The participating systems must develop a consistent market design
across the joined transmission regions and also coordinate their planning and operations.
Market efficiency and system reliability acquire a significantly larger scope. Future
studies will need to include the assessment of the congestion management under the
changed conditions in the new RTO. Such a study will need to explore the ability of the
new structure and markets to create and sustain vibrant competitive markets.
87
REFERENCES
[1] R. Christie, B. Wollenberg and I. Wangensteen, “Transmission Management in
the Deregulated Environment”, Proceedings of the IEEE, Vol. 88, No.2, February
2000
[5] Z. Yu, F.T. Sparrow, D. Gotham, F. Holland, D.G. Nderitu and T. Morin, “The
Impact of Transmission on Imperfect Electricity Competition”, Power
Engineering Society Winter Meeting, 2002, IEEE , Volume 1
[6] Rajesh Rajaraman and Fernando Alvarado, “(Dis)Proving Market Power”, Laurits
R. Christensen Associates, Inc., January 24, 2002
[7] James Bushnell and Celeste Saravia, “An Empirical Assessment of the
Competitiveness of the New England Electricity Market”, Center for the Study of
Energy Markets, May 2002
[9] National Transmission Grid Study and Issue Papers, Department of Energy, May
2002, www.energy.gov
88
[13] “NEPOOL Market Rules and Procedures”, http://www.iso-ne.com/mrp/main.html
[14] “Annual Market Report, May 2000 – April 2001, ISO New England, August 1,
2001”, http://www.iso-ne.com/market_monitoring/Annual_Report_and_Public_
Forum/Annual_Market_Report_May-00_to_Apr-01_Section_1-2.pdf
[16] Allen J. Wood and Bruce F. Wollenberg, Power Generation, Operation and
Control, 2nd ed., John Wiley & Sons, New York, 1996
[18] Linda J. Kelly, “Market Monitoring, Reporting and Market Power Mitigation”,
October 2001, http://www.erranet.org/library/presentations/
Kelly%20Market%20Monitoring%20w%20notes%20Eng.ppt
[19] Office of Economic, Electricity and Natural Gas Analysis, Office of Policy, U.S.
Department of Energy, “Horizontal Market Power in Restructured Electricity
Markets”, Washington D.C., March 2000
[21] “NEPOOL Transmission Congestion Area Uplift Report by Hour” and “NEPOOL
Transmission Congestion Area Uplift Report by Day”, http://www.iso-ne.com/
market_monitoring/transmission_congestion_data_file/
[23] “Annual Market Report, May 1999 – April 2000, ISO New England”,
http://www.iso-ne.com/market_monitoring/Annual_Report_and_Public_Forum/
Annual_Market_Report_May-99_to_Apr-00.pdf
89
[26] H. Merrill, J. Natour and C. Sedlacek, “How Availability Changed in a
Competitive Market”, IEEE Power Engineering Review, January 2002
[27] Daniel Allen, Bruce Biewald and David Schlissel, “Generator Outage Increases:
A Preliminary Analysis of Outage Trends in the New England Electricity
Market”, prepared for Union of Concerned Scientists, January 7, 2001
[29] Sheldon Ross, A First Course in Probability, Macmillan Publishing Co., Inc.,
New York, 1976
[30] David John Finlay, “Optimal Bidding Strategies in Competitive Electric Power
Pools”, master’s thesis, Department of Electrical and Computer Engineering,
University of Illinois at Urbana-Champaign, 1995
[31] George Gross, “The Evolution of the U.S.A. Open Access Transmission Regime”,
University of Illinois at Urbana-Champaign, ICPSOP 2000, Accra, Ghanna
[33] H. Mullholland and C.R. Jones, Fundamentals of statistics, New York Plenum
Press, London, 1968
90
APPENDIX A
During the last decade the electricity markets in many countries underwent major
changes. Chile, England and Wales, Norway and New Zealand were some of the first
shortly.
The driving forces behind the restructuring of electricity markets are economics. The
example of the economic benefits to society resulting from the deregulation of other
industries such as telecommunications and airlines, led to the belief that the introduction
of competitive market forces to the electric utility will result in lower-priced electricity to
In the regulated electricity market the major participants were vertically integrated
utilities, who owned and operated both generation and transmission facilities. Electricity
rates were set by the regulatory agencies and based on the utilities’ production costs [31].
There was no incentive to fully assess the risks of investments, since the costs could be
recovered from end customers as part of the electricity price even if the investment turned
out to have poor results. Also, utilities were not generally obligated to provide
The Energy Policy Act of 1992 (EPAct) provided the Federal Energy Regulatory
91
allow independent suppliers to use their transmission facilities. Any electric utility,
federal power marketing agency or person generating electric energy for sale at wholesale
are allowed to request transmission service from a transmission owning untility (TOU). If
the request is not met, the eligible entity may apply to FERC for a transmission order,
On April 24, 1996 FERC took a big step and released its Orders 888 and 889, which
were aimed at promoting wholesale electricity competition. The Orders were seeking a
number of goals. One of them was to guarantee non-discriminatory open access to the
transmission grid by requiring all utilities that own or control transmission facilities to
provide an open access transmission tariff. The tariff must specify terms and conditions
for using the utilities’ transmission systems. The utilities were also required to
functionally unbundle their activities, which meant to apply the same tariff to their
transmission services for its own uses as charged to all other transmission users, separate
their rates for generation, transmission and ancillary services and rely on the same
information. The primary tool for this is the required Open Access Same-Time
Internet-based database. The Orders further specified the basic service requirements of
ancillary services, which they are reasonably capable of providing. In addition, the Order
No.888 provided the standards and procedures for the recovery of any costs resulting
from increased competition. Today all utilities have filed open access tariffs.
92
The combination of competitive generation and regulated transmission requires some
form of central operation of the power grid. Since there is not a single vertically
integrated utility with control over both generation and transmission anymore, but a large
must be coordinated. Power cannot deliberately be injected into the system and the flow
of electricity, i.e. which transmission facility it will use to travel from one point to
another, can usually not be determined exactly. System reliability is harder to maintain
(ISOs) to operate and control the transmission system. Utilities were supposed to transfer
the control of their transmission facilities to the ISO, while maintaining the ownership.
FERC set out a list of principles such an ISO must comply with. Without economic
interest in power transactions the ISO must administer the open access tariff in a fair and
nondiscriminatory way and ensure a single grid-wide tariff. The ISO has control over the
transmission system operations within the respective region and has the responsibility for
ensuring the operational reliability of the grid. The ISO coordinates transactions with
neighboring control areas and must be able to identify and effectively manage actions to
relieve transmission grid constraints. So far, there are six ISOs operating in the United
States: California ISO; Pennsylvania, New Jersey, Maryland (PJM) ISO; ISO New
England; New York ISO; ERCOT ISO (Texas) and – what has recently assumed
After Order 888 is implemented, there still remain some impediments to a fully
competitive electricity market. There are still complaints that transmission owners
93
discriminate against independent power companies. In a market with a large number of
players, it is becoming more difficult to detect discriminatory behavior. Another big issue
reliability. Transmission expansion is slow, responsibilities are not clear and incentives
are low, since the rapidly changing market situation makes cost recovering insecure.
Furthermore only some areas of the country have formed independent system operators,
some have not. In order to further improve competitive markets, FERC issued Order
2000 in December 1999, which strongly encourages the voluntary formation of regional
utilities that own or operate interstate transmission facilities to form or join a regional
Order 2000 are to increase the efficiency of the power system, improve transmission
transmission access.
94
APPENDIX B
95
UNMITIGATED TOTAL COST = Sum of dispatched MW generation from OOMO bid block *
C (bid block price - ECP).
C UNMITIGATED AVERAGE COST = Total Cost / Total MW.
MITIGATED/NEGOTIATED TOTAL COST = Sum of dispatched MW generation from OOMO
C bid block * (mitigated/negotiated price - ECP).
C MITIGATED/NEGOTIATED AVERAGE COST = Total Cost / Total MW.
The data in this report for months prior to July, 2001 reflects congestion uplift and data after
C July 1, 2001 reflects NCPC uplift for congestion hours.
The data in this report reflects internal NEPOOL generation and uplift and excludes
C congestion from external contracts.
Note:
• The report refers to the NEPOOL region, this is equivalent to the ISO-NE region.
96
APPENDIX C
Given the correlation coefficient r we test it for significance by testing the null
hypothesis that the true correlation is zero [33].
H0: r = 0
t ≥ t5% (n - 2),
we reject the null hypothesis and assume the correlation coefficient r to be significant.
Example:
The correlation coefficient for daily congestion quantities and outages for September,
1999, is rS99 = 0.45564, the number of daily values is n = 30.
30 - 2
tS99 = 0.45564 = 2.71
(1- 0.455642 )
t5% ( 28 ) = 2.05
Since 2.71 > 2.05 the result is significant at the 5% level and we reject the null
hypothesis.
97